Project: WADI SAFAR GOLF COURSE MAIN WORK Risk Assessment Ref: CS/KSA-TRANSMIT-000629
Company Name: CITISCAPE Date: 10-12-2023
Activity Name: BACKFILLING OF TEMPORARY VVIP CLUBHOUSE Site Location WADI SAFAR GOLF COURSE SHORT GAME ACADEMY AREA
Risk Rating without
Sr. Hazards Controlled by Residual Risk
Task Harm control measures Control Measures
No Identified whom
LXS L M H LXS L M H
Arrange toolbox talks meetings with Site team
about the work methodology.
Prior starting any activity Permit to work shall be
Falling
Unplanned obtained.
Foot injuries
work Without Proper PPEs must be given to all the workers.
Preparation Hand
01 following the 4x3 12 Proper supervision must be in place for all the Citiscape 3x1 03
for the job injuries
Approved activities.
Property
Procedure Approved drawings must be followed by the
Damaged.
supervisors.
All the people who will be engaged in that activity
should be safety inducted
02 Clearance of Unsafe Access Falling 4x3 12 Safe access must be provided for the working site. Citiscape 3x1 3
work area Egress Foot Weather protected clear area of minimum 15 x15
Tripping injuries mt shall be set for unloading and storing the
Hazards Hand materials from containers.
Sharp Edges of injuries No material must be store or kept in the access to
material Traffic avoid any slip trip hazard.
Unwanted blocks Access signage must be posted at the access area.
material All the tools, equipment & material must be
stored properly in designated area.
Workplace shall be clean, and wastage must be
removed immediate after the activity.
All personnel working inside the workplace shall
wear reflector vest and clear safety goggles and
Safety shoes.
Avoid direct handling of sharp-edged items.
Properly use of hand gloves
Especial training and supervision of the workers.
Cover or otherwise protect sharp edges.
Use personal protective equipment (PPE)
Wastage collection point shall be allocated, and all
the wastage must be stored in designated area
Likelihood (L)
Possible - 2 Minor - 2 High Risk 8 - 12 4 4 8 12 16 20
Likely - 3 Moderate - 3 Moderate Risk 4 - 6 3 3 6 9 12 15
Often - 4 Major - 4 Low Risk 1 - 3 2 2 4 6 8 10
Frequent/Almost certain - 5 Catastrophic - 5 1 1 2 3 4 5
1 2 3 4 5
Consequence (C)
Assessed by: Asad Hussain Bajwa Approved By: Dawood Akbar
Designation: HSE Engineer Designation: HSE Manager
Signature: Signature: