Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.

800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA


Contractor : VRC-SPIDPL (JV)
Authority Engineer : M/s ICT Pvt. Ltd. in association with VESPL
SPS , COS-1 RA & COS-1A RA : 37
Period: : 01-09-2023 to 30-09-2023

Stage Payment Statement No. SPS-37 (90%)


Cumulative Upto Previous This SPS
SL. No Description
(Rs) (Rs) (Rs)

A Total Amount Based on Works Executed

(a) Work Executed in accordance with Clause 19.3 4,247,241,751 4,194,825,389 52,416,362

(b) Price adjustment as per Clause 19.10 (iv) 332,147,959 332,147,959 -

(c) Change of Scope Order as per Article 13 430,056,099 430,056,099

(d) Price adjustment for Change of Scope of work 66,960,768 66,960,768

(e) Revised Change of Scope Order-1 as per Article 13 22,334,259 22,334,259 -

(f) Price adjustment for Change of Scope of work 4,760,333 4,760,333 -

A Sub Total A=a+b+c+d+e+f 5,103,501,169 5,051,084,807 52,416,362

Recommended 90 % for this Bill as per


B 5,103,501,169 5,051,084,807 47,174,726
Clause No. 19.5.1 = A x 90%

C Extra GST Impact =5.36% x B 32,202,349 29,673,784 2,528,565

D Total Recommended Amount D= B+C 5,135,703,518 5,080,758,591 49,703,291

E Deductions :

Amount to be deducted in accordance with the


(i) provisions of the Agreement except taxes: Interest on 5,662,179 5,662,179 -
excess payment

(ii) Amount towards deduction of taxes

1 Retention Money@ 6% on (e) as per Article 7.5.1 - - -

2 TDS @ 2% U/s 194C w.e.f. 01.04.2021 of B 93,596,815 92,548,487 943,495

3 CGST TDS @ 1% of B 51,035,012 50,510,848 471,747

4 SGST TDS @ 1% of B 51,035,012 50,510,848 471,747

5 Labour Cess @ 1% of B 51,035,012 50,510,848 471,747

6 Any Other (Amount withheld by AE) 122,559,169 122,559,169 -

7 Penalty Amount Previous IPC 3,137,432 3,137,432 -

8 Any Other (Amount Released by AE) (28,689,433) (28,689,433) -

E Total { (i) + (ii) } 349,371,197 346,750,379 2,358,736

F Net Amount (D-E) 4,786,332,321 4,734,008,212 47,344,555


Say 47,344,555
Payable Amount= 47,344,555

Net Amount Payable (in words): Four Crore Seventy Three Lakh Forty Four Thousand Five Hundred Fifty Five Rupees Only/-
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to
Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA


Contractor : VRC-SPIDPL (JV)
Authority Engineer : M/s ICT Pvt. Ltd. in association with VESPL
SPS No. : 37
Period: : 01-09-2023 to 30-09-2023

Stage Payment Statement No. SPS-37 (90%)


Cumulative Upto Previous This SPS
SL. No Description
(Rs) (Rs) (Rs)

A Total Amount Based on Works Executed

(a) Work Executed in accordance with Clause 19.3 4,247,241,751 4,194,825,389 52,416,362

(b) Price adjustment as per Clause 19.10 (iv) 332,147,959 332,147,959 -

A Sub Total A=a+b 4,579,389,709 4,526,973,347 52,416,362

Recommended 90 % for this Bill as per Clause No.


B 4,579,389,709 4,526,973,347 47,174,726
19.5.1 = A x 90%

C Extra GST Impact =5.36% x B 30,777,163 28,248,597 2,528,565

D Total Recommended Amount D= B+C 4,610,166,872 4,555,221,945 49,703,291

E Deductions :

Amount to be deducted in accordance with the


(i) provisions of the Agreement except taxes: Interest on 5,662,179 5,662,179
excess payment

(ii) Amount towards deduction of taxes

(a) Retention Money@ 6% on (e) as per Article 7.5.1 - - -

(b) TDS @ 2% U/s 194C w.e.f. 01.04.2021 83,114,585 82,066,258 943,495

(c) CGST TDS @ 1% 45,793,897 45,269,733 471,747

(d) SGST TDS @ 1% 45,793,897 45,269,733 471,747

(e) Labour Cess @ 1% 45,793,897 45,269,733 471,747

(f) Any Other (Amount withheld by AE) 122,559,169 122,559,169 -

(g) Penalty Amount Previous IPC 3,137,432 3,137,432

(h) Any Other (Amount Released by AE) (28,689,433) (28,689,433) -

E Total { (i) + (ii) } 323,165,624 320,544,806 2,358,736

G Net Amount (D-E) 4,287,001,248 4,234,677,139 47,344,555

Say 47,344,555
Payable Amount= 47,344,555

Net Amount Payable (in words): Four Crore Seventy Three Lakh Forty Four Thousand Five Hundred Fifty Five Rupees Only/-
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAY AUTHORITY OF INDIA
EPC Contractor : VRC-SPIDPL (JV) Period : 01-09-2023 to 30-09-2023
Authority Engineer : M/s Intercontinental Consultants and Technocrats Private Limited in association with VESPL Contract Price : Rs. 5,109,700,000.00
SPS No. 37

Item Weightage in Stage for Payment Percentage Unit Unit Rate Total Qty. Amount Upto Date Previous Bill This Bill Remarks
percentage to the Weightage
Contract Price
Qty. Amount Qty. Amount Qty. Amount

A- Widening and strengthening of existing


road
(1) Earthwork up to top of the sub-grade - MCW 11.02% Km 27362174 11.994 328,168,234 11.734 321060910 11.734 321060910 0.000 -
(Wid)
(2) Sub-Base Course 6.55% Km 16263361 11.994 195,054,622 11.849 192700500 11.849 192700500 0.000 -
(3) Non Bituminious Base 6.33% Km 15772344 11.952 188,503,169 11.729 184997766 11.729 184997766 0.000 -
(4) Bituminous Base Course 14.59% Km 18066842 24.048 434,480,448 23.129 417872504 23.104 417420833 0.025 451,671
(5) Wearing Coat 7.30% Km 8985249 24.194 217,389,121 18.774 168689070 17.504 157277803 1.270 11,411,267
B1- Reconstruction/New 2-lane 0
realignment/bypass (Flexible pavement)
(1) Earthwork up to top of the sub-grade 11.81% Km 37996317 9.256 351,693,906 9.218 350250046 9.218 350250046 0.000 -
Road works (2) Sub-Base Course 2.52% Km 8107597 9.256 75,043,916 8.858 71817092 8.858 71817092 0.000 -
including (3) Non Bituminious Base 3.25% Km 10456226 9.256 96,782,828 8.118 84883643 8.118 84883643 0.000 -
culverts, (4) Bituminous Base Course 11.00% Km 35390303 9.256 327,572,648 7.895 279406445 7.895 279406445 0.000 -
58.28%
widening (5) Wearing Coat 4.34% Km 13963083 9.256 129,242,299 5.180 72328772 5.125 71560802 0.055 767,970
and repair
of culverts C1- Reconstruction/New Service Road
(Flexible pavement)
(1) Earthwork up to top of the sub-grade 2.53% Km 5183112 14.536 75,341,709 12.925 66991716 12.925 66991716 0.000 -
(2) Sub-Base Course 2.46% Km 5039705 14.536 73,257,156 12.325 62114367 12.325 62114367 0.000 -
(3) Non Bituminious Base 3.74% Km 7669378 14.522 111,374,700 12.330 94563425 12.330 94563425 0.000 -
(4) Bituminous Base Course 3.89% Km 7976973 14.522 115,841,600 12.065 96242178 11.625 92732310 0.440 3,509,868
(5) Wearing Coat 2.07% Km 4236647 14.550 61,643,216 7.760 32876382 4.660 19742776 3.100 13,133,606
D- Reconstruction and New Culverts on
existing road, realignments, bypasses :
Culvert (Length<6m) 6.60% No. 1724067 114 196,543,589 113.500 195681555 113.500 195681555 0.000 -

A2- New Minor bridges (Length>6m and <60m)

(1) Foundation + Sub-Structure 9.05% Km 603426523 0.194 116,763,032 0.187 112561229 0.187 112561229 0.0000 -
Minor (2) Super-Structure 11.97% Km 798123257 0.194 154,436,850 0.152 121616934 0.152 121616934 0.000 -
Bridges/
Underpass 25.25% (3) Approaches 7.35% Nos. 11853706 8 94,829,645 4.800 56897787 4.800 56897787 0.000 -
es/ B2- New Underpasses/ Overpasses
Overpasses (1) Foundation + Sub-Structure 23.45% Km 2168829564 0.1395 302,551,724 0.139 301814322 0.139 301814322 0.000 -
(2) Super-Structure 18.10% Km 1674021966 0.1395 233,526,064 0.130 218443126 0.130 218443126 0.000 -
(3) Approaches 30.08% Nos. 27720852 14 388,091,934 12.374 343,007,643 12.271 340160547 0.103 2,847,095
C2- New Elevated section/ Flyovers/ Grade
Separators
(1) Foundation 13.75% Km 382406298 0.070 26,768,441 0.070 26768441 0.070 26768441 0.000 -
(2) Sub-Structure 23.07% Km 641608240 0.070 44,912,577 0.067 42827350 0.067 42827350 0.000 -
(3) Super-Structure (including crash barriers etc. Km 0.049 45601742 0.049 45601742 0.000 -
33.60% 934461936 0.070 65,412,336
complete)
Flyover 3.81% (4) Wearing coat including expansion joints 3.42% Km 95114876 0.070 6,658,041 -
(5) Miscellaneous Items (like- hand rails, crash -
barriers, road markings etc.) 8.01% Km 222769051 0.070 15,593,834
(6) Wings walls/ return walls 0.00% -
(7) Approaches (including Retaining wall, stone -
pitching and protections works) 18.15% Nos. 35334342 1 35,334,342

Other works
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAY AUTHORITY OF INDIA
EPC Contractor : VRC-SPIDPL (JV) Period : 01-09-2023 to 30-09-2023
Authority Engineer : M/s Intercontinental Consultants and Technocrats Private Limited in association with VESPL Contract Price : Rs. 5,109,700,000.00
SPS No. 37

Item Weightage in Stage for Payment Percentage Unit Unit Rate Total Qty. Amount Upto Date Previous Bill This Bill Remarks
percentage to the Weightage
Contract Price
Qty. Amount Qty. Amount Qty. Amount

(i) Toll Plaza 18.69% No. 120903371 1 120,903,371 0.626 75676442 0.493 59644655 0.133 16,031,787
(ii) Road side drains 31.75% Km 14115941 14.550 205,386,946 12.048 170061803 12.048 170061803 0.000 -
(iii) Road signs, markings, km stones, safety 20.23% Km 130,865,446 -
devices, …. 2692705 48.600
(iv) Project facilities -
a) Bus Bays including Bus shelters 0.24% No 35285 44 1,552,531 -
b) Truck lay byes -
c) Rest areas 6.80% No. 43988385 1 43,988,385 -
Other 12.66% d) Others -
works (v) Roadside Plantation 4.71% Km 626922 48.600 30,468,426 2.905 1821209 2.905 1821209 0.000 -
(vi) Repair of protection works other than -
approaches to bridges elevated sections/
Flyovers/ Grade separators and ROBs/RUBs
(vii) Safety and traffic management during -
construction 3.57% No 7697967 3 23,093,902 1.583 12188448 1.583 12188448 0.000
(Viii) Utility Duct 3.96% No 1164398 22 25,616,766 17.000 19794773 17.000 19794773 0.000 -
(ix) Junctions 6.70% No 710516 61 43,341,497 8.000 5684131 2.000 1421033 6.00 4,263,098
(x) Electrical Works 3.35% No 21670749 1 21,670,749 -

Total 100.00% 5,109,700,000 4,247,241,751 4,194,825,389 52,416,362


Details of Withheld/Released Amount (Rs.)

S.No. IPC Withheld Amount (Rs.) Penalty Amount Reasons for Penalty Released Amount (Rs.) Remarks

Withheld Amount Released Amount


Reasons for Withheld Reasons for released
(Rs.) (Rs.)

1 IPC-1 11,000,000 Due to non maintaining of Slope and granular shoulder 0

Finishing work of 36.5 Nos Culverts yet to be done at


2 IPC-2 4,996,768 0
Site.
3 IPC-3 - 0
Amount was released in
4,073,155 Non Submission of drainage plan 0
IPC-5
Reconstruction area Subgrade shall be considered in 4-
Amount was released in
4 IPC-4 1,110,057 laning , hence as per site work of subgrade executed
IPC-8
only LHS by RFI no 1653
Non maintenance of Existing road as per Clause 10.4 of Non maintenance of Existing road Amount was released in
- 200,000 0
CA as per Clause 10.4 of CA IPC-10
Drainage plan has been reviewed by AE ref
Withheld amount in IPC
5 IPC-5 - 4,073,155 letter no (
04
ICT/TL/VRC-S&P/Rohtak-jind/2020-21/278)

Reconstruction area Subgrade are considered in 4-laning


Amount was Released in
in SPS-6 , hence as per site work of subgrade executed
IPC-8 for RFI
RFI no 2787,3152,2277,2993 and 3026 shall be consider
2,522,857 ( 2787,2993) & IPC-9
as half, So 50% amount of RFI shall be withheld until
6 IPC-6 for RFI
CBR confirmation report in reconstruction area is
( 3152,2277,3026)
Submitted

Withheld amount till approval of utility duct location plan Amount was Released in
1,045,582
& drawing IPC-7
Amount of utility duct has been deducted Withheld amount in IPC-
7 IPC-7 - 1,045,582
from gross value of IPC 06 by PIU office 6
CBR Value of Subgrade found More than 8% Withheld amount in IPC-
5,886,623 Finishing work of 43 Nos Culverts yet to be done at Site. 1,110,057
for RFI No 1653 4

Median Width of MNB Ch.309+955 has not been taken


as per IRC SP-84 -2019 where the work has been CBR Value of Subgrade found More than 8% Withheld amount in IPC-
2,364,501 1,210,971
8 IPC-08 executed at site and finishing work is yet to be done for RFI No 2787,2993 6
Hence 20% amount withheld for above said reason

Some defective RE Wall Panels are observed at site so Amount was released in
2,072,411 -
20% amount of casting of RE Panels was withheld. IPC-10

CBR Value of Subgrade found More than 8%


as Submitted by contractor vide letter no
VRC-SP/NH-71/20-21/446,Dated 14.06.2021 Withheld amount in IPC-
9 IPC-09 684,490 Finishing work of 5 Nos Culverts yet to be done at Site. 1,311,886
for RFI No 3152,2277,3026 at Ch. 6
(333+310-360,333+360-470 - LHS) ,
(332+700-800 -RHS )
Details of Withheld/Released Amount (Rs.)

S.No. IPC Withheld Amount (Rs.) Penalty Amount Reasons for Penalty Released Amount (Rs.) Remarks

Withheld Amount Released Amount


Reasons for Withheld Reasons for released
(Rs.) (Rs.)

As per CA Clause 16.1 contractor maintain


the road during construction period, due to
non conplience of authority & AE
observation raised for road maintenance & Withheld amount in IPC-
684,490 Finishing work of 5 Nos Culverts yet to be done at Site. 200,000
safety,hence out of 180 days, 15 days 04
amount already deducted in IPC 06 from
10 IPC-10 item safety & traffic management during
construction

Defective/ Cracks RE Wall Panels have


Withheld amount in IPC-
2,000,000 Due to non maintaining of Slope and granular shoulder 2,072,411 been replaced at site so withheld amount
8
has been released
Finishing work of 12 Nos VUP/CUP yet to be done at
400,000
Site.

11 IPC-11 273,796 Finishing work of 2 Nos Culverts yet to be done at Site.

Bituminous work yet to be done at VUPs Approaches @


11,321,414
324+300 VUP & 324+740 CUP
12 IPC-12
Finishing Work yet to done at VUPs approaches @
1,000,000
324+300 VUP & 324+740 CUP
13 IPC-13 - -
273,796 Finishing work of 2 Nos Culverts yet to be done at Site.

As per CA Clause 16.1 contractor


14 IPC-14 As per CA Clause 16.1 contractor maintain the road maintain the road during
during construction period, due to non conplience of construction period, due to non
- 837,432
authority & AE observation for road maintenance & conplience of authority & AE
safety. observation for road maintenance
& safety.
15 IPC-15 -
As per CA Clause 16.1 contractor
As per CA Clause 16.1 contractor maintain the road maintain the road during
during construction period, due to non conplience of construction period, due to non
16 IPC-16 - 800,000
authority & AE observation for road maintenance & conplience of authority & AE
safety. observation for road maintenance
& safety.

1,206,847 Finishing work of 7 Nos Culverts yet to be done at Site.

As per CA Clause 16.1 contractor


17 IPC-17 As per CA Clause 16.1 contractor maintain the road maintain the road during
during construction period, due to non conplience of construction period, due to non
- 500,000
authority & AE observation for road maintenance & conplience of authority & AE
safety. observation for road maintenance
& safety.
Finishing work of 3 Nos Utility Duct yet to be done at
300,000
Site.

18 IPC-18
Details of Withheld/Released Amount (Rs.)

S.No. IPC Withheld Amount (Rs.) Penalty Amount Reasons for Penalty Released Amount (Rs.) Remarks

Withheld Amount Released Amount


Reasons for Withheld Reasons for released
(Rs.) (Rs.)
As per CA Clause 16.1 contractor
18 IPC-18 As per CA Clause 16.1 contractor maintain the road maintain the road during
during construction period, due to non conplience of construction period, due to non
- 800,000
authority & AE observation for road maintenance & conplience of authority & AE
safety. observation for road maintenance
& safety.

2,100,000 Construction of median drain on the Project Highway.

19 IPC-19 As per CA Clause 16.1 contractor maintain the road


during construction period, due to non conplience of
400,000
authority & AE observation for road maintenance &
safety.
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
20 IPC-20 400,000
authority & AE observation for road maintenance &
safety.
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of Bituminous work done at VUPs Approaches Withheld amount in IPC-
400,000 9,300,000
21 IPC-21 authority & AE observation for road maintenance & @ 324+300 VUP & 324+740 CUP 12 ( Sch-H Changed )
safety.
500,000 Non- Construction of Rain Water Harvesting

Bituminous work done at VUPs Approaches Withheld amount in IPC-


500,000 Shoulder Rain Cut at various location 2,021,414
@ 324+300 VUP & 324+740 CUP 12 ( Sch-H Changed )

As per CA Clause 16.1 contractor maintain the road


22 IPC-22 during construction period, due to non conplience of
400,000
authority & AE observation for road maintenance &
safety.
Deficiency in some RE Pannel of RE Wall-4 at Ch:
300,000
346+520.
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
23 IPC-23 400,000
authority & AE observation for road maintenance &
safety.
IPC-24 205,347 Balance misc. work at Box Culvert- 1.5 Nos.
IPC-24 204,959 02 Nos flyover Girder Erection Balance
As per CA Clause 16.1 contractor maintain the road
24 during construction period, due to non conplience of
IPC-24 400,000
authority & AE observation for road maintenance &
safety.
IPC-24 15,000 Deduction for kerb cutting work.
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
25 IPC-25 200,000
authority & AE observation for road maintenance &
safety.
Details of Withheld/Released Amount (Rs.)

S.No. IPC Withheld Amount (Rs.) Penalty Amount Reasons for Penalty Released Amount (Rs.) Remarks

Withheld Amount Released Amount


Reasons for Withheld Reasons for released
(Rs.) (Rs.)
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
26 IPC-26 200,000
authority & AE observation for road maintenance &
safety.
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
IPC-27 200,000
27 authority & AE observation for road maintenance &
safety.
IPC-27 500,000 Median Kerb and Median Filling (in Rohtak Bypass)

IPC-28 17,582,806 Non approval of Revised Schedule-H ( for MNB & VUP)
IPC-28 1,940,007 Core Cutting are balance Release in SPS 29
28 As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
IPC-28 100,000
authority & AE observation for road maintenance &
safety.
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
IPC-29 200,000
authority & AE observation for road maintenance &
29 safety.
19 .40 Lakhs Withheld in
IPC-29 2,039,449 Core Cutting are balance 1,940,007 Core Cutting report submitted
SPS 28
20.39 Lakhs Withheld in
IPC-30 500,000 Median Drain 2,039,449 Core Cutting report submitted
SPS 29
IPC-30 500,000 Rainwater Harvesting
IPC-30 737,856 Granular Shoulder (on BC)
30
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
IPC-30 200,000
authority & AE observation for road maintenance &
safety.
IPC-31 500,000 Median Drain
IPC-31 500,000 Rainwater Harvesting
IPC-31 400,000 Granular Shoulder
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
31 IPC-31 200,000
authority & AE observation for road maintenance &
safety.
IPC-31 200,000 Core Cutting are balance On Service Road DBM
IPC-31 20,000 Drone video not submitted for the Month of March-23
IPC-32 300,000 Median Drain
IPC-32 200,000 Rainwater Harvesting
IPC-32 150,000 Granular Shoulder (on BC)
32
Details of Withheld/Released Amount (Rs.)

S.No. IPC Withheld Amount (Rs.) Penalty Amount Reasons for Penalty Released Amount (Rs.) Remarks

Withheld Amount Released Amount


Reasons for Withheld Reasons for released
(Rs.) (Rs.)
32 As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
IPC-32 200,000
authority & AE observation for road maintenance &
safety.
Finishing work is Completed at MNB
IPC-33 500,000 Median Drain 2,364,501
309+955
IPC-33 500,000 Rainwater Harvesting
IPC-33 200,000 Core Cutting balance work
IPC-33 924,304 Granular Shoulder
33 IPC-33 200,000 Level Sheet not completed
As per CA Clause 16.1 contractor maintain the road
during construction period, due to non conplience of
IPC-33 100,000
authority & AE observation for road maintenance &
safety.
IPC-33 20,000 Drone video not submitted for the Month of May-23
IPC-34 500,000 Median Drain
IPC-34 500,000 Rainwater Harvesting
IPC-34 3,901,500 Granular Shoulder (4.335 km BC)
IPC-34 400,000 Level Sheet not completed
As per CA Clause 16.1 contractor maintain the road
34 during construction period, due to non conplience of
IPC-34 200,000
authority & AE observation for road maintenance &
safety.
IPC-34 40,000 Drone video not submitted for the Month of June-23
IPC-34 3,510,000 Mastic Asphalt on VUPs (approx area 1350*2* rate 1300)
IPC-35 4,302,233 Granular Shoulder
Drone video not submitted for the Month of July and
IPC-35 80,000
August-23
IPC-35 500,000 Median Drain
IPC-35 500,000 Rainwater Harvesting
IPC-35 500,000 Level Sheet not completed
Safety and Road Maintenance- due to non conplience
IPC-35 100,000 of authority & AE observation for road maintenance &
safety.
35
IPC-35 2,147,600 Mastic Asphalt on MNBs (approx area 1400* rate 1300)

PCC on separator b/w Service Road and RE wall


IPC-35 524,084
( 329+060 To 329+800 RHS -SR)
IPC-35 200,000 Material Invoice not submitted
The Contrator has been repeatedly failing to submit the
MPR as per CA for the last 12 Months. Despite of
IPC-35 100,000
varoious reminder, the contractor is not submitting MPR
on time.
Details of Withheld/Released Amount (Rs.)

S.No. IPC Withheld Amount (Rs.) Penalty Amount Reasons for Penalty Released Amount (Rs.) Remarks

Withheld Amount Released Amount


Reasons for Withheld Reasons for released
(Rs.) (Rs.)

IPC-36 6,191,177 Granular Shoulder

IPC-36 2,301,000 Mastic Asphalt on VUPs (approx area 1500* rate 1300)

IPC-36 1,534,000 Mastic Asphalt on MNBs (approx area 1000* rate 1300)

IPC-36 50,000 Drone video not submitted for the Month of Sep-23

IPC-36 500,000 Median Drain

IPC-36 500,000 Rainwater Harvesting

36 Safety and Road Maintenance- due to non conplience of


IPC-36 100,000 authority & AE observation for road maintenance &
safety.

IPC-36 1,765,911 PCC on separator b/w Service Road and RE wall

The Contrator has been repeatedly failing to submit the


MPR as per CA for more than last 12 Months. Despite of
IPC-36 200,000 varoious reminder, the contractor is not submitting MPR
on time. Even the contractor has not yet submitted the
MPR for the Month of Sep-23.

IPC-36 1,717,687 Median Filling (Earth work) and Earthen Shoulder

IPC-36 237,463 Meadin Kerb on MCW

Total Amount (Rs.) 122,559,169 3,137,432 28,689,433 Balance Amount


Previous Amount (Rs.) 122,559,169 3,137,432 28,689,433
This Bill Amount (Rs.) - - - 93,869,736
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA
Contractor : M/s VRC-SPIDPL (JV) Period
Authority's Engineer : M/s ICT Private Limited in association with VESPL From To
SPS No.-37 01-09-2023 30-09-2023

Price Adjustment Calculation as per Article 19.10.4


CULVERT, MAJOR BRIDGE
EARTHWORK, CONCRETE
BITUMINOUS MINOR AND Base Index Current Index
Component Des. GRANULAR & PAVEMENT Formula for Adjustments of Prices
WORKS BRIDGE & STRUCTURE (October-2019) (April-2023)
OTHER WORK WORK
VUP WORK

Labour PL 20% 20% 20% 15% 15% VRW= 0.85 x RW x (PLx (L1-L0)/L0) L0 288 L1 344.637
Cement PC 5% 0% 20% 15% 15% VRW= 0.85 x RW x (PCx (C1-C0)/C0) C0 118.6 C1 136.000
Steel PS 0% 0% 0% 15% 20% VRW= 0.85 x RW x (PSx (S1-S0)/S0) S0 102.6 S1 145.700
Bitumen PB 0% 15% 0% 0% 0% VRW= 0.85 x RW x (PBx (B1-B0)/B0) B0 34720 B1 50752
Fuel and Lubricants PF 10% 10% 10% 10% 10% VRW= 0.85 x RW x (PFx (F1-F0)/F0) F0 65.03 F1 90.020
All commodities PM 50% 40% 35% 30% 25% VRW= 0.85 x RW x (PMx (M1-M0)/M0) M0 122 M1 151.100
Plant, Machinery and spares PA 15% 15% 15% 15% 15% VRW= 0.85 x RW x (PAx (A1-A0)/A0) A0 74.2 A1 87.100
100% 100% 100% 100% 100%

Description of Working Work Done Labour Cement Steel Bitumen Fuel and Lubricants Plant, Machinery
General Material Gross Amount
Work Period Amount Amount Amount Amount Amount Amount Amount

EARTHWORK, GRANULAR & OTHER WORK 20,294,885 678,490 126,544 - - 662,915 2,057,352 449,865 3,975,166

BITUMINOUS WORKS 30,917,283 1,033,613 - - 1,820,202 1,009,887 2,507,341 685,326 7,056,369

CONCRETE PAVEMENT WORK Sep-23 - - - - - - - - -

CULVERT, MINOR BRIDGE & VUP 1,204,194 30,194 22,525 64,497 - 39,334 73,244 26,693 256,486

MAJOR BRIDGE AND STRUCTURE WORK - - - - - - - - -

TOTAL (A) 52,416,362 11,288,021

Hold Amount 10% (Non approval of EOT-4) 1,128,802

Recommended Amount -
Details of Withheld Price Adjustment due to Non Approval of EOT-4

