PHỤ LỤC 1. MẪU PHIẾU THAO TÁC

CHALEUN SEKONG
ENERGY- NK3 HPP
OPERATION SHEET
OPERATION WORKSHOP

Operation ticket name: Isolate MC 941 for repair................................................................................


Vote writer: .......................................................... Position:...................................................................
Vote reviewer: ...................................................... Position:..............................................................
Vote Supervisor: ..................................................Position:..............................................................
.....................................................................................................................................................................
Vote operator: …...................................................... Position:...............................................................
.....................................................................................................................................................................
Purpose of operation: Isolate MC 941 for repair........................................................
Intend time:
Begin: .................... h .......... Day..................Month ............... Year....................................................
End: ……........... h ........... Day ..................Month ............... Year ...................................................
The unit recommends the operation: Repair workshop.............................................................................
Necessary conditions for implementation: (if any)
1. ...............................................................................................................................................................
2.................................................................................................................................................................
3.................................................................................................................................................................
Note: (if any)
1..................................................................................................................................................................
2..................................................................................................................................................................
3..................................................................................................................................................................
3..................................................................................................................................................................
Vote: / /

Page number: /

Delivery and acceptance of electrical lines and equipment before operation: (if any)
Time Workshop Full name Content

Sequence of operation items:


Location Sequence of operations Time Person

Item Get
Step Content Made Begin End Command
order

I NK3 1 Ask for A0 and stop generating


units H1, H2, H3
2 Check MC901, MC902,
MC903 and QE1, QE2, QE3
open well
3 Convert self-use to region grid
or diesel generator
4 Isolate the control source and
resources and take MC901 to
the test location
5 Isolate the control source and
resources and take MC902 to
the test location
6 Isolate the control source and
resources and take MC903 to
the test location
7 Open MC941, Isolate control
source, power source and take
to test location
8 Open MC942, Isolate control
source, power source and take
to test location
9 Open MC971, Isolate control
source, power source and take
to test location
10 Open MC972, Isolate control
source, power source and take
to test location
Vote: / /

Page number: /

11 Open MC931, Isolate control


source, power source and take
to test location
12 Open MC932, Isolate control
source, power source and take
to test location
13 Check MC Q01 is openning,
Isolate control source, power
source and take to test location
14 Check MC 941 has no power

15 Close DTĐ 941-38

16 Open AB TUC91

17 MC 941 mobile grounding on


the other side
18 Implement safety measures,
post signs, barricades and
allow the work team to work

Delivery and acceptance of electrical lines and equipment after operation: (if any)
Time Workshop Full name Content
Vote: / /

Page number: /

Day.........Month........Year....... Day.........Month........Year.......

Vote writer Vote reviewer

(Sign and write full name) (Sign and write full name)

Abnormal events during operations:………………………………….................................................


……………………………………………………………………………………………………………
Person performing the operation
Day.........Month........Year.......

Supervisor The operator

(Sign and write full name) (Sign and write full name)

Diagram: (attached if necessary)