Professional Documents
Culture Documents
Pub Integral-Logistics-Management Removed
Pub Integral-Logistics-Management Removed
the work centers are monitored and adjusted. This type of planning
provides a production simulation, that is, an actual working
program for the coming days, weeks, or months, according to the
planning horizon. See Section 13.3.1.
• Order-oriented finite loading ensures that as many orders as
possible are executed on time with low levels of goods in process.
Orders are scheduled in their entirety, one after the other, in the
time periods. The objective is to find priority rules that will enable
as many orders as possible to be scheduled. Those orders that can-
not be scheduled for completion on time by a computerized algor-
ithm are highlighted for attention by the planner, who may decide
to change order completion dates. This technique is a commonly
used technique for finite loading. See Section 13.3.2.
• As bottlenecks control the throughput of a production system,
constraint-oriented finite loading plans orders around bottleneck
capacities. It follows a theory of constraints (TOC) approach. An
application of this is drum–buffer–rope. Work centers feeding
bottlenecks should be scheduled at the rate the bottleneck can
process. A time buffer inventory should be established before the
bottleneck. A space buffer should be established after the bottle-
neck. Work centers fed by the bottleneck have their throughput
controlled by the bottleneck. Another application is the optimized
production technology (OPT) technique. First, only orders with a
minimum batch size are generated. These lots then come together
at bottleneck capacities, but are kept separate for the upstream and
downstream operations. Then, operations at the bottleneck
capacities are scheduled. Operations before the bottleneck are then
scheduled backward, while later ones are scheduled forward and
planned using normal lead times. See Section 13.3.3.
• Load-oriented order release (Loor) has high load as its primary
objective. Equally important are its secondary objectives of low
levels of work-in-process, short lead times in the flow of goods,
and delivery reliability. The aim of this heuristic technique is to
adapt the load to the capacity that is actually available. Thanks to a
heuristic, the matching of load to capacity can be limited to one
time period. See Section 14.1.2.
• Capacity-oriented materials management (Corma) is an operations
management principle that enables organizations to play off work-
in-process against limited capacity and lead time for customer
production orders. Corma makes intelligent use of critical capacity
that is available short term, by releasing stock replenishment
orders earlier than needed. This in turn provides for optimal
280 4 The MRP II / ERP Concept: Business Processes and Methods