Withheld Amount (Rs.) Remarks


S.No. IPC
Withheld Amount (Rs.) Reasons for Withheld

Withheld Price Adjustment of SPS27 and COS-1 RA-11-


1 IPC-27 1,517,058
Non Approval of EOT-4

Withheld Price Adjustment of SPS 28 and COS-1 RA-12


2 IPC-28 2,261,597
Non Approval of EOT-4

Withheld Price Adjustment of SPS 29 and COS-1 RA-13


3 IPC-29 1,020,498
Non Approval of EOT-4

Withheld Price Adjustment of SPS 30 and COS-1 RA-14


4 IPC-30 1,838,578
Non Approval of EOT-4

Withheld Price Adjustment of SPS 31 for Non Approval


5 IPC-31 1,486,084
of EOT-4

Withheld Price Adjustment of SPS 32 for Non Approval


6 IPC-32 295,138
of EOT-4

Withheld Price Adjustment of SPS 33 for Non Approval


7 IPC-33 1,844,294
of EOT-4

Withheld Price Adjustment of SPS 34 for Non Approval


8 IPC-34 1,070,015
of EOT-4

Withheld Price Adjustment of SPS 35 for Non Approval


9 IPC-35 730,196
of EOT-4

Withheld Price Adjustment of SPS 36 for Non Approval


10 IPC-36 1,788,936
of EOT-4

Total Amount (Rs.) 13,852,395


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-1) Earthwork up to top of the sub-grade- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl.No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level & FDD Checking of Subgrade Top Layer 326+340 326+500 LHS SG TOP 160 VRC-SP/NH71/HW-82 24-Aug-20 1
2 Level & FDD Checking of Subgrade Top Layer 326+500 326+550 LHS SG TOP 50 VRC-SP/NH71/HW-529 23-Sep-20 1 Checked by AE Rep.
3 Level & FDD Checking of Subgrade Top Layer 326+550 326+650 LHS SG TOP 100 VRC-SP/NH71/HW-6628 20-Oct-21 15 Checked by AE Rep.
4 Level & FDD Checking of Subgrade Top Layer 326+650 326+700 LHS SG TOP 50 VRC-SP/NH71/HW-527 23-Sep-20 1 Checked by AE Rep.
5 Level & FDD Checking of Subgrade Top Layer 326+700 326+950 LHS SG TOP 250 VRC-SP/NH71/HW-81 24-Aug-20 1
6 Level & FDD Checking of Subgrade Top Layer 326+950 327+150 LHS SG TOP 200 VRC-SP/NH71/HW-554 25-Sep-20 1 Checked by AE Rep.
7 Level & FDD Checking of Subgrade Top Layer 327+150 327+650 LHS SG TOP 500 VRC-SP/NH71/HW-455 16-Sep-20 1
8 Level & FDD Checking of Subgrade Top Layer 327+650 327+700 LHS SG TOP 50 VRC-SP/NH71/HW-2787 07-Feb-21 6
9 Level & FDD Checking of Subgrade Top Layer 327+700 327+750 LHS SG TOP 50 VRC-SP/NH-71/HW-5941 07-Aug-21 12 Checked by AE Rep.
10 Level & FDD Checking of Subgrade Top Layer 330+110 330+300 LHS SG TOP 190 VRC-SP/NH-71/HW-1907 31-Dec-20 4
11 Level & FDD Checking of Subgrade Top Layer 330+300 330+430 LHS SG TOP 130 Done by earlier company 1
12 Level & FDD Checking of Subgrade Top Layer 331+140 331+300 LHS SG TOP 160 VRC-SP/NH71/HW-8831 01-Jun-22 22
13 Level & FDD Checking of Subgrade Top Layer 331+300 331+420 LHS SG TOP 120 VRC-SP/NH71/HW-56 21-Aug-20 1
14 Level & FDD Checking of Subgrade Top Layer 331+500 331+550 LHS SG TOP 50.0 VRC-SP/NH71/HW-4259 25-Apr-21 8
15 Level & FDD Checking of Subgrade Top Layer 331+550 331+910 LHS SG TOP 360 Done by earlier company 1
16 Level & FDD Checking of Subgrade Top Layer 331+910 332+000 LHS SG TOP 90 VRC-SP/NH71/HW-541 24-Sep-20 1 Checked by AE Rep.
17 Level & FDD Checking of Subgrade Top Layer 332+000 332+550 LHS SG TOP 550 Done by earlier company 1
18 Level & FDD Checking of Subgrade Top Layer 332+550 332+700 LHS SG TOP 150 VRC-SP/NH71/HW-103 25-Aug-20 1 Checked by AE Rep.
19 Level & FDD Checking of Subgrade Top Layer 332+700 332+750 LHS SG TOP 50 VRC-SP/NH71/HW-5942 07-Aug-21 12
20 Level & FDD Checking of Subgrade Top Layer 333+360 333+470 LHS SG TOP 110 VRC-SP/NH-71/HW-2277 19-Jan-21 6
21 Level & FDD Checking of Subgrade Top Layer 333+470 333+760 LHS SG TOP 290 Done by earlier company 1
22 Level & FDD Checking of Subgrade Top Layer 333+760 334+000 LHS SG TOP 240 VRC-SP/NH71/HW-78 25-Aug-20 1
23 Level & FDD Checking of Subgrade Top Layer 334+000 334+110 LHS SG TOP 110 VRC-SP/NH-71/HW-1653 19-Dec-20 4
24 Level & FDD Checking of Subgrade Top Layer 334+110 334+400 LHS SG TOP 290 Done by earlier company 1
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-1) Earthwork up to top of the sub-grade- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl.No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
25 Level & FDD Checking of Subgrade Top Layer 334+400 334+800 LHS SG TOP 400 VRC-SP/NH71/HW-77 24-Aug-20 1
26 Level & FDD Checking of Subgrade Top Layer 334+800 334+900 LHS SG TOP 100 VRC -SP/NH-71/HW-5349 07-Apr-21 11 Checked by AE Rep.
27 Level & FDD Checking of Subgrade Top Layer 337+360 337+450 LHS SG TOP 90 VRC-SP/NH71/HW-347 11-Sep-20 1
28 Level & FDD Checking of Subgrade Top Layer 337+450 337+500 LHS SG Top 50 VRC -SP/NH-71/HW-2732 05-Feb-21 6 Checked by AE Rep.
29 Level & FDD Checking of Subgrade Top Layer 337+500 337+720 LHS SG TOP 220 VRC-SP/NH71/HW-1025 02-Oct-20 2 Checked by AE Rep.
30 Level & FDD Checking of Subgrade Top Layer 337+720 337+850 LHS SG TOP 130 VRC-SP/NH71/HW-558 25-Sep-20 1 Checked by AE Rep.
31 Level & FDD Checking of Subgrade Top Layer 337+850 338+000 LHS SG TOP 150 VRC-SP/NH71/HW-556 26-Sep-20 1 Checked by AE Rep.
32 Level & FDD Checking of Subgrade Top Layer 338+000 338+280 LHS SG TOP 280 VRC-SP/NH71/HW-361 08-Sep-20 1 Checked by AE Rep.
33 Level & FDD Checking of Subgrade Top Layer 340+200 340+280 LHS SG TOP 80 VRC-SP/NH71/HW-6785 17-Nov-21 15 Checked by AE Rep.
34 Level & FDD Checking of Subgrade Top Layer 338+280 338+430 LHS SG Top 150 VRC-SP/NH-71/HW-3196 20-Feb-21 6
35 Level & FDD Checking of Subgrade Top Layer 340+280 340+360 LHS SG TOP 80 VRC-SP/NH71/HW-124 26-Aug-20 1 Checked by AE Rep.
36 Level & FDD Checking of Subgrade Top Layer 340+360 340+400 LHS SG Top 40 VRC-SP/NH-71/HW-2900 10-Feb-21 6
37 Level & FDD Checking of Subgrade Top Layer 340+400 340+620 LHS SG TOP 220 VRC-SP/NH71/HW-105 25-Aug-20 1
38 Level & FDD Checking of Subgrade Top Layer 340+620 340+850 LHS SG TOP 230 VRC-SP/NH71/HW-2596 30-Jan-21 5 Checked by AE Rep.
39 Level & FDD Checking of Subgrade Top Layer 340+850 340+910 LHS SG TOP 60 VRC-SP/NH71/HW-7995 03-Mar-22 23 Checked by AE Rep.
40 Level & FDD Checking of Subgrade Top Layer 340+910 341+020 LHS SG Top 110 VRC -SP/NH-71/HW-2865 09-Feb-21 6 Checked by AE Rep.
41 Level & FDD Checking of Subgrade Top Layer 341+020 341+075 LHS SG Top 55 VRC-SP/NH-71/HW-5407 07-Aug-21 11
42 Level & FDD Checking of Subgrade Top Layer 341+675 341+700 LHS SG Top 25 VRC-SP/NH-71/HW-6786 17-Nov-21 15 Checked by AE Rep.
43 Level & FDD Checking of Subgrade Top Layer 341+700 342+000 LHS SG TOP 300 VRC-SP/NH71/HW-68 22-Aug-20 1
44 Level & FDD Checking of Subgrade Top Layer 342+000 342+400 LHS SG TOP 400 Done by earlier company 1
45 Level & FDD Checking of Subgrade Top Layer 342+400 342+440 LHS SG TOP 40 VRC-SP/NH71/HW-73 24-Aug-20 1 Checked by AE Rep.
46 Level & FDD Checking of Subgrade Top Layer 342+440 342+800 LHS SG TOP 360 Done by earlier company 1
47 Level & FDD Checking of Subgrade Top Layer 342+800 342+840 LHS SG TOP 40 VRC-SP/NH71/HW-439 15-Sep-20 1
48 Level & FDD Checking of Subgrade Top Layer 342+840 343+100 LHS SG TOP 260 Done by earlier company 1
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-1) Earthwork up to top of the sub-grade- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl.No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
49 Level & FDD Checking of Subgrade Top Layer 343+100 343+380 LHS SG TOP 280 VRC-SP/NH71/HW-363 08-Sep-20 1
50 Level & FDD Checking of Subgrade Top Layer 344+680 344+750 LHS SG TOP 70 Done by earlier company 1
51 Level & FDD Checking of Subgrade Top Layer 344+750 344+790 LHS SG TOP 40 VRC-SP/NH71/HW-119 26-Aug-20 1
52 Level & FDD Checking of Subgrade Top Layer 344+790 345+180 LHS SG TOP 390 Done by earlier company 1
53 Level & FDD Checking of Subgrade Top Layer 345+180 345+240 LHS SG TOP 60 VRC-SP/NH71/HW-190 31-Aug-20 1 Checked by AE Rep.
54 Level & FDD Checking of Subgrade Top Layer 345+240 345+390 LHS SG TOP 150 Done by earlier company 1
55 Level & FDD Checking of Subgrade Top Layer 345+390 345+430 LHS SG TOP 40 VRC-SP/NH71/HW-266 03-Sep-20 1
56 Level & FDD Checking of Subgrade Top Layer 345+430 345+680 LHS SG TOP 250 VRC-SP/NH71/HW-181 31-Aug-20 1
57 Level & FDD Checking of Subgrade Top Layer 345+680 345+810 LHS SG TOP 130 Done by earlier company 1
58 Level & FDD Checking of Subgrade Top Layer 347+120 347+320 LHS SG TOP 200 VRC-SP/NH71/HW-499 21-Sep-20 1 Checked by AE Rep.
59 Level & FDD Checking of Subgrade Top Layer 347+320 347+430 LHS SG TOP 110 Done by earlier company 1
60 Level & FDD Checking of Subgrade Top Layer 347+430 347+790 LHS SG TOP 360 VRC-SP/NH71/HW-147 28-Aug-20 1 Checked by AE Rep.
61 Level & FDD Checking of Subgrade Top Layer 347+790 348+400 LHS SG TOP 610 VRC-SP/NH71/HW-143 28-Aug-20 1 Checked by AE Rep.
62 Level & FDD Checking of Subgrade Top Layer 348+400 348+500 LHS SG TOP 100 VRC-SP/NH71/HW-866 13-Oct-20 2 Checked by AE Rep.
63 Level & FDD Checking of Subgrade Top Layer 348+500 348+804 LHS SG TOP 304 VRC-SP/NH71/HW-481 20-Sep-20 1
Total Qty LHS 11264 m A
1 Level & FDD Checking of Subgrade Top Layer 307+600 307+700 RHS SG TOP 100 VRC-SP/NH71/HW-890 15-Oct-20 2 Checked by AE Rep.
2 Level & FDD Checking of Subgrade Top Layer 307+700 307+950 RHS SG TOP 250 VRC-SP/NH71/HW-294 04-Sep-20 1 Checked by AE Rep.
3 Level & FDD Checking of Subgrade Top Layer 307+950 308+330 RHS SG TOP 380 VRC-SP/NH71/HW-212 01-Sep-20 1 Checked by AE Rep.
4 Level & FDD Checking of Subgrade Top Layer 308+330 308+350 RHS SG TOP 20 VRC-SP/NH71/HW-973 23-Oct-20 2
5 Level & FDD Checking of Subgrade Top Layer 309+400 309+500 RHS SG TOP 100 Done by earlier company 1
6 Level & FDD Checking of Subgrade Top Layer 309+500 309+530 RHS SG TOP 30 VRC-SP/NH71/HW-1606 17-Dec-20 4 Checked by AE Rep.
7 Level & FDD Checking of Subgrade Top Layer 309+530 309+700 RHS SG TOP 170 Done by earlier company 1
8 Level & FDD Checking of Subgrade Top Layer 309+700 309+800 RHS SG TOP 100 VRC-SP/NH71/HW-759 23-Oct-20 2
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-1) Earthwork up to top of the sub-grade- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl.No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
9 Level & FDD Checking of Subgrade Top Layer 309+800 309+940 RHS SG TOP 140 Done by earlier company 1
10 Level & FDD Checking of Subgrade Top Layer 309+940 309+955 RHS SG TOP 15 VRC-SP/NH71/HW-2079 11-Jan-21 5
11 Level & FDD Checking of Subgrade Top Layer 309+963 310+000 RHS SG TOP 37 VRC-SP/NH71/HW-2212 16-Jan-21 5 Checked by AE Rep.
12 Level & FDD Checking of Subgrade Top Layer 310+000 310+140 RHS SG TOP 140 VRC-SP/NH71/HW-295 04-Sep-20 1 Checked by AE Rep.
13 Level & FDD Checking of Subgrade Top Layer 310+140 311+500 RHS SG TOP 1360 Done by earlier company 1
14 Level & FDD Checking of Subgrade Top Layer 311+500 312+300 RHS SG TOP 800 VRC-SP/NH71/HW-129 27-Aug-20 1 Checked by AE Rep.
15 Level & FDD Checking of Subgrade Top Layer 312+300 312+340 RHS SG TOP 40 VRC-SP/NH71/HW-1114 04-Nov-20 3
16 Level & FDD Checking of Subgrade Top Layer 312+340 312+540 RHS SG TOP 200 VRC-SP/NH71/HW-130 27-Aug-20 1 Checked by AE Rep.
17 Level & FDD Checking of Subgrade Top Layer 312+540 312+700 RHS SG TOP 160 VRC-SP/NH71/HW-152 28-Aug-20 1 Checked by AE Rep.
18 Level & FDD Checking of Subgrade Top Layer 312+700 312+760 RHS SG TOP 60 VRC-SP/NH71/HW-505 22-Sep-20 1
19 Level & FDD Checking of Subgrade Top Layer 312+760 312+780 RHS SG TOP 20 VRC-SP/NH71/HW-131 27-Aug-20 1 Checked by AE Rep.
20 Level & FDD Checking of Subgrade Top Layer 312+780 312+900 RHS SG TOP 120 VRC-SP/NH71/HW-169 29-Aug-20 1 Checked by AE Rep.
21 Level & FDD Checking of Subgrade Top Layer 312+900 312+980 RHS SG TOP 80 VRC-SP/NH71/HW-192 31-Aug-20 1 Checked by AE Rep.
22 Level & FDD Checking of Subgrade Top Layer 312+980 313+020 RHS SG TOP 40 VRC-SP/NH71/HW-999 26-Oct-20 2 Checked by AE Rep.
23 Level & FDD Checking of Subgrade Top Layer 313+020 313+400 RHS SG TOP 380 VRC-SP/NH71/HW-133 27-Aug-20 1 Checked by AE Rep.
24 Level & FDD Checking of Subgrade Top Layer 313+400 313+550 RHS SG TOP 150 VRC-SP/NH71/HW-419 12-Sep-20 1
25 Level & FDD Checking of Subgrade Top Layer 313+550 313+650 RHS SG TOP 100 VRC-SP/NH71/HW-509 14-Sep-20 1 Checked by AE Rep.
26 Level & FDD Checking of Subgrade Top Layer 313+650 313+693 RHS SG TOP 43 VRC-SP/NH71/HW-8314 20-Apr-22 20
27 Level & FDD Checking of Subgrade Top Layer 313+703 313+752 RHS SG TOP 48.75 VRC-SP/NH71/HW-8315 20-Apr-22 20 Checked by AE Rep.
28 Level & FDD Checking of Subgrade Top Layer 313+780 313+800 RHS SG TOP 19.75 VRC-SP/NH71/HW-8316 20-Apr-22 20
29 Level & FDD Checking of Subgrade Top Layer 313+800 313+850 RHS SG TOP 50 VRC-SP/NH71/HW-5433 10-Jul-21 11 Checked by AE Rep.
30 Level & FDD Checking of Subgrade Top Layer 313+850 313+950 RHS SG TOP 100 VRC-SP/NH71/HW-1156 09-Nov-20 3 Checked by AE Rep.
31 Level & FDD Checking of Subgrade Top Layer 313+950 314+310 RHS SG TOP 360 VRC-SP/NH71/HW-153 28-Aug-20 1 Checked by AE Rep.
32 Level & FDD Checking of Subgrade Top Layer 314+310 314+380 RHS SG TOP 70 VRC-SP/NH71/HW-416 14-Sep-20 1 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-1) Earthwork up to top of the sub-grade- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl.No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
33 Level & FDD Checking of Subgrade Top Layer 314+380 314+760 RHS SG TOP 380 VRC-SP/NH71/HW-106 26-Aug-20 1
34 Level & FDD Checking of Subgrade Top Layer 314+760 314+840 RHS SG TOP 80 VRC-SP/NH71/HW-695 01-Oct-20 2
35 Level & FDD Checking of Subgrade Top Layer 314+840 314+920 RHS SG TOP 80 VRC-SP/NH71/HW-188 31-Aug-20 1 Checked by AE Rep.
36 Level & FDD Checking of Subgrade Top Layer 314+920 315+180 RHS SG TOP 260 VRC-SP/NH71/HW-107 26-Aug-20 1 Checked by AE Rep.
37 Level & FDD Checking of Subgrade Top Layer 315+180 315+300 RHS SG TOP 120 VRC-SP/NH71/HW-814 09-Oct-20 2 Checked by AE Rep.
38 Level & FDD Checking of Subgrade Top Layer 315+300 315+500 RHS SG TOP 200 Done by earlier company 1
39 Level & FDD Checking of Subgrade Top Layer 315+500 315+530 RHS SG TOP 30 VRC-SP/NH71/HW-3227 23-Feb-21 7 Checked by AE Rep.
40 Level & FDD Checking of Subgrade Top Layer 315+530 315+620 RHS SG TOP 90 VRC-SP/NH71/HW-569 19-Sep-20 1
41 Level & FDD Checking of Subgrade Top Layer 316+650 316+880 RHS SG TOP 230 VRC-SP/NH71/HW-368 09-Sep-20 1 Checked by AE Rep.
42 Level & FDD Checking of Subgrade Top Layer 316+880 316+970 RHS SG TOP 90 VRC-SP/NH71/HW-5430 10-Jul-21 11
43 Level & FDD Checking of Subgrade Top Layer 316+970 317+030 RHS SG TOP 60 VRC-SP/NH71/HW-108 26-Aug-20 1
44 Level & FDD Checking of Subgrade Top Layer 317+030 317+040 RHS SG TOP 10 VRC-SP/NH71/HW-951 21-Oct-20 2 Checked by AE Rep.
45 Level & FDD Checking of Subgrade Top Layer 317+040 317+540 RHS SG TOP 500 VRC-SP/NH71/HW-109 26-Aug-20 1
46 Level & FDD Checking of Subgrade Top Layer 317+540 317+620 RHS SG TOP 80 VRC-SP/NH71/HW-381 10-Sep-20 1
47 Level & FDD Checking of Subgrade Top Layer 317+620 317+880 RHS SG TOP 260 Done by earlier company 1
48 Level & FDD Checking of Subgrade Top Layer 317+880 317+960 RHS SG TOP 80 VRC-SP/NH71/HW-954 21-Oct-20 2
49 Level & FDD Checking of Subgrade Top Layer 317+960 319+160 RHS SG TOP 1200 Done by earlier company 1
50 Level & FDD Checking of Subgrade Top Layer 319+160 319+360 RHS SG TOP 200 VRC-SP/NH71/HW-777 06-Oct-20 2 Checked by AE Rep.
51 Level & FDD Checking of Subgrade Top Layer 319+360 319+400 RHS SG TOP 40 VRC-SP/NH71/HW-3240 24-Feb-21 7
52 Level & FDD Checking of Subgrade Top Layer 319+400 319+500 RHS SG TOP 100 VRC-SP/NH71/HW-335 07-Sep-20 1 Checked by AE Rep.
53 Level & FDD Checking of Subgrade Top Layer 319+500 319+620 RHS SG TOP 120 VRC-SP/NH71/HW-311 05-Sep-20 1
54 Level & FDD Checking of Subgrade Top Layer 319+620 319+820 RHS SG TOP 200 VRC-SP/NH71/HW-236 03-Sep-20 1 Checked by AE Rep.
55 Level & FDD Checking of Subgrade Top Layer 319+820 319+840 RHS SG TOP 20 VRC-SP/NH71/HW-1112 04-Nov-20 3 Checked by AE Rep.
56 Level & FDD Checking of Subgrade Top Layer 319+840 320+300 RHS SG TOP 460 Done by earlier company 1
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-1) Earthwork up to top of the sub-grade- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl.No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
57 Level & FDD Checking of Subgrade Top Layer 320+300 320+320 RHS SG TOP 20 VRC-SP/NH71/HW-1099 03-Nov-20 3
58 Level & FDD Checking of Subgrade Top Layer 320+320 320+460 RHS SG TOP 140 VRC-SP/NH71/HW-429 15-Sep-20 1 Checked by AE Rep.
59 Level & FDD Checking of Subgrade Top Layer 320+460 320+540 RHS SG TOP 80 VRC-SP/NH71/HW-430 15-Sep-20 1
60 Level & FDD Checking of Subgrade Top Layer 320+540 320+600 RHS SG TOP 60 VRC-SP/NH71/HW-1224 12-Nov-20 3
61 Level & FDD Checking of Subgrade Top Layer 327+750 327+890 RHS SG TOP 140 VRC-SP/NH-71/HW-2993 13-Feb-21 6 Checked by AE Rep.
62 Level & FDD Checking of Subgrade Top Layer 327+890 328+000 RHS SG TOP 110 VRC-SP/NH71/HW-80 24-Aug-20 1
63 Level & FDD Checking of Subgrade Top Layer 328+000 328+260 RHS SG TOP 260 VRC-SP/NH71/HW-4450 06-May-21 9 Checked by AE Rep.
64 Level & FDD Checking of Subgrade Top Layer 328+260 328+460 RHS SG TOP 200 VRC-SP/NH71/HW-79 24-Aug-20 1
65 Level & FDD Checking of Subgrade Top Layer 328+460 328+470 RHS SG TOP 10 VRC-SP/NH71/HW-73 23-Aug-20 1 Checked by AE Rep.
66 Level & FDD Checking of Subgrade Top Layer 332+750 332+800 RHS SG TOP 50 VRC-SP/NH71/HW-3026 14-Feb-21 6 Checked by AE Rep.
67 Level & FDD Checking of Subgrade Top Layer 332+800 332+900 RHS SG TOP 100 VRC-SP/NH71/HW-102 25-Aug-20 1
68 Level & FDD Checking of Subgrade Top Layer 332+900 333+100 RHS SG TOP 200 VRC-SP/NH-71/HW-1698 22-Dec-20 4
69 Level & FDD Checking of Subgrade Top Layer 333+100 333+200 RHS SG TOP 100 VRC -SP/NH-71/Hw-8169 02-Apr-22 20
70 Level & FDD Checking of Subgrade Top Layer 333+200 333+310 RHS SG TOP 110 VRC-SP/NH-71/HW-3151 18-Feb-21 6 Checked by AE Rep.
71 Level & FDD Checking of Subgrade Top Layer 333+310 333+360 RHS SG TOP 50 VRC-SP/NH-71/HW-6153 23-Aug-21 12
Total Qty RHS 12204 m B
Total Qty (Both Side) 11.734 Km. C=(A + B)/2
Previous Qty. (Both Side) 11.734 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-2) Sub-Base Course-Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level and FDD Checking of GSB Top Layer 326+340 326+500 LHS GSB TOP 160 VRC-SP/NH71/HW-157 28-Aug-20 1 Checked by AE Rep.
2 Level and FDD Checking of GSB Top Layer 326+500 326+550 LHS GSB TOP 50 VRC-SP/NH71/HW-539 24-Sep-20 1
3 Level and FDD Checking of GSB Top Layer 326+550 326+650 LHS GSB TOP 100 VRC-SP/NH71/HW-6659 24-Oct-21 15 Checked by AE Rep.
4 Level and FDD Checking of GSB Top Layer 326+650 326+700 LHS GSB TOP 50 VRC-SP/NH71/HW-575 24-Sep-20 1 Checked by AE Rep.
5 Level and FDD Checking of GSB Top Layer 326+700 326+950 LHS GSB TOP 250 VRC-SP/NH71/HW-158 28-Aug-20 1 Checked by AE Rep.
6 Level and FDD Checking of GSB Top Layer 326+950 327+160 LHS GSB TOP 210 VRC-SP/NH71/HW-582 26-Sep-20 1
7 Level and FDD Checking of GSB Top Layer 327+160 327+650 LHS GSB TOP 490 VRC-SP/NH71/HW-472 19-Sep-20 1 Checked by AE Rep.
8 Level and FDD Checking of GSB Top Layer 327+650 327+700 LHS GSB Top 50 VRC -SP/NH-71/HW-2822 08-Feb-21 6
9 Level and FDD Checking of GSB Top Layer 327+700 327+750 LHS GSB TOP 50 VRC-SP/NH71/HW-5956 08-Aug-21 12
10 Level and FDD Checking of GSB Top Layer 330+110 330+310 LHS GSB TOP 200 VRC-SP/NH71/HW-2275 19-Jan-21 5
11 Level and FDD Checking of GSB Top Layer 330+310 330+430 LHS GSB TOP 120 Done by earlier company 1
01-05-2022
Level and FDD Checking of GSB Top Layer 330+800 330+900 GSB TOP 100 VRC -SP/NH-71/Hw-8497
12 LHS 02:00:PM 26
13 Level and FDD Checking of GSB Top Layer 331+140 331+300 LHS GSB TOP 160 VRC-SP/NH71/HW-8843 04-Jun-22 22 Checked by AE Rep
14 Level and FDD Checking of GSB Top Layer 331+300 331+420 LHS GSB TOP 120 VRC-SP/NH71/HW-67 22-Aug-20 1
15 Level and FDD Checking of GSB Top Layer 331+420 331+500 LHS GSB TOP 80 VRC-SP/NH71/HW-9782 01-Dec-22 28 Checked by AE Rep. abc
16 Level and FDD Checking of GSB Top Layer 331+500 331+550 LHS GSB Top 50.0 VRC -SP/NH-71/HW-4274 26-Apr-21 8 Checked by AE Rep.
17 Level and FDD Checking of GSB Top Layer 331+550 331+910 LHS GSB TOP 360 Done by earlier company 1
18 Level and FDD Checking of GSB Top Layer 331+910 332+000 LHS GSB TOP 90 VRC-SP/NH71/HW-598 27-Sep-20 1 Checked by AE Rep.
19 Level and FDD Checking of GSB Top Layer 332+000 332+560 LHS GSB TOP 560 Done by earlier company 1
20 Level and FDD Checking of GSB Top Layer 332+560 332+700 LHS GSB TOP 140 VRC-SP/NH71/HW-218 01-Sep-20 1 Checked by AE Rep.
21 Level and FDD Checking of GSB Top Layer 332+700 332+750 LHS GSB TOP 50 VRC-SP/NH71/HW-5957 08-Aug-21 12 Checked by AE Rep.
22 Level and FDD Checking of GSB Top Layer 333+360 333+470 LHS GSB TOP 110 VRC-SP/NH71/HW-2386 22-Jan-21 5
23 Level and FDD Checking of GSB Top Layer 333+470 333+760 LHS GSB TOP 290 Done by earlier company 1
24 Level and FDD Checking of GSB Top Layer 333+760 334+000 LHS GSB TOP 240 VRC-SP/NH71/HW-219 01-Sep-20 1 Checked by AE Rep.
25 Level and FDD Checking of GSB Top Layer 334+000 334+110 LHS GSB TOP 110 VRC-SP/NH-71/HW-1673 21-Dec-20 4
26 Level and FDD Checking of GSB Top Layer 334+110 334+400 LHS GSB TOP 290 Done by earlier company 1
27 Level and FDD Checking of GSB Top Layer 334+400 334+800 LHS GSB TOP 400 VRC-SP/NH71/HW-244 02-Sep-20 1 Checked by AE Rep.
28 Level and FDD Checking of GSB Top Layer 334+800 334+900 LHS GSB TOP 100 VRC -SP/NH-71/HW-5367 07-May-21 11 Checked by AE Rep.
29 Level and FDD Checking of GSB Top Layer 337+360 337+450 LHS GSB TOP 90 VRC-SP/NH71/HW-397 11-Sep-20 1
30 Level and FDD Checking of GSB Top Layer 337+450 337+500 LHS GSB TOP 50 VRC -SP/NH-71/HW-2768 06-Feb-21 6
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-2) Sub-Base Course-Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
31 Level and FDD Checking of GSB Top Layer 337+500 337+720 LHS GSB TOP 220 VRC-SP/NH71/HW-1040 28-Oct-20 2 Checked by AE Rep.
32 Level and FDD Checking of GSB Top Layer 337+720 338+000 LHS GSB TOP 280 VRC-SP/NH71/HW-588 26-Sep-20 1 Checked by AE Rep.
33 Level and FDD Checking of GSB Top Layer 338+000 338+280 LHS GSB TOP 280 VRC-SP/NH71/HW-438 15-Sep-20 1 Checked by AE Rep.
34 Level and FDD Checking of GSB Top Layer 338+280 338+430 LHS GSB TOP 150 VRC -SP/NH-71/HW-3232 23-Feb-21 6
35 Level and FDD Checking of GSB Top Layer 340+200 340+280 LHS GSB TOP 80 VRC -SP/NH-71/HW-6797 18-Nov-21 15
36 Level and FDD Checking of GSB Top Layer 340+280 340+360 LHS GSB TOP 80 VRC-SP/NH71/HW-140 27-Aug-20 1 Checked by AE Rep.
37 Level and FDD Checking of GSB Top Layer 340+360 340+400 LHS GSB TOP 40 VRC -SP/NH-71/HW-2936 11-Feb-21 6 Checked by AE Rep.
38 Level and FDD Checking of GSB Top Layer 340+400 340+620 LHS GSB TOP 220 VRC-SP/NH71/HW-126 26-Aug-20 1
39 Level and FDD Checking of GSB Top Layer 340+620 340+850 LHS GSB Top 230 VRC -SP/NH-71/HW-7096 12-Dec-21 16
40 Level and FDD Checking of GSB Top Layer 340+850 340+910 LHS GSB TOP 60 VRC -SP/NH-71/Hw-8058 14-Mar-22 19
41 Level and FDD Checking of GSB Top Layer 340+910 341+020 LHS GSB TOP 110 VRC -SP/NH-71/HW-2901 10-Feb-21 6 Checked by AE Rep.
42 Level and FDD Checking of GSB Top Layer 341+020 341+075 LHS GSB TOP 55 VRC -SP/NH-71/HW-5422 07-Sep-21 11
43 Level and FDD Checking of GSB Top Layer 341+675 341+700 LHS GSB TOP 25 VRC -SP/NH-71/HW-6798 18-Nov-21 15 Checked by AE Rep.
44 Level and FDD Checking of GSB Top Layer 341+700 342+000 LHS GSB TOP 300 VRC-SP/NH71/HW-600 27-Sep-20 1 Checked by AE Rep.
45 Level and FDD Checking of GSB Top Layer 342+000 342+020 LHS GSB TOP 20 VRC-SP/NH-71/HW-9903 24-Dec-22 28 Checked by AE Rep.
46 Level and FDD Checking of GSB Top Layer 342+020 342+260 LHS GSB TOP 240 VRC-SP/NH71/HW-118 26-Aug-20 1 Checked by AE Rep.
47 Level and FDD Checking of GSB Top Layer 342+260 342+400 LHS GSB TOP 140 Done by earlier company 1
48 Level and FDD Checking of GSB Top Layer 342+400 342+440 LHS GSB TOP 40 VRC-SP/NH71/HW-75 24-Aug-20 1 Checked by AE Rep.
49 Level and FDD Checking of GSB Top Layer 342+440 342+650 LHS GSB TOP 210 Done by earlier company 1
50 Level and FDD Checking of GSB Top Layer 342+650 342+680 LHS GSB TOP 30 VRC-SP/NH71/HW-559 25-Sep-20 1
51 Level and FDD Checking of GSB Top Layer 342+680 342+800 LHS GSB TOP 120 VRC-SP/NH71/HW-443 15-Sep-20 1 Checked by AE Rep.
52 Level and FDD Checking of GSB Top Layer 342+800 342+850 LHS GSB TOP 50 VRC-SP/NH71/HW-576 26-Sep-20 1 Checked by AE Rep.
53 Level and FDD Checking of GSB Top Layer 342+850 342+990 LHS GSB TOP 140 Done by earlier company 1
54 Level and FDD Checking of GSB Top Layer 342+990 343+100 LHS GSB TOP 110 VRC-SP/NH71/HW-114 26-Aug-20 1
55 Level and FDD Checking of GSB Top Layer 343+100 343+380 LHS GSB TOP 280 VRC-SP/NH71/HW-560 25-Sep-20 1
56 Level and FDD Checking of GSB Top Layer 344+680 344+740 LHS GSB TOP 60 Done by earlier company 1
57 Level and FDD Checking of GSB Top Layer 344+740 344+790 LHS GSB TOP 50 VRC-SP/NH-71/HW-4877 03-Jun-21 10
58 Level and FDD Checking of GSB Top Layer 344+790 345+180 LHS GSB TOP 390 Done by earlier company 1
59 Level and FDD Checking of GSB Top Layer 345+180 345+240 LHS GSB TOP 60 VRC-SP/NH71/HW-299 04-Sep-20 1 Checked by AE Rep.
60 Level and FDD Checking of GSB Top Layer 345+240 345+390 LHS GSB TOP 150 Done by earlier company 1
61 Level and FDD Checking of GSB Top Layer 345+390 345+680 LHS GSB TOP 290 VRC-SP/NH71/HW-283 03-Sep-20 1 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-2) Sub-Base Course-Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
62 Level and FDD Checking of GSB Top Layer 345+680 345+810 LHS GSB TOP 130 Done by earlier company 1
63 Level and FDD Checking of GSB Top Layer 347+120 347+320 LHS GSB TOP 200 VRC-SP/NH71/HW-500 21-Sep-20 1 Checked by AE Rep.
64 Level and FDD Checking of GSB Top Layer 347+320 347+430 LHS GSB TOP 110 Done by earlier company 1
65 Level and FDD Checking of GSB Top Layer 347+430 347+790 LHS GSB TOP 360 VRC-SP/NH71/HW-276 03-Sep-20 1
66 Level and FDD Checking of GSB Top Layer 347+790 348+000 LHS GSB TOP 210 VRC-SP/NH71/HW-161 29-Aug-20 1 Checked by AE Rep.
67 Level and FDD Checking of GSB Top Layer 348+000 348+390 LHS GSB TOP 390 VRC-SP/NH71/HW-145 28-Aug-20 1
68 Level and FDD Checking of GSB Top Layer 348+390 348+500 LHS GSB TOP 110 VRC-SP/NH71/HW-898 15-Oct-20 2 Checked by AE Rep.
69 Level and FDD Checking of GSB Top Layer 348+500 348+804 LHS GSB TOP 304 VRC-SP/NH71/HW-655 29-Sep-20 1 Checked by AE Rep.
Total Qty LHS 11444.0 m A
1 Level and FDD Checking of GSB Top Layer 307+600 307+700 RHS GSB TOP 100 VRC-SP/NH71/HW-6541 05-Oct-21 14
2 Level and FDD Checking of GSB Top Layer 307+700 307+950 RHS GSB TOP 250 VRC-SP/NH71/HW-314 05-Sep-20 1 Checked by AE Rep.
3 Level and FDD Checking of GSB Top Layer 307+950 308+330 RHS GSB TOP 380 VRC-SP/NH71/HW-262 03-Sep-20 1 Checked by AE Rep.
4 Level and FDD Checking of GSB Top Layer 308+330 308+350 RHS GSB TOP 20 VRC-SP/NH71/HW-4105 17-Apr-21 8
5 Level and FDD Checking of GSB Top Layer 309+400 309+500 RHS GSB TOP 100 Done by earlier company 1
6 Level and FDD Checking of GSB Top Layer 309+500 309+530 RHS GSB TOP 30 VRC-SP/NH-71/HW-1798 28-Dec-20 4 Checked by AE Rep.
7 Level and FDD Checking of GSB Top Layer 309+530 309+700 RHS GSB TOP 170 Done by earlier company 1
8 Level and FDD Checking of GSB Top Layer 309+700 309+800 RHS GSB TOP 100 VRC-SP/NH71/HW-792 07-Oct-20 2
9 Level and FDD Checking of GSB Top Layer 309+800 309+940 RHS GSB TOP 140 VRC-SP/NH71/HW-313 05-Sep-20 1
10 Level and FDD Checking of GSB Top Layer 309+940 309+955 RHS GSB TOP 15 VRC-SP/NH71/HW-4106 17-Apr-21 8 Checked by AE Rep.
11 Level and FDD Checking of GSB Top Layer 309+963 310+000 RHS GSB TOP 37 VRC-SP/NH71/HW-2225 18-Jan-21 5 Checked by AE Rep.
12 Level and FDD Checking of GSB Top Layer 310+000 310+140 RHS GSB TOP 140 VRC-SP/NH71/HW-878 14-Oct-20 2
13 Level and FDD Checking of GSB Top Layer 310+140 310+500 RHS GSB TOP 360 Done by earlier company 1
14 Level and FDD Checking of GSB Top Layer 310+500 310+600 RHS GSB TOP 100 VRC-SP/NH-71/HW-1453 03-Dec-20 4 Checked by AE Rep.
15 Level and FDD Checking of GSB Top Layer 310+600 311+500 RHS GSB TOP 900 Done by earlier company 1
16 Level and FDD Checking of GSB Top Layer 311+500 311+900 RHS GSB TOP 400 VRC-SP/NH71/HW-166 28-Aug-20 1 Checked by AE Rep.
17 Level and FDD Checking of GSB Top Layer 311+900 312+120 RHS GSB TOP 220 VRC-SP/NH71/HW-627 28-Sep-20 1 Checked by AE Rep.
18 Level and FDD Checking of GSB Top Layer 312+120 312+180 RHS GSB TOP 60 VRC-SP/NH71/HW-168 29-Aug-20 1 Checked by AE Rep.
19 Level and FDD Checking of GSB Top Layer 312+180 312+300 RHS GSB TOP 120 VRC-SP/NH71/HW-167 29-Aug-20 1 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-2) Sub-Base Course-Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

20 Level and FDD Checking of GSB Top Layer 312+300 312+340 RHS GSB TOP 40 VRC-SP/NH71/HW-1115 04-Nov-20 3
21 Level and FDD Checking of GSB Top Layer 312+340 312+700 RHS GSB TOP 360 VRC-SP/NH71/HW-332 07-Sep-20 1 Checked by AE Rep.
22 Level and FDD Checking of GSB Top Layer 312+700 312+760 RHS GSB TOP 60 VRC-SP/NH71/HW-506 22-Sep-20 1 Checked by AE Rep.
23 Level and FDD Checking of GSB Top Layer 312+760 312+900 RHS GSB TOP 140 VRC-SP/NH71/HW-333 07-Sep-20 1 Checked by AE Rep.
24 Level and FDD Checking of GSB Top Layer 312+900 313+040 RHS GSB TOP 140 VRC-SP/NH71/HW-1001 26-Oct-20 2
25 Level and FDD Checking of GSB Top Layer 313+040 313+400 RHS GSB TOP 360 VRC-SP/NH71/HW-165 29-Aug-20 1 Checked by AE Rep.
26 Level and FDD Checking of GSB Top Layer 313+400 313+550 RHS GSB TOP 150 VRC-SP/NH71/HW-432 15-Sep-20 1 Checked by AE Rep.
27 Level and FDD Checking of GSB Top Layer 313+550 313+650 RHS GSB TOP 100 VRC-SP/NH71/HW-744 04-Oct-20 2
28 Level and FDD Checking of GSB Top Layer 313+650 313+693 RHS GSB TOP 43 VRC-SP/NH-71/HW-8327 21-Apr-22 20
29 Level and FDD Checking of GSB Top Layer 313+703 313+752 RHS GSB TOP 48.75 VRC-SP/NH-71/HW-8328 21-Apr-22 20
30 Level and FDD Checking of GSB Top Layer 313+780 313+800 RHS GSB TOP 19.75 VRC-SP/NH-71/HW-8329 21-Apr-22 20 Checked by AE Rep.
31 Level and FDD Checking of GSB Top Layer 313+800 313+950 RHS GSB TOP 150 VRC-SP/NH71/HW-5435 02-Jul-21 11 Checked by AE Rep.
32 Level and FDD Checking of GSB Top Layer 313+950 314+310 RHS GSB TOP 360 VRC-SP/NH71/HW-207 01-Sep-20 1 Checked by AE Rep.
33 Level and FDD Checking of GSB Top Layer 314+310 314+380 RHS GSB TOP 70 VRC-SP/NH71/HW-524 23-Sep-20 1
34 Level and FDD Checking of GSB Top Layer 314+380 314+760 RHS GSB TOP 380 VRC-SP/NH71/HW-148 28-Aug-20 1 Checked by AE Rep.
35 Level and FDD Checking of GSB Top Layer 314+760 314+840 RHS GSB TOP 80 VRC-SP/NH71/HW-717 02-Oct-20 2
36 Level and FDD Checking of GSB Top Layer 314+840 314+920 RHS GSB TOP 80 VRC-SP/NH71/HW-193 31-Aug-20 1
37 Level and FDD Checking of GSB Top Layer 314+920 315+180 RHS GSB TOP 260 VRC-SP/NH71/HW-149 28-Aug-20 1 Checked by AE Rep.
38 Level and FDD Checking of GSB Top Layer 315+180 315+300 RHS GSB TOP 120 VRC-SP/NH71/HW-858 02-Oct-20 2
39 Level and FDD Checking of GSB Top Layer 315+300 315+500 RHS GSB TOP 200 Done by earlier company 1
40 Level and FDD Checking of GSB Top Layer 315+500 315+550 RHS GSB TOP 50 3388 08-Mar-21 7 Checked by AE Rep.
41 Level and FDD Checking of GSB Top Layer 315+550 315+620 RHS GSB TOP 70 VRC-SP/NH71/HW-803 08-Oct-20 2
42 Level and FDD Checking of GSB Top Layer 316+650 316+680 RHS GSB TOP 30 VRC-SP/NH71/HW-371 09-Sep-20 1
43 Level and FDD Checking of GSB Top Layer 316+680 316+880 RHS GSB TOP 200 VRC-SP/NH71/HW-382 10-Sep-20 1
44 Level and FDD Checking of GSB Top Layer 316+880 316+970 RHS GSB TOP 90 VRC-SP/NH71/HW-5452 11-Jul-21 11
45 Level and FDD Checking of GSB Top Layer 316+970 317+020 RHS GSB TOP 50 VRC-SP/NH71/HW-150 28-Aug-20 1 Checked by AE Rep.
46 Level and FDD Checking of GSB Top Layer 317+020 317+040 RHS GSB TOP 20 VRC-SP/NH71/HW-952 21-Oct-20 2
47 Level and FDD Checking of GSB Top Layer 317+040 317+100 RHS GSB TOP 60 VRC-SP/NH71/HW-213 01-Sep-20 1
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-2) Sub-Base Course-Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

48 Level and FDD Checking of GSB Top Layer 317+100 317+500 RHS GSB TOP 400 VRC-SP/NH71/HW-151 28-Aug-20 1 Checked by AE Rep.
49 Level and FDD Checking of GSB Top Layer 317+500 317+530 RHS GSB TOP 30 VRC-SP/NH71/HW-1097 03-Nov-20 3 Checked by AE Rep.
50 Level and FDD Checking of GSB Top Layer 317+530 317+540 RHS GSB TOP 10 VRC-SP/NH71/HW-1225 12-Nov-20 3
51 Level and FDD Checking of GSB Top Layer 317+540 317+620 RHS GSB TOP 80 VRC-SP/NH71/HW-434 15-Sep-20 1 Checked by AE Rep.
52 Level and FDD Checking of GSB Top Layer 317+620 317+880 RHS GSB TOP 260 Done by earlier company 1
53 Level and FDD Checking of GSB Top Layer 317+880 317+960 RHS GSB TOP 80 VRC-SP/NH71/HW-1314 19-Nov-20 3
54 Level and FDD Checking of GSB Top Layer 317+960 319+160 RHS GSB TOP 1200 Done by earlier company 1
55 Level and FDD Checking of GSB Top Layer 319+160 319+360 RHS GSB TOP 200 VRC-SP/NH71/HW-787 07-Oct-20 2
56 Level and FDD Checking of GSB Top Layer 319+360 319+400 RHS GSB TOP 40 3252 25-Feb-21 7
57 Level and FDD Checking of GSB Top Layer 319+400 319+500 RHS GSB TOP 100 VRC-SP/NH71/HW-354 08-Sep-20 1
58 Level and FDD Checking of GSB Top Layer 319+500 319+620 RHS GSB TOP 120 VRC-SP/NH71/HW-758 05-Oct-20 2
59 Level and FDD Checking of GSB Top Layer 319+620 319+820 RHS GSB TOP 200 VRC-SP/NH71/HW-334 07-Sep-20 1 Checked by AE Rep.
60 Level and FDD Checking of GSB Top Layer 319+820 319+840 RHS GSB TOP 20 VRC-SP/NH71/HW-1113 04-Nov-20 3 Checked by AE Rep.
61 Level and FDD Checking of GSB Top Layer 319+840 320+300 RHS GSB TOP 460 Done by earlier company 1
62 Level and FDD Checking of GSB Top Layer 320+300 320+320 RHS GSB TOP 20 VRC-SP/NH71/HW-1325 20-Nov-20 4
63 Level and FDD Checking of GSB Top Layer 320+320 320+460 RHS GSB TOP 140 VRC-SP/NH71/HW-449 16-Sep-20 1
64 Level and FDD Checking of GSB Top Layer 320+460 320+540 RHS GSB TOP 80 VRC-SP/NH71/HW-450 16-Sep-20 1 Checked by AE Rep.
65 Level and FDD Checking of GSB Top Layer 320+540 320+600 RHS GSB TOP 60 VRC-SP/NH71/HW-1239 14-Nov-20 3
66 Level and FDD Checking of GSB Top Layer 327+750 327+890 RHS GSB Top 140 VRC-SP/NH-71/HW-3025 14-Feb-21 6
67 Level and FDD Checking of GSB Top Layer 327+890 328+000 RHS GSB TOP 110 VRC-SP/NH71/HW-178 29-Aug-20 1 Checked by AE Rep.
68 Level and FDD Checking of GSB Top Layer 328+000 328+260 RHS GSB TOP 260 VRC-SP/NH71/HW-4469 07-May-21 9 Checked by AE Rep.
69 Level and FDD Checking of GSB Top Layer 328+260 328+460 RHS GSB TOP 200 VRC-SP/NH71/HW-179 29-Aug-20 1 Checked by AE Rep.
70 Level and FDD Checking of GSB Top Layer 328+460 328+470 RHS GSB TOP 10 VRC-SP/NH71/HW-76 24-Aug-20 1
02-05-2022
71 Level and FDD Checking of GSB Top Layer 330+800 330+850 RHS GSB TOP 50 VRC -SP/NH-71/Hw-8499 26
02:00:PM
72 Level and FDD Checking of GSB Top Layer 332+750 332+800 RHS GSB Top 50 VRC-SP/NH-71/HW-3058 15-Feb-21 6
73 Level and FDD Checking of GSB Top Layer 332+800 332+900 RHS GSB TOP 100 VRC-SP/NH71/HW-214 01-Sep-20 1
74 Level and FDD Checking of GSB Top Layer 332+900 333+070 RHS GSB TOP 170 VRC-SP/NH-71/HW-1726 23-Dec-20 4
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-2) Sub-Base Course-Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

75 Level and FDD Checking of GSB Top Layer 333+070 333+100 RHS GSB TOP 30 VRC-SP/NH-71/HW-1715 23-Dec-20 4
76 Level and FDD Checking of GSB Top Layer 333+100 333+200 RHS GSB TOP 100 VRC -SP/NH-71/Hw-8172 03-Apr-22 20 Checked by AE Rep abc
77 Level and FDD Checking of GSB Top Layer 333+200 333+310 RHS GSB Top 110 VRC -SP/NH-71/HW-4040 13-Apr-21 8 Checked by AE Rep.
78 Level and FDD Checking of GSB Top Layer 333+310 333+360 RHS GSB TOP 50 VRC-SP/NH-71/HW-6162 24-Aug-21 12
Total Qty RHS 12253.5 m B
Total Qty (Both Side) 11.849 Km. C=(A + B)/2
Previous Qty. (Both Side) 11.849 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-3) Non Bituminious Base- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level and FDD Checking of WMM Top Layer 326+340 326+500 LHS WMM TOP 160 VRC-SP/NH71/HW-526 23-Sep-20 1
2 Level and FDD Checking of WMM Top Layer 326+500 326+550 LHS WMM TOP 50 VRC-SP/NH71/HW-614 28-Sep-20 1 Checked by AE Rep.
3 Level and FDD Checking of WMM Top Layer 326+550 326+650 LHS WMM TOP 100 VRC-SP/NH71/HW-6924 28-Nov-21 15 Checked by AE Rep.
4 Level and FDD Checking of WMM Top Layer 326+650 326+700 LHS WMM TOP 50 VRC-SP/NH71/HW-615 28-Sep-20 1 Checked by AE Rep.
5 Level and FDD Checking of WMM Top Layer 326+700 326+950 LHS WMM TOP 250 VRC-SP/NH71/HW-435 15-Sep-20 1
6 Level and FDD Checking of WMM Top Layer 326+950 327+160 LHS WMM TOP 210 VRC-SP/NH71/HW-613 28-Sep-20 1 Checked by AE Rep.
7 Level and FDD Checking of WMM Top Layer 327+160 327+460 LHS WMM TOP 300 VRC-SP/NH71/HW-513 22-Sep-20 1
8 Level and FDD Checking of WMM Top Layer 327+460 327+700 LHS WMM TOP 240 VRC-SP/NH-71/HW-2894 10-Feb-21 6
9 Level and FDD Checking of WMM Top Layer 327+700 327+750 LHS WMM TOP 50 VRC-SP/NH-71/HW-5985 10-Aug-21 12 Checked by AE Rep.
10 Level and FDD Checking of WMM Top Layer 330+110 330+310 LHS WMM TOP 200 VRC-SP/NH71/HW-2383 22-Jan-21 5 Checked by AE Rep.
11 Level and FDD Checking of WMM Top Layer 330+310 330+430 LHS WMM TOP 120 VRC-SP/NH71/HW-584 26-Sep-20 1 Checked by AE Rep.
12 Level and FDD Checking of WMM Top Layer 331+140 331+300 LHS WMM TOP 160 VRC-SP/NH71/HW-9800 08-Dec-22 28 Checked by AE Rep.
13 Level and FDD Checking of WMM Top Layer 331+300 331+420 LHS WMM TOP 120 VRC-SP/NH71/HW-601 27-Sep-20 1 Checked by AE Rep.
14 Level and FDD Checking of WMM Top Layer 331+500 331+550 LHS WMM Top 50.0 VRC-SP/NH-71/HW-4316 28-Apr-21 8 Checked by AE Rep.
15 Level and FDD Checking of WMM Top Layer 331+550 332+000 LHS WMM TOP 450 VRC-SP/NH71/HW-679 30-Sep-20 1 Checked by AE Rep.
16 Level and FDD Checking of WMM Top Layer 332+000 332+560 LHS WMM TOP 560 VRC-SP/NH71/HW-597 27-Sep-20 1 Checked by AE Rep.
17 Level and FDD Checking of WMM Top Layer 332+560 332+700 LHS WMM TOP 140 VRC-SP/NH71/HW-586 26-Sep-20 1 Checked by AE Rep.
18 Level and FDD Checking of WMM Top Layer 332+700 332+750 LHS WMM TOP 50 VRC-SP/NH-71/HW-5986 10-Aug-21 12 Checked by AE Rep.
19 Level and FDD Checking of WMM Top Layer 333+360 333+470 LHS WMM TOP 110 VRC-SP/NH71/HW-2453 24-Jan-21 5 Checked by AE Rep.
20 Level and FDD Checking of WMM Top Layer 333+470 333+560 LHS WMM TOP 90 VRC-SP/NH71/HW-1996 05-Jan-21 5 Checked by AE Rep.
21 Level and FDD Checking of WMM Top Layer 333+560 333+770 LHS WMM TOP 210 Done by earlier company 1
22 Level and FDD Checking of WMM Top Layer 333+770 334+000 LHS WMM TOP 230 VRC-SP/NH71/HW-436 15-Sep-20 1 Checked by AE Rep.
23 Level and FDD Checking of WMM Top Layer 334+000 334+120 LHS WMM TOP 120 VRC-SP/NH-71/HW-1788 26-Dec-20 4
24 Level and FDD Checking of WMM Top Layer 334+120 334+400 LHS WMM TOP 280 Done by earlier company 1
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-3) Non Bituminious Base- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
25 Level and FDD Checking of WMM Top Layer 334+400 334+750 LHS WMM TOP 350 VRC-SP/NH71/HW-437 15-Sep-20 1 Checked by AE Rep.
26 Level and FDD Checking of WMM Top Layer 334+750 334+800 LHS WMM TOP 50 VRC-SP/NH71/HW-4534 10-May-21 9
27 Level and FDD Checking of WMM Top Layer 334+800 334+900 LHS WMM TOP 100 VRC -SP/NH-71/HW-5391 07-Jul-21 11 Checked by AE Rep.
28 Level and FDD Checking of WMM Top Layer 337+360 337+450 LHS WMM TOP 90 VRC-SP/NH71/HW-427 14-Sep-20 1
29 Level and FDD Checking of WMM Top Layer 337+450 337+500 LHS WMM Top 50 VRC -SP/NH-71/HW-2827 08-Feb-21 6 Checked by AE Rep.
30 Level and FDD Checking of WMM Top Layer 337+500 337+720 LHS WMM TOP 220 VRC-SP/NH71/HW-1073 30-Oct-20 2 Checked by AE Rep.
31 Level and FDD Checking of WMM Top Layer 337+720 337+850 LHS WMM TOP 130 VRC-SP/NH71/HW-677 30-Sep-20 1 Checked by AE Rep.
32 Level and FDD Checking of WMM Top Layer 337+850 338+000 LHS WMM TOP 150 VRC-SP/NH71/HW-683 30-Sep-20 1 Checked by AE Rep.
33 Level and FDD Checking of WMM Top Layer 338+000 338+280 LHS WMM TOP 280 VRC-SP/NH71/HW-477 20-Sep-20 1 Checked by AE Rep.
34 Level and FDD Checking of WMM Top Layer 338+280 338+430 LHS WMM Top 150 VRC -SP/NH-71/HW-3257 25-Feb-21 6
35 Level and FDD Checking of WMM Top Layer 340+200 340+280 LHS WMM Top 80 VRC -SP/NH-71/HW-7667 31-Jan-22 17 Checked by AE Rep.
36 Level and FDD Checking of WMM Top Layer 340+280 340+360 LHS WMM TOP 80 VRC-SP/NH71/HW-514 22-Sep-20 1 Checked by AE Rep.
37 Level and FDD Checking of WMM Top Layer 340+360 340+400 LHS WMM TOP 40 VRC-SP/NH71/HW-3550 19-Mar-21 9
38 Level and FDD Checking of WMM Top Layer 340+400 340+620 LHS WMM TOP 220 VRC-SP/NH71/HW-515 24-Sep-20 1 Checked by AE Rep.
39 Level and FDD Checking of WMM Top Layer 340+620 340+850 LHS WMM Top 230 VRC -SP/NH-71/HW-7125 14-Dec-21 16 Checked by AE Rep.
40 Level and FDD Checking of WMM Top Layer 340+850 340+910 LHS WMM TOP 60 VRC -SP/NH-71/Hw-8062 15-Mar-22 19
41 Level and FDD Checking of WMM Top Layer 340+910 341+020 LHS WMM TOP 110 VRC-SP/NH-71/HW-2973 12-Feb-21 6 Checked by AE Rep.
42 Level and FDD Checking of WMM Top Layer 341+020 341+075 LHS WMM TOP 55 VRC -SP/NH-71/HW-5460 07-Nov-21 11 Checked by AE Rep.
43 Level and FDD Checking of WMM Top Layer 341+670 341+750 LHS WMM TOP 80 VRC -SP/NH-71/HW-7081 11-Dec-21 17
44 Level and FDD Checking of WMM Top Layer 341+750 342+000 LHS WMM TOP 250 VRC-SP/NH-71/HW-3256 25-Feb-21 6 Checked by AE Rep.
45 Level and FDD Checking of WMM Top Layer 342+000 342+040 LHS WMM TOP 40 VRC-SP/NH-71/HW-9918 25-Dec-22 28 Checked by AE Rep.
46 Level and FDD Checking of WMM Top Layer 342+040 342+260 LHS WMM TOP 220 VRC-SP/NH71/HW-465 17-Sep-20 1
47 Level and FDD Checking of WMM Top Layer 342+260 342+650 LHS WMM TOP 390 VRC-SP/NH71/HW-83 24-Aug-20 1 Checked by AE Rep.
48 Level and FDD Checking of WMM Top Layer 342+650 342+850 LHS WMM TOP 200 VRC-SP/NH71/HW-625 28-Sep-20 1 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-3) Non Bituminious Base- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
49 Level and FDD Checking of WMM Top Layer 342+850 343+100 LHS WMM TOP 250 VRC-SP/NH71/HW-444 15-Sep-20 1
50 Level and FDD Checking of WMM Top Layer 343+100 343+280 LHS WMM TOP 180 VRC-SP/NH71/HW-626 28-Sep-20 1 Checked by AE Rep.
51 Level and FDD Checking of WMM Top Layer 343+280 343+380 LHS WMM TOP 100 VRC-SP/NH-71/HW-6446 23-Sep-20
52 Level and FDD Checking of WMM Top Layer 344+680 344+790 LHS WMM TOP 110 VRC-SP/NH-71/HW-4885 04-Jun-21 10
53 Level and FDD Checking of WMM Top Layer 344+790 345+000 LHS WMM TOP 210 Done by earlier company 1
54 Level and FDD Checking of WMM Top Layer 345+000 345+300 LHS WMM TOP 300 VRC-SP/NH71/HW-341 07-Sep-20 1 Checked by AE Rep.
55 Level and FDD Checking of WMM Top Layer 345+300 345+600 LHS WMM TOP 300 VRC-SP/NH71/HW-657 29-Sep-20 1 Checked by AE Rep.
56 Level and FDD Checking of WMM Top Layer 345+600 345+810 LHS WMM TOP 210 VRC-SP/NH71/HW-339 07-Sep-20 1 Checked by AE Rep.
57 Level and FDD Checking of WMM Top Layer 347+120 347+300 LHS WMM TOP 180 VRC-SP/NH71/HW-654 29-Sep-20 1 Checked by AE Rep.
58 Level and FDD Checking of WMM Top Layer 347+300 347+450 LHS WMM TOP 150 VRC-SP/NH71/HW-583 26-Sep-20 1 Checked by AE Rep.
59 Level and FDD Checking of WMM Top Layer 347+450 347+490 LHS WMM TOP 40 VRC-SP/NH-71/HW-5202 26-Jun-21 12
60 Level and FDD Checking of WMM Top Layer 347+490 347+790 LHS WMM TOP 300 VRC-SP/NH71/HW-318 05-Sep-20 1 Checked by AE Rep.
61 Level and FDD Checking of WMM Top Layer 347+790 348+000 LHS WMM TOP 210 VRC-SP/NH71/HW-623 28-Sep-20 1 Checked by AE Rep.
62 Level and FDD Checking of WMM Top Layer 348+000 348+400 LHS WMM TOP 400 VRC-SP/NH71/HW-656 29-Sep-20 1 Checked by AE Rep.
63 Level and FDD Checking of WMM Top Layer 348+400 348+500 LHS WMM TOP 100 VRC-SP/NH71/HW-972 22-Oct-20 2 Checked by AE Rep.
64 Level and FDD Checking of WMM Top Layer 348+500 348+804 LHS WMM TOP 304 VRC-SP/NH71/HW-690 30-Sep-20 1 Checked by AE Rep.
Total Qty LHS 11269.00 m A
1 Level and FDD Checking of WMM Top Layer 307+600 307+900 RHS WMM TOP 300 VRC-SP/NH71/HW-6554 07-Oct-21 14
2 Level and FDD Checking of WMM Top Layer 307+900 308+000 RHS WMM TOP 100 VRC-SP/NH71/HW-5792 28-Jul-21 11
3 Level and FDD Checking of WMM Top Layer 308+000 308+200 RHS WMM TOP 200 VRC-SP/NH71/HW-5490 13-Jul-21 11 Checked by AE Rep.
4 Level and FDD Checking of WMM Top Layer 308+200 308+350 RHS WMM TOP 150 VRC-SP/NH71/HW-5512 14-Jul-21 11
5 Level and FDD Checking of WMM Top Layer 309+400 309+500 RHS WMM TOP 100 VRC-SP/NH71/HW-874 15-Oct-20 2 Checked by AE Rep.
6 Level and FDD Checking of WMM Top Layer 309+500 309+560 RHS WMM TOP 60 VRC-SP/NH71/HW-2197 15-Jan-21 5 Checked by AE Rep.
7 Level and FDD Checking of WMM Top Layer 309+560 309+800 RHS WMM TOP 240 VRC-SP/NH71/HW-1105 03-Nov-20 3 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-3) Non Bituminious Base- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
8 Level and FDD Checking of WMM Top Layer 309+800 309+940 RHS WMM TOP 140 VRC-SP/NH71/HW-2077 11-Jan-21 5
9 Level and FDD Checking of WMM Top Layer 309+940 309+955 RHS WMM TOP 15 VRC-SP/NH71/HW-4171 20-Apr-21 8 Checked by AE Rep.
10 Level and FDD Checking of WMM Top Layer 309+963 310+000 RHS WMM TOP 37 VRC-SP/NH71/HW-2284 20-Jan-21 5 Checked by AE Rep.
11 Level and FDD Checking of WMM Top Layer 310+000 310+140 RHS WMM TOP 140 VRC-SP/NH71/HW-960 22-Oct-20 2 Checked by AE Rep.
12 Level and FDD Checking of WMM Top Layer 310+140 310+500 RHS WMM TOP 360 VRC-SP/NH71/HW-155 28-Aug-20 1 Checked by AE Rep.
13 Level and FDD Checking of WMM Top Layer 310+500 310+600 RHS WMM TOP 100 VRC-SP/NH71/HW-1585 16-Dec-20 4 Checked by AE Rep.
14 Level and FDD Checking of WMM Top Layer 310+600 311+050 RHS WMM TOP 450 VRC-SP/NH71/HW-211 01-Sep-20 1 Checked by AE Rep.
15 Level and FDD Checking of WMM Top Layer 311+050 311+500 RHS WMM TOP 450 VRC-SP/NH71/HW-504 22-Sep-20 1
16 Level and FDD Checking of WMM Top Layer 311+500 311+700 RHS WMM TOP 200 VRC-SP/NH71/HW-488 21-Sep-20 1
17 Level and FDD Checking of WMM Top Layer 311+700 311+900 RHS WMM TOP 200 VRC-SP/NH71/HW-743 04-Oct-20 2 Checked by AE Rep.
18 Level and FDD Checking of WMM Top Layer 311+900 312+120 RHS WMM TOP 220 VRC-SP/NH71/HW-693 01-Oct-20 2 Checked by AE Rep.
19 Level and FDD Checking of WMM Top Layer 312+120 312+300 RHS WMM TOP 180 VRC-SP/NH71/HW-694 01-Oct-20 2 Checked by AE Rep.
20 Level and FDD Checking of WMM Top Layer 312+300 312+340 RHS WMM TOP 40 VRC-SP/NH71/HW-1137 06-Nov-20 3 Checked by AE Rep.
21 Level and FDD Checking of WMM Top Layer 312+340 312+500 RHS WMM TOP 160 VRC-SP/NH71/HW-634 28-Sep-20 1 Checked by AE Rep.
22 Level and FDD Checking of WMM Top Layer 312+500 312+700 RHS WMM TOP 200 VRC-SP/NH71/HW-672 30-Sep-20 1 Checked by AE Rep.
23 Level and FDD Checking of WMM Top Layer 312+700 312+760 RHS WMM TOP 60 VRC-SP/NH71/HW-8742 25-May-22 22
24 Level and FDD Checking of WMM Top Layer 312+760 312+900 RHS WMM TOP 140 VRC-SP/NH71/HW-768 06-Oct-20 2
25 Level and FDD Checking of WMM Top Layer 312+900 312+950 RHS WMM TOP 50 VRC-SP/NH71/HW-1273 17-Nov-20 3
26 Level and FDD Checking of WMM Top Layer 312+950 313+040 RHS WMM TOP 90 VRC-SP/NH71/HW-1257 16-Nov-20 3
27 Level and FDD Checking of WMM Top Layer 313+040 313+240 RHS WMM TOP 200 VRC-SP/NH71/HW-461 17-Sep-20 1 Checked by AE Rep.
28 Level and FDD Checking of WMM Top Layer 313+240 313+400 RHS WMM TOP 160 VRC-SP/NH71/HW-433 15-Sep-20 1 Checked by AE Rep.
29 Level and FDD Checking of WMM Top Layer 313+400 313+650 RHS WMM TOP 250 VRC-SP/NH71/HW-4329 29-Apr-21 8 Checked by AE Rep.

30 Level and FDD Checking of WMM Top Layer 313+650 313+690 RHS WMM TOP 39.5 VRC-SP/NH71/HW-8361 23-Apr-22 20
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-3) Non Bituminious Base- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

31 Level and FDD Checking of WMM Top Layer 313+707 313+748 RHS WMM TOP 41.75 VRC-SP/NH71/HW-8362 23-Apr-22 20

32 Level and FDD Checking of WMM Top Layer 313+784 313+800 RHS WMM TOP 16.25 VRC-SP/NH71/HW-8363 23-Apr-22 20
33 Level and FDD Checking of WMM Top Layer 313+800 313+950 RHS WMM TOP 150 VRC-SP/NH71/HW-6353 08-Sep-21 14
34 Level and FDD Checking of WMM Top Layer 313+950 314+280 RHS WMM TOP 330 VRC-SP/NH71/HW-939 20-Oct-20 2 Checked by AE Rep.
35 Level and FDD Checking of WMM Top Layer 314+280 314+380 RHS WMM TOP 100 VRC-SP/NH71/HW-1145 07-Nov-20 3
36 Level and FDD Checking of WMM Top Layer 314+380 314+760 RHS WMM TOP 380 VRC-SP/NH71/HW-315 05-Sep-20 1 Checked by AE Rep.
37 Level and FDD Checking of WMM Top Layer 314+760 314+840 RHS WMM TOP 80 VRC-SP/NH71/HW-816 09-Oct-20 2
38 Level and FDD Checking of WMM Top Layer 314+840 315+180 RHS WMM TOP 340 VRC-SP/NH71/HW-929 19-Oct-20 2 Checked by AE Rep.
39 Level and FDD Checking of WMM Top Layer 315+180 315+300 RHS WMM TOP 120 VRC-SP/NH71/HW-885 15-Oct-20 2
40 Level and FDD Checking of WMM Top Layer 315+300 315+500 RHS WMM TOP 200 VRC-SP/NH71/HW-270 03-Sep-20 1
41 Level and FDD Checking of WMM Top Layer 315+500 315+620 RHS WMM TOP 120 VRC-SP/NH71/HW-4172 20-Apr-21 8 Checked by AE Rep.
42 Level and FDD Checking of WMM Top Layer 316+650 316+970 RHS WMM TOP 320 VRC-SP/NH71/HW-6171 26-Aug-21 12 Checked by AE Rep.
43 Level and FDD Checking of WMM Top Layer 316+970 317+100 RHS WMM TOP 130 VRC-SP/NH71/HW-987 24-Oct-20 2 Checked by AE Rep.
44 Level and FDD Checking of WMM Top Layer 317+100 317+500 RHS WMM TOP 400 VRC-SP/NH71/HW-813 09-Oct-20 2 Checked by AE Rep.
45 Level and FDD Checking of WMM Top Layer 317+500 317+530 RHS WMM TOP 30 VRC-SP/NH71/HW-1351 23-Nov-20 3 Checked by AE Rep.
46 Level and FDD Checking of WMM Top Layer 317+530 317+540 RHS WMM TOP 10 VRC-SP/NH71/HW-1256 16-Nov-20 3
47 Level and FDD Checking of WMM Top Layer 317+540 317+620 RHS WMM TOP 80 VRC-SP/NH71/HW-462 17-Sep-20 1 Checked by AE Rep.
48 Level and FDD Checking of WMM Top Layer 317+620 317+880 RHS WMM TOP 260 Done by earlier company 1
49 Level and FDD Checking of WMM Top Layer 317+880 317+960 RHS WMM TOP 80 VRC-SP/NH71/HW-1360 24-Nov-20 3 Checked by AE Rep.
50 Level and FDD Checking of WMM Top Layer 317+960 319+160 RHS WMM TOP 1200 Done by earlier company 1
51 Level and FDD Checking of WMM Top Layer 319+160 319+360 RHS WMM TOP 200 VRC-SP/NH71/HW-855 12-Oct-20 2 Checked by AE Rep.
52 Level and FDD Checking of WMM Top Layer 319+360 319+460 RHS WMM TOP 100 VRC-SP/NH71/HW-3306 01-Mar-21 7 Checked by AE Rep.
53 Level and FDD Checking of WMM Top Layer 319+460 319+620 RHS WMM TOP 160 VRC-SP/NH71/HW-901 16-Oct-20 2 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-3) Non Bituminious Base- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
54 Level and FDD Checking of WMM Top Layer 319+620 319+820 RHS WMM TOP 200 VRC-SP/NH71/HW-922 18-Oct-20 2
55 Level and FDD Checking of WMM Top Layer 319+820 319+840 RHS WMM TOP 20 VRC-SP/NH71/HW-1136 06-Nov-20 3
56 Level and FDD Checking of WMM Top Layer 319+840 320+000 RHS WMM TOP 160 VRC-SP/NH71/HW-297 04-Sep-20 1
57 Level and FDD Checking of WMM Top Layer 320+000 320+200 RHS WMM TOP 200 VRC-SP/NH71/HW-316 05-Sep-20 1
58 Level and FDD Checking of WMM Top Layer 320+200 320+300 RHS WMM TOP 100 Done by earlier company 1
59 Level and FDD Checking of WMM Top Layer 320+300 320+320 RHS WMM TOP 20 VRC-SP/NH-71/HW-1444 02-Dec-20 4
60 Level and FDD Checking of WMM Top Layer 320+320 320+540 RHS WMM TOP 220 VRC-SP/NH71/HW-902 16-Oct-20 2
61 Level and FDD Checking of WMM Top Layer 320+540 320+600 RHS WMM TOP 60 VRC-SP/NH71/HW-1272 17-Nov-20 3 Checked by AE Rep.
62 Level and FDD Checking of WMM Top Layer 327+750 327+890 RHS WMM TOP 140 VRC-SP/NH-71/HW-3089 16-Feb-21 6 Checked by AE Rep.
63 Level and FDD Checking of WMM Top Layer 327+890 328+000 RHS WMM TOP 110 VRC-SP/NH71/HW-589 27-Sep-20 1 Checked by AE Rep.
64 Level and FDD Checking of WMM Top Layer 328+000 328+260 RHS WMM TOP 260 VRC-SP/NH71/HW-4512 09-May-21 9 Checked by AE Rep.
65 Level and FDD Checking of WMM Top Layer 328+260 328+460 RHS WMM TOP 200 VRC-SP/NH71/HW-473 19-Sep-20 1
66 Level and FDD Checking of WMM Top Layer 328+460 328+470 RHS WMM TOP 10 VRC-SP/NH71/HW-596 27-Sep-20 1 Checked by AE Rep.
67 Level and FDD Checking of WMM Top Layer 332+750 332+800 RHS WMM TOP 50 VRC -SP/NH-71/HW-3124 17-Feb-21 6
68 Level and FDD Checking of WMM Top Layer 332+800 332+900 RHS WMM TOP 100 VRC-SP/NH71/HW-599 27-Sep-20 1 Checked by AE Rep.
69 Level and FDD Checking of WMM Top Layer 332+900 333+070 RHS WMM TOP 170 VRC-SP/NH-71/HW-1879 30-Dec-20 4
70 Level and FDD Checking of WMM Top Layer 333+070 333+100 RHS WMM TOP 30 VRC-SP/NH-71/HW-1880 30-Dec-20 4
71 Level and FDD Checking of WMM Top Layer 333+100 333+200 RHS WMM TOP 100 VRC -SP/NH-71/Hw-8179 04-Apr-20 20
72 Level and FDD Checking of WMM Top Layer 333+200 333+310 RHS WMM Top 110 VRC -SP/NH-71/HW-4078 15-Apr-21 8 Checked by AE Rep.
73 Level and FDD Checking of WMM Top Layer 333+310 333+360 RHS WMM TOP 50 VRC-SP/NH-71/HW-6184 27-Aug-21 12 Checked by AE Rep.

Total Qty RHS 12190 m B


Total Qty (Both Side) 11.729 Km C=(A + B)/2
Previous Qty. (Both Side) 11.729 Km D
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-3) Non Bituminious Base- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
Net Payable Qty (Both Side) 0.000 Km E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
0
1 Laying of DBM Layer 307+600 308+350 LHS Top 750 VRC-SP/NH71/HW-7928 27-Feb-22 18
2 Laying of DBM Layer 309+400 309+860 LHS Top 460 VRC-SP/NH71/HW-7957 28-Feb-22 18 Checked by AE Rep.
3 Laying of DBM Layer 309+860 309+955 LHS Top 95 VRC-SP/NH71/HW-6121 20-Aug-21 36
4 Laying of DBM Layer 309+963 310+200 LHS Top 237 VRC-SP/NH71/HW-6123 20-Aug-21 12
Checked by AE Rep.
Laying of DBM Layer 310+200 310+500 LHS Top 300 VRC-SP/NH71/HW-6081 18-Aug-21 12 & 36 ( 100 mtr length
5 released)
6 Laying of DBM Layer 310+500 312+100 LHS Top 1600 VRC-SP/NH71/HW-3795 27-Mar-21 7
7 Laying of DBM Layer 312+100 312+900 LHS Top 800 VRC-SP/NH71/HW-9468 30-Aug-22 25 Checked by AE Rep.
8 Laying of DBM Layer 312+900 313+450 LHS Top 550 VRC-SP/NH71/HW-7896 26-Feb-22 18 Checked by AE Rep.
9 Laying of DBM Layer 313+450 313+690 LHS Top 239.5 VRC-SP/NH71/HW-10266 16-Feb-23 30 Checked by AE Rep.
10 Laying of DBM Layer 313+707 313+748 LHS Top 41.75 VRC-SP/NH71/HW-10312 22-Feb-23 30 Checked by AE Rep.
11 Laying of DBM Layer 313+784 314+060 LHS Top 276.25 VRC-SP/NH71/HW-10276 18-Feb-23 33 Checked by AE Rep.
12 Laying of DBM Layer 314+060 314+285 LHS Top 225 VRC-SP/NH71/HW-6540 04-Oct-21 14
13 Laying of DBM Layer 314+285 314+475 LHS Top 190 VRC-SP/NH71/HW-7932 27-Feb-22 19 Checked by AE Rep.
14 Laying of DBM Layer 314+475 315+000 LHS Top 525 VRC-SP/NH71/HW-6540 04-Oct-21 14
15 Laying of DBM Layer 315+000 315+500 LHS Top 500 VRC-SP/NH71/HW-3687 23-Mar-21 7
16 Laying of DBM Layer 315+500 315+620 LHS Top 120 VRC-SP/NH71/HW-7961 28-Feb-22 19
17 Laying of DBM Layer 316+650 316+820 LHS Top 170 VRC-SP/NH71/HW-8300 19-Apr-22 20
18 Laying of DBM Layer 316+820 317+040 LHS Top 220 VRC-SP/NH71/HW-9177 05-Jul-22 24 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
19 Laying of DBM Layer 317+040 317+530 LHS Top 490 VRC-SP/NH71/HW-10343 26-Feb-23 30
20 Laying of DBM Layer 317+530 318+000 LHS Top 470 VRC-SP/NH71/HW-9863 18-Dec-22 28 Checked by AE Rep.
21 Laying of DBM Layer 318+000 318+200 LHS Top 200 VRC-SP/NH71/HW-6662 24-Oct-21 14
22 Laying of DBM Layer 318+200 318+800 LHS Top 600 VRC-SP/NH71/HW-6602 16-Oct-21 14
23 Laying of DBM Layer 318+800 319+200 LHS Top 400 VRC-SP/NH71/HW-6604 17-Oct-21 14
24 Laying of DBM Layer 319+200 319+500 LHS Top 300 VRC-SP/NH71/HW-6618 19-Oct-21 14
25 Laying of DBM Layer 319+500 320+200 LHS Top 700 VRC-SP/NH71/HW-6626 20-Oct-21 14
26 Laying of DBM Layer 320+200 320+600 LHS Top 400 VRC-SP/NH71/HW-6638 21-Oct-21 14
27 Laying of DBM Layer 326+340 326+550 LHS Top 210 VRC-SP/NH71/HW-782 06-Oct-20 2 Checked by AE Rep.
28 Laying of DBM Layer 326+550 326+650 LHS Top 100 VRC -SP/NH-71/Hw-8246 13-Apr-22 20
29 Laying of DBM Layer 326+650 327+460 LHS Top 810 VRC-SP/NH71/HW-732 06-Oct-20 2 Checked by AE Rep.
30 Laying of DBM Layer 327+460 327+700 LHS Top 240 VRC -SP/NH-71/HW-3673 22-Mar-21 8 Checked by AE Rep.
31 Laying of DBM Layer 327+700 328+000 LHS Top 300 VRC -SP/NH-71/HW-5018 13-Jun-21 10 Checked by AE Rep.
32 Laying of DBM Layer 328+000 328+470 LHS Top 470 VRC -SP/NH-71/HW-6125 20-Aug-21 12 Checked by AE Rep.
33 Laying of DBM Layer 330+320 330+430 LHS Top 110 VRC -SP/NH-71/Hw-8517 06-May-22 21
34 Laying of DBM Layer 330+110 330+320 LHS Top 210 VRC-SP/NH71/HW-3580 20-Mar-21 7
35 Laying of DBM Layer 331+140 331+460 LHS Top 320 VRC-SP/NH-71/HW-10107 28-Jan-23 29 Checked by AE Rep.
17.5 mtr Str. Portion
Laying of DBM Layer 331+460 331+490 LHS Top 12.5 VRC-SP/NH-71/HW-10530 13-Apr-23 32
36 Deduction (Checked)

37 Laying of DBM Layer 331+490 331+550 LHS Top 60 VRC-SP/NH-71/HW-10101 27-Jan-23 29 Checked by AE Rep.
38 Laying of DBM Layer 331+550 332+700 LHS Top 1150 VRC-SP/NH71/HW-1077 30-Oct-20 2 Checked by AE Rep.
39 Laying of DBM Layer 332+700 333+100 LHS Top 400 VRC -SP/NH-71/HW-6141 22-Aug-21 12
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
40 Laying of DBM Layer 333+180 333+310 LHS Top 130 VRC-SP/NH-71/HW-10114 29-Jan-23 29 Checked by AE Rep.
41 Laying of DBM Layer 333+310 333+360 LHS Top 50 VRC -SP/NH-71/HW-6234 30-Aug-21 12
42 Laying of DBM Layer 333+360 333+560 LHS Top 200 VRC-SP/NH71/HW-3629 21-Mar-21 7
43 Laying of DBM Layer 333+560 333+760 LHS Top 200 VRC-SP/NH71/HW-670 30-Sep-20 1
44 Laying of DBM Layer 333+760 334+000 LHS Top 240 VRC-SP/NH71/HW-796 07-Oct-20 2 Checked by AE Rep.
45 Laying of DBM Layer 334+000 334+120 LHS Top 120 VRC-SP/NH71/HW-3675 22-Mar-21 7 Checked by AE Rep.
46 Laying of DBM Layer 334+120 334+400 LHS Top 280 VRC-SP/NH71/HW-682 30-Sep-20 1 Checked by AE Rep.
47 Laying of DBM Layer 334+400 334+750 LHS Top 350 VRC-SP/NH71/HW-752 04-Oct-20 2 Checked by AE Rep.
48 Laying of DBM Layer 334+750 334+800 LHS Top 50 VRC-SP/NH71/HW-4602 14-May-21 9
49 Laying of DBM Layer 334+800 334+900 LHS Top 100 VRC -SP/NH-71/HW-6154 23-Aug-21 12 Checked by AE Rep.
50 Laying of DBM Layer 337+360 337+450 LHS Top 90 VRC-SP/NH-71/HW-4842 30-May-21 9
51 Laying of DBM Layer 337+450 337+750 LHS Top 300 VRC-SP/NH71/HW-3631 21-Mar-21 7 Checked by AE Rep.
52 Laying of DBM Layer 337+750 338+270 LHS Top 520 VRC-SP/NH71/HW-982 23-Oct-20 2 Checked by AE Rep.
53 Laying of DBM Layer 338+270 338+430 LHS Top 160 VRC-SP/NH71/HW-3632 21-Mar-21 7
54 Laying of DBM Layer 340+200 340+280 LHS Top 80 VRC-SP/NH71/HW-7706 02-Feb-22 18 Checked by AE Rep.
55 Laying of DBM Layer 340+280 340+410 LHS Top 130 VRC-SP/NH71/HW-3676 22-Mar-21 7
56 Laying of DBM Layer 340+410 340+620 LHS Top 210 VRC-SP/NH71/HW-935 19-Oct-20 2 Checked by AE Rep.
57 Laying of DBM Layer 340+620 340+850 LHS Top 230 VRC-SP/NH71/HW-7717 04-Feb-22 18
22 (15+7) mtr
deducted for MNB
Laying of DBM Layer 340+850 340+920 LHS Top 48 VRC-SP/NH71/HW-10854 17-Aug-23 36
and its approach slab
58 Checked by AE
59 Laying of DBM Layer 340+920 341+032 LHS Top 112 VRC -SP/NH-71/Hw-10219 09-Feb-23 30 Checked by AE Rep.
60 Laying of DBM Layer 341+718 341+800 LHS Top 82 VRC -SP/NH-71/Hw-10157 04-Feb-23 30 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
61 Laying of DBM Layer 341+800 342+000 LHS Top 200 VRC-SP/NH71/HW-3678 22-Mar-21 7 Checked by AE Rep.

62 Laying of DBM Layer 342+000 342+040 LHS Top VRC-SP/NH-71/HW-9939 27-Dec-22 Deficiency
63 Laying of DBM Layer 342+040 342+300 LHS Top 260 VRC-SP/NH-71/HW-5224 27-Jun-21 10 Checked by AE Rep.
64 Laying of DBM Layer 342+300 342+800 LHS Top 500 VRC-SP/NH-71/HW-6493 28-Sep-21 13
65 Laying of DBM Layer 342+800 342+960 LHS Top 160 VRC-SP/NH-71/HW-6494 28-Sep-21 13
66 Laying of DBM Layer 342+960 343+380 LHS Top 420 VRC-SP/NH-71/HW-6600 16-Oct-21 14
67 Laying of DBM Layer 344+680 344+800 LHS Top 120 VRC-SP/NH-71/HW-4919 15-Jun-21 10
68 Laying of DBM Layer 344+800 345+000 LHS Top 200 VRC-SP/NH-71/HW-4818 28-May-21 9 Checked by AE Rep.
69 Laying of DBM Layer 345+000 345+600 LHS Top 600 VRC-SP/NH-71/HW-4798 27-May-21 9 Checked by AE Rep.
70 Laying of DBM Layer 345+600 345+770 LHS Top 170 VRC-SP/NH-71/HW-4816 28-May-21 9
71 Laying of DBM Layer 345+770 345+810 LHS Top 40 VRC-SP/NH-71/HW-5076 17-Jun-21 10
72 Laying of DBM Layer 347+120 347+510 LHS Top 390 VRC-SP/NH-71/HW-5269 29-Jun-21 10
73 Laying of DBM Layer 347+510 348+130 LHS Top 620 VRC-SP/NH-71/HW-4790 26-May-21 9 Checked by AE Rep.
74 Laying of DBM Layer 348+130 348+510 LHS Top 380 VRC-SP/NH-71/HW-4757 23-May-21 9
75 Laying of DBM Layer 348+510 348+750 LHS Top 240 VRC-SP/NH-71/HW-6660 24-Oct-21 14
Total Qty LHS 23186 m A
1 Laying of DBM Layer 307+600 307+650 LHS Top 50 VRC-SP/NH71/HW-9304 24-Jul-22 37
2 Laying of DBM Layer 307+650 308+200 RHS Top 550 VRC-SP/NH71/HW-6673 25-Oct-21 14
3 Laying of DBM Layer 308+200 308+350 RHS Top 150 VRC-SP/NH71/HW-7966 28-Feb-22 18 Checked by AE Rep.
4 Laying of DBM Layer 309+400 309+860 RHS Top 460 VRC-SP/NH71/HW-6063 17-Aug-21 12 Checked by AE Rep.
5 Laying of DBM Layer 309+860 309+955 RHS Top 95 VRC-SP/NH71/HW-10327 24-Feb-23 33
6 Laying of DBM Layer 309+963 310+090 RHS Top 127.5 VRC-SP/NH71/HW-6079 18-Aug-21 12
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
7 Laying of DBM Layer 310+090 311+000 RHS Top 910 VRC-SP/NH71/HW-3266 26-Feb-21 7
8 Laying of DBM Layer 311+000 312+100 RHS Top 1100 VRC-SP/NH71/HW-3276 27-Feb-21 7 Checked by AE Rep.
9 Laying of DBM Layer 312+100 312+570 RHS Top 470 VRC-SP/NH71/HW-10248 13-Feb-23 33 Checked by AE Rep.
10 Laying of DBM Layer 312+570 312+900 RHS Top 330 VRC-SP/NH71/HW-9457 29-Aug-22 24
11 Laying of DBM Layer 312+900 313+400 RHS Top 500 VRC-SP/NH71/HW-3286 28-Feb-21 7 Checked by AE Rep.
12 Laying of DBM Layer 313+400 313+650 RHS Top 250 VRC-SP/NH71/HW-7926 27-Feb-22 18 Checked by AE Rep.
13 Laying of DBM Layer 313+650 313+690 RHS Top 39.500 VRC-SP/NH71/HW-8679 21-May-22 21 Checked by AE Rep.
14 Laying of DBM Layer 313+707 313+748 RHS Top 41.750 VRC-SP/NH71/HW-8677 21-May-22 21 Checked by AE Rep.
15 Laying of DBM Layer 313+784 313+800 RHS Top 16.250 VRC-SP/NH71/HW-8678 21-May-22 21
16 Laying of DBM Layer 313+800 314+000 RHS Top 200 VRC-SP/NH71/HW-7969 28-Feb-22 18
17 Laying of DBM Layer 314+000 314+500 RHS Top 500 VRC-SP/NH71/HW-2803 08-Feb-21 7
18 Laying of DBM Layer 314+500 315+500 RHS Top 1000 VRC-SP/NH71/HW-2786 07-Feb-21 7 Checked by AE Rep.
19 Laying of DBM Layer 315+500 315+620 RHS Top 120 VRC-SP/NH71/HW-10333 25-Feb-23 30
20 Laying of DBM Layer 316+650 317+040 RHS Top 390 VRC-SP/NH71/HW-6208 29-Aug-21 12
21 Laying of DBM Layer 317+040 317+200 RHS Top 160 VRC-SP/NH71/HW-8404 25-Apr-22 20
22 Laying of DBM Layer 317+200 317+550 RHS Top 350 VRC-SP/NH71/HW-9471 30-Aug-22 24 Checked by AE Rep.
23 Laying of DBM Layer 317+550 317+620 RHS Top 70 VRC-SP/NH71/HW-10354 27-Feb-23 33 Checked by AE Rep.
24 Laying of DBM Layer 317+620 317+880 RHS Top 260 VRC-SP/NH71/HW-946 21-Oct-20 2 Checked by AE Rep.
25 Laying of DBM Layer 317+880 317+960 RHS Top 80 VRC-SP/NH71/HW-9491 31-Aug-22 30 Checked by AE Rep.
26 Laying of DBM Layer 317+960 318+200 RHS Top 240 VRC-SP/NH71/HW-910 17-Oct-20 2 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
27 Laying of DBM Layer 318+200 318+300 RHS Top 100 VRC-SP/NH71/HW-10420 (A) 15-Mar-23 36
28 Laying of DBM Layer 318+300 319+160 RHS Top 860 VRC-SP/NH71/HW-10397 06-Mar-23 36
29 Laying of DBM Layer 319+160 319+360 RHS Top 200 VRC-SP/NH71/HW-2641 03-Feb-21 6 Checked by AE Rep.
30 Laying of DBM Layer 319+360 319+500 RHS Top 140 VRC-SP/NH71/HW-3499 16-Mar-21 7 Checked by AE Rep.
31 Laying of DBM Layer 319+500 320+000 RHS Top 500 VRC-SP/NH71/HW-2585 30-Jan-21 5 Checked by AE Rep.
32 Laying of DBM Layer 320+000 320+600 RHS Top 600 VRC-SP/NH71/HW-1695 22-Dec-20 4 Checked by AE Rep.
33 Laying of DBM Layer 326+340 326+550 RHS Top 210 VRC-SP/NH71/HW-4787 26-May-21 9
34 Laying of DBM Layer 326+550 326+700 RHS Top 150 VRC-SP/NH71/HW-4811 28-May-21 9
35 Laying of DBM Layer 326+700 327+400 RHS Top 700 VRC-SP/NH71/HW-4385 02-May-21 9 Checked by AE Rep.
36 Laying of DBM Layer 327+400 327+780 RHS Top 380 VRC-SP/NH71/HW-4794 27-May-21 9 Checked by AE Rep.
37 Laying of DBM Layer 327+780 328+000 RHS Top 220 VRC -SP/NH-71/HW-3674 22-Mar-21 8
38 Laying of DBM Layer 328+000 328+260 RHS Top 260 VRC -SP/NH-71/HW-4558 12-May-21 9
39 Laying of DBM Layer 328+260 328+460 RHS Top 200 VRC -SP/NH-71/HW-3628 21-Mar-21 8
40 Laying of DBM Layer 328+460 328+470 RHS Top 10 VRC -SP/NH-71/HW-10082 24-Jan-23 29 Checked by AE Rep.
41 Laying of DBM Layer 330+110 330+200 RHS Top 90 VRC -SP/NH-71/HW-4722 21-May-21 9
42 Laying of DBM Layer 330+200 330+430 RHS Top 230 VRC -SP/NH-71/Hw-8777 27-May-22 21 Checked by AE Rep.
43 Laying of DBM Layer 331+140 331+250 RHS Top 110 VRC -SP/NH-71/Hw-10759 07-Jul-23 35 Checked by AE Rep.
44 Laying of DBM Layer 331+250 331+450 RHS Top 200 VRC -SP/NH-71/Hw-10143 01-Feb-23 30
17.5 mtr Str. Portion
Laying of DBM Layer 331+450 331+520 RHS Top 52.5 VRC -SP/NH-71/HW-10534 16-Apr-23 32
45 Deduction (Checked)
46 Laying of DBM Layer 331+520 331+650 RHS Top 130 VRC -SP/NH-71/Hw-10148 02-Feb-23 30 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
47 Laying of DBM Layer 331+650 331+700 RHS Top 50 VRC -SP/NH-71/HW-3989 07-Apr-21 8
48 Laying of DBM Layer 331+700 332+000 RHS Top 300 VRC-SP/NH71/HW-3807 27-Mar-21 7 Checked by AE Rep.
49 Laying of DBM Layer 332+000 332+300 RHS Top 300 VRC-SP/NH71/HW-3808 27-Mar-21 7 Checked by AE Rep.
50 Laying of DBM Layer 332+300 332+700 RHS Top 400 VRC-SP/NH71/HW-3702 23-Mar-21 7 Checked by AE Rep.
51 Laying of DBM Layer 332+700 333+100 RHS Top 400 VRC-SP/NH71/HW-3630 21-Mar-21 7 Checked by AE Rep.
Checked by AE Rep.
32 (25+7) mtr
Laying of DBM Layer 333+100 333+195 RHS Top 63 VRC -SP/NH-71/Hw-10769 16-Jul-23 35
deducted for MNB
52 and its approach slab
53 Laying of DBM Layer 333+195 333+440 RHS Top 245.00 VRC -SP/NH-71/Hw-8122 25-Mar-22 19 Checked by AE Rep.
54 Laying of DBM Layer 333+440 333+830 RHS Top 390 VRC-SP/NH71/HW-4559 12-May-21 9
55 Laying of DBM Layer 333+830 334+000 RHS Top 170 VRC -SP/NH-71/HW-3835 28-Mar-21 8 Checked by AE Rep.
56 Laying of DBM Layer 334+000 334+100 RHS Top 100 VRC -SP/NH-71/HW-5640 19-Jul-21 12
57 Laying of DBM Layer 334+100 334+200 RHS Top 100 VRC -SP/NH-71/HW-4619 15-May-21 9
58 Laying of DBM Layer 334+200 334+440 RHS Top 240 VRC -SP/NH-71/HW-3836 28-Mar-21 8 Checked by AE Rep.
59 Laying of DBM Layer 334+440 334+800 RHS Top 360 VRC -SP/NH-71/HW-4620 15-May-21 9
60 Laying of DBM Layer 334+800 334+900 RHS Top 100 VRC -SP/NH-71/Hw-8123 25-Mar-22 19 Checked by AE Rep.
61 Laying of DBM Layer 337+360 337+450 RHS Top 90 VRC-SP/NH-71/HW-9985 31-Dec-22 28 Checked by AE Rep.
62 Laying of DBM Layer 337+500 337+640 RHS Top 140 VRC -SP/NH-71/Hw-8148 25-Mar-22 19 Checked by AE Rep.
63 Laying of DBM Layer 337+640 338+240 RHS Top 600 VRC -SP/NH-71/HW-5136 22-Jun-21 10 Checked by AE Rep.
64 Laying of DBM Layer 338+240 338+430 RHS Top 190 VRC -SP/NH-71/Hw-8149 29-Mar-22 19 Checked by AE Rep.
65 Laying of DBM Layer 340+200 340+300 RHS Top 100 VRC -SP/NH-71/HW-7764 12-Feb-22 18 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
66 Laying of DBM Layer 340+300 340+600 RHS Top 300 VRC -SP/NH-71/HW-7750 09-Feb-22 18 Checked by AE Rep.
67 Laying of DBM Layer 340+600 340+700 RHS Top 100 VRC-SP/NH71/HW-9052 26-Jun-22 22 Checked by AE Rep
68 Laying of DBM Layer 340+700 340+840 RHS Top 140 VRC-SP/NH-71/HW-10120 30-Jan-23 29 Checked by AE Rep
22 (15+7) mtr
Laying of DBM Layer 340+840 340+920 RHS Top 58 VRC-SP/NH-71/HW-10850 13-Aug-23 36 deducted for MNB
and its approach slab
69 Checked by AE
70 Laying of DBM Layer 340+920 341+032 RHS Top 112 VRC -SP/NH-71/Hw-10162 05-Feb-23 30 Checked by AE Rep
71 Laying of DBM Layer 341+718 342+000 RHS Top 282 VRC -SP/NH-71/Hw-10179 06-Feb-23 30 Checked by AE Rep
72 Laying of DBM Layer 342+000 342+600 RHS Top 600 VRC -SP/NH-71/HW-7639 27-Jan-22 17 Checked by AE Rep.
73 Laying of DBM Layer 342+600 343+250 RHS Top 650 VRC -SP/NH-71/HW-7640 27-Jan-22 17 Checked by AE Rep.
74 Laying of DBM Layer 343250 343380 RHS Top 130 VRC-SP/NH-71/HW-10041 15-Jan-23 29
75 Laying of DBM Layer 344+800 345+000 RHS Top 200 VRC-SP/NH-71/HW-7794 17-Feb-22 18 Checked by AE Rep.
76 Laying of DBM Layer 345+000 345+780 RHS Top 780 VRC-SP/NH-71/HW-7943 27-Feb-22 18
77 Laying of DBM Layer 345+780 345+810 RHS Top 30 VRC-SP/NH-71/HW-10437 21-Mar-23 31 Checked by AE Rep.
78 Laying of DBM Layer 347+120 347+810 RHS Top 690 VRC-SP/NH-71/HW-5292 30-Jun-21 10
79 Laying of DBM Layer 347+810 348+300 RHS Top 490 VRC-SP/NH-71/HW-5294 30-Jun-21 10 Checked by AE Rep.
80 Laying of DBM Layer 348+300 348+500 RHS Top 200 VRC-SP/NH-71/HW-6632 20-Oct-21 14
81 Laying of DBM Layer 348+500 348+670 RHS Top 170 VRC-SP/NH-71/HW-9776 28-Nov-22 27 Checked by AE Rep.

Total Qty RHS 23072.5 m B


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-4) Bituminous Base Course- Widening & Existing Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
Total Qty (Both Side) 23.129 Km. C=(A + B)/2
Previous Qty. (Both Side) 23.104 Km. D
Net Payable Qty (Both Side) 0.025 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-5) Wearing Coat-Widening
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
1 Laying of BC Layer 307+600 307+960 LHS Top 360 VRC-SP/NH-71/HW-10774 18-Jul-23 35 Checked by AE Rep

2 Laying of BC Layer 307+960 308+350 LHS Top 390 VRC-SP/NH-71/HW-10777 20-Jul-23 35 Checked by AE Rep

3 Laying of BC Layer 309+400 309+780 LHS Top 380 VRC-SP/NH-71/HW-10771 17-Jul-23 35 Checked by AE Rep

1 Laying of BC Layer 309+780 310+000 LHS Top 220 VRC-SP/NH-71/HW-10771 17-Jul-23 37

VRC-SP/NH-71/HW-
2 Laying of BC Layer 310+000 310+080 LHS Top 80 14-Jul-23 37
10765(A)

6 Laying of BC Layer 310+080 311+000 LHS Top 920 VRC-SP/NH-71/HW-10765 14-Jul-23 36


Checked by AE Rep
7 Laying of BC Layer 311+000 312+100 LHS Top 1100 VRC-SP/NH-71/HW-10763 13-Jul-23 35
(312+100 to 312+440 NCR)
8 Laying of BC Layer 312+440 312+500 LHS Top 60 VRC-SP/NH-71/HW-10800 29-Jul-23 35

9 Laying of BC Layer 312+500 312+980 LHS Top 480 VRC-SP/NH-71/HW-10806 31-Jul-23 35 Checked by AE Rep

10 Laying of BC Layer 312+980 313+500 LHS Top 520 VRC-SP/NH-71/HW-10758 07-Jul-23 35 Checked by AE Rep

11 Laying of BC Layer 313+500 314+500 LHS Top 1000 VRC-SP/NH-71/HW-10752 05-Jul-23 35 Checked by AE Rep

12 Laying of BC Layer 314+500 315+500 LHS Top 1000 VRC-SP/NH-71/HW-10741 30-Jun-23 34 Checked by AE Rep

13 Laying of BC Layer 314+700 314+800 LHS Top -100 34


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-5) Wearing Coat-Widening
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)

3 Laying of BC Layer 315+500 315+620 LHS Top 120 VRC-SP/NH-71/HW-10843 12-Aug-23 37

15 Laying of BC Layer 316+650 317+040 LHS Top 390 VRC-SP/NH-71/HW-10869 25-Aug-23 36 Checked by AE Rep

16 Laying of BC Layer 317+040 317+500 LHS Top 460 VRC-SP/NH-71/HW-10873 26-Aug-23 36 Checked by AE Rep

17 Laying of BC Layer 317+500 318+010 LHS Top 510 VRC-SP/NH-71/HW-10858 17-Aug-23 36 Checked by AE Rep

18 Laying of BC Layer 318+010 318+500 LHS Top 490 VRC-SP/NH-71/HW-10733 27-Jul-23 34

19 Laying of BC Layer 318+500 319+000 LHS Top 500 VRC-SP/NH-71/HW-10731 26-Jun-23 34

20 Laying of BC Layer 319+000 320+000 LHS Top 1000 VRC-SP/NH-71/HW-10725 24-Jun-23 34 Checked by AE Rep

21 Laying of BC Layer 320+000 320+600 LHS Top 600 VRC-SP/NH-71/HW-10722 23-Jun-23 34

22 Laying of BC Layer 326+340 328+470 LHS Top 2130 VRC-SP/NH71/HW-10547 29-May-23 33 Checked by AE Rep

23 Laying of BC Layer 330+110 330+430 LHS Top 320 VRC-SP/NH71/HW-10470 09-May-23 33 Checked by AE Rep

24 Laying of BC Layer 331+140 331+650 LHS Top 510 VRC-SP/NH71/HW-10679 15-Jun-23 34 Checked by AE Rep

25 Laying of BC Layer 331+650 333+000 LHS Top 1350 VRC -SP/NH-71/Hw-10348 26-Feb-23 30 Checked by AE Rep

26 Laying of BC Layer 333+000 333+360 LHS Top 360 VRC -SP/NH-71/Hw-10768 15-Jul-23 35 Checked by AE Rep

27 Laying of BC Layer 333+360 334+900 LHS Top 1540 VRC -SP/NH-71/Hw-10357 27-Feb-23 30 Checked by AE Rep
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-5) Wearing Coat-Widening
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
28 Laying of BC Layer 337+390 338+200 LHS Top 810 VRC -SP/NH-71/Hw-10338 25-Feb-23 30 Checked by AE Rep

29 Laying of BC Layer 338+200 338+430 LHS Top 230 VRC -SP/NH-71/Hw-10779 20-Jul-23 35 Checked by AE Rep

30 Laying of BC Layer 340+200 340+680 LHS Top 480 VRC -SP/NH-71/Hw-10328 24-Feb-23 30 Checked by AE Rep

31 Laying of BC Layer 340+680 341+032 LHS Top 352 VRC -SP/NH-71/Hw-10860 18-Aug-23 36 Checked by AE Rep

32 Laying of BC Layer 341+718 342+000 LHS Top 282 VRC-SP/NH71/HW-10794 26-Jul-23 35 Checked by AE Rep
0
Total Qty LHS 18844 m 37 A
1 Laying of BC Layer 307+600 308+000 RHS Top 400 VRC-SP/NH-71/HW-10526 22-May-23 33 Checked by AE Rep

2 Laying of BC Layer 308+000 308+350 RHS Top 350 VRC-SP/NH-71/HW-10530 23-May-23 33 Checked by AE Rep

3 Laying of BC Layer 309+400 310+000 RHS Top 600 VRC-SP/NH-71/HW-10549 30-May-23 33 Checked by AE Rep

4 Laying of BC Layer 309+840 310+090 RHS Top -250 35 MNB Merging balance

5 Laying of BC Layer 310+000 311+000 RHS Top 1000 VRC-SP/NH-71/HW-10557 31-May-23 33 Checked by AE Rep
Checked by AE Rep
6 Laying of BC Layer 311+000 311+500 RHS Top 440 VRC-SP/NH-71/HW-10511 16-May-23 33
60 mtr deducted
7 Laying of BC Layer 311+500 312+100 RHS Top 600 VRC-SP/NH-71/HW-10521 19-May-23 33

1 Laying of BC Layer 312+100 312+500 RHS Top 400 VRC-Sp/NH-71/HW-10811 02-Aug-23 37


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-5) Wearing Coat-Widening
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
2 Laying of BC Layer 312+500 313+060 RHS Top 560 VRC-Sp/NH-71/HW-10815 03-Aug-23 37

10 Laying of BC Layer 313+060 314+000 RHS Top 940 VRC-SP/NH-71/HW-10534 25-May-23 33 Checked by AE Rep

11 Laying of BC Layer 313+830 313+880 RHS Top -50 35 MNB Merging balance

12 Laying of BC Layer 314+000 314+500 RHS Top 500 VRC-SP/NH-71/HW-10539 27-May-23 33 Checked by AE Rep

13 Laying of BC Layer 314+500 315+000 RHS Top 500 VRC-SP/NH-71/HW-10541 27-May-23 33 Checked by AE Rep
Median Openning Merging
14 Laying of BC Layer 314+800 314+900 RHS Top -100 33
balance
15 Laying of BC Layer 315+000 315+520 RHS Top 500 VRC-SP/NH-71/HW-10545 28-May-23 33 20 mtr length deducted

16 Laying of BC Layer 315+520 315+620 RHS Top 100 VRC-SP/NH-71/HW-10841 11-Aug-23 36 Checked by AE Rep

17 Laying of BC Layer 316+650 317+040 RHS Top 390 VRC-SP/NH-71/HW-10829 07-Aug-23 36 Checked by AE Rep

18 Laying of BC Layer 317+040 317+500 RHS Top 460 VRC-SP/NH-71/HW-10829 08-Aug-23 36 Checked by AE Rep

19 Laying of BC Layer 317+500 318+000 RHS Top 500 VRC-SP/NH-71/HW-10827 07-Aug-23 36 Checked by AE Rep

3 Laying of BC Layer 318+000 319+160 RHS Top 1160 VRC-SP/NH-71/HW-10598 11-Jun-23 37

21 Laying of BC Layer 319+160 320+000 RHS Top 840 VRC-SP/NH-71/HW-10600 12-Jun-23 34 Checked by AE Rep
Median Openning Merging
22 Laying of BC Layer 319+700 319+790 RHS Top -90 35
balance
23 Laying of BC Layer 320+000 320+400 RHS Top 400 VRC-SP/NH-71/HW-10609 14-Jun-23 34
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-5) Wearing Coat-Widening
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)

24 Laying of BC Layer 320+400 320+600 RHS Top 200 VRC-SP/NH-71/HW-10690 19-Jun-23 34

25 Laying of BC Layer 326+340 327+200 RHS Top 860 VRC-SP/NH71/HW-10482 31-Mar-23 31 Checked by AE Rep.

26 Laying of BC Layer 327+200 328+160 RHS Top 960 VRC-SP/NH71/HW-10480 30-Mar-23 31 Checked by AE Rep.

27 Laying of BC Layer 328+160 328+470 RHS Top 310 VRC-SP/NH71/HW-10862 21-Aug-23 36 Checked by AE Rep

28 Laying of BC Layer 330+110 330+430 RHS Top 320 VRC-SP/NH71/HW-10650 14-Jun-23 34 Checked by AE Rep

29 Laying of BC Layer 331+140 331+400 RHS Top 260 VRC-SP/NH71/HW-10866 24-Aug-23 36 Checked by AE Rep

30 Laying of BC Layer 331+400 331+660 RHS Top 260 VRC-SP/NH71/HW-10651 14-Jun-23 34 Checked by AE Rep

31 Laying of BC Layer 331+660 332+960 RHS Top 1300 VRC-SP/NH71/HW-10355 27-Feb-23 30 Checked by AE Rep

32 Laying of BC Layer 332+960 333+350 RHS Top 390 VRC-SP/NH71/HW-10780 21-Jul-23 35 Checked by AE Rep

33 Laying of BC Layer 333+350 334+900 RHS Top 1550 VRC-SP/NH71/HW-10362 28-Feb-23 30 Checked by AE Rep

34 Laying of BC Layer 337+400 338+290 RHS Top 890 VRC-SP/NH71/HW-10346 26-Feb-23 30 Checked by AE Rep

35 Laying of BC Layer 338+290 338+430 RHS Top 140 VRC-SP/NH71/HW-10870 25-Aug-23 36 Checked by AE Rep

36 Laying of BC Layer 340+200 340+680 RHS Top 480 VRC-SP/NH71/HW-10336 25-Feb-23 30 Checked by AE Rep
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(A-5) Wearing Coat-Widening
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)

