No Uraian Upah, Material,Alat,Safety Dan Operasional Koefisien Satuan

1 Mobilisasi Dan Manpower


- Fuel Dexlite 10 Kali Pengisian Dalam Sebulan 170.00 Liter
- Makan Siang Manpower 7 Orang / Hari 30.00 Hari

2 Safety
- Sarung Tangan 14.00 Lusin
- Kaca mata Safety 7.00 Pcs

3 Material
- Beton K250 46.20 M³
- Beton K100 Lean Concrete 19.25 M³
- wiremesh M8-1 Layer 2097.81 Kg
- Besi Ø12 Tie Beam 393.99 Kg
- Plastic Cor 385.00 M²
- Joint Sealent 1.00 Pail
- Kawat Bendrat 10.00 Kg
- Plywood 9mm 5.00 Lembar
- Paku 2'',2,5",3" 6.00 Kg
- Kayu 4/4 30.00 Batang

4 Upah
- Pekerjaan Beton K250 46.20 M³
- Pekerjaan K100 Lean Concrete 19.25 M³
- Pekerjaan wiremesh M8-1 Layer 2097.81 Kg
- Pekerjaan Besi Ø12 Tie Beam 393.99 Kg
- Pekerjaan Plastic Cor 385.00 M²
- Pekerjaan Joint Sealent 1.00 Lot
- Pekerjaan Bekisting 12.42 M²
Harga Satuan Jumlah

Rp 17,700.00 Rp 3,009,000.00
Rp 105,000.00 Rp 3,150,000.00
Rp 6,159,000.00

Rp 35,000.00 Rp 490,000.00
Rp 35,000.00 Rp 245,000.00
Rp 735,000.00
2097.81
Rp 1,500,000.00 Rp 69,300,000.00
Rp 1,300,000.00 Rp 25,025,000.00
Rp 22,000.00 Rp 46,151,820.00
Rp 11,168.00 Rp 4,400,080.32 393.99
Rp 5,000.00 Rp 1,925,000.00
Rp 1,500,000.00 Rp 1,500,000.00
Rp 16,250.00 Rp 162,500.00
Rp 180,000.00 Rp 900,000.00
Rp 24,000.00 Rp 144,000.00
Rp 35,000.00 Rp 1,050,000.00
Rp 150,558,400.32

Rp 450,000.00 Rp 20,790,000.00
Rp 350,000.00 Rp 6,737,500.00
Rp 4,000.00 Rp 8,391,240.00
Rp 5,000.00 Rp 1,969,950.00
Rp 3,000.00 Rp 1,155,000.00
Rp 300,000.00 Rp 300,000.00
Rp 135,000.00 Rp 1,676,700.00
Rp 41,020,390.00
34
Rp 44,200,000
Rp 21,070

40
Rp 4,400,000
Rp 11,168

16250

Rp 198,472,790.32