Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

PROJECT CRASHING

Presentor:

Engr. Larry C. Zafico


Faculty, Civil Engineering Department
The Owner wants you to finish the project in 110 days. Find the
minimum possible cost from the project if you want to finish it on
110 days. All times are in days.

Direct Cost
Nodes Activity Normal Accelerated
Time Cost Time Cost
1-5 A 120 12,000 100 14,000
1-2 B 20 1,800 15 2,800
2-3 C 40 16,000 30 22,000
3-4 D 30 1,400 20 2,000
4-5 E 50 3,600 40 4,800
2-4 F 60 13,500 45 18,000
TOTAL COST = P48,300
Crash D by 10 days

TOTAL COST = P48,300 + (10 x P60) = P48,900


Crash E by 10 days

TOTAL COST = P48,900 + (10 x P120) = P50,100


Crash A by 10 days
Crash B by 5 days & C by 5 days &
F by 5 days

TOTAL COST = P50,100 + (10 x P100) + (5 x P200) +


(5 x P600) + (5 x P300) = P56,600

You might also like