WEEKLY PROGRESS REPORT

CONSTRUCTION OF NEW COLLEGE OF


PHARMACY BUILDING,
QATAR UNIVERSITY

REPORT NO. 04

From 31st Jan to 5th Feb 15

SUB CONTRACT NO. : HQPP0099


CLIENT : QATAR UNIVERSITY
CONSULTANT : KHATIB & ALAMI
CONTRACTOR : SHAPOORJI PALLONJI QATAR WLL

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 1
1. EXECUTIVE SUMMARY

ENGINEERING
PLANNED = 87.65%
ACTUAL = 24.68%

MATERIAL SUBMISSION
PLANNED = 57.78%
ACTUAL = 30.37%

CONSTRUCTION
PLANNED = 1.26%
ACTUAL = 1.25%

COMMISSIONING
PLANNED = 0.00%
ACTUAL = 0.00%

MANDAYS

Budget : 37,966
Utilized : 477
%Utilized : 1.25%

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 2
2. IMPORTANT ACHIEVEMENTS OF THIS WEEK

 Thermocol fixing & conduting for Stair case 2 retaining wall at


Basement floor
 ELV'S point relocated for lift 3 as per consultant comment at Basement
floor
 Thermocol fixing & conduting for Electrical provision in Stair case 2 and
pump room retaining wall at Basement floor
 Female toilet columns H.D point relocated at Auditorium
 Earth valve testing from consultant at Basement floor
 Puddle flange shifting for domestic water tank at Basement floor
 Thermocol fixing & conduting for Fire alram point & power socket to
Domestic water tank at Basement floor
 Additional Thermocol fixing & conduting for Stair case 3 & Lift 3 at
Basement floor
 Thermocol fixing & conduting for LCP panel to Domestic water tank
retaining wall at Basement floor
 Electrical room CBS point relocated at Basement floor
 Sleeve fixing for lift 1 and stair case 2 at Basement floor
 Marking & installation of UPVC pipes for sump pit at Basement floor
 Thermocol fixing and conduit rising for lighting protection system at
Basement floor

Material submittals :

 Neutralization tank
 Lighting Control System

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 3
Resubmittals :
 HDPE pipes and Fittings for Kitchen waste and Laboratory drainage

Drawing submittals :

 Overall ground floor fire protection works


 Ground floor fire protection works part-1
 Ground floor fire protection works part-2
 Ground floor fire protection works part-3
 Ground floor fire protection works part-4
 Overall ground floor water supply layout
 Ground floor water supply layout part-1
 Ground floor water supply layout part-2
 Ground floor water supply layout part-3
 Ground floor water supply layout part-4
 Ground floor water supply layout part-5
 Overall ground floor drainage layout
 Ground floor drainage layout part-1
 Ground floor drainage layout part-2
 Ground floor drainage layout part-3
 Ground floor drainage layout part-4
 Ground floor plan fire alarm containment layout
 Ground floor plan fire alarm containment layout (sheet 1 of 4)
 Ground floor plan fire alarm containment layout(sheet 2 of 4)
 Ground floor plan fire alarm containment layout(sheet 3 of 4)
 Ground floor plan fire alarm containment layout(sheet 4 of 4)
 Ground floor plan bms system containment layout
 Ground floor plan bms system containment layout(sheet 1 of 2)
 Ground floor plan bms system containment layout(sheet 2 of 2)
DOC. NO. AAC/FM/104
REV. 0 / DATE: 01-02-15 4
Resubmittals :

 Overall ground floor plan mep builders work layout


 Ground floor plan mep builders work layout part-1
 Ground floor plan mep builders work layout part-2
 Ground floor plan mep builders work layout part-3
 Ground floor plan mep builders work layout part-4

