Article The River Plate Experience 68 01
Article The River Plate Experience 68 01
Alan Lievens
The 1990s will be considered a landmark for economic However the success of the privatised port could not
reform in the Latin American continent. A key element have taken place without a drastic improvement of the
in this economic reform is the privatisation process that maintenance of Argentine’s principal waterway, the
is ongoing in most of the Latin American countries. River Plate (Rio de la Plata). Indeed Argentina depends
Public industries and services are, to a large extent, for 70% on the exportation of its products, particularly
being transferred to private enterprises. In order to grain and cereals, on the waterway that consists of the
cope with the economic growth, infrastructure in River Plate and the Parana River. It extends from Punta
general, the ports in particular have to be reorganised, Indio (km 205.3) on the River Plate up to Santa Fe
modernised and improved. It is generally reckoned that (km 589) on the Parana River, over a distance of almost
in terms of ports and shipping Argentina has “traveled 700 km. This waterway however has a continuous
further along the road” towards liberalisation than any need for maintenance dredging over a majority of its
other country in Latin America. length (see Figure 1).
3
Terra et Aqua – Number 68 – September 1997
Figure 1. Maintenance dredging on the River Plate in the foreground; shipping traffic in the background.
4
The River Plate Experience
Figure 2. Dredging was done in stages: this drawing of the River Plate indicates the volumes to be dredged in each stage (V1, V2, V3).
The terms of reference of the tender were quite simple: signalisation system according to the international
– to dredge and maintain a 100 m wide waterway over standard (Figure 3);
a length of approximately 700 km, and, – a geotechnical investigation of the materials to be
– to refurbish the navigational aids over the entire dredged and the corresponding output calculations
distance according to the international lighthouse of the different dredges to be used during the
standards. project;
– hydrographic surveys and an interpretation of the
Works had to be carried out in three construction historic hydrological data of water levels and
phases (Figure 2): frequencies;
1. During phase one the waterway had to be dredged – volume calculations during the construction stage
to a depth of 28 ft over a period of 9 months including sedimentation at 28 and 32 ft depths and a
including the time for mobilisation. forecast of the future sedimentation during the
2. During phase 2 the waterway had to be deepened maintenance period; and
to 32 ft. The maximum execution period for this – finally a traffic study (Figures 4 and 5) divided over
phase was 24 months. the consecutive sections of the waterway in order to
3. During phase 3 the waterway had to be maintained establish the level of income to be expected from
at a depth of 32 ft. until the end of the ten year the toll.
concession period.
The Financial Proposal
The tender procedure itself consisted of two packages: The financial proposal was a single figure: the amount
a technical and a financial proposal. of the toll to be applied per net registered tonnage of a
vessel using the waterway.
The Technical Proposal In total the Argentine Ministry of Economy and Public
The technical proposal included amongst other things: Works received six proposals. After a technical evalu-
– the redesign of the waterway including a complete ation, three offers were retained and their financial bids
5
Terra et Aqua – Number 68 – September 1997
Figure 3. Signalisation system was adapted to international standards. This drawing of the River Plate indicates the number of
signals (buoys and beacons) per stage (S1, S2).
Figure 4. Traffic control: The river was divided into consecutive sections in order to estimate the expected toll income.
6
The River Plate Experience
Figure 5. As an example, traffic control from Buenos Aires to Recalada for one ship, the Bilbao Express.
opened. The group of Jan De Nul was lowest bidder Global Positioning System (DGPS) system. The satellite
and consequently awarded the contract. The total signal is corrected via three differential antennas installed
estimated contract value was US$650 million with along the waterway, one covering the River Plate area,
approximately one third of this figure attributed to the the other two the River Parana area.
collection of the toll. The progress of the works and the amount of sedimen-
tation is monitored by means of continuous hydrograph-
ic surveys which requires the use of four, sometimes
T HE W ORK five survey vessels, with each of these covering its
own allocated section of the river.
The work involved in the first phase included the The project also requires substantial logistic support
deepening of the River Plate channels and the Parana which is mainly provided from two sources: Buenos
River up to Puerto San Martin (km 452) to a depth of Aires and Rosario (400 km up river). A fleet of tugs and
28 ft and secondly the deepening of the Parana River support vessels ensure the timely transport of man-
from Puerto San Martin (km 452) up to Santa Fe power, fuel and supplies.
(km 589) to a depth of 22 ft.