37 Laying of BC Layer 340+680 341+032 RHS Top 352 VRC-SP/NH71/HW-10856 17-Aug-23 36 Checked by AE Rep

38 Laying of BC Layer 341+718 342+000 RHS Top 282 VRC-SP/NH71/HW-10798 28-Jul-23 35 Checked by AE Rep

Total Qty RHS 18704 m 37 B

Total Qty (Both Side) 18.774 Km. 37 C=(A + B)/2

Previous Qty. (Both Side) 17.504 Km. 37 D

Net Payable Qty (Both Side) 1.270 Km. 37 E=(C - D)


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-1) Earthwork up to top of the sub-grade- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level & FDD Checking of Subgrade Top Layer 320+600 320+770 LHS SG TOP 170 VRC-SP/NH71/HW-5316 02-Jul-21 11
2 Level & FDD Checking of Subgrade Top Layer 320+770 320+930 LHS SG TOP 160 VRC-SP/NH71/HW-1830 29-Dec-20 4
3 Level & FDD Checking of Subgrade Top Layer 320+930 321+000 LHS SG TOP 70 VRC-SP/NH71/HW-2317 21-Jan-21 5 Checked by AE Rep.
4 Level & FDD Checking of Subgrade Top Layer 321+000 321+200 LHS SG TOP 200 VRC-SP/NH71/HW-292 04-Sep-20 1
5 Level & FDD Checking of Subgrade Top Layer 321+200 321+360 LHS SG TOP 160 VRC-SP/NH71/HW-385 10-Sep-20 1
6 Level & FDD Checking of Subgrade Top Layer 321+360 321+500 LHS SG TOP 140 VRC-SP/NH71/HW-336 07-Sep-20 1 Checked by AE Rep.
7 Level & FDD Checking of Subgrade Top Layer 321+500 321+550 LHS SG TOP 50 VRC-SP/NH71/HW-1213 12-Nov-20 3
8 Level & FDD Checking of Subgrade Top Layer 321+550 321+650 LHS SG TOP 100 VRC-SP/NH71/HW-3238 24-Feb-21 7 Checked by AE Rep.
9 Level & FDD Checking of Subgrade Top Layer 321+650 321+930 LHS SG TOP 280 VRC-SP/NH71/HW-135 27-Aug-20 1 Checked by AE Rep.
10 Level & FDD Checking of Subgrade Top Layer 322+480 322+500 LHS SG TOP 20 VRC-SP/NH71/HW-1834(A) 29-Dec-20 31 Checked by AE Rep.
11 Level & FDD Checking of Subgrade Top Layer 323+010 323+380 LHS SG TOP 370 VRC-SP/NH71/HW-104 25-Aug-20 1
12 Level & FDD Checking of Subgrade Top Layer 323+380 323+410 LHS SG TOP 30 VRC-SP/NH71/HW-750 04-Oct-20 2 Checked by AE Rep.
13 Level & FDD Checking of Subgrade Top Layer 323+410 323+600 LHS SG TOP 190 Done by earlier company 1
14 Level & FDD Checking of Subgrade Top Layer 323+600 323+810 LHS SG TOP 210 VRC-SP/NH71/HW-298 04-Sep-20 1
15 Level & FDD Checking of Subgrade Top Layer 323+810 323+870 LHS SG TOP 60 VRC-SP/NH71/HW-160 28-Aug-20 1
16 Level & FDD Checking of Subgrade Top Layer 325+200 326+340 LHS SG TOP 1140 Done by earlier company 1
17 Level & FDD Checking of Subgrade Top Layer 334+900 334+940 LHS SG TOP 40 VRC -SP/NH-71/HW-5349 07-Apr-21 11 Checked by AE Rep.
18 Level & FDD Checking of Subgrade Top Layer 334+940 335+010 LHS SG TOP 70 VRC-SP/NH71/HW-93 25-Aug-20 1 Checked by AE Rep.
19 Level & FDD Checking of Subgrade Top Layer 335+010 335+260 LHS SG TOP 250 Done by earlier company 1
20 Level & FDD Checking of Subgrade Top Layer 335+260 335+320 LHS SG TOP 60 VRC-SP/NH71/HW-95 25-Aug-20 1 Checked by AE Rep.
21 Level & FDD Checking of Subgrade Top Layer 335+320 335+520 LHS SG TOP 200 VRC-SP/NH71/HW-96 25-Aug-20 1
22 Level & FDD Checking of Subgrade Top Layer 335+520 335+580 LHS SG TOP 60 VRC-SP/NH71/HW-252 02-Sep-20 1
23 Level & FDD Checking of Subgrade Top Layer 336+710 337+360 LHS SG TOP 650 Done by earlier company 1 Checked by AE Rep.
24 Level & FDD Checking of Subgrade Top Layer 339+580 339+800 LHS SG TOP 220 VRC-SP/NH71/HW-6486 27-Sep-21 13
25 Level & FDD Checking of Subgrade Top Layer 339+800 340+200 LHS SG TOP 400 VRC-SP/NH71/HW-6784 17-Nov-21 15 Checked by AE Rep.
26 Level & FDD Checking of Subgrade Top Layer 348+804 348+900 LHS SG TOP 96 VRC-SP/NH71/HW-481 20-Sep-20 1
27 Level & FDD Checking of Subgrade Top Layer 348+900 349+500 LHS SG TOP 600 VRC-SP/NH-71/HW-5806 28-Jul-21 11
28 Level & FDD Checking of Subgrade Top Layer 349+500 350+050 LHS SG TOP 550 VRC-SP/NH-71/HW-6265 31-Aug-21 12 Checked by AE Rep.
29 Level & FDD Checking of Subgrade Top Layer 350+960 351+250 LHS SG TOP 290 VRC-SP/NH71/HW-4362 30-Apr-21 8 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-1) Earthwork up to top of the sub-grade- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
30 Level & FDD Checking of Subgrade Top Layer 351+250 351+550 LHS SG TOP 300 VRC-SP/NH71/HW-4479 07-May-21 9 Checked by AE Rep.
31 Level & FDD Checking of Subgrade Top Layer 351+550 351+770 LHS SG TOP 220 VRC-SP/NH71/HW-4581 13-May-21 9 Checked by AE Rep.
32 Level & FDD Checking of Subgrade Top Layer 351+770 351+840 LHS SG TOP 70 VRC-SP/NH71/HW-4658 17-May-21 9
33 Level & FDD Checking of Subgrade Top Layer 351+840 351+900 LHS SG TOP 60 VRC-SP/NH71/HW-4679 18-May-21 9
34 Level & FDD Checking of Subgrade Top Layer 351+900 352+000 LHS SG TOP 100 VRC-SP/NH71/HW-4715 20-May-21 9 Checked by AE Rep.
35 Level & FDD Checking of Subgrade Top Layer 352+000 352+230 LHS SG TOP 230 VRC-SP/NH71/HW-4799 27-May-21 9
36 Level & FDD Checking of Subgrade Top Layer 352+230 352+660 LHS SG TOP 430 VRC-SP/NH-71/HW-5077 17-Jun-21 10 Checked by AE Rep.
37 Level & FDD Checking of Subgrade Top Layer 352+660 352+720 LHS SG TOP 60 VRC-SP/NH-71/HW-5711 23-Jul-21 11 Checked by AE Rep.
38 Level & FDD Checking of Subgrade Top Layer 352+720 352+900 LHS SG TOP 180 VRC-SP/NH71/HW-3444 12-Mar-21 8
39 Level & FDD Checking of Subgrade Top Layer 353+710 353+860 LHS SG TOP 150 VRC-SP/NH71/HW-389 10-Sep-20 1 Checked by AE Rep.
40 Level & FDD Checking of Subgrade Top Layer 353+860 353+980 LHS SG TOP 120 VRC-SP/NH71/HW-3975 06-Apr-21 9 Checked by AE Rep.
41 Level & FDD Checking of Subgrade Top Layer 353+980 354+100 LHS SG TOP 120 VRC-SP/NH71/HW-390 10-Sep-20 1
42 Level & FDD Checking of Subgrade Top Layer 354+100 354+200 LHS SG TOP 100 VRC-SP/NH71/HW-4819 28-May-21 9
43 Level & FDD Checking of Subgrade Top Layer 354+200 354+300 LHS SG TOP 100 VRC-SP/NH71/HW-447 15-Sep-20 1 Checked by AE Rep.
44 Level & FDD Checking of Subgrade Top Layer 354+300 354+400 LHS SG TOP 100 VRC-SP/NH71/HW-414 12-Sep-20 1 Checked by AE Rep.
45 Level & FDD Checking of Subgrade Top Layer 354+400 354+500 LHS SG TOP 100 VRC-SP/NH-71/HW-5721 24-Jul-21 11 Checked by AE Rep.
Total Qty LHS 9276 m A
1 Level & FDD Checking of Subgrade Top Layer 320+600 320+740 RHS SG TOP 140 VRC-SP/NH71/HW-1353 23-Nov-20 3 Checked by AE Rep.
2 Level & FDD Checking of Subgrade Top Layer 320+740 320+770 RHS SG TOP 30 VRC-SP/NH-71/HW-7264 24-Dec-21 16 Checked by AE Rep.
3 Level & FDD Checking of Subgrade Top Layer 320+770 320+930 RHS SG TOP 160 VRC-SP/NH71/HW-729 03-Oct-20 2 Checked by AE Rep.
4 Level & FDD Checking of Subgrade Top Layer 320+930 321+000 RHS SG TOP 70 VRC-SP/NH71/HW-2318 21-Jan-21 5 Checked by AE Rep.
5 Level & FDD Checking of Subgrade Top Layer 321+000 321+200 RHS SG TOP 200 VRC-SP/NH71/HW-269 03-Sep-20 1 Checked by AE Rep.
6 Level & FDD Checking of Subgrade Top Layer 321+200 321+400 RHS SG TOP 200 VRC-SP/NH71/HW-891 15-Oct-20 2 Checked by AE Rep.
7 Level & FDD Checking of Subgrade Top Layer 321+400 321+480 RHS SG TOP 80 VRC-SP/NH71/HW-892 15-Oct-20 2 Checked by AE Rep.
8 Level & FDD Checking of Subgrade Top Layer 321+480 321+550 RHS SG TOP 70 VRC-SP/NH71/HW-571 26-Sep-20 2 Checked by AE Rep.
9 Level & FDD Checking of Subgrade Top Layer 321+550 321+650 RHS SG TOP 100 VRC-SP/NH71/HW-3237 24-Feb-21 7
10 Level & FDD Checking of Subgrade Top Layer 321+650 321+930 RHS SG TOP 280 VRC-SP/NH71/HW-135 27-Aug-20 1 Checked by AE Rep.
11 Level & FDD Checking of Subgrade Top Layer 323+010 323+380 RHS SG TOP 370 VRC-SP/NH71/HW-104 25-Aug-20 1 Checked by AE Rep.
12 Level & FDD Checking of Subgrade Top Layer 323+380 323+410 RHS SG TOP 30 VRC-SP/NH71/HW-749 04-Oct-20 2 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-1) Earthwork up to top of the sub-grade- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
13 Level & FDD Checking of Subgrade Top Layer 323+410 323+600 RHS SG TOP 190 Done by earlier company 1
14 Level & FDD Checking of Subgrade Top Layer 323+600 323+810 RHS SG TOP 210 VRC-SP/NH71/HW-298 04-Sep-20 1 Checked by AE Rep.
15 Level & FDD Checking of Subgrade Top Layer 323+810 323+870 RHS SG TOP 60 VRC-SP/NH71/HW-160 28-Aug-20 1 Checked by AE Rep.
16 Level & FDD Checking of Subgrade Top Layer 325+200 326+100 RHS SG TOP 900 Done by earlier company 1
17 Level & FDD Checking of Subgrade Top Layer 326+100 326+220 RHS SG TOP 120 VRC-SP/NH71/HW-537 24-Sep-20 1
18 Level & FDD Checking of Subgrade Top Layer 326+220 326+340 RHS SG TOP 120 VRC-SP/NH71/HW-3617 21-Mar-21 7 Checked by AE Rep.
19 Level & FDD Checking of Subgrade Top Layer 334+900 334+940 RHS SG TOP 40 VRC-SP/NH71/HW-6986 04-Dec-21 16 Checked by AE Rep.
20 Level & FDD Checking of Subgrade Top Layer 334+940 335+020 RHS SG TOP 80 VRC-SP/NH71/HW-92 25-Aug-20 1
21 Level & FDD Checking of Subgrade Top Layer 335+020 335+260 RHS SG TOP 240 Done by earlier company 1
22 Level & FDD Checking of Subgrade Top Layer 335+260 335+320 RHS SG TOP 60 VRC-SP/NH71/HW-94 25-Aug-20 1
23 Level & FDD Checking of Subgrade Top Layer 335+320 335+520 RHS SG TOP 200 VRC-SP/NH71/HW-97 25-Aug-20 1 Checked by AE Rep.
24 Level & FDD Checking of Subgrade Top Layer 335+520 335+580 RHS SG TOP 60 VRC-SP/NH71/HW-253 02-Sep-20 1 Checked by AE Rep.
25 Level & FDD Checking of Subgrade Top Layer 336+710 337+360 RHS SG TOP 650 Done by earlier company 1
26 Level & FDD Checking of Subgrade Top Layer 339+900 340+200 RHS SG TOP 300 VRC -SP/NH-71/HW-7111 13-Dec-21 17
27 Level & FDD Checking of Subgrade Top Layer 339+580 339+900 RHS SG Top 320 VRC -SP/NH-71/HW-7110 13-Dec-21 16 Checked by AE Rep.
28 Level & FDD Checking of Subgrade Top Layer 348+900 349+500 RHS SG TOP 600 VRC-SP/NH-71/HW-6225 29-Aug-21 12
29 Level & FDD Checking of Subgrade Top Layer 349+500 350+050 RHS SG TOP 550 VRC-SP/NH-71/HW-6266 31-Aug-21 12 Checked by AE Rep.
30 Level & FDD Checking of Subgrade Top Layer 350+960 351+250 RHS SG TOP 290 VRC-SP/NH71/HW-4363 30-Apr-21 8
31 Level & FDD Checking of Subgrade Top Layer 351+250 351+550 RHS SG TOP 300 VRC-SP/NH71/HW-4498 08-May-21 9
32 Level & FDD Checking of Subgrade Top Layer 351+550 351+770 RHS SG TOP 220 VRC-SP/NH71/HW-4564 12-May-21 9 Checked by AE Rep.
33 Level & FDD Checking of Subgrade Top Layer 351+770 351+840 RHS SG TOP 70 VRC-SP/NH71/HW-4659 17-May-21 9
34 Level & FDD Checking of Subgrade Top Layer 351+840 351+900 RHS SG TOP 60 VRC-SP/NH71/HW-4680 18-May-21 9
35 Level & FDD Checking of Subgrade Top Layer 351+900 352+000 RHS SG TOP 100 VRC-SP/NH71/HW-4716 20-May-21 9
36 Level & FDD Checking of Subgrade Top Layer 352+000 352+230 RHS SG TOP 230 VRC-SP/NH71/HW-4800 27-May-21 9
37 Level & FDD Checking of Subgrade Top Layer 352+230 352+660 RHS SG TOP 430 VRC-SP/NH-71/HW-5078 17-Jun-21 10 Checked by AE Rep.
38 Level & FDD Checking of Subgrade Top Layer 352+660 352+720 RHS SG TOP 60 VRC-SP/NH-71/HW-5712 23-Jul-21 11
39 Level & FDD Checking of Subgrade Top Layer 352+720 352+900 RHS SG TOP 180 VRC-SP/NH71/HW-3445 12-Mar-21 8 Checked by AE Rep.
40 Level & FDD Checking of Subgrade Top Layer 353+710 353+860 RHS SG TOP 150 VRC-SP/NH71/HW-389 10-Sep-20 1 Checked by AE Rep.
41 Level & FDD Checking of Subgrade Top Layer 353+860 353+980 RHS SG TOP 120 VRC-SP/NH71/HW-4027 12-Apr-21 9 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-1) Earthwork up to top of the sub-grade- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
42 Level & FDD Checking of Subgrade Top Layer 353+980 354+100 RHS SG TOP 120 VRC-SP/NH71/HW-390 10-Sep-20 1
43 Level & FDD Checking of Subgrade Top Layer 354+100 354+200 RHS SG TOP 100 VRC-SP/NH71/HW-4820 28-May-21 9
44 Level & FDD Checking of Subgrade Top Layer 354+200 354+300 RHS SG TOP 100 VRC-SP/NH71/HW-447 15-Sep-20 1 Checked by AE Rep.
45 Level & FDD Checking of Subgrade Top Layer 354+300 354+400 RHS SG TOP 100 VRC-SP/NH71/HW-414 12-Sep-20 1 Checked by AE Rep.
46 Level & FDD Checking of Subgrade Top Layer 354+400 354+500 RHS SG TOP 100 VRC-SP/NH-71/HW-5722 24-Jul-21 11 Checked by AE Rep.

Total Qty RHS 9160 m


Total Qty (Both Side) 9.218 Km.
Previous Qty. (Both Side) 9.218 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-2) Sub-Base Course- Bypass

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level and FDD Checking of GSB Top Layer 320+600 320+770 LHS GSB TOP 170 VRC-SP/NH71/HW-5469 12-Jul-21 11 Checked by AE Rep.
2 Level and FDD Checking of GSB Top Layer 320+770 320+930 LHS GSB TOP 160 VRC-SP/NH71/HW-1884 31-Dec-20 4
3 Level and FDD Checking of GSB Top Layer 320+930 321+000 LHS GSB TOP 70 VRC-SP/NH71/HW-2389 22-Jan-21 5
4 Level and FDD Checking of GSB Top Layer 321+000 321+200 LHS GSB TOP 200 VRC-SP/NH71/HW-312 05-Sep-20 1 Checked by AE Rep.
5 Level and FDD Checking of GSB Top Layer 321+200 321+360 LHS GSB TOP 160 VRC-SP/NH71/HW-402 11-Sep-20 1
6 Level and FDD Checking of GSB Top Layer 321+360 321+500 LHS GSB TOP 140 VRC-SP/NH71/HW-355 08-Sep-20 1 Checked by AE Rep.
7 Level and FDD Checking of GSB Top Layer 321+500 321+650 LHS GSB TOP 150 VRC-SP/NH71/HW-3321 02-Mar-21 7 Checked by AE Rep.
8 Level and FDD Checking of GSB Top Layer 321+650 321+930 LHS GSB TOP 280 VRC-SP/NH71/HW-205 01-Sep-20 1
9 Level and FDD Checking of GSB Top Layer 323+010 323+370 LHS GSB TOP 360 VRC-SP/NH71/HW-137 27-Aug-20 1 Checked by AE Rep.
10 Level and FDD Checking of GSB Top Layer 323+370 323+410 LHS GSB TOP 40 VRC-SP/NH71/HW-762 05-Oct-20 2 Checked by AE Rep.
11 Level and FDD Checking of GSB Top Layer 323+410 323+600 LHS GSB TOP 190 Done by earlier company 1
12 Level and FDD Checking of GSB Top Layer 323+600 323+810 LHS GSB TOP 210 VRC-SP/NH71/HW-317 05-Sep-20 1 Checked by AE Rep.
13 Level and FDD Checking of GSB Top Layer 323+810 323+870 LHS GSB TOP 60 VRC-SP/NH71/HW-300 04-Sep-20 1
14 Level and FDD Checking of GSB Top Layer 325+200 326+340 LHS GSB TOP 1140 Done by earlier company 1
15 Level and FDD Checking of GSB Top Layer 334+900 334+940 LHS GSB TOP 40 VRC -SP/NH-71/HW-5367 07-May-21 11 Checked by AE Rep.
16 Level and FDD Checking of GSB Top Layer 334+940 335+010 LHS GSB TOP 70 VRC-SP/NH71/HW-112 26-Aug-20 1
17 Level and FDD Checking of GSB Top Layer 335+010 335+260 LHS GSB TOP 250 Done by earlier company 1
18 Level and FDD Checking of GSB Top Layer 335+260 335+520 LHS GSB TOP 260 VRC-SP/NH71/HW-115 26-Aug-20 1
19 Level and FDD Checking of GSB Top Layer 335+520 335+580 LHS GSB TOP 60 VRC-SP/NH71/HW-274 03-Sep-20 1
20 Level and FDD Checking of GSB Top Layer 336+710 337+330 LHS GSB TOP 620 Done by earlier company 1
21 Level and FDD Checking of GSB Top Layer 337+330 337+360 LHS GSB TOP 30 VRC-SP/NH71/HW-397 11-Sep-20 1
22 Level and FDD Checking of GSB Top Layer 339+580 339+800 LHS GSB TOP 220 VRC-SP/NH71/HW-6775 16-Nov-21 15 Checked by AE Rep.
23 Level and FDD Checking of GSB Top Layer 339+800 340+200 LHS GSB TOP 400 VRC-SP/NH71/HW-6796 18-Nov-21 15
24 Level and FDD Checking of GSB Top Layer 348+804 348+900 LHS GSB TOP 96 VRC-SP/NH71/HW-655 29-Sep-20 1 Checked by AE Rep.
25 Level and FDD Checking of GSB Top Layer 348+900 349+200 LHS GSB TOP 300 VRC-SP/NH-71/HW-7580 20-Jan-21 17 Checked by AE Rep.
26 Level and FDD Checking of GSB Top Layer 349+200 349+700 LHS GSB TOP 500 VRC-SP/NH-71/HW-7621 24-Jan-21 17 Checked by AE Rep.
27 Level and FDD Checking of GSB Top Layer 350+960 351+480 LHS GSB TOP 520 VRC-SP/NH-71/HW-4539 10-May-21 9 Checked by AE Rep.
28 Level and FDD Checking of GSB Top Layer 351+480 351+920 LHS GSB TOP 440 VRC-SP/NH-71/HW-4759 23-May-21 9 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-2) Sub-Base Course- Bypass

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
29 Level and FDD Checking of GSB Top Layer 351+920 352+230 LHS GSB TOP 310 VRC-SP/NH-71/HW-4821 28-May-21 9
30 Level and FDD Checking of GSB Top Layer 352+230 352+550 LHS GSB TOP 320 VRC-SP/NH-71/HW-5140 26-Jun-21 10
31 Level and FDD Checking of GSB Top Layer 352+550 352+720 LHS GSB TOP 170 VRC-SP/NH-71/HW-5723 24-Jul-21 11 Checked by AE Rep.
32 Level and FDD Checking of GSB Top Layer 352+720 352+900 LHS GSB TOP 180 VRC-SP/NH71/HW-3462 13-Mar-21 8 Checked by AE Rep.
33 Level and FDD Checking of GSB Top Layer 353+710 354+000 LHS GSB TOP 290 VRC-SP/NH-71/HW-4806 27-May-21 9
34 Level and FDD Checking of GSB Top Layer 354+000 354+500 LHS GSB TOP 500 VRC-SP/NH-71/HW-7953 27-Feb-22 18 Checked by AE Rep.
Total Qty LHS 8906 m A
1 Level and FDD Checking of GSB Top Layer 320+600 320+710 RHS GSB TOP 110 VRC-SP/NH71/HW-1361 24-Nov-20 3 Checked by AE Rep.
2 Level and FDD Checking of GSB Top Layer 320+710 320+840 RHS GSB TOP 130 VRC-SP/NH71/HW-7281 25-Dec-21 16 Checked by AE Rep.
3 Level and FDD Checking of GSB Top Layer 320+840 321+000 RHS GSB TOP 160 VRC-SP/NH71/HW-3427 11-Mar-21 7
4 Level and FDD Checking of GSB Top Layer 321+000 321+200 RHS GSB TOP 200 VRC-SP/NH71/HW-291 04-Sep-20 1 *
5 Level and FDD Checking of GSB Top Layer 321+200 321+400 RHS GSB TOP 200 VRC-SP/NH71/HW-904 16-Oct-20 2 Checked by AE Rep.
6 Level and FDD Checking of GSB Top Layer 321+400 321+480 RHS GSB TOP 80 VRC-SP/NH71/HW-1017 27-Oct-20 2 Checked by AE Rep.
7 Level and FDD Checking of GSB Top Layer 321+480 321+650 RHS GSB TOP 170 VRC-SP/NH71/HW-3351 05-Mar-21 7 Checked by AE Rep.
8 Level and FDD Checking of GSB Top Layer 321+650 321+930 RHS GSB TOP 280 VRC-SP/NH71/HW-226 02-Sep-20 1 Checked by AE Rep.
9 Level and FDD Checking of GSB Top Layer 323+010 323+370 RHS GSB TOP 360 VRC-SP/NH71/HW-137 27-Aug-20 1 Checked by AE Rep.
10 Level and FDD Checking of GSB Top Layer 323+370 323+410 RHS GSB TOP 40 VRC-SP/NH71/HW-761 05-Oct-20 2 Checked by AE Rep.
11 Level and FDD Checking of GSB Top Layer 323+410 323+600 RHS GSB TOP 190 Done by earlier company 1
12 Level and FDD Checking of GSB Top Layer 323+600 323+810 RHS GSB TOP 210 VRC-SP/NH71/HW-317 05-Sep-20 1 Checked by AE Rep.
13 Level and FDD Checking of GSB Top Layer 323+810 323+870 RHS GSB TOP 60 VRC-SP/NH71/HW-300 04-Sep-20 1 Checked by AE Rep.
14 Level and FDD Checking of GSB Top Layer 325+200 326+100 RHS GSB TOP 900 Done by earlier company 1
15 Level and FDD Checking of GSB Top Layer 326+100 326+220 RHS GSB TOP 120 VRC-SP/NH71/HW-555 25-Sep-20 1 Checked by AE Rep.
16 Level and FDD Checking of GSB Top Layer 326+220 326+340 RHS GSB TOP 120 VRC -SP/NH-71/HW-3667 22-Mar-21 7 Checked by AE Rep.
17 Level and FDD Checking of GSB Top Layer 334+900 334+940 RHS GSB TOP 40 VRC -SP/NH-71/HW-6999 05-Dec-21 17
18 Level and FDD Checking of GSB Top Layer 334+940 335+020 RHS GSB TOP 80 VRC-SP/NH71/HW-111 26-Aug-20 1 Checked by AE Rep.
19 Level and FDD Checking of GSB Top Layer 335+020 335+260 RHS GSB TOP 240 Done by earlier company 1
20 Level and FDD Checking of GSB Top Layer 335+260 335+520 RHS GSB TOP 260 VRC-SP/NH71/HW-116 26-Aug-20 1
21 Level and FDD Checking of GSB Top Layer 335+520 335+580 RHS GSB TOP 60 VRC-SP/NH71/HW-9003 24-Jun-22 22
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-2) Sub-Base Course- Bypass

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
21 Level and FDD Checking of GSB Top Layer 336+710 337+280 RHS GSB TOP 570 Done by earlier company 1
22 Level and FDD Checking of GSB Top Layer 337+280 337+360 RHS GSB TOP 80 VRC-SP/NH-71/HW-9901 24-Dec-22 28 Checked by AE Rep.
23 Level and FDD Checking of GSB Top Layer 339+580 339+900 RHS GSB TOP 320 VRC -SP/NH-71/HW-7122 14-Dec-21 17
24 Level and FDD Checking of GSB Top Layer 339+900 340+200 RHS GSB TOP 300 VRC -SP/NH-71/HW-7123 14-Dec-21 17
25 Level and FDD Checking of GSB Top Layer 348+900 349+200 RHS GSB TOP 300 VRC-SP/NH-71/HW-7587 21-Jan-21 17 Checked by AE Rep.
26 Level and FDD Checking of GSB Top Layer 349+200 349+700 RHS GSB TOP 500 VRC-SP/NH-71/HW-7622 24-Jan-21 17 Checked by AE Rep.
27 Level and FDD Checking of GSB Top Layer 350+960 351+480 RHS GSB TOP 520 VRC-SP/NH-71/HW-4540 10-May-21 9 Checked by AE Rep.
28 Level and FDD Checking of GSB Top Layer 351+480 351+550 RHS GSB TOP 70 VRC-SP/NH-71/HW-4741 22-May-21 9
29 Level and FDD Checking of GSB Top Layer 351+550 351+700 RHS GSB TOP 150 VRC -SP/NH-71/HW-4582 13-May-21 9
30 Level and FDD Checking of GSB Top Layer 351+700 351+920 RHS GSB TOP 220 VRC-SP/NH-71/HW-4742 22-May-21 9
31 Level and FDD Checking of GSB Top Layer 351+920 352+230 RHS GSB TOP 310 VRC-SP/NH-71/HW-4835 29-May-21 9
32 Level and FDD Checking of GSB Top Layer 352+230 352+550 RHS GSB TOP 320 VRC-SP/NH-71/HW-5141 26-Jun-21 10 Checked by AE Rep.
33 Level and FDD Checking of GSB Top Layer 352+550 352+720 RHS GSB TOP 170 VRC-SP/NH-71/HW-5724 24-Jul-21 11
34 Level and FDD Checking of GSB Top Layer 352+720 352+900 RHS GSB TOP 180 VRC-SP/NH71/HW-3463 13-Mar-21 8
35 Level and FDD Checking of GSB Top Layer 353+710 354+000 RHS GSB TOP 290 VRC-SP/NH-71/HW-4807 27-May-21 9
36 Level and FDD Checking of GSB Top Layer 354+000 354+500 RHS GSB TOP 500 VRC-SP/NH-71/HW-7954 27-Feb-22 18

Total Qty RHS 8810 m B


Total Qty (Both Side) 8.858 Km. C=(A + B)/2
Previous Qty. (Both Side) 8.858 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37

Road works including culverts, widening and repair of culverts


Stage Payment Statement No. SPS-37 (90%)
(B-3) Non Bituminious Base- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level and FDD Checking of WMM Top Layer 320+600 320+770 LHS WMM TOP 170 VRC-SP/NH71/HW-5768 27-Jul-21 11 Checked by AE Rep.
2 Level and FDD Checking of WMM Top Layer 320+770 320+850 LHS WMM TOP 80 VRC-SP/NH71/HW-3251 25-Feb-21 7 Checked by AE Rep.
3 Level and FDD Checking of WMM Top Layer 320+850 320+980 LHS WMM TOP 130 VRC-SP/NH71/HW-3262 26-Feb-21 7 Checked by AE Rep.
4 Level and FDD Checking of WMM Top Layer 320+980 321+000 LHS WMM TOP 20 VRC-SP/NH71/HW-3320 02-Mar-21 7
5 Level and FDD Checking of WMM Top Layer 321+000 321+200 LHS WMM TOP 200 VRC-SP/NH71/HW-1020 27-Oct-20 2
6 Level and FDD Checking of WMM Top Layer 321+200 321+400 LHS WMM TOP 200 VRC-SP/NH71/HW-1047 29-Oct-20 2
7 Level and FDD Checking of WMM Top Layer 321+400 321+480 LHS WMM TOP 80 VRC-SP/NH71/HW-1101 03-Nov-20 3
8 Level and FDD Checking of WMM Top Layer 321+480 321+650 LHS WMM TOP 170 VRC-SP/NH71/HW-3338 04-Mar-21 7 Checked by AE Rep.
9 Level and FDD Checking of WMM Top Layer 321+650 321+930 LHS WMM TOP 280 VRC-SP/NH71/HW-1402 03-Nov-20 3 Checked by AE Rep.
10 Level and FDD Checking of WMM Top Layer 323+010 323+080 LHS WMM TOP 70 VRC-SP/NH71/HW-422 14-Sep-20 1 Checked by AE Rep.
11 Level and FDD Checking of WMM Top Layer 323+080 323+100 LHS WMM TOP 20 VRC-SP/NH71/HW-903 16-Oct-20 4
12 Level and FDD Checking of WMM Top Layer 323+100 323+360 LHS WMM TOP 260 VRC-SP/NH71/HW-408 12-Sep-20 1 Checked by AE Rep.
13 Level and FDD Checking of WMM Top Layer 323+360 323+420 LHS WMM TOP 60 VRC-SP/NH71/HW-794 07-Oct-20 2 Checked by AE Rep.
14 Level and FDD Checking of WMM Top Layer 323+420 323+810 LHS WMM TOP 390 VRC-SP/NH71/HW-512 22-Sep-20 1 Checked by AE Rep.
15 Level and FDD Checking of WMM Top Layer 323+810 323+870 LHS WMM TOP 60 VRC-SP/NH71/HW-594 27-Sep-20 1 Checked by AE Rep.
16 Level and FDD Checking of WMM Top Layer 325+200 325+240 LHS WMM TOP 40 VRC-SP/NH71/HW-590 27-Sep-20 1 Checked by AE Rep.
17 Level and FDD Checking of WMM Top Layer 325+240 326+220 LHS WMM TOP 980 Done by earlier company 1
18 Level and FDD Checking of WMM Top Layer 326+220 326+340 LHS WMM TOP 120 VRC-SP/NH71/HW-526 23-Sep-20 1
19 Level and FDD Checking of WMM Top Layer 334+900 334+940 LHS WMM TOP 40 VRC -SP/NH-71/HW-5391 07-Jul-21 11
20 Level and FDD Checking of WMM Top Layer 334+940 335+000 LHS WMM TOP 60 VRC-SP/NH71/HW-251 02-Sep-20 1
21 Level and FDD Checking of WMM Top Layer 335+000 335+250 LHS WMM TOP 250 Done by earlier company 1
22 Level and FDD Checking of WMM Top Layer 335+250 335+520 LHS WMM TOP 270 VRC-SP/NH71/HW-273 03-Sep-20 1
23 Level and FDD Checking of WMM Top Layer 335+520 335+580 LHS WMM TOP 60 VRC-SP/NH71/HW-483 20-Sep-20 1 Checked by AE Rep.
24 Level and FDD Checking of WMM Top Layer 336+710 337+330 LHS WMM TOP 620 Done by earlier company 1
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37

