Professional Documents
Culture Documents
2B Castro CT222 Typings
2B Castro CT222 Typings
2B Castro CT222 Typings
From the Schedule Phase, there are four output that can be obtained:
1. The schedule of activities in the network showing the following:
a. The Critical Activities
b. The Earliest Start date for each activity
c. The Earliest Finish date for each activity
d. The Latest Start date for each activity
e. The Latest Finish date for each activity
f. The Float which refers to the amount of extra time available for an activity.
2. A Bar Chart or a Time Scaled Network (arrow diagram network for the project).
3. A Resource Analysis showing the number and kind of resources, man power, equipment
and others that are required for each day of the project.
4. A Cash Requirement prediction indicating how much cash to be disbursed for the job and
the amount of money that will be collected as a result of work accomplishment.
The Control Monitor Phase uses actual data which includes:
1. Additions to the project - This refers to the new activities.
2. Deletion from the project
3. Changes as to duration, description, trade indicators, cost estimates or resource estimates.
4. Actual starting dates
5. Actual finishing dates.
The Output Phase consists of the following:
1. Time status report
2. Revised schedules
3. Revised Bar Charts/ Arrow Diagram or Network
4. Revised resource analysis
5. Revised cash flow predictions
6. Cost status reports
There are three major reasons for construction failure:
1. Unbalanced organization due to lack of planning and scheduling
2. Lack of financial planning
3. Poor cost control
ILLUSTRATION 5-7
From the following network, activities a and b both precede activity e. But d's start is dependent
only on completion of activity b, and not on activity a's. Similarly e is dependent on c.
FIGURE 5-16
ILLUSTRATION 5-8
Starting and ending arrows are sometimes used during development of a network diagram for more
clarity.
FIGURE 5-17
Rules for Numbering Events in a Network Diagram
1. All events should be numbered starting from left to right.
2. No event number should be lower than the number of event preceding it (left to right
direction).
3. Event number shall increase from left to right.
Events should be numbered from top to bottom. Similarly, Increasing should be consistent
from top to bottom or from bottom to top When a group of N parallel activities starts from the
same event and ends with the same subsequent event, N-1 parallel activities in the group should
be joined to the subsequent event with dummy activities for identification purposes.
FIGURE 5-18
ILLUSTRATION 5-9
From the following table of information, (a) Draw a precedence diagram, (b) Find the
Critical Path, (c) Determine the expected duration of the project.
Activity Precedes Expected time (days)
a c, b 4
c d 12
d i 2
b i 5
e f 3
f j 8
i j 12
j end 9
g h 1
h k 3
k end 15
SOLUTION
1. Use pencil in constructing precedence diagram.
2. Activities without predecessors are placed at the start of the network (left side)
3. Activities with multiple predecessors are located at path intersections.
4. Start with a single node and end with a single node
5. Avoid having paths that cross with each other.
6. Number nodes from left to right
7. Activities should go from left to right.
8. Use only one arrow between any pair of nodes.
Examining the table of informations above; Letters a, e and g are absent in the precedes
column.
Therefore, these are the activities without predecessors.
a precedes c, d
e precedes f
g precedes h
The next question is to find the Critical Path.
Examining the above network diagram we have the following route or path.
Path:
a, c, d, i,j = 4+12+2+12+9 = 39"
a, b, i,j = 4+5+12+9 = 30
e. f.j = 3+8 +9 = 20
g, h, k = 1+3+15= 19
From the above tabulation, the highest number is 39, thus, Path a, c, d, i, j is the Critical Path
which means the longest route.
Similarly, the duration of the project is 39 which could be in terms of days, weeks or months.
Problem Exercise
(1.) Number the events of the following networks in proper sequence
Problem Exercise
(3.) Construct a Network Diagram from the following informations:
Activity Precedes Expected time (weeks)
a c 15
b c, d 13
c e 8
d end 5
e end 3
(4.)
Activity Precedes Expected time (days)
f g, h 10
g i, j 10
h j 8
i end 6
j k 12
k end 7
(5.) From the following informations, draw the CPM network and number the events in their proper
sequence.
*A, B and C are starting activities and may begin at the same time.
*D and E follows A and cannot start until A is completed.
*G follows and depends on C.
*F is dependent on the completion of B and D.
*G and F must be done before H can start
*J also depends on G and F and it is an ending activity.
*I is also an ending activity but it cannot start until E and H are completed
(6.) Draw the network diagram of the following information.
A-is the first job of the project
O and N are the two final jobs for project completion
K -Precedes 0
N - follows L and M
J - restricts the start of K and M
C and B depends on the completion of A
D follows B and may go on in parallel with C and E
E follows C
I - restricts the start of J and L
H and G also restrict K and M
F must precede G and may go in parallel with H
E and D restrict H and I
C-must precede F.
(7.) Draw the Network Diagram of the following information:
a. At the start of the project, each of 3 separate activities A, B and C may or may not begin
and progress concurrently.
b. D may begin until A is completed.
c. E may also begin only after completion of A
d. F follows activity of B.
e. G cannot be started until both E and F are completed.
f. Completion on both G and H allow J to start.
g. The start of J is further restrained by a notice of completion of D.
h. K follows D and culminates in the same (completion) as event J.
(8.) Draw the following network:
a. G follows F but precede H
b. G follows D but precede J
c. M follows H but precede L
d. K follows A but precede L
e. F follows A
f. A and D start at the same time
g. J and L terminate at the same time.
(9.) From the following data, construct a network diagram.
Activity Precedes
a c
b d, e
c f
d g
e g
f end
g end
Scheduling - is only secondary to planning. It is the process of allocating calendar dates to jobs
based on the approved plan.
General time boundaries are determined for each job during the process of planning.