Date: 9/6/2023

Work: Proposed Development commercials at Kitengela Balozi road


client:Serenidad Ltd
P. O BOX
Thank you for inviting us to work for you.
Our quotation is as follows:-

Work description Amount


1 Plot excavation 1.5m maximum and tipping the unwanted soil 300,000.00
(Depending on ground conditions)
2 Setting out (transferring plan to the ground) 50,000.00
3 Trench excavation 130,000.00
Materials and quantities Quatity (@)Rate
1 White wash 5 pcts 300 per pct 1,500.00
2 Props 150 pcs 180 per pc 27,000.00
3 Nails 3” 25 kgs 180 per kg 4,500.00
4 4'' 25 kgs 180 per kg 4,500.00
5 Site store 55,000.00

Foudation
Blinding materials for the trenches and labour
1 Ballast 5 trucks 25,000 per 20 tons lorry 125,000.00
2 Sand 4 trucks 31,000 per 20 tons lorry 124,000.00
3 Cement 250 bags 650 per bag 162,500.00
Labour 90,000.00

Steel fixing
1 Bars D-12 for pilars and base 80 pcs 1,500 per pc 120,000.00
3 Rings/ footing D-8 180 pcs 690 per pc 124,200.00
Footing bars D-10 rings 180 pcs 1,000 per pc 180,000.00
4 Binding wire 6 rolls 3,000 per roll 18,000.00
Labour steel fixing 150,000.00

Foundation Trenches /concrete casting


1 Ballast 6 trucks 25,000 per 20 tons lorry 150,000.00
2 Sand 4 trucks 31,000 per 20 tons lorry 124,000.00
3 Cement 250 bags 650 per bag 162,500.00
Labour 120,000.00

Foundation walling
1 Cement 220 bgs 650 per bag 143,000.00
2 Stones 9,000 ffts 500 per lorry (25,000) 396,000.00
3 Hoop iron 12 rolls 3,000 per roll 36,000.00
4 Wheel barrows 10 pcs 4,500 per pc 45,000.00
5 Buckets 15 pcs 300 per pc 4,500.00
6 marine boards 20 pcs 2,600 per pc 52,000.00
7 Timber 6x1 3,500 ffts 35 per fft 122,500.00
8 Spades 15 pcs 550 per pc 8,250.00
9 Panga 3 pcs 450 per pc 1,350.00
10 Walling labour 350,000.00

kathoz building co.ltd


Murrum Filling
1 Estimated murram 95 lorries 6,000 per lorry 570,000.00
2 Compactor on site 10,000.00
3 Labour marram filling using shovel 95,000.00

Slab laying
1 Polythene paper 15 rolls 3,000 per roll 45,000.00
2 B.R.C size A-65 48m 12 rolls 14,500 per roll 174,000.00
3 Antitermite 6 litres 2,000 per ltr 12,000.00
4 Ballast 8 trucks 25,000 per 20 tons lorry 200,000.00
5 Sand 6 trucks 31,000 per 20 tons lorry 186,000.00
6 Cement 450 bags 650 per bag 292,500.00
7 Pointing materials (plumbing) 60,000.00
8 Labour 170,000.00

Building
1 Machine cut 9''x9'' 12,000 pcs 50 per pc 600,000.00
2 Cement 300 bags 650 per bag 195,000.00
4 Hoop iron 15 rolls 3,000 per roll 45,000.00
5 Water 60,000.00
6 Sand 12 trucks 31,000 per truck 372,000.00
7 Building and Pillars, formwork and casting labour 400,000.00

Ring Beam
1 Rings D-8 200 pcs 690 per pc 138,000.00
2 Main bars D-12 220 pcs 1,500 per pc 330,000.00
4 Labour 125,000.00
7 Cement 100 bags 650 per bag 65,000.00
8 Ballast 3 trucks 25,000 per truck 75,000.00
9 Sand 2 trucks 31,000 per truck 62,000.00
10 Polythene papers 3 rolls 3,000 per roll 9,000.00
4 Labour 90,000.00

Roofing materials and labour


1 Timber 4x2 10,000 ffts 70 per ft 700,000.0
2 3x2 9,500 ffts 28 per ft 266,000.0
3 2x2 7,500 ffts 25 per ft 187,500.0
4 Facia Board 600 ffts 120 per ft 72,000.0
5 Nails roofing 300 kg 250 per kg 75,000.0
6 Normal 3'' nails 200 kg 180 per kg 36,000.0
7 ''4'' nails 250 kg 180 per kg 45,000.0
7 Fascia board nails '2'' nails 25 kg 200 per kg 5,000.0
8 Roof covering
Decra tiles 1500X600mm size 2,000 pcs 1,100 per pc 2,200,000.0
9 Soft hoop iron 25 kgs 200 per kg 5,000.0
10 Ridge caps 95 pcs 680 per ft 64,600.0
11 valleys 120 pcs 700 per pc 84,000.0
Labour for roofing 400,000.0

kathoz building co.ltd


GRAND TOTAL 11,901,900.00

kathoz building co.ltd


NB: This quotation is for the structure only. The finishing will be quantified after the
completion of the skeleton
The client shall provide the store keeper
The cost of materials is prior to change.

Yours :Muinde
Director for Planswift Building and Construction Ltd
Cell : 0727948802
Thank you