Professional Documents
Culture Documents
AAC-FM-104 Rev. 0 01.02.15 Weekly Progress Report
AAC-FM-104 Rev. 0 01.02.15 Weekly Progress Report
AAC-FM-104 Rev. 0 01.02.15 Weekly Progress Report
REPORT NO. 04
ENGINEERING
PLANNED = 87.65%
ACTUAL = 24.68%
MATERIAL SUBMISSION
PLANNED = 57.78%
ACTUAL = 30.37%
CONSTRUCTION
PLANNED = 1.26%
ACTUAL = 1.25%
COMMISSIONING
PLANNED = 0.00%
ACTUAL = 0.00%
MANDAYS
Budget : 37,966
Utilized : 477
%Utilized : 1.25%
Material submittals :
Neutralization tank
Lighting Control System
Drawing submittals :
Thermocol fixing & conduting for Domestic water tank- Main building
Grid (G-H/7)
Thermocol fixing & conduting for Lift 1 - Main building Grid( C-D/2)
Sleeve fixing for electrical works at Sump pit 3 Grid (F-G/3-4)
Puddle flange fixing for Irrigation water tank at Basement floor
Puddle flange fixing for Retaining wall at Basement floor Grid ( H-J/7)
Sleeve pipe fixing for Sump pit 3 and sump pit 4 at Basement floor
Thermocol fixing & conduting for Lift 4 at Auditorium
Puddle flange fixing for Stair 1 and retaining wall at Basement floor
(Grid K-J/7-8)
Puddle flange fixing for Retaining wall at Auditorium Grid (A-B/7-6)
Material submittals :
Vibration Isolators
Expansion Tank
Isolator
DOC. NO. AAC/FM/104
REV. 0 / DATE: 01-02-15 5
Variable Frequency drive (VFD)
Drawing submittals :
4. AREA OF CONCERN
PHOTOGRAPHS