Milestone Activities for 3 sites Amount Planned Start Date Planned Finish Date
Existing Buildings Survey/Site Plan 14-Jan-19 29-Jan-19
Preliminary Architectural Concept Design 14-Jan-19 4-Feb-19
Review by UNOPS 4-Feb-19 10-Feb-19
1 30 % of contract price
Final Architecture Concept Design 11-Feb-19 22-Feb-19
8-Mar-19
12-Mar-19
Delayed due to
freezing of plans.