Road works including culverts, widening and repair of culverts


Stage Payment Statement No. SPS-37 (90%)
(B-3) Non Bituminious Base- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
25 Level and FDD Checking of WMM Top Layer 337+330 337+360 LHS WMM TOP 30 VRC-SP/NH71/HW-427 14-Sep-20 1 Checked by AE Rep.
26 Level and FDD Checking of WMM Top Layer 339+580 340+200 LHS WMM TOP 620 VRC-SP/NH71/HW-6923 28-Nov-21 15
27 Level and FDD Checking of WMM Top Layer 348+804 348+900 LHS WMM TOP 96 VRC-SP/NH71/HW-690 30-Sep-20 1
28 Level and FDD Checking of WMM Top Layer 348+900 349+600 LHS WMM TOP 700 VRC-SP/NH-71/HW-7948 27-Feb-22 18
29 Level and FDD Checking of WMM Top Layer 351+600 352+200 LHS WMM TOP 600 VRC-SP/NH-71/HW-7885 25-Feb-22 18 Checked by AE Rep.
30 Level and FDD Checking of WMM Top Layer 352+200 352+900 LHS WMM TOP 700 VRC-SP/NH-71/HW-7886 25-Feb-22 18
31 Level and FDD Checking of WMM Top Layer 353+710 354+500 LHS WMM TOP 790 VRC-SP/NH-71/HW-8085 23-Mar-22 19 Checked by AE Rep.
Total Qty LHS 8166 m A
1 Level and FDD Checking of WMM Top Layer 320+600 320+710 RHS WMM TOP 110 VRC-SP/NH71/HW-1385 26-Nov-20 3
2 Level and FDD Checking of WMM Top Layer 320+710 320+800 RHS WMM TOP 90 VRC-SP/NH71/HW-7812 19-Feb-22 18 Checked by AE Rep.
3 Level and FDD Checking of WMM Top Layer 320+800 320+840 RHS WMM TOP 40 VRC-SP/NH71/HW-7429 06-Jan-22 17 Checked by AE Rep.
4 Level and FDD Checking of WMM Top Layer 320+840 321+000 RHS WMM TOP 160 VRC-SP/NH71/HW-3440 12-Mar-21 7
5 Level and FDD Checking of WMM Top Layer 321+000 321+200 RHS WMM TOP 200 VRC-SP/NH71/HW-1019 27-Oct-20 2 Checked by AE Rep.
6 Level and FDD Checking of WMM Top Layer 321+200 321+400 RHS WMM TOP 200 VRC-SP/NH71/HW-1016 27-Oct-20 2
7 Level and FDD Checking of WMM Top Layer 321+400 321+480 RHS WMM TOP 80 VRC-SP/NH71/HW-1091 02-Nov-20 3
8 Level and FDD Checking of WMM Top Layer 321+480 321+650 RHS WMM TOP 170 VRC-SP/NH71/HW-3370 07-Mar-21 7 Checked by AE Rep.
9 Level and FDD Checking of WMM Top Layer 321+650 321+930 RHS WMM TOP 280 VRC-SP/NH71/HW-1391 26-Nov-20 3 Checked by AE Rep.
10 Level and FDD Checking of WMM Top Layer 323+010 323+080 RHS WMM TOP 70 VRC-SP/NH71/HW-423 14-Sep-20 1 Checked by AE Rep.
11 Level and FDD Checking of WMM Top Layer 323+080 323+100 RHS WMM TOP 20 VRC-SP/NH71/HW-879 14-Oct-20 4
12 Level and FDD Checking of WMM Top Layer 323+100 323+360 RHS WMM TOP 260 VRC-SP/NH71/HW-408 12-Sep-20 1 Checked by AE Rep.
13 Level and FDD Checking of WMM Top Layer 323+360 323+420 RHS WMM TOP 60 VRC-SP/NH71/HW-793 07-Oct-20 2 Checked by AE Rep.
14 Level and FDD Checking of WMM Top Layer 323+420 323+620 RHS WMM TOP 200 VRC-SP/NH71/HW-475 19-Sep-20 1 Checked by AE Rep.
15 Level and FDD Checking of WMM Top Layer 323+620 323+810 RHS WMM TOP 190 VRC-SP/NH71/HW-476 20-Sep-20 1 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37

Road works including culverts, widening and repair of culverts


Stage Payment Statement No. SPS-37 (90%)
(B-3) Non Bituminious Base- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
16 Level and FDD Checking of WMM Top Layer 323+810 323+870 RHS WMM TOP 60 VRC-SP/NH71/HW-594 27-Sep-20 1
17 Level and FDD Checking of WMM Top Layer 325+200 325+260 RHS WMM TOP 60 VRC-SP/NH71/HW-591 27-Sep-20 1
18 Level and FDD Checking of WMM Top Layer 325+260 326+100 RHS WMM TOP 840 Done by earlier company 1 *
19 Level and FDD Checking of WMM Top Layer 326+100 326+220 RHS WMM TOP 120 VRC-SP/NH71/HW-595 27-Sep-20 1 Checked by AE Rep.
20 Level and FDD Checking of WMM Top Layer 326+220 326+340 RHS WMM TOP 120 VRC-SP/NH71/HW-3718 24-Mar-21 7 Checked by AE Rep.
21 Level and FDD Checking of WMM Top Layer 334+900 334+940 RHS WMM TOP 40 VRC-SP/NH71/HW-7019 07-Dec-21 17
22 Level and FDD Checking of WMM Top Layer 334+940 335+020 RHS WMM TOP 80 VRC-SP/NH71/HW-250 02-Sep-20 1 Checked by AE Rep.
23 Level and FDD Checking of WMM Top Layer 335+020 335+250 RHS WMM TOP 230 Done by earlier company 1
24 Level and FDD Checking of WMM Top Layer 335+250 335+520 RHS WMM TOP 270 VRC-SP/NH71/HW-272 03-Sep-20 1 Checked by AE Rep.
25 Level and FDD Checking of WMM Top Layer 335+520 335+580 RHS WMM TOP 60 VRC-SP/NH-71/HW-9691 28-Oct-22 26
26 Level and FDD Checking of WMM Top Layer 336+710 337+280 RHS WMM TOP 570 Done by earlier company 1
27 Level and FDD Checking of WMM Top Layer 337+280 337+360 RHS WMM TOP 80 VRC-SP/NH-71/HW-9916 25-Dec-22 28 Checked by AE Rep.
28 Level and FDD Checking of WMM Top Layer 339+580 340+200 RHS WMM TOP 620 VRC-SP/NH71/HW-7302 26-Dec-21 17
29 Level and FDD Checking of WMM Top Layer 348+900 349+600 RHS WMM TOP 700 VRC-SP/NH-71/HW-7949 27-Feb-22 18 Checked by AE Rep.
30 Level and FDD Checking of WMM Top Layer 351+600 352+200 RHS WMM TOP 600 VRC-SP/NH-71/HW-7946 27-Feb-22 18 Checked by AE Rep.
31 Level and FDD Checking of WMM Top Layer 352+200 352+900 RHS WMM TOP 700 VRC-SP/NH-71/HW-7947 27-Feb-22 18
32 Level and FDD Checking of WMM Top Layer 353+710 354+500 RHS WMM TOP 790 VRC-SP/NH-71/HW-7980 28-Feb-22 18
Total Qty RHS 8070 m B
Total Qty (Both Side) 8.118 Km. C=(A + B)/2
Previous Qty. (Both Side) 8.118 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-4) Bituminous Base Course- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
1 Laying of DBM Layer 320+600 320+770 LHS Top 170 VRC-SP/NH-71/HW-6641 22-Oct-21 14
2 Laying of DBM Layer 320+770 321+480 LHS Top 710 VRC-SP/NH-71/HW-3408 09-Mar-21 7 Checked by AE Rep.
3 Laying of DBM Layer 321+480 321+930 LHS Top 450 VRC-SP/NH-71/HW-3426 11-Mar-21 7 Checked by AE Rep.
4 Laying of DBM Layer 323+010 323+100 LHS Top 90 VRC-SP/NH71/HW-966 22-Oct-20 4 ###
5 Laying of DBM Layer 323+100 323+800 LHS Top 700 VRC-SP/NH71/HW-1060 29-Oct-20 2 Checked by AE Rep.
6 Laying of DBM Layer 323+800 323+870 LHS Top 70 VRC-SP/NH71/HW-3583 20-Mar-21 7 Checked by AE Rep.
7 Laying of DBM Layer 325+200 325+240 LHS Top 40 VRC-SP/NH71/HW-3581 20-Mar-21 7 Checked by AE Rep.
8 Laying of DBM Layer 325+240 326+220 LHS Top 980 VRC-SP/NH71/HW-665 29-Sep-20 1 Checked by AE Rep.
9 Laying of DBM Layer 326+220 326+340 LHS Top 120 VRC-SP/NH71/HW-782A 06-Oct-20 2 ###
10 Laying of DBM Layer 334+900 334+940 LHS Top 40 VRC -SP/NH-71/HW-6155 23-Aug-21 12 Checked by AE Rep.
11 Laying of DBM Layer 334+940 335+000 LHS Top 60 VRC-SP/NH-71/HW-9823 12-Dec-22 28 Checked by AE Rep.
12 Laying of DBM Layer 335+000 335+500 LHS Top 500 VRC-SP/NH-71/HW-7688 31-Jan-22 17 Checked by AE Rep.
13 Laying of DBM Layer 335+500 335+580 LHS Top 80 VRC-SP/NH-71/HW-9890 22-Dec-22 29 Checked by AE Rep.
14 Laying of DBM Layer 336+710 337+360 LHS Top 650 VRC-SP/NH-71/HW-4842 30-May-21 9 ###
15 Laying of DBM Layer 339+580 340+200 LHS Top 620 VRC-SP/NH-71/HW-7686 31-Jan-22 17 Checked by AE Rep.
16 Laying of DBM Layer 349+050 349+480 LHS Top 430 VRC-SP/NH-71/HW-7975 28-Feb-22 19 ###
17 Laying of DBM Layer 349+480 349+600 LHS Top 120 VRC-SP/NH-71/HW-7975 28-Feb-22 18
18 Laying of DBM Layer 351+600 352+200 LHS Top 600 VRC-SP/NH-71/HW-7977 28-Feb-22 18 Checked by AE Rep.
19 Laying of DBM Layer 352+200 352+900 LHS Top 700 VRC-SP/NH-71/HW-7978 28-Feb-22 18 Checked by AE Rep.
20 Laying of DBM Layer 353+710 354+500 LHS Top 790 VRC-SP/NH-71/HW-8126 25-Mar-22 19 ###
Total Qty LHS 7920 m A
1 Laying of DBM Layer 320+600 320+650 RHS Top 50 VRC-SP/NH71/HW-1723 23-Dec-20 4 Checked by AE Rep.
2 Laying of DBM Layer 320+650 320+840 RHS Top 190 VRC-SP/NH71/HW-7906 26-Feb-22 19 Checked by AE Rep.
3 Laying of DBM Layer 320+840 321+000 RHS Top 160 VRC-SP/NH-71/HW-3492 15-Mar-21 7 ###
4 Laying of DBM Layer 321+000 321+480 RHS Top 480 VRC-SP/NH-71/HW-3438 12-Mar-21 7 Checked by AE Rep.
5 Laying of DBM Layer 321+480 321+930 RHS Top 450 VRC-SP/NH-71/HW-3452 13-Mar-21 7 Checked by AE Rep.
6 Laying of DBM Layer 323+010 323+100 RHS Top 90 VRC-SP/NH71/HW-976 23-Oct-20 4 ###
Stage Payment Statement No. SPS-37 (90%)
(B-4) Bituminous Base Course- Bypass
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
7 Laying of DBM Layer 323+100 323+800 RHS Top 700 VRC-SP/NH71/HW-1062 29-Oct-20 2 Checked by AE Rep.
8 Laying of DBM Layer 323+800 323+870 RHS Top 70 VRC-SP/NH71/HW-3584 20-Mar-21 7 Checked by AE Rep.
9 Laying of DBM Layer 325+200 325+260 RHS Top 60 VRC-SP/NH71/HW-3582 20-Mar-21 7 ###
10 Laying of DBM Layer 325+260 326+100 RHS Top 840 VRC-SP/NH71/HW-612 28-Sep-20 1 ###
11 Laying of DBM Layer 326+100 326+340 RHS Top 240 VRC -SP/NH-71/HW-3926 04-Apr-21 8 Checked by AE Rep.
12 Laying of DBM Layer 334+940 335+000 RHS Top 60 VRC-SP/NH-71/HW-9824 12-Dec-22 28 Checked by AE Rep.
13 Laying of DBM Layer 335+000 335+500 RHS Top 500 VRC-SP/NH-71/HW-7691 31-Jan-22 17 Checked by AE Rep.
14 Laying of DBM Layer 335+500 335+580 RHS Top 80 VRC-SP/NH-71/HW-9891 22-Dec-22 29 Checked by AE Rep.
15 Laying of DBM Layer 336+710 337+280 RHS Top 570 VRC-SP/NH-71/HW-4844 30-May-21 9 Checked by AE Rep.
16 Laying of DBM Layer 337+280 337+360 RHS Top 80 VRC-SP/NH-71/HW-9984 31-Dec-22 28 Checked by AE Rep.
17 Laying of DBM Layer 339+580 339+800 RHS Top 220 VRC-SP/NH-71/HW-7822 20-Feb-22 18
18 Laying of DBM Layer 339+800 340+000 RHS Top 200 VRC -SP/NH-71/Hw-8136 27-Mar-22 19
19 Laying of DBM Layer 340+000 340+200 RHS Top 200 VRC-SP/NH-71/HW-7798 18-Feb-22 18
20 Laying of DBM Layer 349+060 349+600 RHS Top 540 VRC-SP/NH-71/HW-7975 28-Feb-22 18 Checked by AE Rep.
21 Laying of DBM Layer 351+600 351+880 RHS Top 280 VRC-SP/NH-71/HW-7977A 28-Feb-22 18 Checked by AE Rep.
22 Laying of DBM Layer 351+880 352+200 RHS Top 320 VRC-SP/NH-71/HW-8131 26-Mar-22 19 ###
23 Laying of DBM Layer 352+200 352+700 RHS Top 500 VRC-SP/NH-71/HW-7978 28-Feb-22 18 Checked by AE Rep.
24 Laying of DBM Layer 352+700 352+900 RHS Top 200 VRC-SP/NH-71/HW-8112 24-Mar-22 19 Checked by AE Rep.
25 Laying of DBM Layer 353+710 354+500 RHS Top 790 VRC-SP/NH-71/HW-8111 24-Mar-22 19 ###

Total Qty RHS 7870 m B


Total Qty (Both Side) 7.895 Km. C=(A + B)/2
Previous Qty. (Both Side) 7.895 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(B-5) Wearing Coat- Bypass
MEASUREMENT SHEET
Quantity
Sl. No. Description Chainage Side Layer No. RFI No. Date SPS No. Remarks
(MTR)
1 Laying of BC Layer 321+900 321+930 LHS Top 30 VRC-SP/NH-71/HW-10887 03-Sep-23 37

Total Qty LHS 5180 m 37 A


1 Laying of BC Layer 321+850 321+930 RHS Top 80 VRC-SP/NH-71/HW-10902 09-Sep-23 37

Total Qty RHS 5180 m 37 B


Total Qty (Both Side) 5.180 Km. 37 C=(A + B)/2
Previous Qty. (Both Side) 5.125 Km. 37 D
Net Payable Qty (Both Side) 0.055 Km. 37 E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-1) Earthwork up to top of the sub-grade-Service Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level & FDD Checking of Subgrade Top Layer 308+350 308+400 LHS SG Top 50 VRC-SP/NH71/HW-1689 22-Dec-20 4 Checked by AE Rep.
2 Level & FDD Checking of Subgrade Top Layer 308+400 308+500 LHS SG Top 100 VRC-SP/NH71/HW-1668 21-Dec-20 4 Checked by AE Rep.
3 Level & FDD Checking of Subgrade Top Layer 308+500 308+600 LHS SG Top 100 VRC-SP/NH71/HW-1625 18-Dec-20 4
4 Level & FDD Checking of Subgrade Top Layer 308+600 308+800 LHS SG Top 200 VRC-SP/NH71/HW-1604 16-Dec-20 4 Checked by AE Rep.
5 Level & FDD Checking of Subgrade Top Layer 308+800 308+900 LHS SG Top 100 VRC-SP/NH71/HW-1743 24-Dec-20 4
6 Level & FDD Checking of Subgrade Top Layer 308+900 309+200 LHS SG Top 300 VRC-SP/NH71/HW-1882 31-Dec-20 4 Checked by AE Rep.
7 Level & FDD Checking of Subgrade Top Layer 309+200 309+400 LHS SG Top 200 VRC-SP/NH71/HW-1883 31-Dec-20 4
8 Level & FDD Checking of Subgrade Top Layer 315+620 315+630 LHS SG Top 10 VRC-SP/NH71/HW-3096 17-Feb-21 7 Checked by AE Rep.
9 Level & FDD Checking of Subgrade Top Layer 315+630 315+800 LHS SG Top 170 VRC-SP/NH71/HW-2285 20-Jan-21 5
10 Level & FDD Checking of Subgrade Top Layer 315+800 316+100 LHS SG Top 300 VRC-SP/NH71/HW-2522 28-Jan-21 5 Checked by AE Rep.
11 Level & FDD Checking of Subgrade Top Layer 316+100 316+200 LHS SG Top 100 VRC-SP/NH-71/HW-9269 21-Jul-22 23 Checked by AE Rep.
12 Level & FDD Checking of Subgrade Top Layer 316+200 316+450 LHS SG Top 250 VRC-SP/NH71/HW-3132 18-Feb-21 7
13 Level & FDD Checking of Subgrade Top Layer 316+450 316+650 LHS SG Top 200 VRC-SP/NH71/HW-3162 19-Feb-21 7 Checked by AE Rep.
14 Level & FDD Checking of Subgrade Top Layer 321+930 322+150 LHS SG Top 220 VRC-SP/NH71/HW-1796 28-Dec-20 4 Checked by AE Rep.
15 Level & FDD Checking of Subgrade Top Layer 322+150 322+480 LHS SG Top 330 VRC-SP/NH71/HW-1834 29-Dec-20 4
16 Level & FDD Checking of Subgrade Top Layer 322+500 322+750 LHS SG Top 250 VRC-SP/NH71/HW-1998 06-Jan-21 5 Checked by AE Rep.
17 Level & FDD Checking of Subgrade Top Layer 322+750 322+890 LHS SG Top 140 VRC-SP/NH71/HW-2523 28-Jan-21 5
18 Level & FDD Checking of Subgrade Top Layer 322+890 323+010 LHS SG Top 120 VRC-SP/NH71/HW-3714 24-Mar-21 9 Checked by AE Rep.
19 Level & FDD Checking of Subgrade Top Layer 323+870 324+100 LHS SG TOP 230 VRC-SP/NH71/HW-994 24-Oct-20 2
20 Level & FDD Checking of Subgrade Top Layer 324+100 324+250 LHS SG TOP 150 VRC-SP/NH71/HW-1002 26-Oct-20 2 Checked by AE Rep.
21 Level & FDD Checking of Subgrade Top Layer 324+250 324+450 LHS SG TOP 200 VRC-SP/NH71/HW-1035 28-Oct-20 2 Checked by AE Rep.
22 Level & FDD Checking of Subgrade Top Layer 324+450 324+700 LHS SG TOP 250 VRC-SP/NH71/HW-1006 26-Oct-20 2
23 Level & FDD Checking of Subgrade Top Layer 324+700 324+900 LHS SG TOP 200 VRC-SP/NH71/HW-990 24-Oct-20 2 Checked by AE Rep.
24 Level & FDD Checking of Subgrade Top Layer 324+900 325+100 LHS SG TOP 200 VRC-SP/NH71/HW-940 20-Oct-20 2 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-1) Earthwork up to top of the sub-grade-Service Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
25 Level & FDD Checking of Subgrade Top Layer 325+100 325+200 LHS SG TOP 100 VRC-SP/NH71/HW-1022 27-Oct-20 2 Checked by AE Rep.
26 Level & FDD Checking of Subgrade Top Layer 328+470 328+900 LHS SG Top 430 VRC-SP/NH71/HW-3923 04-Mar-21 8 Checked by AE Rep.
27 Level & FDD Checking of Subgrade Top Layer 328+900 329+350 LHS SG TOP 450 VRC-SP/NH71/HW-1038 28-Oct-20 2 Checked by AE Rep.
28 Level & FDD Checking of Subgrade Top Layer 329+350 329+450 LHS SG TOP 100 VRC-SP/NH71/HW-2544 28-Jan-21 5 Checked by AE Rep.
29 Level & FDD Checking of Subgrade Top Layer 329+450 329+600 LHS SG TOP 150 VRC-SP/NH71/HW-1819 28-Dec-20 4
30 Level & FDD Checking of Subgrade Top Layer 329+600 329+700 LHS SG TOP 100 VRC-SP/NH71/HW-321 05-Sep-20 1 Checked by AE Rep.
31 Level & FDD Checking of Subgrade Top Layer 329+700 329+800 LHS SG TOP 100 VRC-SP/NH71/HW-176 29-Aug-20 1
32 Level & FDD Checking of Subgrade Top Layer 329+800 329+900 LHS SG TOP 100 VRC-SP/NH71/HW-177 29-Aug-20 1 Checked by AE Rep.
33 Level & FDD Checking of Subgrade Top Layer 329+900 330+000 LHS SG TOP 100 VRC-SP/NH71/HW-284 03-Sep-20 1 Checked by AE Rep.
34 Level & FDD Checking of Subgrade Top Layer 330+000 330+110 LHS SG TOP 110 VRC-SP/NH71/HW-319 05-Sep-20 1 Checked by AE Rep.
35 Level & FDD Checking of Subgrade Top Layer 330+430 330+630 LHS SG TOP 200 VRC-SP/NH71/HW-1039 28-Oct-20 2
36 Level & FDD Checking of Subgrade Top Layer 330+630 330+800 LHS SG Top 170 VRC-SP/NH71/HW-4060 14-Apr-21 8 Checked by AE Rep.
37 Level & FDD Checking of Subgrade Top Layer 330+800 330+900 LHS SG TOP 100 VRC -SP/NH-71/Hw-8496 01-May-22 21 Checked by AE Rep.
38 Level & FDD Checking of Subgrade Top Layer 330+900 331+000 LHS SG Top 100 VRC -SP/NH-71/HW-4884 06-Apr-21 11 Checked by AE Rep.
39 Level & FDD Checking of Subgrade Top Layer 331+000 331+140 LHS SG Top 140 VRC-SP/NH-71/HW-6278 01-Sep-21 13
40 Level & FDD Checking of Subgrade Top Layer 335+580 335+830 LHS SG Top 250 VRC-SP/NH-71/HW-7271 24-Dec-21 16 Checked by AE Rep.
41 Level & FDD Checking of Subgrade Top Layer 335+830 336+120 LHS SG Top 290 VRC-SP/NH-71/HW-7305 26-Dec-21 16
42 Level & FDD Checking of Subgrade Top Layer 336+120 336+710 LHS SG Top 590 VRC-SP/NH71/HW-3924 03-Apr-21 8 Checked by AE Rep.
43 Level & FDD Checking of Subgrade Top Layer 338+430 338+680 LHS SG Top 250 VRC-SP/NH71/HW-1849 29-Dec-20 4
44 Level & FDD Checking of Subgrade Top Layer 338+680 338+900 LHS SG Top 220 VRC-SP/NH71/HW-3343 04-Mar-21 7 Checked by AE Rep.
45 Level & FDD Checking of Subgrade Top Layer 338+900 339+100 LHS SG Top 200 VRC -SP/NH-71/HW-5329 07-Feb-21 11 Checked by AE Rep.
46 Level & FDD Checking of Subgrade Top Layer 339+100 339+400 LHS SG Top 300 VRC-SP/NH71/HW-4883 04-Jun-21 10 Checked by AE Rep.
47 Level & FDD Checking of Subgrade Top Layer 339+400 339+550 LHS SG Top 150 VRC-SP/NH71/HW-5220 27-Jun-21 10 Checked by AE Rep.
48 Level & FDD Checking of Subgrade Top Layer 339+550 339+580 LHS SG Top 30 VRC -SP/NH-71/HW-5238 28-06-2021 11
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-1) Earthwork up to top of the sub-grade-Service Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
49 Level & FDD Checking of Subgrade Top Layer 343+380 344+000 LHS SG TOP 620 VRC-SP/NH71/HW-2517 27-Jan-20 5 Checked by AE Rep.
50 Level & FDD Checking of Subgrade Top Layer 344+000 344+680 LHS SG TOP 680 VRC-SP/NH71/HW-2552 28-Jan-20 5 Checked by AE Rep.
51 Level & FDD Checking of Subgrade Top Layer 345+810 346+500 LHS SG TOP 690 VRC-SP/NH71/HW-2569 29-Jan-20 5 Checked by AE Rep.
52 Level & FDD Checking of Subgrade Top Layer 346+500 347+120 LHS SG TOP 620 VRC-SP/NH71/HW-2572 29-Jan-20 5 Checked by AE Rep.
53 Level & FDD Checking of Subgrade Top Layer 352+900 353+300 LHS SG TOP 400 VRC-SP/NH-71/HW-8078 21-Mar-22 19 Checked by AE Rep.
54 Level & FDD Checking of Subgrade Top Layer 353+300 353+710 LHS SG TOP 410 VRC-SP/NH-71/HW-8079 21-Mar-22 19
55 Level & FDD Checking of Subgrade Top Layer 354+500 355+000 LHS SG TOP 500 VRC-SP/NH-71/HW-8487 30-Apr-22 20
56 Level & FDD Checking of Subgrade Top Layer 355+000 355+600 LHS SG TOP VRC-SP/NH-71/HW-8488 30-Apr-22 20
Total Qty LHS 13020 m A
1 Level & FDD Checking of Subgrade Top Layer 308+350 308+610 RHS SG Top 260 VRC-SP/NH71/HW-1518 11-Dec-20 4 Checked by AE Rep.
2 Level & FDD Checking of Subgrade Top Layer 308+610 308+630 RHS SG Top 20 VRC-SP/NH71/HW-3715 24-Mar-21 8 Checked by AE Rep.
3 Level & FDD Checking of Subgrade Top Layer 308+630 308+800 RHS SG Top 170 VRC-SP/NH71/HW-1560 15-Dec-20 4 Checked by AE Rep.
4 Level & FDD Checking of Subgrade Top Layer 308+800 308+840 RHS SG Top 40 VRC-SP/NH-71/HW-6058 17-Aug-21 12 Checked by AE Rep.
5 Level & FDD Checking of Subgrade Top Layer 308+840 309+000 RHS SG Top 160 VRC-SP/NH71/HW-1628 18-Dec-20 4
6 Level & FDD Checking of Subgrade Top Layer 309+000 309+250 RHS SG Top 250 VRC-SP/NH71/HW-1624 18-Dec-20 4 Checked by AE Rep.
7 Level & FDD Checking of Subgrade Top Layer 309+250 309+400 RHS SG Top 150 VRC-SP/NH71/HW-1647 19-Dec-20 4 Checked by AE Rep.
8 Level & FDD Checking of Subgrade Top Layer 315+620 315+800 RHS SG Top 180 VRC-SP/NH71/HW-4671 18-May-21 9 Checked by AE Rep.
9 Level & FDD Checking of Subgrade Top Layer 315+800 316+000 RHS SG Top 200 VRC-SP/NH71/HW-4669 18-May-21 9
10 Level & FDD Checking of Subgrade Top Layer 316+000 316+200 RHS SG Top 200 VRC-SP/NH71/HW-4704 20-May-21 9 Checked by AE Rep.
11 Level & FDD Checking of Subgrade Top Layer 316+200 316+450 RHS SG Top 250 VRC-SP/NH71/HW-1454 03-Dec-20 4
12 Level & FDD Checking of Subgrade Top Layer 316+450 316+650 RHS SG Top 200 VRC-SP/NH71/HW-1462 04-Dec-20 4 Checked by AE Rep.
13 Level & FDD Checking of Subgrade Top Layer 321+930 322+150 RHS SG Top 220 VRC-SP/NH71/HW-2623 02-Feb-21 7 Checked by AE Rep.
14 Level & FDD Checking of Subgrade Top Layer 322+150 322+300 RHS SG Top 150 VRC-SP/NH71/HW-2804 08-Feb-21 7
15 Level & FDD Checking of Subgrade Top Layer 322+300 322+480 RHS SG Top 180 VRC-SP/NH71/HW-3062 16-Feb-21 7 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-1) Earthwork up to top of the sub-grade-Service Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
16 Level & FDD Checking of Subgrade Top Layer 322+480 322+550 RHS SG Top 70 VRC-SP/NH71/HW-3548 19-Mar-21 9 Checked by AE Rep.
17 Level & FDD Checking of Subgrade Top Layer 322+550 322+750 RHS SG Top 200 VRC-SP/NH71/HW-1627 18-Dec-20 4 Checked by AE Rep.
18 Level & FDD Checking of Subgrade Top Layer 322+750 323+000 RHS SG Top 250 VRC-SP/NH71/HW-1648 19-Dec-20 4 Checked by AE Rep.
19 Level & FDD Checking of Subgrade Top Layer 323+000 323+010 RHS SG Top 10 VRC-SP/NH-71/HW-3714 24-Mar-21 25
20 Level & FDD Checking of Subgrade Top Layer 323+870 324+100 RHS SG TOP 230 VRC-SP/NH71/HW-863 13-Oct-20 2 Checked by AE Rep.
21 Level & FDD Checking of Subgrade Top Layer 324+100 324+250 RHS SG TOP 150 VRC-SP/NH71/HW-880 14-Oct-20 2
22 Level & FDD Checking of Subgrade Top Layer 324+250 324+460 RHS SG TOP 210 VRC-SP/NH71/HW-1033 28-Oct-20 2
23 Level & FDD Checking of Subgrade Top Layer 324+460 324+610 RHS SG TOP 150 VRC-SP/NH71/HW-905 16-Oct-20 2
24 Level & FDD Checking of Subgrade Top Layer 324+610 324+700 RHS SG TOP 90 VRC-SP/NH71/HW-913 17-Oct-20 2
25 Level & FDD Checking of Subgrade Top Layer 324+700 324+900 RHS SG TOP 200 VRC-SP/NH71/HW-969 22-Oct-20 2
26 Level & FDD Checking of Subgrade Top Layer 324+900 325+100 RHS SG TOP 200 VRC-SP/NH71/HW-942 20-Oct-20 2 Checked by AE Rep.
27 Level & FDD Checking of Subgrade Top Layer 325+100 325+200 RHS SG TOP 100 VRC-SP/NH71/HW-1021 27-Oct-20 2 Checked by AE Rep.
28 Level & FDD Checking of Subgrade Top Layer 328+470 328+800 RHS SG TOP 330 VRC-SP/NH71/HW-3314 01-Mar-21 7 Checked by AE Rep.
29 Level & FDD Checking of Subgrade Top Layer 328+800 328+860 RHS SG TOP 60 VRC-SP/NH-71/HW-8999 24-Jun-22 22
30 Level & FDD Checking of Subgrade Top Layer 328+980 329+060 RHS SG TOP 80 VRC-SP/NH-71/HW-10744 02-Jul-23 35 Checked by AE Rep.
31 Level & FDD Checking of Subgrade Top Layer 329+060 329+200 RHS SG TOP 140 VRC-SP/NH71/HW-4494 08-May-21 9
32 Level & FDD Checking of Subgrade Top Layer 329+200 329+460 RHS SG Top 260 VRC-SP/NH71/HW-4154 19-Apr-21 8 Checked by AE Rep.
33 Level & FDD Checking of Subgrade Top Layer 329+460 329+600 RHS SG TOP 140 VRC-SP/NH71/HW-100 25-Aug-20 1 Checked by AE Rep.
34 Level & FDD Checking of Subgrade Top Layer 329+600 329+800 RHS SG TOP 200 VRC-SP/NH71/HW-198 31-Aug-20 1 Checked by AE Rep.
35 Level & FDD Checking of Subgrade Top Layer 329+800 329+900 RHS SG TOP 100 VRC-SP/NH71/HW-217 01-Sep-20 1 Checked by AE Rep.
36 Level & FDD Checking of Subgrade Top Layer 329+900 330+110 RHS SG TOP 210 VRC-SP/NH71/HW-3340 04-Mar-21 7 Checked by AE Rep.
37 Level & FDD Checking of Subgrade Top Layer 330+430 330+800 RHS SG Top 370 VRC-SP/NH71/HW-3898 02-Apr-21 8
38 Level & FDD Checking of Subgrade Top Layer 330+800 330+850 RHS SG TOP 50 VRC -SP/NH-71/Hw-8500 02-May-22 21
39 Level & FDD Checking of Subgrade Top Layer 330+850 331+000 RHS SG Top 150 VRC -SP/NH-71/HW-5306 07-Jan-21 11 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-1) Earthwork up to top of the sub-grade-Service Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
40 Level & FDD Checking of Subgrade Top Layer 331+000 331+140 RHS SG Top 140 VRC -SP/NH-71/HW-10844 12-Aug-23 36 Checked by AE Rep.
40 Level & FDD Checking of Subgrade Top Layer 335+580 335+850 RHS SG TOP 270 VRC-SP/NH-71/HW-7157 25-Nov-21 16 Checked by AE Rep.
41 Level & FDD Checking of Subgrade Top Layer 335+850 336+120 RHS SG Top 270 VRC -SP/NH-71/HW-6837 21-Nov-21 15 Checked by AE Rep.
42 Level & FDD Checking of Subgrade Top Layer 336+120 336+710 RHS SG Top 590 VRC-SP/NH71/HW-4250 24-Apr-21 8
43 Level & FDD Checking of Subgrade Top Layer 338+430 338+660 RHS SG TOP 230 VRC-SP/NH71/HW-1878 30-Dec-20 4
44 Level & FDD Checking of Subgrade Top Layer 338+660 338+940 RHS SG TOP 280 VRC-SP/NH71/HW-1825 28-Dec-20 4
45 Level & FDD Checking of Subgrade Top Layer 338+940 339+000 RHS SG Top 60 VRC-SP/NH71/HW-2863 09-Feb-21 6 Checked by AE Rep.
46 Level & FDD Checking of Subgrade Top Layer 339+000 339+080 RHS SG Top 80 VRC -SP/NH-71/HW-5334 07-Mar-21 11
47 Level & FDD Checking of Subgrade Top Layer 339+080 339+200 RHS SG Top 120 VRC-SP/NH71/HW-3332 03-Mar-21 7 Checked by AE Rep.
48 Level & FDD Checking of Subgrade Top Layer 339+200 339+400 RHS SG TOP 200 VRC-SP/NH71/HW-2595 30-Jan-21 5
49 Level & FDD Checking of Subgrade Top Layer 339+400 339+450 RHS SG TOP 50 VRC -SP/NH-71/HW-5260 29-06-2021 11
50 Level & FDD Checking of Subgrade Top Layer 339+450 339+500 RHS SG TOP 50 VRC -SP/NH-71/Hw-8228 11-Apr-22 20 Checked by AE Rep.
51 Level & FDD Checking of Subgrade Top Layer 339+500 339+520 RHS SG TOP 20 VRC -SP/NH-71/Hw-10812 02-Aug-23 36
51 Level & FDD Checking of Subgrade Top Layer 343+380 344+100 RHS SG TOP 720 VRC-SP/NH-71/HW-9103 28-Jun-22 22 Checked by AE Rep
52 Level & FDD Checking of Subgrade Top Layer 344+100 344+300 RHS SG TOP 200 VRC-SP/NH71/HW-2551 28-Jan-20 5
53 Level & FDD Checking of Subgrade Top Layer 344+300 344+680 RHS SG TOP 380 VRC-SP/NH71/HW-2568 29-Jan-20 5 Checked by AE Rep.
54 Level & FDD Checking of Subgrade Top Layer 345+810 346+200 RHS SG TOP 390 VRC-SP/NH71/HW-2570 29-Jan-20 5
55 Level & FDD Checking of Subgrade Top Layer 346+200 346+400 RHS SG TOP 200 VRC-SP/NH71/HW-2573 29-Jan-20 5 Checked by AE Rep.
56 Level & FDD Checking of Subgrade Top Layer 346+400 347+120 RHS SG TOP 720 VRC-SP/NH-71/HW-7860 24-Feb-22 19 Checked by AE Rep.
57 Level & FDD Checking of Subgrade Top Layer 352+900 353+300 RHS SG TOP 400 VRC-SP/NH-71/HW-8087 22-Mar-22 19 Checked by AE Rep.
58 Level & FDD Checking of Subgrade Top Layer 353+300 353+710 RHS SG TOP 410 VRC-SP/NH-71/HW-8088 22-Mar-22 19
59 Level & FDD Checking of Subgrade Top Layer 354+500 354+970 RHS SG TOP 470 VRC-SP/NH-71/HW-8478 29-Apr-22 20 Checked by AE Rep.

