Professional Documents
Culture Documents
2022 Maintenance Pillar Handbook (150-200)
2022 Maintenance Pillar Handbook (150-200)
2022 Maintenance Pillar Handbook (150-200)
For deep cleaning and tagging, downtime of about 4 to 6 hours is required. As the machine is deep
cleaned by the team, the machine is inspected and defects identified. The technician/artisan in the team
plays an important role in coaching the operator and team leader as to what is a defect. Defects such as
missing bolts, loose mechanisms, leaks, damaged electrical cables, collapsed bearings, dirty areas,
unsafe parts of the machine etc. are tagged as a defect.
The tag is a visual indicator of a defect. It helps make sure that a defect no matter how small is clearly
visible. When tagging, it is important that the tag is placed on the machine in such a way that it does not
interfere with the normal operation of the machine. The tag can be placed close to where the defect is
and not necessarily on the defect if doing this will interfere with the working of the machine.
Confidential ©AB InBev 2021. All rights reserved. Page 150 of 282
MAINTENANCE PILLAR BOOK
Figure 20 is an example of a defect identification tag that can be used for Autonomous Operations
tagging. It is important that the Autonomous Operations tag is different from the 5S red tag. The 5S red
tag is used to identify items that should not be in an area. An Autonomous Operations tag is used to
identify defects on a machine.
At the end of the initial or first deep clean and tag, a large number of tags would have been identified.
The next step will explain how these tags will be dealt with. However of critical importance is that the
deep clean and tag step is not done once only. It is repeated weekly so that the entire process area and
machine is deep cleaned and any defects that were missed the first time are picked up on the next
successive deep cleaning. Repeating the deep cleaning and tagging activity every week for two to three
months will also ensure that all team leaders and operators from all shifts get involved in the
Autonomous Operations process. Eventually, after several weeks of cleaning and tagging, no more new
tags will be found despite the machine been deep cleaned. This indicates that all defects have been
identified.
Confidential ©AB InBev 2021. All rights reserved. Page 151 of 282
MAINTENANCE PILLAR BOOK
All the tags raised during the deep clean and tag activity will need to be reviewed by the team and a
decision made as to how they need to be fixed. For example, if a part is loose because it is missing a
bolt, then the action is simply to replace the missing bolt and fasten the loose part in position. This action
is captured on the tag list as per the example in Figure 22.
However just fixing the defect identified by the tag is not good enough; the root cause of the defect
needs to be fixed. The team therefore needs to analyze each defect using a simple 5 why analysis in an
attempt to establish what the root cause of the defect it. It may not be possible to find the root cause of
some of the tags, but for others the root cause can be found. Once the root cause is found, an action
needs to be put in place to resolve the root cause. Therefore for every tag there will be two actions; one
to deal with tag (e.g. missing bolt) and one to deal with the root cause of the tag (e.g. create a torque
specification for the bolt). The action for the root cause is also captured on the tag list as per Figure 22.
Confidential ©AB InBev 2021. All rights reserved. Page 152 of 282
MAINTENANCE PILLAR BOOK
Dirty, dangerous, and difficult tags deserve special mention, as they are issues that directly affect the
operator. By addressing these tags, the life of the operator will be made easier and safer. Therefore,
specific care must be taken that the dirty, dangerous and difficult tags are highlighted and that the
resolution to these tags is decided in collaboration with the operator:
• Dirty – the first prize is to eliminate the source of contamination. If an area does not get dirty,
then it does not need to be cleaned. If a source of contamination cannot be eliminated then it
must be contained. In other words rather than having the contamination spreading across the
entire machine, it can be collected in a container and easily disposed of. Finally if source of
contamination cannot be contained then cleaning is required; however consideration should be
given to making cleaning easier such as providing a special tool to assist with the cleaning. All
these options will need to be discussed and a solution defined for each tag related to dirty.
• Difficult – tags related to difficult are those situations where tasks are difficult to execute. For
example when a machine is shutdown, the air supply needs to be turned off. However, the air
supply is 2 meters in the air requiring that the operator has to find a ladder, climb onto it, turn the
valve of and then put the ladder back in its place. It would be much easier if the valve were
moved to a position where the operator can reach it without a ladder. Difficult tags are discussed
within the team and various solutions are implemented to reduce difficult tasks. Visual controls
can really help with difficult tasks. For example if a part of the machine needs to be inspected by
removing some guarding, this can be made easier by making the guard transparent and adding
green and red indicators.
• Dangerous – tags related to dangerous are eliminated or controlled. For example, a nip point
when identified is then properly guarded.
As per Figure 23, dirty, dangerous and difficult tags will have their own individual tag list on the
Autonomous Operations activity board.
Figure 23: Dirty, dangerous and difficult tags have their own dedicated tag lists
Confidential ©AB InBev 2021. All rights reserved. Page 153 of 282
MAINTENANCE PILLAR BOOK
As various solutions to the root causes of tags are defined, a record of them needs to be kept. These
solutions are documented on an improvement record an example of which is shown in Figure 25.
Confidential ©AB InBev 2021. All rights reserved. Page 154 of 282
MAINTENANCE PILLAR BOOK
One of the tools used to deal with sources of contamination (i.e. dirty tags) is the contamination map.
Figure 26 shows an example of a contamination map. To create a contamination map, the locations of
the various dirty tags are plotted on a drawing of the process area/machine. The contamination map
helps visualize where the dirty areas are and in fact will then point to a generic problem area i.e. the
area where lots of dirty tags exist. Solutions to these sources of contamination can then be developed.
Confidential ©AB InBev 2021. All rights reserved. Page 155 of 282
MAINTENANCE PILLAR BOOK
By the end of the Analyze and Solve step, there will be:
• A list of dirty tags with their root causes identified. There will be actions to address the dirty tag
and its root cause. A contamination map will help visualize the dirty parts of the machine.
• A list of difficult tags with their root causes identified. There will be actions to address the difficult
tags and its root cause.
• A list of dangerous tags and their root causes identified. There will be actions to address the dirty
tag and its root cause
• A list of all other machine tags with their root causes identified. There will be actions to address
these tags and their root causes.
The Autonomous Operations activity board should be updated with all the relevant tables and charts and
should look like Figure 27.
Confidential ©AB InBev 2021. All rights reserved. Page 156 of 282
MAINTENANCE PILLAR BOOK
Figure 27: Autonomous Operations activity board updated during the analyze and solve step
The work to analyze the tags, root causes and deciding on actions to resolve them is done during the 4
to 6 hour period that the line has stopped for Autonomous Operations activities. Some of this time is
spent for deep cleaning and some of this time on analyzing and categorizing the tags.
In order to manage the tag lists the following will need to be done:
• The tag lists on each activity board associated with an Autonomous Operations program must be
kept up to date by the team. This list is reviewed weekly during the Autonomous Operations
Confidential ©AB InBev 2021. All rights reserved. Page 157 of 282
MAINTENANCE PILLAR BOOK
activity and any completed actions are recorded. Additionally new tags and actions are added to
the tag list.
• Machine related tags must be raised as a work order in the Computerized Maintenance
Management System (CMMS) and dealt with through this system. Each tag has a unique
reference number and this reference number is captured in the CMMS system so that progress
can be tracked.
For clarity, the steps of Deep Cleaning and Tagging, Analyze and Solve Tags and Fix Tags and Root
Causes all take place at the same time. Time allocated to Autonomous Operations activities each week
needs to be sufficient such that all three steps can be performed. Typically, 6 hours per week needs to
be allocated to Autonomous Operations activities, 4 hours for deep cleaning and tagging and another 2
hours for reviewing tags and implementing solutions to the tags and root causes. Note that the amount
of time spent on deep cleaning and tagging will decrease over time as the initial dirty and grime is
removed and the machine condition is improved. Thus, several weeks into the Autonomous Operations
implementation program, less time can be spent on deep cleaning and tagging and more time on
analyzing and fixing tags. This time can be slotted into the maintenance stop of the process area but
care must be taken that the routine maintenance activities of the process area/machine are not
compromised. Fixing of tags does not only have to take place during the Autonomous Operations stop.
They can be fixed anytime an opportunity presents itself.
At this stage of the Autonomous Operations program, the operator has little technical skill and the bulk
of the technical tasks will fall to the technicians/artisans to execute. Where possible however, such
actions that are within the capability of the operator should be allocated to the operator. Things like
updating the activity board, updating operating procedures, applying visual control etc. can be allocated
to the operator to close of the tag action list.
In order to track the closure of tags and their root causes the following KPI’s must be measured and
displayed on the activity board.
• Number of tags raised and closed
• Number of root causes solved
• Number of dirty, dangerous and difficult improvement made
• Number of One Point Lessons or Standard Operating Procedures created or modified
• Number of maintenance schedules created or updated (mandatory)
• Progress towards achieving the goal e.g. LEF graph
Other KPI’s can be plotted, but the above is mandatory. As the fix tag and root causes step is executed,
the activity board is continuously updated.
Confidential ©AB InBev 2021. All rights reserved. Page 158 of 282
MAINTENANCE PILLAR BOOK
Figure 28: Autonomous Operations activity board updated during the fix tag and root causes step
After two to three months of deep cleaning, tagging, analyzing tags and fixing tags and root causes, a
number of things would have happened:
• The operator and technicians/artisans would have learnt the importance of cleaning and that
cleaning is inspection
• The operator having worked closely with the technician/artisan would have developed a better
understanding of how his machine works and what a defect is
• The operator and technician/artisan having worked closely together would have developed a
better relationship
• Dirty, dangerous and difficult areas would have been eliminated or addressed. As a result of this
the operators work will be much safer and easier.
• Other machine defects (such as worn parts) will be eliminated and overall the machine condition
will be ‘as new’. The performance of the machine from a reliability, waste and quality point of
view will improve.
• The root causes of many of the problems would be eliminated and systems such as
technician/artisan maintenance schedules, operating procedures and one point lessons will be in
place to systemize the solution
However, to fully sustain the improvements that have been realized through Autonomous Operations, it
is key that the operator starts to take responsibility for the certain basic maintenance tasks. In the next
step of establishing the Foundations, this will be done.
Confidential ©AB InBev 2021. All rights reserved. Page 159 of 282
MAINTENANCE PILLAR BOOK
It is key to note that cleaning, inspection and lubrication standards are created after all tags and their
root causes have been addressed. This will ensure that the dirty, dangerous and difficult areas have
been eliminated or managed and a minimal number of cleaning, inspection and lubrication tasks need to
be done. There is no point putting a cleaning standard in place if by solving a leaking valve, you can
eliminate the need for cleaning in the first place.
It is key to note that cleaning, inspection and lubrication standards are created after all tags and their
root causes have been addressed. This will ensure that the dirty, dangerous and difficult areas have
been eliminated or managed and a minimal number of cleaning, inspection and lubrication tasks need to
be done. There is no point putting a cleaning standard in place if by solving a leaking valve, you can
Confidential ©AB InBev 2021. All rights reserved. Page 160 of 282
MAINTENANCE PILLAR BOOK
The team that was involved in the Autonomous Operations activity will develop the tentative cleaning,
inspection and lubrication maintenance schedules. Collaboration of the operators and
technicians/artisans is important in this process, to ensure ownership of the operator of the cleaning,
inspection and lubrication standards. In order to do this the team needs to do the following:
• The manufacturers operating and maintenance manual will need to be reviewed to see if there
are any cleaning, inspection or lubrication tasks that the operator could be doing
• A review is made of the contamination map to identify sources of contamination that were not
eliminated. This would direct where the cleaning schedules would start.
• A review is made of existing technician/artisan maintenance schedules to see if there are any
cleaning, inspection and lubrication tasks that the operator could do
• Finally the team brainstorms other cleaning, inspection and lubrication tasks that the operator
could do and that will add value
Based upon the above process a set of inspection, lubrication and cleaning standards can be defined. It
may take several weeks of trial and improvement before the final cleaning, inspection and lubrication
standard is developed.
Cleaning, inspection and lubrication schedules must be visual i.e. they are permanently on display near
the relevant process area/machine. This will ensure that the operator, team leader, technician and or
anyone else walking by the process area/machine will be completely aware of what the status is of the
machine. A cleaning, inspection and lubrication standard must consist of the following information:
• Task
• Standard that has to be attained
• Frequency of check
• Tools to be used
• Indication that task was done e.g. operator signature
Typically, the frequency of operator cleaning inspection and lubrication activities are less than a shift,
every shift, every day or every week. Cleaning, inspection or lubrication tasks that are less frequent such
as monthly or quarterly do not have to be visually displayed but can be planned through the planned
maintenance system.
The diagram below illustrates an example of an inspection standard. A similar design can be used for
cleaning and lubrication. As the team develops and refines these cleaning, inspection and lubrication
standards, they are displayed on the Autonomous Operations activity board as per Figure 29.
Confidential ©AB InBev 2021. All rights reserved. Page 161 of 282
MAINTENANCE PILLAR BOOK
The establishment of cleaning, inspection and lubrication standards provides an ideal opportunity to
utilize visual standards:
• If a gauge needs to be checked, then make sure it is marked in green and red to indicate the
correct operating zone
• If a lubricant level needs to be checked, then the level must be marked red and green
• If a chain or belt tension needs to be checked, then the guarding can be made transparent and
the position indicated by red and green markers
• If a guard needs to be removed, then the guard can be made transparent so that checks can be
done without removing guards
• Add manually activated lights to places that are dark so that a quick visual inspection can be
performed
• If things need to be aligned, add a marker indicating the correct position
• Add color coded labels to lubrication points so that the type of lubricant that needs to be used is
clear
It is expected that during the development of cleaning, lubrication and inspection standards, effort is
made to create a corresponding set of visual standards.
Confidential ©AB InBev 2021. All rights reserved. Page 162 of 282
MAINTENANCE PILLAR BOOK
Figure 30: In this example, the stainless steel guarding at the bottom of the machine was replaced with a clear
material so that inspecting under the machine was made easier
Confidential ©AB InBev 2021. All rights reserved. Page 163 of 282
MAINTENANCE PILLAR BOOK
Figure 31: Example of the use of visual standards to highlight lubrication points and levels
Confidential ©AB InBev 2021. All rights reserved. Page 164 of 282
MAINTENANCE PILLAR BOOK
Confidential ©AB InBev 2021. All rights reserved. Page 165 of 282
MAINTENANCE PILLAR BOOK
As the cleaning, lubrication and inspection standards are developed, the Autonomous Operations
activity board is updated with the latest standard.
Confidential ©AB InBev 2021. All rights reserved. Page 166 of 282
MAINTENANCE PILLAR BOOK
Figure 34: Autonomous Operations activity board updated with cleaning, lubrication and inspection standards
Team leaders, departmental managers and maintenance managers as part of their MCRS, will need to
check that the above is in place for every process area/machine that has completed the Foundations
phase of Autonomous Operations.
Confidential ©AB InBev 2021. All rights reserved. Page 167 of 282
MAINTENANCE PILLAR BOOK
If the above conditions are sustained for several weeks, a Foundations phase audit can be performed
and the process area/machine signed off. The audit can be done by the site maintenance manager or
the plant manager. The sign off can be used as an opportunity to recognize the team for a job well done.
Once the process area/machine has been signed off, then the Autonomous Operations activity board
can be discontinued:
• The cleaning, lubrication and inspection standards can be made into a visual standalone board
as per the example in Figure 35. These need to be positioned close the to process
area/machine so that the operator is clear on the cleaning, inspection and lubrication tasks that
must be done
• A place needs to be found where blank tags can be stored. Similarly, a place needs to be found
where completed tags can be placed so that they can be collected and reviewed.
• Some of the KPI’s can be incorporated into the KPI’s for the process area/machine and tracked
and displayed the record of all the improvements made to the machine or systems (such as
maintenance schedules) should be filed for record keeping.
• The tag lists should be completely implemented and can be filed for record keeping
• The contamination map can be discarded as either all sources of contamination have been
eliminated or a cleaning standard exists.
