PROJECT CRASHING 3rd Example
PROJECT CRASHING 3rd Example
Presentor:
Direct Cost
Nodes Activity Normal Accelerated
Time Cost Time Cost
1-5 A 120 12,000 100 14,000
1-2 B 20 1,800 15 2,800
2-3 C 40 16,000 30 22,000
3-4 D 30 1,400 20 2,000
4-5 E 50 3,600 40 4,800
2-4 F 60 13,500 45 18,000
TOTAL COST = P48,300
Crash D by 10 days