Total Qty RHS 12830 m B


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-1) Earthwork up to top of the sub-grade-Service Road
MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

Total Qty (Both Side) 12.925 Km. C=(A + B)/2


Previous Qty. (Both Side) 12.925 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-2) Sub-Base Course- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level and FDD Checking of GSB Top Layer 308+350 308+600 LHS GSB Top 250 VRC-SP/NH71/HW-3472 14-Mar-21 7
2 Level and FDD Checking of GSB Top Layer 308+600 308+800 LHS GSB Top 200 VRC-SP/NH71/HW-3488 15-Mar-21 7 Checked by AE Rep.
3 Level and FDD Checking of GSB Top Layer 308+800 308+900 LHS GSB Top 100 VRC-SP/NH71/HW-10442 23-Mar-23 31 Checked by AE Rep.
4 Level and FDD Checking of GSB Top Layer 308+900 309+200 LHS GSB Top 300 VRC-SP/NH71/HW-3713 24-Mar-21 7 Checked by AE Rep.
5 Level and FDD Checking of GSB Top Layer 309+200 309+400 LHS GSB Top 200 VRC-SP/NH71/HW-3741 25-Mar-21 7
6 Level and FDD Checking of GSB Top Layer 315+620 315+800 LHS GSB Top 180 VRC-SP/NH71/HW-3455 13-Mar-21 7 Checked by AE Rep.
7 Level and FDD Checking of GSB Top Layer 315+800 316+000 LHS GSB Top 200 VRC-SP/NH71/HW-4187 21-Apr-21 8 Checked by AE Rep.
8 Level and FDD Checking of GSB Top Layer 316+000 316+500 LHS GSB Top 500 VRC-SP/NH71/HW-9285 22-Jul-22 23 Checked by AE Rep.
9 Level and FDD Checking of GSB Top Layer 316+500 316+650 LHS GSB Top 150 VRC-SP/NH71/HW-3802 27-Mar-21 7
10 Level and FDD Checking of GSB Top Layer 321+930 322+480 LHS GSB Top 550 VRC-SP/NH71/HW-3800 27-Mar-21 7 Checked by AE Rep.
11 Level and FDD Checking of GSB Top Layer 322+480 322+550 LHS GSB Top 70 VRC-SP/NH71/HW-3800(a) 27-Mar-21 31 Checked by AE Rep.
12 Level and FDD Checking of GSB Top Layer 322+550 323+010 LHS GSB Top 460 VRC-SP/NH71/HW-3827 28-Mar-21 7
13 Level and FDD Checking of GSB Top Layer 323+870 324+100 LHS GSB TOP 230 VRC-SP/NH71/HW-1007 26-Oct-20 2 Checked by AE Rep.
14 Level and FDD Checking of GSB Top Layer 324+100 324+250 LHS GSB TOP 150 VRC-SP/NH71/HW-1005 26-Oct-20 2 Checked by AE Rep.
15 Level and FDD Checking of GSB Top Layer 324+250 324+450 LHS GSB TOP 200 VRC-SP/NH71/HW-1053 29-Oct-20 2
16 Level and FDD Checking of GSB Top Layer 324+450 324+700 LHS GSB TOP 250 VRC-SP/NH71/HW-1036 28-Oct-20 2 Checked by AE Rep.
17 Level and FDD Checking of GSB Top Layer 324+700 324+900 LHS GSB TOP 200 VRC-SP/NH71/HW-1003 26-Oct-20 2
18 Level and FDD Checking of GSB Top Layer 324+900 325+100 LHS GSB TOP 200 VRC-SP/NH71/HW-956 21-Oct-20 2 Checked by AE Rep.
19 Level and FDD Checking of GSB Top Layer 325+100 325+200 LHS GSB TOP 100 VRC-SP/NH71/HW-1037 28-Oct-20 2
20 Level and FDD Checking of GSB Top Layer 328+470 328+900 LHS GSB Top 430 VRC -SP/NH-71/HW-3941 04-Apr-21 8 Checked by AE Rep.
21 Level and FDD Checking of GSB Top Layer 328+900 329+350 LHS GSB TOP 450 VRC-SP/NH71/HW-1054 29-Oct-20 2 Checked by AE Rep.
22 Level and FDD Checking of GSB Top Layer 329+350 329+450 LHS GSB TOP 100 VRC-SP/NH71/HW-2563 29-Jan-21 5
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-2) Sub-Base Course- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
23 Level and FDD Checking of GSB Top Layer 329+450 329+600 LHS GSB TOP 150 VRC-SP-NH-71-HW-1850 29-Dec-20 4
24 Level and FDD Checking of GSB Top Layer 329+600 329+700 LHS GSB TOP 100 VRC-SP/NH71/HW-242 02-Sep-20 1 Checked by AE Rep.
25 Level and FDD Checking of GSB Top Layer 329+700 329+800 LHS GSB TOP 100 VRC-SP/NH71/HW-199 31-Aug-20 1
26 Level and FDD Checking of GSB Top Layer 329+800 329+900 LHS GSB TOP 100 VRC-SP/NH71/HW-200 31-Aug-20 1 Checked by AE Rep.
27 Level and FDD Checking of GSB Top Layer 329+900 330+000 LHS GSB TOP 100 VRC-SP/NH71/HW-320 05-Sep-20 1 Checked by AE Rep.
28 Level and FDD Checking of GSB Top Layer 330+000 330+110 LHS GSB TOP 110 VRC-SP/NH71/HW-359 08-Sep-20 1 Checked by AE Rep.
29 Level and FDD Checking of GSB Top Layer 330+430 330+630 LHS GSB TOP 200 VRC-SP/NH71/HW-1072 30-Oct-20 2
30 Level and FDD Checking of GSB Top Layer 330+630 330+800 LHS GSB Top 170 VRC -SP/NH-71/HW-4080 15-04-2021 8
31 Level and FDD Checking of GSB Top Layer 330+900 331+000 LHS GSB Top 100 VRC -SP/NH-71/HW-4901 06-May-21 11
32 Level and FDD Checking of GSB Top Layer 331+000 331+140 LHS GSB Top 140 VRC-SP/NH-71/HW-6291 02-Sep-21 13
33 Level and FDD Checking of GSB Top Layer 335+580 335+830 LHS GSB Top 250 VRC -SP/NH-71/HW-7304 26-Dec-21 17
34 Level and FDD Checking of GSB Top Layer 335+830 336+120 LHS GSB Top 290 VRC-SP/NH-71/HW-7365 31-Dec-21 16 Checked by AE Rep.
35 Level and FDD Checking of GSB Top Layer 336+120 336+710 LHS GSB Top 590 VRC-SP/NH-71/HW-4251 26-Apr-21 8 Checked by AE Rep.
36 Level and FDD Checking of GSB Top Layer 338+430 338+680 LHS GSB Top 250 VRC-SP/NH71/HW-3342 04-Mar-21 7 Checked by AE Rep.
37 Level and FDD Checking of GSB Top Layer 338+680 338+900 LHS GSB Top 220 VRC-SP/NH71/HW-3356 05-Mar-21 7 Checked by AE Rep.
38 Level and FDD Checking of GSB Top Layer 338+900 339+100 LHS GSB Top 200 VRC -SP/NH-71/HW-5335 07-Mar-21 11 Checked by AE Rep.
39 Level and FDD Checking of GSB Top Layer 339+100 339+400 LHS GSB Top 300 VRC -SP/NH-71/HW-4900 05-Jun-21 10 Checked by AE Rep.
40 Level and FDD Checking of GSB Top Layer 339+400 339+550 LHS GSB Top 150 VRC -SP/NH-71/HW-5237 28-Jun-21 10
41 Level and FDD Checking of GSB Top Layer 339+550 339+580 LHS GSB Top 30 VRC -SP/NH-71/HW-5257 29-06-2021 11
42 Level and FDD Checking of GSB Top Layer 343+380 343+420 LHS GSB Top 40 VRC-SP/NH-71/HW-9026 25-Jun-22 22 Checked by AE Rep
43 Level and FDD Checking of GSB Top Layer 343+420 343+960 LHS GSB Top 540 VRC-SP/NH-71/HW-8787 28-May-22 21 Checked by AE Rep.
44 Level and FDD Checking of GSB Top Layer 343+960 344+000 LHS GSB Top 40 VRC-SP/NH-71/HW-9027 25-Jun-22 22 Checked by AE Rep
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-2) Sub-Base Course- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
45 Level and FDD Checking of GSB Top Layer 344+000 344+680 LHS GSB Top 680 VRC-SP/NH-71/HW-8483 29-Apr-22 20
46 Level and FDD Checking of GSB Top Layer 345+810 346+500 LHS GSB Top 690 VRC -SP/NH-71/HW-7660 29-Jan-22 17
47 Level and FDD Checking of GSB Top Layer 346+520 347+120 LHS GSB Top 600 VRC -SP/NH-71/HW-7641 27-Jan-22 17 Checked by AE Rep.
48 Level and FDD Checking of GSB Top Layer 352+900 353+300 LHS GSB Top 400 VRC-SP/NH-71/HW-8102 23-Mar-22 19 Checked by AE Rep.
49 Level and FDD Checking of GSB Top Layer 353+300 353+710 LHS GSB Top 410 VRC-SP/NH-71/HW-8103 23-Mar-22 19
Total Qty LHS 12420 m A
1 Level and FDD Checking of GSB Top Layer 308+350 308+610 RHS GSB TOP 260 VRC-SP/NH71/HW-1531 12-Dec-20 4 Checked by AE Rep.
2 Level and FDD Checking of GSB Top Layer 308+610 308+630 RHS GSB Top 20 VRC-SP/NH71/HW-3742 25-Mar-21 8
3 Level and FDD Checking of GSB Top Layer 308+630 308+800 RHS GSB TOP 170 VRC-SP/NH71/HW-1626 18-Dec-20 4 Checked by AE Rep.
4 Level and FDD Checking of GSB Top Layer 308+800 308+840 RHS GSB Top 40 VRC-SP/NH71/HW-6059 17-Aug-21 12 Checked by AE Rep.
5 Level and FDD Checking of GSB Top Layer 308+840 309+100 RHS GSB TOP 260 VRC-SP/NH71/HW-1650 19-Dec-20 4 Checked by AE Rep.
6 Level and FDD Checking of GSB Top Layer 309+100 309+400 RHS GSB Top 300 VRC-SP/NH71/HW-3804 27-Mar-21 7 Checked by AE Rep.
7 Level and FDD Checking of GSB Top Layer 315+620 315+800 RHS GSB Top 180 VRC-SP/NH71/HW-4708 20-May-21 9
8 Level and FDD Checking of GSB Top Layer 315+800 316+000 RHS GSB Top 200 VRC-SP/NH71/HW-4693 19-May-21 9 Checked by AE Rep.
9 Level and FDD Checking of GSB Top Layer 316+000 316+200 RHS GSB Top 200 VRC-SP/NH71/HW-5475 12-Jul-21 11
10 Level and FDD Checking of GSB Top Layer 316+200 316+450 RHS GSB TOP 250 VRC-SP/NH71/HW-1463 04-Dec-20 4 Checked by AE Rep.
11 Level and FDD Checking of GSB Top Layer 316+450 316+650 RHS GSB TOP 200 VRC-SP/NH71/HW-1480 07-Dec-20 4
12 Level and FDD Checking of GSB Top Layer 321+930 322+480 RHS GSB Top 550 VRC-SP/NH71/HW-3799 27-Mar-21 7
13 Level and FDD Checking of GSB Top Layer 322+480 322+500 RHS GSB Top 20 VRC-SP/NH71/HW-8342 22-Apr-22 22 Checked by AE Rep.
14 Level and FDD Checking of GSB Top Layer 322+500 322+710 RHS GSB Top 210 VRC-SP/NH71/HW-3651 22-Mar-21 7 Checked by AE Rep.
15 Level and FDD Checking of GSB Top Layer 322+710 323+010 RHS GSB Top 300 VRC-SP/NH71/HW-3797 27-Mar-21 7
16 Level and FDD Checking of GSB Top Layer 323+870 324+100 RHS GSB TOP 230 VRC-SP/NH71/HW-893 15-Oct-20 2 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-2) Sub-Base Course- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
17 Level and FDD Checking of GSB Top Layer 324+100 324+250 RHS GSB TOP 150 VRC-SP/NH71/HW-894 15-Oct-20 2 Checked by AE Rep.
18 Level and FDD Checking of GSB Top Layer 324+250 324+460 RHS GSB TOP 210 VRC-SP/NH71/HW-1048 29-Oct-20 2
19 Level and FDD Checking of GSB Top Layer 324+460 324+610 RHS GSB TOP 150 VRC-SP/NH71/HW-926 18-Oct-20 2
20 Level and FDD Checking of GSB Top Layer 324+610 324+700 RHS GSB TOP 90 VRC-SP/NH71/HW-925 18-Oct-20 2
21 Level and FDD Checking of GSB Top Layer 324+700 324+900 RHS GSB TOP 200 VRC-SP/NH71/HW-991 24-Oct-20 2 Checked by AE Rep.
22 Level and FDD Checking of GSB Top Layer 324+900 325+100 RHS GSB TOP 200 VRC-SP/NH71/HW-957 21-Oct-20 2 Checked by AE Rep.
23 Level and FDD Checking of GSB Top Layer 325+100 325+200 RHS GSB TOP 100 VRC-SP/NH71/HW-1034 28-Oct-20 2
24 Level and FDD Checking of GSB Top Layer 328+470 328+620 RHS GSB TOP 150 VRC-SP/NH71/HW-3331 03-Mar-21 7 Checked by AE Rep.
25 Level and FDD Checking of GSB Top Layer 328+620 328+800 RHS GSB Top 180 VRC -SP/NH-71/HW-3921 04-Mar-21 8
26 Level and FDD Checking of GSB Top Layer 328+800 328+860 RHS GSB Top 60 VRC-SP/NH-71/HW-9025 25-Jun-22 22 Checked by AE Rep
27 Level and FDD Checking of GSB Top Layer 329+060 329+200 RHS GSB Top 140 VRC -SP/NH-71/HW-4495 08-May-21 9
28 Level and FDD Checking of GSB Top Layer 329+200 329+460 RHS GSB Top 260 VRC -SP/NH-71/HW-4175 20-04-2021 8
29 Level and FDD Checking of GSB Top Layer 329+460 329+600 RHS GSB TOP 140 VRC-SP/NH71/HW-138 27-Aug-20 1 Checked by AE Rep.
30 Level and FDD Checking of GSB Top Layer 329+600 329+800 RHS GSB TOP 200 VRC-SP/NH71/HW-201 31-Aug-20 1 Checked by AE Rep.
31 Level and FDD Checking of GSB Top Layer 329+800 329+900 RHS GSB TOP 100 VRC-SP/NH71/HW-282 03-Sep-20 1 Checked by AE Rep.
32 Level and FDD Checking of GSB Top Layer 329+900 330+110 RHS GSB Top 210 VRC -SP/NH-71/HW-3897 04-Feb-21 8
33 Level and FDD Checking of GSB Top Layer 330+430 330+800 RHS GSB Top 370 VRC -SP/NH-71/HW-3920 04-Mar-21 8 Checked by AE Rep.
34 Level and FDD Checking of GSB Top Layer 330+850 331+000 RHS GSB Top 150 VRC -SP/NH-71/HW-5326 07-Feb-21 11 Checked by AE Rep.
35 Level and FDD Checking of GSB Top Layer 331+000 331+140 RHS GSB Top 140 VRC -SP/NH-71/HW-10845 12-Aug-23 36 Checked by AE Rep.
35 Level and FDD Checking of GSB Top Layer 335+580 335+830 RHS GSB Top 250 VRC -SP/NH-71/HW-7291 25-Dec-21 17 Checked by AE Rep.
36 Level and FDD Checking of GSB Top Layer 335+830 336+120 RHS GSB Top 290 VRC -SP/NH-71/HW-6895 25-Nov-21 15
37 Level and FDD Checking of GSB Top Layer 336+120 336+710 RHS GSB Top 590 VRC -SP/NH-71/HW-4364 30-Apr-21 8
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-2) Sub-Base Course- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
38 Level and FDD Checking of GSB Top Layer 338+430 338+800 RHS GSB Top 370 VRC -SP/NH-71/HW-4881 04-Jun-21 10 Checked by AE Rep.
39 Level and FDD Checking of GSB Top Layer 338+800 339+000 RHS GSB Top 200 VRC -SP/NH-71/HW-4882 04-Jun-21 10 Checked by AE Rep.
40 Level and FDD Checking of GSB Top Layer 339+000 339+080 RHS GSB TOP 80 VRC -SP/NH-71/HW-5352 07-Apr-21 11
41 Level and FDD Checking of GSB Top Layer 339+080 339+200 RHS GSB TOP 120 VRC-SP/NH71/HW-3341 04-Mar-21 7
42 Level and FDD Checking of GSB Top Layer 339+200 339+400 RHS GSB TOP 200 VRC-SP/NH71/HW-3381 07-Mar-21 7 Checked by AE Rep.
43 Level and FDD Checking of GSB Top Layer 339+400 339+450 RHS GSB TOP 50 VRC -SP/NH-71/HW-5261 29-06-2021 11 Checked by AE Rep.
44 Level and FDD Checking of GSB Top Layer 339+450 339+500 RHS GSB TOP 50 VRC -SP/NH-71/Hw-8244 13-Apr-22 20
45 Level and FDD Checking of GSB Top Layer 339+500 339+520 RHS GSB TOP 20 VRC -SP/NH-71/Hw-10817 03-Aug-23 36 Checked by AE Rep.
45 Level and FDD Checking of GSB Top Layer 343+380 344+100 RHS GSB TOP 720 VRC -SP/NH-71/Hw-9357 31-Jul-22 23 Checked by AE Rep.
46 Level and FDD Checking of GSB Top Layer 344+100 344+680 RHS GSB Top 580 VRC-SP/NH-71/HW-8441 26-Apr-22 20 Checked by AE Rep.
47 Level and FDD Checking of GSB Top Layer 345+810 346+500 RHS GSB Top 690 VRC-SP/NH-71/HW-8323 20-Apr-22 20 Checked by AE Rep.
48 Level and FDD Checking of GSB Top Layer 346+500 346+600 RHS GSB Top 100 VRC-SP/NH-71/HW-9140 29-Jun-22 22
48 Level and FDD Checking of GSB Top Layer 346+600 347+120 RHS GSB Top 520 VRC-SP/NH-71/HW-8324 20-Apr-22 20
49 Level and FDD Checking of GSB Top Layer 352+900 353+300 RHS GSB Top 400 VRC-SP/NH-71/HW-8482 29-Apr-22 20 Checked by AE Rep.
50 Level and FDD Checking of GSB Top Layer 353+300 353+710 RHS GSB Top 410 VRC-SP/NH-71/HW-8786 28-May-22 22
Total Qty RHS 12230 m B
Total Qty (Both Side) 12.325 Km. C=(A + B)/2
Previous Qty. (Both Side) 12.325 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work)
on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-3) Non Bituminious Base- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
1 Level and FDD Checking of WMM Top Layer 308+350 308+500 LHS WMM Top 150 VRC-SP/NH71/HW-3708 24-Mar-21 7 Checked by AE Rep.
2 Level and FDD Checking of WMM Top Layer 308+500 308+800 LHS WMM Top 300 VRC-SP/NH71/HW-3801 27-Mar-21 7 Checked by AE Rep.
3 Level and FDD Checking of WMM Top Layer 308+800 308+900 LHS WMM Top 100 VRC-SP/NH71/HW-10451 24-Mar-23 31 Checked by AE Rep.
4 Level and FDD Checking of WMM Top Layer 308+900 309+400 LHS WMM Top 500 VRC-SP/NH71/HW-3832 28-Mar-21 7 Checked by AE Rep.
5 Level and FDD Checking of WMM Top Layer 315+620 315+900 LHS WMM Top 280 VRC-SP/NH71/HW-4220 23-Apr-21 8 Checked by AE Rep.
6 Level and FDD Checking of WMM Top Layer 315+900 316+500 LHS WMM Top 600 VRC-SP/NH71/HW-9315 24-Jul-21 23
7 Level and FDD Checking of WMM Top Layer 316+500 316+650 LHS WMM Top 150 VRC-SP/NH71/HW-4313 28-Apr-21 8
8 Level and FDD Checking of WMM Top Layer 321+930 322+480 LHS WMM Top 550 VRC-SP/NH71/HW-3830 28-Mar-21 7
9 Level and FDD Checking of WMM Top Layer 322+480 322+550 LHS WMM Top 70 VRC-SP/NH71/HW-3830(a) 28-Mar-21 31 Checked by AE Rep.
10 Level and FDD Checking of WMM Top Layer 322+550 323+010 LHS WMM Top 460 VRC-SP/NH71/HW-3849 31-Mar-21 7
11 Level and FDD Checking of WMM Top Layer 323+870 324+500 LHS WMM TOP 630 VRC-SP/NH71/HW-1070 30-Oct-20 4
12 Level and FDD Checking of WMM Top Layer 324+500 325+200 LHS WMM TOP 700 VRC-SP/NH71/HW-1071 30-Oct-20 4
13 Level and FDD Checking of WMM Top Layer 328+470 329+000 LHS WMM TOP 530 VRC-SP/NH-71/HW-6074 17-Aug-21 12
14 Level and FDD Checking of WMM Top Layer 329+000 329+250 LHS WMM TOP 250 VRC-SP/NH71/HW-4813 28-May-21 9
15 Level and FDD Checking of WMM Top Layer 329+250 329+400 LHS WMM TOP 150 VRC-SP/NH71/HW-4712 20-May-21 9
16 Level and FDD Checking of WMM Top Layer 329+400 329+800 LHS WMM TOP 400 VRC-SP/NH71/HW-4457 06-May-21 9 Checked by AE Rep.
17 Level and FDD Checking of WMM Top Layer 329+800 330+110 LHS WMM TOP 310 VRC-SP/NH71/HW-4458 06-May-21 9 Checked by AE Rep.
18 Level and FDD Checking of WMM Top Layer 330+430 331+000 LHS WMM TOP 570 VRC -SP/NH-71/Hw-8519 06-May-22 21 Checked by AE Rep.
19 Level and FDD Checking of WMM Top Layer 331+000 331+140 LHS WMM TOP 140 VRC-SP/NH71/HW-6304 03-Sep-21 13
20 Level and FDD Checking of WMM Top Layer 335+580 336+120 LHS WMM TOP 540 VRC-SP/NH-71/HW-7843 23-Feb-22 19
21 Level and FDD Checking of WMM Top Layer 336+120 336+300 LHS WMM TOP 180 VRC-SP/NH-71/HW-7867 24-Feb-22 19 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work)
on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-3) Non Bituminious Base- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
22 Level and FDD Checking of WMM Top Layer 336+300 336+710 LHS WMM TOP 410 VRC-SP/NH-71/HW-5007 12-Jun-21 10
23 Level and FDD Checking of WMM Top Layer 338+430 338+900 LHS WMM TOP 470 VRC -SP/NH-71/HW-5081 18-Jun-21 10 Checked by AE Rep.
24 Level and FDD Checking of WMM Top Layer 338+900 339+100 LHS WMM TOP 200 VRC -SP/NH-71/HW-5353 07-Apr-21 11 Checked by AE Rep.
25 Level and FDD Checking of WMM Top Layer 339+100 339+200 LHS WMM TOP 100 VRC -SP/NH-71/HW-6518 30-Sep-21 14
26 Level and FDD Checking of WMM Top Layer 339+200 339+400 LHS WMM TOP 200 VRC -SP/NH-71/HW-5219 27-Jun-21 10
27 Level and FDD Checking of WMM Top Layer 339+400 339+550 LHS WMM TOP 150 VRC -SP/NH-71/HW-5281 30-Jun-21 10 Checked by AE Rep.
28 Level and FDD Checking of WMM Top Layer 339+550 339+580 LHS WMM TOP 30 VRC -SP/NH-71/HW-5282 30-06-2021 11
29 Level and FDD Checking of WMM Top Layer 343+380 344+000 LHS WMM TOP 620 VRC-SP/NH-71/HW-9608 27-Sep-22 25 Checked by AE Rep.
30 Level and FDD Checking of WMM Top Layer 344+000 344+680 LHS WMM TOP 680 VRC-SP/NH-71/HW-9609 27-Sep-22 25 Checked by AE Rep.
31 Level and FDD Checking of WMM Top Layer 345+810 346+500 LHS WMM TOP 690 VRC-SP/NH-71/HW-9110 28-Jun-22 22 Checked by AE Rep.
32 Level and FDD Checking of WMM Top Layer 346+500 347+120 LHS WMM TOP 620 VRC-SP/NH-71/HW-9111 28-Jun-22 22 Checked by AE Rep.
33 Level and FDD Checking of WMM Top Layer 352+900 353+300 LHS WMM TOP 400 VRC-SP/NH-71/HW-8992 23-Jun-22 22
34 Level and FDD Checking of WMM Top Layer 353+300 353+710 LHS WMM TOP 410 VRC-SP/NH-71/HW-8993 23-Jun-22 22
Total Qty LHS 12540 m A
1 Level and FDD Checking of WMM Top Layer 308+350 308+500 RHS WMM Top 150 VRC-SP/NH71/HW-2110 12-Jan-21 5 Checked by AE Rep.
2 Level and FDD Checking of WMM Top Layer 308+500 308+610 RHS WMM Top 110 VRC-SP/NH71/HW-5732 25-Jul-21 11
3 Level and FDD Checking of WMM Top Layer 308+610 308+800 RHS WMM Top 190 VRC-SP/NH71/HW-3806 27-Mar-21 7 Checked by AE Rep.
4 Level and FDD Checking of WMM Top Layer 308+800 308+850 RHS WMM Top 50 VRC-SP/NH71/HW-6082 18-Aug-21 12
5 Level and FDD Checking of WMM Top Layer 308+850 309+100 RHS WMM Top 250 VRC-SP/NH71/HW-4345 30-Apr-21 8 Checked by AE Rep.
6 Level and FDD Checking of WMM Top Layer 309+100 309+400 RHS WMM Top 300 VRC-SP/NH71/HW-3834 28-Mar-21 7 Checked by AE Rep.
7 Level and FDD Checking of WMM Top Layer 315+620 315+800 RHS WMM Top 180 VRC-SP/NH71/HW-5471 12-Jul-21 11
8 Level and FDD Checking of WMM Top Layer 315+800 316+000 RHS WMM Top 200 VRC-SP/NH71/HW-5521 14-Jul-21 11
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work)
on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-3) Non Bituminious Base- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
9 Level and FDD Checking of WMM Top Layer 316+000 316+200 RHS WMM Top 200 VRC-SP/NH71/HW-5540 15-Jul-21 11 Checked by AE Rep.
10 Level and FDD Checking of WMM Top Layer 316+200 316+450 RHS WMM Top 250 VRC-SP/NH71/HW-1715 21-Dec-20 4 Checked by AE Rep.
11 Level and FDD Checking of WMM Top Layer 316+450 316+650 RHS WMM Top 200 VRC-SP/NH71/HW-1584 16-Dec-20 4
12 Level and FDD Checking of WMM Top Layer 321+930 322+160 RHS WMM Top 230 VRC-SP/NH71/HW-8367 23-Apr-22 22 Checked by AE Rep
13 Level and FDD Checking of WMM Top Layer 322+160 322+440 RHS WMM Top 280 VRC-SP/NH71/HW-5994 11-Aug-21 12 Checked by AE Rep.
14 Level and FDD Checking of WMM Top Layer 322+440 322+500 RHS WMM Top 60 VRC-SP/NH71/HW-8386 24-Apr-22 20 Checked by AE Rep.
15 Level and FDD Checking of WMM Top Layer 322+500 323+010 RHS WMM Top 510 VRC-SP/NH71/HW-3828 28-Mar-21 7
16 Level and FDD Checking of WMM Top Layer 323+870 324+500 RHS WMM TOP 630 VRC-SP/NH71/HW-1068 30-Oct-20 4
17 Level and FDD Checking of WMM Top Layer 324+500 325+200 RHS WMM TOP 700 VRC-SP/NH71/HW-1069 30-Oct-20 4
18 Level and FDD Checking of WMM Top Layer 328+470 328+700 RHS WMM Top 230 VRC-SP/NH-71/HW-6163 24-Aug-21 12
19 Level and FDD Checking of WMM Top Layer 329+060 329+450 RHS WMM Top 390 VRC-SP/NH-71/HW-6055 16-Aug-21 12 Checked by AE Rep.
20 Level and FDD Checking of WMM Top Layer 329+450 329+500 RHS WMM Top 50 VRC-SP/NH-71/HW-10747 03-Jul-23 35 Checked by AE Rep.
21 Level and FDD Checking of WMM Top Layer 329+500 329+900 RHS WMM TOP 400 VRC -SP/NH-71/HW-4899 05-Jun-21 10
22 Level and FDD Checking of WMM Top Layer 329+900 330+110 RHS WMM TOP 210 VRC-SP/NH71/HW-4814 28-May-21 9
23 Level and FDD Checking of WMM Top Layer 330+430 330+760 RHS WMM TOP 330 VRC -SP/NH-71/HW-5047 15-Jun-21 10
24 Level and FDD Checking of WMM Top Layer 330+760 330+850 RHS WMM TOP 90 VRC -SP/NH-71/Hw-8548 10-May-22 21 Checked by AE Rep.
25 Level and FDD Checking of WMM Top Layer 330+850 331+000 RHS WMM Top 150 VRC -SP/NH-71/HW-5351 07-Apr-21 11 Checked by AE Rep.
26 Level and FDD Checking of WMM Top Layer 331+000 331+140 RHS WMM Top 140 VRC -SP/NH-71/HW-10848 13-Aug-23 36 Checked by AE Rep.
26 Level and FDD Checking of WMM Top Layer 335+580 336+120 RHS WMM TOP 540 VRC-SP/NH-71/HW-7844 23-Feb-22 19 Checked by AE Rep.
27 Level and FDD Checking of WMM Top Layer 336+120 336+710 RHS WMM TOP 590 VRC-SP/NH-71/HW-4979 10-Jun-21 10 Checked by AE Rep.
28 Level and FDD Checking of WMM Top Layer 338+430 338+480 RHS WMM TOP 50 VRC-SP/NH-71/HW-8937 17-Jun-22 22
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work)
on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-3) Non Bituminious Base- Service Road

MEASUREMENT SHEET
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)
29 Level and FDD Checking of WMM Top Layer 338+480 339+000 RHS WMM TOP 520 VRC -SP/NH-71/HW-5119 21-Jun-21 10 Checked by AE Rep.
30 Level and FDD Checking of WMM Top Layer 339+000 339+080 RHS WMM TOP 80 VRC -SP/NH-71/HW-5370 07-May-21 11 Checked by AE Rep.
31 Level and FDD Checking of WMM Top Layer 339+080 339+400 RHS WMM TOP 320 VRC -SP/NH-71/HW-5082 18-Jun-21 10
32 Level and FDD Checking of WMM Top Layer 339+400 339+450 RHS WMM TOP 50 VRC -SP/NH-71/HW-5285 30-06-2021 11
33 Level and FDD Checking of WMM Top Layer 339+450 339+500 RHS WMM TOP 50 VRC -SP/NH-71/Hw-8291 18-Apr-22 20
33 Level and FDD Checking of WMM Top Layer 339+500 339+520 RHS WMM TOP 20 VRC -SP/NH-71/Hw-10821 05-Aug-23 36 Checked by AE Rep.
34 Level and FDD Checking of WMM Top Layer 343+380 344+000 RHS WMM TOP 620 VRC-SP/NH-71/HW-9624 28-Sep-22 25
35 Level and FDD Checking of WMM Top Layer 344+000 344+680 RHS WMM TOP 680 VRC-SP/NH-71/HW-9625 28-Sep-22 25
36 Level and FDD Checking of WMM Top Layer 345+810 347+120 RHS WMM TOP 1310 VRC -SP/NH-71/Hw-9356 31-Jul-22 23 Checked by AE Rep.
37 Level and FDD Checking of WMM Top Layer 352+900 353+300 RHS WMM TOP 400 VRC-SP/NH-71/HW-9032 25-Jun-22 22
38 Level and FDD Checking of WMM Top Layer 353+300 353+710 RHS WMM TOP 410 VRC-SP/NH-71/HW-9033 25-Jun-22 22 Checked by AE Rep