Confidential ©AB InBev 2021. All rights reserved. Page 168 of 282
MAINTENANCE PILLAR BOOK
Confidential ©AB InBev 2021. All rights reserved. Page 169 of 282
MAINTENANCE PILLAR BOOK
Confidential ©AB InBev 2021. All rights reserved. Page 170 of 282
MAINTENANCE PILLAR BOOK
by performing basic cleaning, lubrication and inspection tasks. His work would have been made easier
because sources of contamination would have been eliminated, difficult tasks made easier and
dangerous conditions rectified.
Despite doing all of the above however, the operator’s knowledge of equipment and machines is still
quite limited and his ability to detect equipment deterioration and failure is limited by this. The aim of the
Clean and Inspect phase of Autonomous Operations is to resolve this by further developing the
operator’s technical skills.
Figure 38 shows the specific outcomes of Manage to Sustain phase as contained in the Autonomous
Operations GOP. Figure 39 illustrates the steps that need to be followed to implement the Manage to
Sustain phase.
Manage to Sustain
Confidential ©AB InBev 2021. All rights reserved. Page 171 of 282
MAINTENANCE PILLAR BOOK
Manage to Sustain
Confidential ©AB InBev 2021. All rights reserved. Page 172 of 282
MAINTENANCE PILLAR BOOK
Figure 39: Steps to be followed when implementing the Manage to Sustain Phase
Site Preparation
Commencement of the Manage to Sustain phase marks the next significant Autonomous Operations
event. The site will need to adequately prepare for this:
• Developing operator technical skills is a cornerstone of this phase of Autonomous Operations.
This can be done in-house or outsourced but the site must have a clear plan as to how this will
be done.
• Training the operators on technical skills will require about 80 hours or 10 days of training.
Operators will need to be released from the workplace. There needs to exist a plan as to how
operators released for training will be relieved on their shifts.
• Funding of the training and the relief labor needs to be identified and budgeted.
• The management routines required to oversee the implementation of Autonomous Operations on
the site needs to be established. Typically, this would be the site Autonomous Operations pillar
group, the departmental task forces and the site steering committee.
• An overall plan the implementation of the Manage to Sustain phase across the site needs to be
developed.
Once the above has been clarified by management, communication to the site can be done.
Confidential ©AB InBev 2021. All rights reserved. Page 173 of 282
MAINTENANCE PILLAR BOOK
It is estimated that all the above training will take 100 hours or 12 days to deliver.
The training will be directed toward the operators and team leaders who work in the selected process
area. The above technical training will need to be structured as follows:
• The training is formally delivered in a classroom/workshop type setting.
• The operator needs to receive a workbook or file containing all the information he was trained on.
This will allow him to review the contents if required.
• There needs to be physical examples of the various machine components for the operator to
feel, hold and work with.
• For complex machines such as pumps and motors, there needs to be cut-out models showing
the internal workings of the machine
• There needs to be failed or failing components so that the operator can see what failure looks
like
• There needs to be simple hydraulic and pneumatic circuits so that the operator can understand
Confidential ©AB InBev 2021. All rights reserved. Page 174 of 282
MAINTENANCE PILLAR BOOK
The technical skills training can be delivered in-house or outsourced to a suitable technical training
institution. If done inhouse, then a technician/artisan with flair and interest in people development can be
used to deliver this training. The various machine components used to train operators can be sourced
from obsolete or failed equipment in the plant thereby keeping costs to a minimum.
With a more thorough knowledge of machine components, the operator will find additional defects on the
machine that were initially missed because the operator did not understand that they were defects.
These defects and their root causes are eliminated once again separating out the dirty, dangerous and
difficult tags for particular attention. Finally, the cleaning, inspection and lubrication standards developed
in the Foundations phase are reviewed and given the operators deeper machine understanding, the
operator can create the final set of cleaning, inspection and lubrication standards for the process
area/machine.
As with the Foundations phase, time will need to be allocated for cleaning, tagging and elimination of
defects. However, given that basic conditions have already been established, the entire Clean and
Inspect phase should take 6 to 8 weeks per process areas/machine as opposed to the 12 to 16 weeks it
would have taken in the Foundations phase.
The changeover and maintenance tasks need to be formally documented in a standard operating
procedure or work instruction. The operator is trained on this and coached by the artisan responsible for
this process area/machine.
Confidential ©AB InBev 2021. All rights reserved. Page 175 of 282
MAINTENANCE PILLAR BOOK
Once this is done, the operator must be given a chance to operate the second process area until he/she
is completely competent in this area.
Confidential ©AB InBev 2021. All rights reserved. Page 176 of 282
MAINTENANCE PILLAR BOOK
Team leaders, departmental managers and maintenance managers as part of their MCRS, will need to
check that the above is in place for every process area/machine that has completed the Manage to
Sustain phase of Autonomous Operations.
If the above conditions are sustained for several weeks, a Manage to Sustain phase audit can be
performed and the process area/machine signed off. The audit can be done by the site maintenance
manager or the plant manager. The sign off can be used as an opportunity to recognize the team for a
job well done.
Once the process area/machine has been signed off, then the Autonomous Operations activity board
can be discontinued:
• The cleaning, lubrication and inspection standards can be made into a visual standalone board
as per the example in Figure 35. These need to be positioned close the to process
area/machine so that the operator is clear on the cleaning, inspection and lubrication tasks that
must be done
• Some of the KPI’s can be incorporated into the KPI’s for the process area/machine and tracked
and displayed
• The record of all the improvements made to the machine or systems (such as maintenance
schedules) should be filed for record keeping.
• The tag lists should be completely implemented and can be filed for record keeping
• The contamination map can be discarded as either all sources of contamination have been
eliminated or a cleaning standard exists.
Basic cleaning and tagging, inspection and lubrication (ATM Levels 1-5) is fully
entrenched in all areas.
