ID Task Name Work Successors Predecessors Resource Names Resource Resource Start Finish Early Start Early Finish

Resource Start Finish Early Start Early Finish Duration


Mar '24 Apr '24
Initials Initials 31
0 Small Building 90 days Mon 15/04/24 Mon 15/07/24 Mon 15/04/24 Mon 15/07/24 76 days
Construction
1 Excavate 5 days 2 Project Manager PM PM Mon 15/04/24 Fri 19/04/24 Mon 15/04/24 Fri 19/04/24 5 days
2 Lay foundation 8 days 3,4 1 Engineer EN EN Sat 20/04/24 Mon 29/04/24 Sat 20/04/24 Mon 29/04/24 8 days
3 Rough Plumbing 5 days 8 2 Foreman FR FR Tue 30/04/24 Mon 06/05/24 Tue 30/04/24 Mon 06/05/24 5 days
4 Frame 10 days 5,6,7 2 Skilled Laborer 1 SL1 SL1 Tue 30/04/24 Sat 11/05/24 Tue 30/04/24 Sat 11/05/24 10 days
5 Finish Exterior 8 days 8 4 Skilled Laborer 2 SL2 SL2 Mon 13/05/24 Tue 21/05/24 Mon 13/05/24 Tue 21/05/24 8 days
6 Install HVAC 4 days 8 4 Skilled Laborer 3 SL3 SL3 Mon 13/05/24 Thu 16/05/24 Mon 13/05/24 Thu 16/05/24 4 days
7 Rough Electric 6 days 8 4 Skilled Laborer 4 SL4 SL4 Mon 13/05/24 Sat 18/05/24 Mon 13/05/24 Sat 18/05/24 6 days
8 Sheet Rock 8 days 9,10 3,5,6,7 Unskilled Laborer 1 US1 US1 Wed 22/05/24 Thu 30/05/24 Wed 22/05/24 Thu 30/05/24 8 days
9 Install cabinets 11 days 11 8 Unskilled Laborer 2 US2 US2 Fri 31/05/24 Thu 13/06/24 Fri 31/05/24 Thu 13/06/24 11 days
10 Paint 10 days 12 8 Unskilled Laborer 3 US3 US3 Fri 31/05/24 Tue 11/06/24 Fri 31/05/24 Tue 11/06/24 10 days
11 Final Plumbing 4 days 13 9 Unskilled Laborer 4 US4 US4 Fri 14/06/24 Tue 18/06/24 Fri 14/06/24 Tue 18/06/24 4 days
12 Final Electric 4 days 13 10 Unskilled Laborer 5 US5 US5 Thu 13/06/24 Mon 17/06/24 Thu 13/06/24 Mon 17/06/24 4 days
13 Install Flooring 7 days 11,12 Unskilled Laborer 6 US6 US6 Wed 19/06/24 Wed 26/06/24 Wed 19/06/24 Wed 26/06/24 7 days
14 FINISH 0 days Mon 15/07/24 Mon 15/07/24 Mon 15/07/24 Mon 15/07/24 0 days

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Late

Project: Small Building Construc Milestone Manual Task External Tasks Progress
Date: Thu 18/04/24 Summary Duration-only External Milestone Manual Progress

Project Summary Manual Summary Rollup Deadline Slack

Inactive Task Manual Summary Critical

Page 1
Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27

Project Manager
Engineer
Foreman
Skilled Laborer 1
Skilled Laborer 2
Skilled Laborer 3
Skilled Laborer 4
Unskilled Laborer 1
Unskilled Laborer 2
Unskilled Laborer 3
Unskilled Laborer 4
Unskilled Laborer 5
Unskilled Laborer 6
15/07

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Late

Project: Small Building Construc Milestone Manual Task External Tasks Progress
Date: Thu 18/04/24 Summary Duration-only External Milestone Manual Progress

Project Summary Manual Summary Rollup Deadline Slack

Inactive Task Manual Summary Critical