In order to complete the work of the first phase by the The First Phase
end of 1995 various sections of the waterway had to During the first phase of the project an enormous effort
be tackled simultaneously. Upon signature of the was made to bring the navigational signalisation system
contract three dredges of Jan De Nul were mobilised in up to the required international standard. From Punta
Argentina, one cutter suction dredge and two hopper Indio to Puerto San Martin the system was completely
dredges (Figure 6). The latter took care of the sandbars redesigned and upgraded. Detailed engineering
on the Parana River whilst the cutter suction dredge included simulation techniques in the laboratory of
dredged the Emilio Mitre channel, the classical bottle- Wageningen in Holland. There the project engineers
neck of the waterway. Two dredges of the Ministry designed and calculated the best solution for the curves
that were made available under the concession con- of the Parana de las Palmas, a particularly difficult
tract, were put to work in the outer channels of the section of the river tonegotiate and a real challenge for
River Plate. In order to achieve accurate and efficient Panama size vessels. In total more than 500 buoys
dredging along the whole stretch of the waterway, the and beacons had to be converted or modernised and
concessionaire installed a completely new Differential reinstalled.
7
Terra et Aqua – Number 68 – September 1997
T HE R ESULTS
8
The River Plate Experience
From To subsection
Subsection 0.0 1.1 1.2 1.3 3.0
0.0 0.00 1.96 5.00 6.96 1.96
1.1 1.96 3.04 3.04 5.00 0.00
1.2 5.00 3.04 3.04 1.96 3.04
1.3 6.96 5.00 1.96 1.96 5.00
3.0 1.96 0.00 3.04 5.00 0.00
From To subsection
Subsection 0.0 1.1 1.2 1.3 3.0
0.0 0.00 22.88 34.52 60.78 22.28
1.1 22.88 11.64 11.64 37.91 0.00
1.2 34.52 11.64 11.64 26.26 11.64
1.3 60.78 37.91 26.26 26.26 37.91
3.0 22.28 0.00 11.64 37.91 0.00
Figure 8. Procentual values (Ts = toll signalisation; Td = toll dredging) for the section between Recalada and San Martin for 28 feet.
once phase two is completed. The toll is calculated as a Prefecture has the authority to check upon payment by
function of the vessel’s Net Registered Tonnage (NRT), the ship’s agent prior to issuing any port clearance to
its maximum draught and the actual depth of the the vessel.
channel (28 or 32 ft). The whole channel is divided in
sections and subsections. Ships are charged tolls
according to the sections and subsections of the water- Conclusions
way that they actually use (Figures 8, 9, 10 and 11).
The response of the shipping industry to the changes
The total toll consists of two tariffs: has been quite positive. After an initial reluctance to pay
– one taking into account the dredging work, and tolls for maintenance dredging and signalisation, ship
– the other taking into account the navigational signali- owners and terminals alike are now realising the enor-
sation. mous benefits of the system. The figures that illustrate
the impact of the concession on transport prices are
Cooperation impressive.
In order to implement a correct toll system, a constant Before the start of the concession, the transport cost of
monitoring of the channel traffic is imperative and one tonne of cereal from Argentina to Europe was
requires close cooperation with the maritime authori- around US$27 /tonne compared with US$16 /tonne
ties. In respect to this cooperation, an agreement was today.
signed between the Prefectura Naval, the Naval In 1992 in total 200 ships with a length of around 150 m
Authority and the concessionaire in order to guarantee were loaded at the private terminals of Rosario. Only
a constant monitoring of all ship movements which 17 could sail with full holds representing an average
include satellite communications. The concessionaire is cargo of 12,000 tonnes only. In 1995 260 ships of the
responsible for collecting the toll, whilst the Naval same size were loaded , 120 of them with full loads
9
Terra et Aqua – Number 68 – September 1997
From To subsection
Subsection 0.0 1.1 1.2 1.3 3.0
0.0 0.00 2.61 6.41 8.37 2.61
1.1 2.61 3.80 3.80 5.76 0.00
1.2 6.41 3.80 3.80 1.96 3.80
1.3 8.37 5.76 1.96 1.96 5.76
3.0 2.61 0.00 3.80 5.76 0.00
From To subsection
Subsection 0.0 1.1 1.2 1.3 3.0
0.0 0.00 44.44 61.50 100.00 44.44
1.1 44.44 17.06 17.06 55.56 0.00
1.2 61.50 17.06 17.06 38.50 17.06
1.3 100.00 55.56 38.50 38.50 55.56
3.0 44.44 0.00 17.06 55.56 0.00
Figure 9. Procentual values (Ts = toll signalisation; Td = toll dredging) for the section between Recalada and San Martin for 32 feet.
10