Site preparation
The Competency Framework is expanded to include defined equipment
inspection, lubrication and reaction plans (ATM Levels 2, 3 and 4) for operators.
Confidential ©AB InBev 2021. All rights reserved. Page 177 of 282
MAINTENANCE PILLAR BOOK
The focus areas for the next phase of Autonomous Operations (including minor
Select process
repairs) are selected based upon an analysis of losses and equipment
area/machine
problems.
Standards of equipment cleanliness have been sustained after the deep clean
for all equipment.
One-point lessons have been developed and are used in the workplace.
"As-new" (restored to inherent reliability and deep cleaned) conditions for all
equipment have been established and are being maintained.
Individual teams are capable of executing the full set of ATM levels 1 to 8.
Operators perform equipment setups, changeovers and adjustments according
to ATM Level 6.
Train operator on
Identified operators perform technical tasks according to ATM levels 7-8.
changeovers and basic
The competency framework is expanded to include defined minor maintenance
maintenance
tasks on equipment (ATM Levels 6-8).
Confidential ©AB InBev 2021. All rights reserved. Page 178 of 282
MAINTENANCE PILLAR BOOK
Site Preparation
The site needs to be prepared for this phase of autonomous operations. Clear communication needs to
take place with the site so that everyone understands what is trying to be achieved in this phase. Any
concerns that may be raised needs to be dealt with.
Confidential ©AB InBev 2021. All rights reserved. Page 179 of 282
MAINTENANCE PILLAR BOOK
Once the machine or process area has been selected, then the team can be selected. The team
consists of the people who work in that area. It is important that a process expert such as a process
engineer is included in the team. The process expert will coach the operator on the process.
The operator is then trained on how their equipment’s specific process e.g. bottle washing, lautering or
CO2 liquefaction. The theoretical training that was provided earlier to the operator will allow the operator
to better understand their equipment’s process.
Process Analysis
In this step, the equipment or process area is analyzed to understand how product quality and waste is
related to process inputs and machine condition. For example consider the jetter process on the filler.
This process is analyzed by the operator to understand process inputs (in this case jetter water
temperature and jetter water pressure) and machine conditions (in this case jetter nozzle diameter)
impact on product quality (in this case TPO) and waste (in this case filler beer loss).
The operator will map out the entire machine or process area in order to understand how the various
machine processes and conditions affect product quality and waste. Additionally the process input limits
and machine condition limits are defined. For example, what is the required temperature range for jetter
water?
As a result of this analysis the operator will define for the process:
• Machine conditions that have to be sustained via maintenance (cleaning, inspection or
lubrication)
Confidential ©AB InBev 2021. All rights reserved. Page 180 of 282
MAINTENANCE PILLAR BOOK
• Control points of the process that must be managed to ensure the process runs perfectly. This is
done through inspection standards and/or by using process control charts.
Other more traditional condition monitoring tasks such as simple oil sampling, vibration and
thermography can be transferred to the operator.
Once this is complete, a new focus machine can be selected and the entire process repeated.
Confidential ©AB InBev 2021. All rights reserved. Page 181 of 282
MAINTENANCE PILLAR BOOK
Policy
Maintenance program development calls for the use of several techniques (FMECA, RCM etc.) for the
development of preventive and predictive maintenance programs. Each site is expected to implement
these techniques as per the maintenance handbook.
The job matrix for maintenance supervisors, engineers and managers needs to reflect the key skills in
this area:
• Using OEM manuals to develop basic preventive and predictive maintenance schedules
• Using the outcomes of problem solving and cleaning & tagging to continuously improve
preventive and predictive maintenance schedules
• Using Abridged RCM to develop preventative and predictive maintenance schedules for B
criticality equipment
• Using FMECA and RCM to develop preventative and predictive schedules for A criticality
equipment
Each site is expected to develop structured check sheets for FMECA and RCM analysis. These need to
be aligned with the standards defined in the maintenance handbook.
Procedure
A comprehensive description is provided in the “Detailed Implementation Guide’ sub-section on how to
implement FMECA and RCM. This approach has been linked to criticality analysis thereby providing an
integrated method for developing strong preventive and predictive maintenance programs.
Responsibilities
It is the responsibility of the site Technical Services Manager to ensure that Maintenance Program
Development is implemented on a site including compliance to the requirements of the maintenance
handbook, documenting the analysis using appropriate check-sheets and ensuring that employees are
skilled in the procedure.
It is the responsibility of planners and maintenance supervisors to ensure that Maintenance Program
Development is carried out.
Confidential ©AB InBev 2021. All rights reserved. Page 182 of 282
MAINTENANCE PILLAR BOOK
Create Maintenance
Program Development A CI R
(FMECA/RCM) skills
Link to maintenance
A R
system
Develop FMECA check
A R I
sheets
Link to department
A CI R
training plan
R = Responsible
A = Accountable
C = Consulted
I = Informed
Note: Changes in plant organizational structure may change RACI.
Confidential ©AB InBev 2021. All rights reserved. Page 183 of 282
MAINTENANCE PILLAR BOOK
• Once equipment reaches 90 % LEF (98 % availability for a process area), forced deterioration
has been mostly eliminated and time effort can be spent developing more sophisticated
maintenance programs. For B criticality equipment the Abridged RCM process is required. This
process is less onerous than the FMECA + RCM process.
• For A criticality equipment operating above 90 % LEF (98 % availability for a process area) the
FMECA + RCM process is required.
• The zone may have best practice maintenance programs for common equipment. These
maintenance programs must be adopted by plants as they represent a more comprehensive
view of maintenance tasks.
Below 85 % LEF, forced deterioration is the major driver of equipment failure and the central effort of the
maintenance program is to eliminate forced deterioration.
OEM Recommendations
OEM recommendations are the starting point of all maintenance programs. The OEM has particular
knowledge about the technology installed and will have specific requirements defined in the
maintenance and operating manuals.
Confidential ©AB InBev 2021. All rights reserved. Page 184 of 282
MAINTENANCE PILLAR BOOK
All plants need to ensure that the requirements of the OEM are captured into preventive and/or
predictive program.
Continuous Improvement
While OEMs can provide a basic maintenance program, their recommendations form at best a basic
maintenance program. Problems you will encounter with OEM recommended maintenance include:
• Frequency of the maintenance tasks are incorrect
• Maintenance tasks are missing
• Maintenance tasks have no specification e.g. check belt for wear
• Maintenance tasks are generic e.g. check machine for damage
It is important that basic OEM maintenance programs are improved. This is done in three ways:
• Improvements from equipment failure problem solving
• Improvements from tag root cause analysis
• Improvements from routine schedule reviews
When equipment fails, it will meet a problem trigger as defined in the problem-solving section of the
maintenance handbook. Problem solving will then be performed to identify the root cause. In general,
there are six categories of root causes (known as the 6M’s); man, material, method, machine,
environment and measurement. If the root cause falls into the machine category, then a preventive or
predictive maintenance task can in most cases deal with these kinds of problems. Thus, when
equipment fails, and a machine root cause is found, existing maintenance programs can be improved by
including appropriate tasks to counter the machine root cause. For example if a cam fails because
natural wear and tear, then a preventative maintenance task can be put in place to measure the cam
wear and to replace the cam before failure.
It is critically important to note that preventative maintenance tasks should not be created for non-
machine root causes i.e. man, material, method, environment and measurement. These types of root
causes can be dealt with in other ways. For example, if a machine fails because the operator did not do
a changeover correctly, it does not make sense to put a preventative maintenance task to inspect for the
failure. Rather train the operator to perform the changeover correctly.
For example, if a machine fails because the operator did not do a changeover correctly, it does not
make sense to put a preventative maintenance task to inspect for the failure. Rather train the operator to
perform the changeover correctly.
Maintenance programs can be further continuously improved through the root causes of tags. As
cleaning and tagging is done in the plant, various tags are analyzed to define their root causes. As with
equipment failure, if the root causes are machine related, then preventative or predictive maintenance
Confidential ©AB InBev 2021. All rights reserved. Page 185 of 282
MAINTENANCE PILLAR BOOK
tasks can be created to manage this. Once again if the root cause is not machine related, then the
preventive maintenance program must not be used to manage those problems.
Finally, maintenance programs can be improved through a regular review routine. This routine is
performed by the machine owner/expert and maintenance planner who review the maintenance
schedule.
Maintenance program reviews should be in the MCRS of the machine owner/expert and the planner. All
equipment in the plant should be reviewed at least once in a 3 year cycle. The following items should be
reviewed as part of the process:
• The PM or PdM is allocated to the correct resource
• The estimated time on the PM or PdM is correct. The planner can review actual times taken for a
task and compare then to the estimated time and improve the estimated time.
• Check that the frequency of the maintenance schedule is correct. Initially when a schedule is
created there is no solid indicator of a frequency so often this may turn out to be a guess. As the
maintenance schedules are executed, defects or even failures may occur. We are typically
looking for 1 defect from 3 inspections. This rule of thumb will allow the planner to review how
many defects arrive from a particular schedule and adjust its frequency to achieve a 1 in 3 ratio.
• Confirm that all tasks on a PM or PdM have similar failure rates i.e. items that can fail weekly
should not be mixed with items that can fail montly
• Confirm that ALL OEM required maintenance tasks are on the PM or PdM schedule. If not, there
must be a good reliability related reason for this.
• Check if there are tasks in the PM or PdM schedule which are trying to solve non-machine
related problems. These should be eliminated, and the non-machine related root cause solved
using other methods.
• Check that all maintenance tasks have a specification. Often maintenance inspections have no
specification leaving it up to the opinion of the person doing the inspection tasks. All tasks need
to have a specification so that it is clear if an item is within specification or not. For example a
task that says “Check that v belts are not loose” is completely open to interpretation. This
maintenance task should have a specification e.g. “Check that v belts have a tension of 4.8
Newtons following the method described in the work instruction M78904”.
• Assess if there are missing tasks. Look at historical failures and if the root cause of these failures
are machine (but not random), then there should be a PM or PdM task.
• Assess if there are tasks that should not be there. Sometimes there are tasks in a maintenance
program that should not be there. It could be that the task is outdated as the machine has been
upgraded or that the task is superfluous as it is trying to deal with a non-machine related failure
mode (such as operator error)
• Assess if there are duplicated tasks either within the same maintenance program or in another
maintenance program with a different frequency. Eliminate one of the duplicate tasks.
• If the zone has standardized zone PM’s for particular machines, ensure that the plant’s PM
aligns with the zone standardized PM.
Confidential ©AB InBev 2021. All rights reserved. Page 186 of 282
MAINTENANCE PILLAR BOOK
The above items are contained in a template (Figure 43) which can be used to manage and document
the review process. Through a process of problem solving, tag root cause analysis and routine reviews,
a basic OEM maintenance program can be continuously improved into a strong well-developed
program.