3. CRITICAL ACTIVITIES PLANNED FOR NEXT MONTH

 Thermocol fixing & conduting for Domestic water tank- Main building
Grid (G-H/7)
 Thermocol fixing & conduting for Lift 1 - Main building Grid( C-D/2)
 Sleeve fixing for electrical works at Sump pit 3 Grid (F-G/3-4)
 Puddle flange fixing for Irrigation water tank at Basement floor
 Puddle flange fixing for Retaining wall at Basement floor Grid ( H-J/7)
 Sleeve pipe fixing for Sump pit 3 and sump pit 4 at Basement floor
 Thermocol fixing & conduting for Lift 4 at Auditorium
 Puddle flange fixing for Stair 1 and retaining wall at Basement floor
(Grid K-J/7-8)
 Puddle flange fixing for Retaining wall at Auditorium Grid (A-B/7-6)

Material submittals :

 Vibration Isolators
 Expansion Tank
 Isolator
DOC. NO. AAC/FM/104
REV. 0 / DATE: 01-02-15 5
 Variable Frequency drive (VFD)

Drawing submittals :

 Schedule of equipments drainage system


 Overall lower roof floor drainage layout
 Overall upper roof floor strom water layout
 Upper roof floor drainage layout part-1
 Upper roof floor drainage layout part-2
 Upper roof floor drainage layout part-3

 Overall lower roof floor strom water layout


 Lower roof floor strom water layout part-1
 Lower roof floor strom water layout part-2
 Lower roof floor strom water layout part-3
 Telephone & data structured cabling system riser diagram
 Db schedule sheet 4 of 4

4. AREA OF CONCERN

 RFI Response awaiting from SPQ


 Awaiting Material/shop drawings approvals

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 6
5. UPDATED DRAWING REGISTER [Attached]

SL. NO. STATUS DETAILS NOS. %


1 SUBMITTED 116 24.68%
2 APPROVED 16 13.8%
3 REVISED AND RESUBMIT 37 31.90%
4 RESUBMITTED 30 25.86%
5 PENDING FROM CONSULTANT 33 28.44%
6 REJECTED 0 0.00%
7 PENDING 354 75.31%
8
TOTAL 470

6. UPDATED MATERIAL SUBMITTAL / PROCUREMENT REGISTER

SL. NO. STATUS DETAILS NOS. %


1 SUBMITTED 41 30.37%
2 APPROVED 12 29.26%
3 REVISED AND RESUBMIT 10 24.39%
4 RESUBMITTED 5 12.19%
5 PENDING FROM CONSULTANT 11 26.82%
6 REJECTED 3 7.31%
7 PENDING 94 69.26%

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 7
8
TOTAL 135

7. MAN POWER STATUS – ( 31st Jan – 5th Feb 15 )

PLANNED MAN ACTUAL MAN


POWER POWER
ELECTRICIAN 17 3
ELEC.HELPER 17 1
PLUMBERS 6 2
PLUM.HELPERS 6 2
PIPE FITTER 0 0
PIPE. HELPER 0 0
DUCTMAN 0 0
DUCT.HELPER 0 0
INSULATOR 0 0
INSULATOR HELPER 0 0
A/C TECHNICIAN 0 0
A/C TECHNICIAN HELPER 0 0
CHILL WATER PIPE FITTER 0 0

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 8
WEEKLY PROGRESS

PHOTOGRAPHS

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 9
Puddle flange installation to Domestic water tank

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 10
Thermocol fixing & conduting for domestic water tank

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 11
Thermocol fixing & conduting for Stair case 1

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 12
Thermocol fixing & conduting for Hd point to Female toilet column at Auditorium

Blinding works in progress for Zone no 02 & 04

WATER PROOFING WORKS IN PROGRESS IN ZONE NO. 01

DOC. NO. AAC/FM/104


REV. 0 / DATE: 01-02-15 13

Footing (Concreting) in Zone no. 01


Basement Column reinforcement
Basement Columnworks in progress
Rebar Works ininprogress
Zone no.in
01Zone no. 04