PM Review
Other Participants
A. Details of Existing PM
PM Name
Equipment
B. Overall PM Review
Y/N Corrective Action
1. Is this PM attached to the correct functional location level?
2. Are the safety instructions on the PM approriate for the tasks being performed?
3. Has the schedule been allocated to the correct person or group?
4. Is the estimated time correct for the PM?
5. Is the frequency of the PM correct?
6. Are all the OEM requirements for this machine, trade and frequency been included?
7. If a zone PM standard for this equipment exists, does this PM contain all the zone defined
tasks?
D. PM Integration
Y/N Corrective Action
1. Review the root cause analysis of historic failures. Are there any machine related root
causes that this PM does not currently address?
2. Are there any similar equipment in the plant that needs to be updated with the changes
made to this specific PM
3. Are there any PM tasks in similar equipment in the plant that needs to be added to this
PM
4. Are inspection tasks mixed with scheduled lubrication, discard or restoration tasks?
5. If the PM covers multiple equipment, does the route make sense?
There are specific guidelines in the autonomous operations section of the maintenance handbook
around how the CIL standards will need to be developed.
Confidential ©AB InBev 2021. All rights reserved. Page 187 of 282
MAINTENANCE PILLAR BOOK
The FMECA & RCM process is used for critical A equipment when LEF is greater than 90 % (availability
of a process area greater than 98 %). It is a very detailed and precise process that requires significant
time and effort. For this reason, implementation of the full FMECA & RCM process is limited to critical A
equipment. Additionally, only when forced deterioration is eliminated (i.e. LEF > 90 %) is it appropriate to
implement a more sophisticated maintenance program.
FMECA is an acronym for Failure Mode, Effects and Criticality Analysis. In essence, an FMECA process
involves:
• Breaking a machine into its component parts
• Assessing how each part can fail i.e. the failure modes
• Understanding what the impact is of each failure mode on the overall machine i.e. the failure
effects
• Determining the significance of each failure effect i.e. a criticality assessment based upon the
probability of occurrence and severity of the consequence
The criticality of a failure can be assessed using the probability/consequence diagram in Figure 44 as a
guide.
Confidential ©AB InBev 2021. All rights reserved. Page 188 of 282
MAINTENANCE PILLAR BOOK
RCM analysis at this point complements the FMECA approach in that for each failure mode, RCM will
provide a decision tree that will allow you to select the most appropriate maintenance task to manage
that failure mode. Figure 45 illustrates the RCM decision tree.
The RCM decision tree is separated into two broad parts i.e. Level 1 and Level 2. Figure 46 illustrates
the decision tree with Level 1 elements circled. Level 1 of the decision tree aims to classify failures into
the following categories:
• Evident
o Safety/Environment
o Production
o Non-production
• Hidden
o Safety/Environment
o Not safety/environment
Evident failures are those failures that can be detected by the operator as he performs his normal duties.
Hidden failures are those failures that cannot be detected by the operator in his normal duties. Evident
and hidden failures are sub-classified into:
• Safety/Environment – those failures that affect safety or the environment.
• Production failures - those failures that affect production i.e. the ability to produce in specification
product
• Non – production – those failures that do not affect production directly i.e. in specification product
can still be produced
• Non-safety – failures that do not have an impact on safety or the environment
The reason for this classification is that depending on the impact of failure, a different scheduled
maintenance approach will be taken.
Confidential ©AB InBev 2021. All rights reserved. Page 189 of 282
MAINTENANCE PILLAR BOOK
Level 2 of the decision tree focuses on specific scheduled maintenance activities that need to be
performed.
Confidential ©AB InBev 2021. All rights reserved. Page 190 of 282
MAINTENANCE PILLAR BOOK
In using the Level 2 decision logic, the user is required to evaluate the technical feasibility and financial
impact of each possible scheduled maintenance activity so that they best schedule maintenance activity
is chosen.
Figure 46 illustrates the Level 2 decision tree for an evident production effect failure. To perform the
RCM analysis the decision tree is followed. The first question is whether lubrication or cleaning tasks will
be effective in delaying or eliminating the failure. To answer this question, you will need to determine two
things:
Confidential ©AB InBev 2021. All rights reserved. Page 191 of 282
MAINTENANCE PILLAR BOOK
• From a technical point is there evidence that cleaning or lubrication will delay or eliminate failure.
If there is no evidence or strong indicator that this will be the case, then cleaning or lubrication is
not technically feasible.
• From a financial point of view, if the task is technically feasible, then the cost of the task must be
established. For a cleaning or lubrication task, that cost will be the cost of the labor, the standing
time of the machine, the cost of the cleaning materials etc. Obtaining costs will allow you to then
evaluate multiple technically feasible tasks against each other to select which one will be the
most cost effective.
Once the cleaning/lubrication question has been answered, the next task, which is operator crew
monitoring, must be evaluated from a technical feasibility and cost point of view. In fact, every
maintenance task on the evident production effect decision tree must be evaluated from a technical and
cost point of view. At the end, you will have a list of maintenance tasks that are technically feasible and
the costs of each of these feasible tasks. The most cost effective technically feasible task is then
selected.
Confidential ©AB InBev 2021. All rights reserved. Page 192 of 282
MAINTENANCE PILLAR BOOK
Given the above description of the FMECA and RCM processes they can be applied in the following way
to develop a maintenance package.
The selected machine is broken down into its component parts. The partitioning can be done using the
template below.
Confidential ©AB InBev 2021. All rights reserved. Page 193 of 282
MAINTENANCE PILLAR BOOK
Confidential ©AB InBev 2021. All rights reserved. Page 194 of 282
MAINTENANCE PILLAR BOOK
Confidential ©AB InBev 2021. All rights reserved. Page 195 of 282
MAINTENANCE PILLAR BOOK
Abridged RCM
The RCM methodology offers a powerful way of developing planned maintenance schedules. However,
due to their complexity RCM cannot be used for every piece of equipment in the plant. The guidance is
that it is used only for critical A equipment. For critical B equipment a shortened form of RCM is used
called Abridged RCM.
Confidential ©AB InBev 2021. All rights reserved. Page 196 of 282
MAINTENANCE PILLAR BOOK
Once the critical process area/machine has been selected, then an analysis must be performed to
identify the machine root cause failures of the selected process area/machine over the past 6 to 12
months. It is important to note that this is not all failures but rather those failures where the root cause is
machine. As noted earlier only machine root causes can be effectively dealt with by a scheduled
maintenance system. It is expected that you should have no more than 20 to 30 such machine root
cause failures per process area/machine over a period of six months to a year.
Confidential ©AB InBev 2021. All rights reserved. Page 197 of 282
MAINTENANCE PILLAR BOOK
applied. Figure 53 illustrates a template that can be used to capture the results of the decision tree
analysis.
Figure 53: Example of a template to capture the RCM decision tree analysis
Figure 54: Example of the complete RCM template including creating of the maintenance tasks and allocation of
resources
It is important that when a maintenance task is created, it has a clear specification. For example, if a
task is created to check for wear, then there must be a specification for how much wear is acceptable or
not. It is not good enough to create a task with requires a specification but does not have one. Some
Confidential ©AB InBev 2021. All rights reserved. Page 198 of 282
MAINTENANCE PILLAR BOOK
tasks such as discard will not require a specification but tasks such as operator inspection or technician
inspection must have a specification included.
Task frequency is the next critical area that needs to be defined. Failure history (Mean Time between
Failures) on the component should give you an idea of the frequency of the scheduled maintenance
task. For example, if a component fails every year then a scheduled task just shorter than a year will
prevent the failure. It is important that the MTBF history if used to determine task frequencies covers
only the period of natural deterioration, not forced deterioration.
As part of the maintenance schedule review cycle, the sub work orders arising out of a scheduled
maintenance task will be assessed. Typically, the sub work order % needs to be 30 %, so if the
frequency of a task is incorrect, it will be identified by a low or high sub work order %.
Task duration also needs to be defined. This is informs the planner determine how much time it will take
a resource to complete the task and is especially important when developing the entire maintenance
plan/schedule for the week.
Update Schedule
With the completion of the previous step, the maintenance tasks to prevent machine root cause failure
should be thoroughly defined. The planned maintenance schedules for the machine can then be
updated with the new tasks.
However, when this is done, there will be some older tasks on the planned maintenance schedule that
are already being executed. It is worthwhile reviewing these tasks to ensure that:
• Are the existing tasks designed to address machine root causes or are they addressing other
root causes such as man. If they do not address machine root causes then they should be
removed. Other actions may be necessary to manage non-machine root causes
• Do all the existing tasks have a specification (if the task requires it)? If not, then the tasks need to
be modified to include a specification.
• Are the existing tasks the most economic and technically effective to prevent the failure?
Considering the logic of the RCM decision tree are there alternative maintenance tasks that are
perhaps better than the existing maintenance task.
• Is the frequency of the existing tasks correct? A useful check of this is the measure the sub work
order % for the maintenance task. If less than 30 % then the task frequency is too high; while if
more than 30 % then the task frequency is not high enough
• Confirm that the correct resources are allocated to existing tasks
• Review the planned time against actual time and confirm if the planned time for the existing tasks
Confidential ©AB InBev 2021. All rights reserved. Page 199 of 282
MAINTENANCE PILLAR BOOK
are correct
Once the new tasks have been built into the schedule and existing tasks reviewed the entire process is
complete, and the next critical machine can be selected for the process to be repeated.
Definition
The term problem solving is used widely and has different meanings for different people. For VPO,
problem solving is a systematic way of defining, analyzing and solving a problem so that the root cause
of the problem is managed. The finding and managing of root causes is the key point.
Often in everyday language, people will refer to the fact that they are problem solving but the reality is
that they are merely trying to find and solve the symptom of the problem rather than the root cause. For
example, a technician may spend several minutes ‘problem solving’ a conveyor which does not run
properly. He may discover that the drive sprocket was worn, replace the drive sprocket and then say that
he has solved the problem. Within the AB InBev definition of problem solving, the technician has merely
found the symptom of the problem and not the root cause.
Consider the example of a worn sprocket that results in a conveyor not running. The worn sprocket is a
symptom and not the ultimate cause of the problem. Let’s assume for this example that the reason the
sprocket is worn, is that the lubrication system of the conveyor was setup incorrectly because the person
who needed to set this up, did not completely understand how to do this.
By replacing the work sprocket, the problem is only temporarily fixed. The person who is responsible for
setting up the chain lubrication system will still not know how to do this and you will find that the worn
sprocket will come back in several months’ time. Even if you put a preventative maintenance plan in
place to pick up the worn sprocket and prevent the failure, you are spending needless resources trying
to manage a problem that can be easily eradicated. By finding and solving the root cause of the problem
(in this example training the person who does not know how to set up conveyor lubrication systems) the
problem is permanently eliminated.
Confidential ©AB InBev 2021. All rights reserved. Page 200 of 282