Total Qty RHS 12120 m B


Total Qty (Both Side) 12.330 Km. C=(A + B)/2
Previous Qty. (Both Side) 12.330 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
Road works including culverts, widening and repair of culverts
Stage Payment Statement No. SPS-37 (90%)
(C-4) Bituminous Base Course- Service Road

MEASUREMENT SHEET
Sl. Quantity
Description Chainage Side Layer No. RFI No. Date SPS No. Remarks
No. (m)
1 Laying of DBM Layer 309+060 309+260 LHS Top Layer 200 VRC-SP/NH-71/HW-10510 14-May-23 37
2 Laying of DBM Layer 321+930 322+500 LHS DBM 570 VRC-SP/NH-71/HW-10377 03-Mar-23 37

Total Qty LHS 12200 m 37 A

3 Laying of DBM Layer 322+440 322+550 RHS DBM 110 VRC-SP/NH-71/HW-10847 13-Aug-23 37

Total Qty RHS 11930 m 37 B


Total Qty (Both Side) 12.065 Km. 37 C=(A + B)/2
Previous Qty. (Both Side) 11.625 Km. 37 D
Net Payable Qty (Both Side) 0.440 Km. 37 E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37

Road works including culverts, widening and repair of culverts

Stage Payment Statement No. SPS-37 (90%)


(C-5) Wearing Coat On Service Road

MEASUREMENT SHEET
Quantity
Sl. No. Description Chainage Side Layer No. RFI No. Date SPS No. Remarks
(m)
1 Laying of BC Layer 308+350 309+400 LHS Top 1050 VRC-SP/NH-71/HW-10918 16-Sep-23 37
BC damages at
2 Laying of BC Layer 315+620 316+000 LHS Top 300 VRC-SP/NH-71/HW-10951 29-Sep-23 37
locations patch

deduction 20 mtr
3 Laying of BC Layer 316+000 316+650 LHS Top 630 VRC-SP/NH-71/HW-10949 27-Sep-23 37
crack create

4 Laying of BC Layer 321+930 322+500 LHS Top 570 VRC-SP/NH-71/HW-10914 13-Sep-23 37


5 Laying of BC Layer 322+500 322+990 LHS Top 490 VRC-SP/NH-71/HW-10911 12-Sep-23 37
Total Qty LHS 7870 m 37 A
1 Laying of BC Layer 308+350 309+400 RHS Top 1050 VRC-SP/NH-71/HW-10924 19-Sep-23 37

2 Laying of BC Layer 315+620 316+000 RHS Top 380 VRC-SP/NH-71/HW-10928 20-Sep-23 37

3 Laying of BC Layer 316+000 316+650 RHS Top 650 VRC-SP/NH-71/HW-10929 20-Sep-23 37

4 Laying of BC Layer 321+930 322+700 RHS Top 770 VRC-SP/NH-71/HW-10916 16-Sep-23 37

5 Laying of BC Layer 322+700 323+010 RHS Top 310 VRC-SP/NH-71/HW-10920 17-Sep-23 37

Total Qty RHS 7650 m B


Total Qty (Both Side) 7.760 Km. C=(A + B)/2
Previous Qty. (Both Side) 4.660 Km. D
Net Payable Qty (Both Side) 3.100 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

BOX CULVERT
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
1 308+260 RHS 0.500 VRC-SP/NH71/STR-1620 11-Dec-20 4 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
2 308+260 LHS 0.500 VRC-SP/NH71/STR-7647 05-Aug-21 12 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
3 308+270 RHS 0.500 VRC-SP/NH71/STR-2383 22-Dec-20 4 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
4 308+270 LHS 0.500 VRC-SP/NH71/STR-8668 21-Dec-21 16 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
5 315+547 RHS 0.500 VRC-SP/NH71/STR-2659 28-Dec-20 4 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
6 315547 LHS 0.5 VRC-SP/NH71/STR-10361 19-Jun-22 22 Checked by AE Rep
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
7 315+580 LHS 0.500 VRC-SP/NH71/STR-8100 28-Sep-21 14
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
8 315+580 RHS 0.500 VRC-SP/NH71/STR-2660 28-Dec-20 4
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
9 315+995 RHS 0.500 VRC-SP/NH71/STR-4806 20-Feb-21 7 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
10 315+995 LHS 0.500 VRC-SP/NH71/STR-9031 19-Jan-22 17 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
11 319+395 RHS 0.500 VRC-SP/NH71/STR-3420 14-Jan-21 5 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
12 319+395 LHS 0.500 VRC-SP/NH71/STR-6692 07-Jun-21 10
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
13 320+937 LHS 0.500 VRC-SP/NH71/STR-1649 30-Nov-20 4 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
14 320+937 RHS 0.500 VRC-SP/NH71/STR-1197 28-Oct-20 2 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
15 321+568 LHS 0.500 VRC-SP/NH71/STR-4093 28-Jan-21 5 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
16 321+568 RHS 0.500 VRC-SP/NH71/STR-4025 27-Jan-21 5
Box Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
17 321+594 B/S 1.000 VRC-SP/NH71/STR-1658 30-Nov-20 4 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
18 322+100 RHS 0.500 VRC-SP/NH71/STR-2757 29-Dec-20 4 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
19 322+100 LHS 0.500 VRC-SP/NH71/STR-2929 31-Dec-20 4
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
20 323+081 B/S 1.000 VRC-SP/NH71/STR-52 23-Aug-20 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
21 323+391 B/S 1.000 VRC-SP/NH71/STR-317 16-Sep-20 1 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
22 324+423 B/S 1.000 VRC-SP/NH71/STR-1045 21-Oct-20 2
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
23 328+176 RHS 0.500 VRC-SP/NH71/STR-1256 31-Oct-20 2 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
24 328+176 LHS 0.500 VRC -SP/NH-71/STR-6742 10-Jun-21 10 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
25 329+121 LHS 0.500 VRC-SP/NH71/STR-553 30-Sep-20 1 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
26 329+121 RHS 0.500 VRC-SP/NH71/STR-5239 16-Mar-21 7
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
27 332+030 LHS 0.500 VRC-SP/NH71/STR-542 30-Sep-20 1 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
28 332+030 RHS 0.500 VRC-SP/NH71/STR-4993 04-Mar-21 7
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
29 332+539 LHS 0.500 VRC-SP/NH71/STR-522 29-Sep-20 1 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
30 332+539 RHS 0.500 VRC -SP/NH-71/STR-4899 26-Feb-21 6 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
31 333+471 LHS 0.500 VRC-SP/NH71/STR-23 21-Aug-20 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
32 333+471 RHS 0.500 VRC-SP/NH71/STR-5354 22-Mar-21 7 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
33 333+842 LHS 0.500 VRC-SP/NH71/STR-22 21-Aug-20 1
Box Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
34 333+842 RHS 0.500 VRC-SP/NH71/STR-5352 22-Mar-21 7
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
35 334+045 LHS 0.500 VRC-SP/NH71/STR-1175 27-Oct-20 2 Checked by AE Rep.
Box Culvert
36 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab 334+045 RHS 0.500 VRC -SP/NH-71/STR-5633 10-Apr-21 8 Checked by AE Rep.
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
37 334+454 LHS 0.500 VRC-SP/NH71/STR-1176 27-Oct-20 2 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
38 334+454 RHS 0.500 VRC-SP/NH71/STR-5350 22-Mar-21 7 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
39 334+870 LHS 0.500 VRC-SP/NH71/STR-189 05-Sep-20 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
40 334+870 RHS 0.500 Done by Earlier 17
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
41 335+345 RHS 0.500 VRC-SP/NH71/STR-219 08-Sep-20 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
42 335+345 LHS 0.500 Done by Earlier 17
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
43 335+553 RHS 0.500 VRC-SP/NH71/STR-267 12-Sep-20 1 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
44 335+553 RHS 0.500 Done by Earlier 17
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
45 336+668 BHS 1.000 VRC-SP/NH71/STR-221 08-Sep-20 1 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
46 337+524 BHS 1.000 VRC-SP/NH71/STR-4120 28-Jan-21 5 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
47 338+473 LHS 0.500 VRC-SP-NH-71-Str-2771 29-Dec-20 4
Box Culvert
22-04-2021
48 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab 338+473 RHS 0.500 VRC -SP/NH-71/STR-5851 8 Checked by AE Rep.
06:30:PM
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 28-12-2020
49 338+643 LHS 0.500 VRC-SP-NH-71-Str-2702 4
Box Culvert 2:40PM
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 21-May-21
50 338+643 RHS 0.500 VRC-SP-NH-71-Str-6392 9 Checked by AE Rep.
Box Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 30-Nov-20
51 338+818 LHS 0.500 VRC-SP/NH71/STR-1664 3 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 18-May-21
52 338+818 RHS 0.500 VRC-SP/NH71/STR-6350 9 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 28-Nov-20
53 338+887 LHS 0.500 VRC-SP/NH71/STR-1630 3
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 28-May-21
54 338+887 RHS 0.500 VRC-SP/NH71/STR-6497 9 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 31-Jan-21
55 339+477 LHS 0.500 VRC-SP/NH71/STR-4266 5 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 06-May-21
56 339+477 RHS 0.500 VRC-SP/NH71/STR-6174 9
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 30-Nov-21
57 339+750 RHS 0.500 VRC-SP/NH71/STR-8472 15 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 31-Jan-21
58 339+774 LHS 0.500 VRC -SP/NH-71/STR-4268 6 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 31-Jan-21
59 340+249 LHS 0.500 VRC-SP/NH71/STR-4270 5 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of VRC -SP/NH-71/STR-8610 16-Dec-21
60 340+249 RHS 0.500 16 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 30-Nov-20
61 340+382 LHS 0.500 VRC-SP/NH71/STR-1666 3 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of VRC -SP/NH-71/STR-8611 16-Dec-21
62 340+382 RHS 0.500 16 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 22-Dec-20
63 340+681 LHS 0.500 VRC-SP/NH-71/Str-2429 4
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 16-Dec-21
64 340+681 RHS 0.500 VRC-SP/NH-71/Str-8612 16
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
65 341+007 LHS 0.500 VRC-SP/NH71/STR-1177 27-Oct-20 2
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
66 341+007 RHS 0.500 VRC -SP/NH-71/Str-8948 10-Jan-22 17 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 10-Sep-20
67 342+023 LHS 0.500 VRC-SP/NH71/STR-242 1
Box Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 16-Jan-22
68 342+023 RHS 0.500 VRC-SP/NH-71/STR-9011 17 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 10-Sep-20
69 342+190 LHS 0.500 VRC-SP/NH71/STR-242 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 24-Jan-22
70 342+190 RHS 0.500 VRC-SP/NH-71/STR-9082 17 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 10-Sep-20
71 342+683 LHS 0.500 VRC-SP/NH71/STR-242 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 28-Jan-22
72 342+683 RHS 0.500 VRC-SP/NH-71/STR-9123 17 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 10-Sep-20
73 343+150 LHS 0.500 VRC-SP/NH71/STR-242 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 12-Jan-22
74 343+150 RHS 0.500 VRC-SP/NH-71/STR-8972 17 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 14-Sep-20
75 343+425 LHS 0.500 VRC-SP/NH71/STR-280 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 11-Jun-22
76 343425 RHS 0.500 VRC-SP/NH-71/STR-10317 25 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 14-Sep-20
77 343+727 LHS 0.500 VRC-SP/NH71/STR-280 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 25-May-22
78 343+727 RHS 0.500 VRC-SP/NH71/STR-10134 24 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 14-Sep-20
79 344+216 LHS 0.500 VRC-SP/NH71/STR-280 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 26-May-22
80 344216 RHS 0.500 VRC-SP/NH-71/STR-10148 23
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 14-Sep-20
81 344+387 LHS 0.500 VRC-SP/NH71/STR-280 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 24-May-22
82 344+387 RHS 0.500 VRC-SP/NH71/STR-10119 24 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Sep-20
83 344+789 LHS 0.500 VRC-SP/NH71/STR-331 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
84 344+789 RHS 0.500 VRC-SP/NH-71/STR-8817 31-Dec-21 16 Checked by AE Rep.
Box Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Sep-20
85 345+252 LHS 0.500 VRC-SP/NH71/STR-331 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
86 345+252 RHS 0.500 VRC-SP/NH-71/STR-8752 27-Dec-21 16
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Sep-20
87 345+933 LHS 0.500 VRC-SP/NH71/STR-331 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 23-Jul-21
88 345+933 RHS 0.500 VRC-SP/NH-71/STR-7481 11 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Sep-20
89 346+110 LHS 0.500 VRC-SP/NH71/STR-331 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 22-Apr-22
90 346110 RHS 0.5 VRC-SP/NH-71/STR-9749 21 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Sep-20
91 346+421 LHS 0.500 VRC-SP/NH71/STR-332 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 31-Mar-22
92 346421 RHS 0.5 VRC-SP/NH-71/STR-9595 19 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Sep-20
93 347+005 LHS 0.500 VRC-SP/NH71/STR-332 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 30-Apr-22
94 347005 RHS 0.5 VRC-SP/NH-71/STR-9875 20 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Sep-20
95 347+300 LHS 0.500 VRC-SP/NH71/STR-332 1
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 22-Apr-21
96 347+300 RHS 0.500 VRC-SP/NH71/STR-5860 8
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 17-Oct-20
97 347+467 LHS 0.500 VRC-SP/NH71/STR-970 2 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 30-Apr-21
98 347+467 RHS 0.500 VRC-SP/NH71/STR-6010 8
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 22-Oct-20
99 348+405 LHS 0.500 VRC-SP/NH71/STR-1085 2 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 08-Apr-21
100 348+405 RHS 0.500 VRC-SP/NH71/STR-5604 9
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 30-Jun-21
101 349+680 BHS 1.000 VRC-SP/NH-71/STR-7160 10
Box Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 12-Apr-21
102 352+230 BHS 1.000 VRC-SP/NH71/STR-5678 8
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 21-Jun-21
103 352+687 BHS 1.000 VRC-SP/NH-71/STR-6944 10 Checked by AE Rep.
Box Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of 12-Apr-21
104 354+081 BHS 1.000 VRC-SP/NH71/STR-5678 9 Checked by AE Rep.
Box Culvert
Total Qty 57.000 Nos. A

HUME PIPE CULVERT


Checking of Reinforcement, Shuttering and Pouring of RCC in Head
1 309+269 RHS 0.500 VRC-SP/NH71/STR-2748 29-Dec-20 4 Checked by AE Rep.
Wall Final Lift
2 Checking R/F,Shuttering & Concrete Pouring of Encasing for HPC 309+269 LHS 0.5 VRC-SP/NH71/STR-10009 18-May-22 21 Checked by AE Rep.
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
3 309+555 LHS 0.500 VRC-SP/NH71/STR-8316 25-Oct-21 14
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
4 309+555 RHS 0.500 VRC-SP/NH71/STR-2321 21-Dec-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
5 309+846 LHS 0.500 VRC-SP/NH71/STR-8241 17-Oct-21 14
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
6 309+846 RHS 0.500 VRC-SP/NH71/STR-2087 15-Dec-20 4
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
7 310+109 LHS 0.500 VRC-SP/NH71/STR-5182 13-Mar-21 7 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
8 310+109 RHS 0.500 VRC-SP/NH71/STR-1643 30-Nov-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
9 311+237 LHS 0.500 VRC-SP/NH71/STR-5183 13-Mar-21 7 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
10 311+237 RHS 0.500 VRC-SP/NH71/STR-2130 16-Dec-20 4
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
11 312+333 LHS 0.500 VRC-SP/NH71/STR-5397 26-Mar-21 7 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
12 312+333 RHS 0.500 VRC-SP/NH71/STR-1735 03-Dec-20 4 Checked by AE Rep.
Wall Final Lift
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Head
13 312+935 LHS 0.500 VRC-SP/NH71/STR-5328 21-Mar-21 7 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
14 312+935 RHS 0.500 VRC-SP/NH71/STR-1431 12-Nov-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
15 313+024 RHS 0.500 VRC-SP/NH71/STR-752 09-Oct-20 2
Wall Final Lift
16 Checking Concrete Pouring of Encasing for HPC 313+024 LHS 0.5 VRC-SP/NH71/STR-10087 22-May-22 21
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
17 313+479 RHS 0.500 VRC-SP/NH71/STR-785 10-Oct-20 2
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
18 313+479 RHS 0.5 VRC-SP/NH71/STR-10685 29-Jul-22 23
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
19 313+677 RHS 0.500 VRC-SP/NH71/STR-992 19-Oct-20 2
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
20 313+677 LHS 0.5 VRC-SP/NH71/STR-10073 21-May-22 21
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
21 313+856 LHS 0.500 VRC-SP/NH71/STR-8315 25-Oct-21 14
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
22 313+856 RHS 0.500 VRC-SP/NH71/STR-1736 03-Dec-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
23 314+267 LHS 0.500 VRC-SP/NH71/STR-5307 20-Mar-21 7 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
24 314+267 RHS 0.500 VRC-SP/NH71/STR-1432 12-Nov-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
25 316+845 RHS 0.500 VRC-SP/NH71/STR-2384 22-Dec-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
26 316+845 LHS 0.5 VRC-SP/NH71/STR-9442 14-Feb-22 21
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
27 317+066 RHS 0.500 VRC-SP/NH71/STR-884 14-Oct-20 2
Wall Final Lift
28 Checking Pipe Laying & Jointing 317+066 LHS 0.5 VRC-SP/NH71/STR-10035 19-May-22 21 Checked by AE Rep.
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
29 317+907 RHS 0.500 VRC-SP/NH71/STR-2083 15-Dec-20 4
Wall Final Lift
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
30 319+456 LHS 0.500 VRC-SP/NH71/STR-6933 21-Jun-21 11
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
31 319+456 RHS 0.500 VRC-SP/NH71/STR-1423 11-Nov-20 4
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
32 319+848 LHS 0.500 VRC-SP/NH71/STR-6912 20-Jun-21 11
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
33 319+848 RHS 0.500 VRC-SP/NH71/STR-1433 12-Nov-20 4
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
34 320+395 LHS 0.500 VRC-SP/NH71/STR-7369 16-Jul-21 11
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
35 320+395 RHS 0.500 VRC-SP/NH71/STR-1372 07-Nov-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
36 321+329 B/S 1.000 VRC-SP/NH71/STR-1256 02-Nov-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
37 321+927 B/S 1.000 VRC-SP/NH71/STR-102 31-Aug-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
38 323+612 B/S 1.000 VRC-SP/NH71/STR-54 23-Aug-20 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
39 325+064 B/S 1.000 VRC-SP/NH71/STR-1257 31-Oct-20 2 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
40 325+914 B/S 1.000 VRC-SP/NH71/STR-53 23-Aug-20 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
41 326+695 LHS 0.500 VRC-SP/NH71/STR-344 19-Sep-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
42 326+695 RHS 0.500 VRC-SP/NH71/STR-5130 10-Mar-21 7 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
43 327+100 LHS 0.500 VRC-SP/NH71/STR-297 15-Sep-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
44 327+100 RHS 0.500 VRC-SP/NH71/STR-5301 19-Mar-21 7 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
45 327+638 LHS 0.500 VRC-SP/NH71/STR-559 30-Sep-20 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
46 327+638 RHS 0.500 VRC-SP/NH71/STR-6420 23-May-21 9
Pipe Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Head
47 327+871 RHS 0.500 VRC-SP/NH71/STR-519 29-Sep-20 1 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
48 327+871 LHS 0.500 VRC -SP/NH-71/STR-6667 06-Jun-21 10
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
49 328+211 LHS 0.500 VRC -SP/NH-71/STR-6725 09-Jun-21 10 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
50 328+211 RHS 0.500 VRC-SP/NH71/STR-5254 17-Mar-21 7
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
51 328+843 LHS 0.500 VRC-SP/NH71/STR-5304 19-Mar-21 7 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
52 328+843 RHS 0.500 VRC-SP/NH71/STR-1072 22-Oct-20 2 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
53 329+228 LHS 0.500 VRC-SP/NH71/STR-56 23-Aug-20 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
54 329+228 RHS 0.500 VRC-SP/NH71/STR-5258 17-Mar-21 7 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
55 329+577 LHS 0.500 VRC-SP/NH71/STR-57 23-Aug-20 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
56 329+577 RHS 0.500 VRC -SP/NH-71/STR-4746 17-Feb-21 6 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
57 330+251 LHS 0.500 VRC-SP/NH71/STR-3334 11-Jan-21 5 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
58 330+251 RHS 0.500 VRC-SP/NH71/STR-4258 31-Jan-21 5
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
59 330+618 LHS 0.500 VRC-SP/NH71/STR-867 13-Oct-20 2
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
60 330+618 RHS 0.500 VRC-SP/NH71/STR-5381 24-Mar-21 7
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
61 330+904 LHS 0.500 VRC-SP/NH71/STR-1258 31-Oct-20 2 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
62 330+904 RHS 0.500 VRC-SP/NH71/STR-5428 28-Mar-21 7 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
63 331+288 LHS 0.500 VRC-SP/NH71/STR-4114 28-Jan-21 5 Checked by AE Rep.
Wall Final Lift
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Head
64 331+288 RHS 0.500 VRC-SP/NH71/STR-8408 18-Nov-21 15
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
65 331+625 LHS 0.500 VRC-SP/NH71/STR-19 23-Aug-20 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
66 331+625 RHS 0.500 VRC -SP/NH-71/STR-4214 30-Jan-21 6 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
67 331+871 LHS 0.500 VRC-SP/NH71/STR-1146 26-Oct-20 2
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
68 331+871 RHS 0.500 VRC -SP/NH-71/STR-4262 31-Jan-21 5 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
69 332+258 LHS 0.500 VRC-SP/NH71/STR-1075 22-Oct-20 2
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
70 332+258 RHS 0.500 VRC -SP/NH-71/STR-4927 28-Feb-21 6 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
71 332+724 LHS 0.500 VRC-SP/NH71/STR-506 28-Sep-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
72 332+724 RHS 0.500 VRC-SP/NH71/STR-4218 30-Jan-21 5 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
73 332+852 RHS 0.500 VRC-SP/NH71/STR-560 30-Sep-20 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
74 332+852 LHS 0.500 VRC -SP/NH-71/STR-7003 24-Jun-21 10
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
75 332+977 LHS 0.500 VRC -SP/NH-71/STR-7004 24-Jun-21 10 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
76 332+977 RHS 0.500 VRC-SP/NH71/STR-520 29-Sep-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
77 333+250 LHS 0.500 VRC-SP/NH71/STR-5134 10-Mar-21 7 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
78 333+250 RHS 0.500 VRC-SP/NH71/STR-134 02-Sep-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
79 335+675 RHS 0.500 Done by earlier company 17
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
80 335+675 LHS 0.500 Done by earlier company 1
Pipe Culvert
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
81 337+200 LHS 0.500 VRC-SP/NH71/STR-68 26-Aug-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
82 337+200 RHS 0.500 Done by earlier company 17
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
83 338+299 LHS 0.500 VRC-SP/NH71/STR-1259 31-Oct-20 2 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
84 338+299 RHS 0.500 VRC -SP/NH-71/STR-5688 13-Apr-21 8 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
85 338+399 LHS 0.500 VRC -SP/NH-71/STR-1260 31-Oct-20 2 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
86 338+399 RHS 0.500 VRC -SP/NH-71/STR-5954 26-Apr-21 8 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
87 342+822 LHS 0.500 VRC-SP/NH71/STR-86 29-Aug-20 1 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
88 342+822 RHS 0.500 VRC-SP/NH-71/STR-8693 23-Dec-21 16
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
89 343+995 LHS 0.500 Done by earlier company 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
90 343+995 RHS 0.500 VRC-SP/NH-71/STR-10869 24-Aug-22 24 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
91 345+413 LHS 0.500 Done by earlier company 1
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
92 345+413 RHS 0.500 VRC-SP/NH-71/STR-8709 24-Dec-21 16 Checked by AE Rep.
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of
93 348+545 LHS 0.500 Done by earlier company 17
Pipe Culvert
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
94 348+545 RHS 0.500 VRC-SP/NH71/STR-5655 11-Apr-21 8 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
95 349+180 BHS 1.000 VRC-SP/NH-71/STR-9157 31-Jan-22 17 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
96 349+450 BHS 1.000 VRC-SP/NH-71/STR-6547 30-May-21 9
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
97 351+129 BHS 1.000 VRC-SP/NH71/STR-2819 29-Dec-20 4
Wall Final Lift
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Road works including culverts, widening and repair of culverts
D- Reconstruction and New Culverts on existing road, realignments, bypasses :

S No Description CHAINAGE Side Quantity RFI NO Date SPS No. Remarks


Checking of Reinforcement, Shuttering and Pouring of RCC in Head
98 351+930 BHS 1.000 VRC-SP/NH71/STR-2725 28-Dec-20 4 Checked by AE Rep.
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
99 352+379 BHS 1.000 VRC-SP/NH71/STR-2820 28-Dec-20 4
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head Checked by AE Rep.
100 352945 BHS 1.000 VRC-SP/NH71/STR-2728 28-Dec-20 4
Wall Final Lift
Checking of Reinforcement, Shuttering and Pouring of RCC in Head
101 353+580 BHS 1.000 VRC-SP/NH71/STR-2818 29-Dec-20 4 Checked by AE Rep.
Wall Final Lift

Total Qty 56.500 Nos. B


Total Qty (Both Side) 113.500 Nos. C=(A + B)
Previous Qty. (Both Side) 113.500 Nos. D
Net Payable Qty (Both Side) 0.000 Nos. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 27
Weightage bifrication for Minor Bridge
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
Stage for Payment Percentage Unit Unit Rate Total Qty. Amount Upto Date Previous Bill This Bill Remarks
Weightage (in Rs.) Qty. Amount Qty. Amount Qty. Amount
(in Rs.) (in Rs.) (in Rs.)
A2- New Minor bridges (Length>6m and <60m) 0.34782608696

(1) Foundation + Substructure 9.05% Km 676887143 0.1725 116763032

(1) Foundation + Substructure ( Without Pile-34.78%) 34.78% Km 676887143 0.06 40613229 0.060 40613229 0 40613229

(1) Foundation + Substructure ( With Pile-65.22%) 65.22% 676887143 0.1125 76149804

(a) Pile { 49% of (1)} 49.00% No. 176007 212 37313404 200 35201324 157 27633040 43 7568285
(b) Pile Cap { 25% of (1)} 25.00% No. 732210 26 19037451 24.000 17573032 14.000 10250935 10 7322096
(c) Abutment / Pier { 15% of (1)} 15.00% No. 439326 26 11422471 21.0000 9225842 10.0000 4393258 11 4832584
(d) Abutment / Pier Cap { 9% of (1)} 9.00% No. 263595 26 6853482 18 4744719 10 2635955 8 2108764
(e) Pedestal & Bearing { 2% of (1)} 2.00% No. 10020 152 1522996 60 601183 40 400788 20 200394
TOTAL 107959327 85927204 22032123

(1) Foundation + Substructure 9.05% Km 676887143 0.173 116,763,032 0.159 107959327 0.127 85927204 0.03255 22032123

A2- New Minor bridges (Length>6m and <60m)

(2) Super-Structure 11.97% Km 895286088 0.1725 154436850

(A) Deck Slab Without Girder 34.78% 895286088 0.060 53717165 0.060 53717165 0 53717165

(B) Super-Structure With Girder 65.22% 895286088 0.1125 100719685

(a) Girder 47.00% No. 622872 76 47338252 64.000 39863791 30 18686152 34.000 21177639

(b) Deck Slab With Girder 53.00% Km 474501627 0.1125 53381433 0.060 28232847 0.030 14116423 0.030 14116423
TOTAL 121813803 86519741 35294062

(2) Super-Structure 11.97% Km 895286088 0.1725 154,436,850 0.1361 121813803 0.0966 86519741 0.0394 35294062
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Weightage bifrication for Minor Bridge
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)

Stage for Payment Percentage Unit Unit Rate Total Qty. Amount Upto Date Previous Bill This Bill Remarks
Weightage (in Rs.) Qty. Amount Qty. Amount Qty. Amount
(in Rs.) (in Rs.) (in Rs.)
A2- New Minor bridges (Length>6m and <60m) 0.31007751938

(1) Foundation + Substructure 9.05% Km 603426523 0.1935 116763032


(1) Foundation + Substructure ( Without Pile-
34.78%)
31.01% Km 603426523 0.06 36205591 0.060 36205591 0.060 36205591 - -

(1) Foundation + Substructure ( With Pile-65.22%) 68.99% 603426523 0.1335 80557441

(a) Pile { 49% of (1)} 49.00% No. 197366 200 39473146 200 39473146 200 39473146 - -
(b) Pile Cap { 25% of (1)} 25.00% No. 839140 24 20139360 24.0 20139360 24.0 20139360 - -
(c) Abutment / Pier { 15% of (1)} 15.00% No. 503484 24 12083616 21.0 10573164 21.0 10573164 - -
(d) Abutment / Pier Cap { 9% of (1)} 9.00% No. 302090 24 7250170 18 5437627 18 5437627 - -
(e) Pedestal & Bearing { 2% of (1)} 2.00% No. 12206 132 1611149 60 732340 60 732340 - -
TOTAL 112,561,229 112,561,229 -

(1) Foundation + Substructure 9.05% Km 603426523 0.1935 116,763,032 0.187 112,561,229 0.187 112,561,229 - -

A2- New Minor bridges (Length>6m and <60m)

(2) Super-Structure 11.97% Km 798123257 0.1935 154436850

(A) Deck Slab Without Girder 31.01% 798123257 0.060 47887395 0.060 47887395 0.060 47887395 - -

(B) Super-Structure With Girder 68.99% 798123257 0.134 106549455

(a) Girder 47.00% No. 758761 66 50078244 64.000 48560721 64 48560721 - -

(b) Deck Slab With Girder 53.00% Km 423005326 0.1335 56471211 0.060 25168817 0.060 25168817 - -
TOTAL 121616934 121616934 -

(2) Super-Structure 11.97% Km 798123257 0.1935 154,436,850 0.1524 121616934 0.1524 121616934 - -
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
CHAINAGE
S No Description Side Quantity RFI NO Date SPS No. Remarks
MNPR Design
FOUNDATION
1 Checking of Reinforcement, Shuttering and Pouring of RCC in Raft of MNBR MNB 309+955 RHS 3.75 VRC-SP/NH-71/STR-2451 23-Dec-20 4
2 Checking of Reinforcement, Shuttering and Pouring of RCC in raft of MNB MNB 355+028 LHS 7.00 VRC-SP/NH-71/STR-9150 30-Jan-22 17
3 Checking of Reinforcement, Shuttering and Pouring of RCC in raft of MNB MNB 355+028 RHS 7.00 0.01775
Total Qty 0.018 Km.
Previous Qty. 0.018 Km.
Net Payable Qty 0.0000 Km.
SUBSTRUCTURE
1 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of MNB MNB 309+955 RHS 3.750 VRC-SP/NH-71/STR-2658 28-Dec-20 4
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of MNB MNB 309+955 LHS 3.750 VRC-SP/NH-71/STR-5213 15-Mar-21 8
3 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of MNB MNB 313+698 RHS 5.000 VRC-SP/NH-71/STR-5330 21-Mar-21 7
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall final lift of MNB MNB 313+698 LHS 5.0 VRC-SP/NH-71/STR-10632 22-Jul-22 23 Checked by AE Rep.
5 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall final lift of MNB MNB 355+028 RHS 7.000 VRC-SP/NH-71/STR-9119 28-Jan-22 17 Checked by AE Rep.
Checking Concrete Pouring for Wall Final lift With Bracket Wall Abutment A1&A2 MNB 313+766 RHS VRC-SP/NH-71/STR-9215 12-Feb-22 18 Checked by AE Rep.
6 14.250
Checking Concrete Pouring for Wall Final lift Wall Inner A1&A2 MNB 313+766 RHS VRC-SP/NH-71/STR-9213 12-Feb-22 18
Checking Concrete Pouring for Wall Final lift With Bracket Wall Abutment A1&A2 313+766 LHS VRC-SP/NH-71/STR-10103 23-May-22 21 Checked by AE Rep.
7 14.250
Checking Concrete Pouring for Wall Final lift Wall Inner A1&A2 313+766 LHS VRC-SP/NH-71/STR-9965 12-May-22 21
8 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall final lift of MNB MNB 355+028 LHS 3.5 VRC-SP/NH-71/STR-9876 30-Apr-22 20
9 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall final lift of MNB MNB 355+028 LHS 3.5 VRC-SP/NH-71/STR-10190 29-May-22 21 Checked by AE Rep.

Total Qty 0.0600 Km.


Previous Qty. 0.060 Km.
Net Payable Qty 0.0000 Km.
SUPERSTRUCTURE
1 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNBR MNB 309+955 RHS 3.750 VRC-SP/NH-71/STR-2930 31-Dec-20 4 Checked by AE Rep.
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 309+955 LHS 3.750 VRC-SP/NH-71/STR-5410 27-Mar-21 8 Checked by AE Rep.
3 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 313+698 RHS 5.000 VRC-SP/NH-71/STR-5434 31-Mar-21 7 Checked by AE Rep.
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 313+698 LHS 5.0 VRC-SP/NH-71/STR-10632 22-Jul-22 23 Checked by AE Rep
5 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 355028 RHS 7.000 VRC-SP/NH-71/STR-9144 29-Jan-22 17 Checked by AE Rep.
6 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 355028 LHS 7 VRC-SP/NH-71/STR-10545 30-Jun-22 22 Checked by AE Rep
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB A1 MNB 313+766 RHS VRC-SP/NH-71/STR-9454 15-Mar-22 19 Checked by AE Rep.
7 14.25
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
CHAINAGE
S No Description Side Quantity RFI NO Date SPS No. Remarks
MNPR Design
7 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB A2 MNB 313+766 RHS 14.25 VRC-SP/NH-71/STR-9462 16-Mar-22 19 Checked by AE Rep.
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB A3 MNB 313+766 RHS VRC-SP/NH-71/STR-9467 17-Mar-22 19 Checked by AE Rep.
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB A1 MNB 313+766 LHS VRC-SP/NH-71/STR-10305 11-Jun-22 22 Checked by AE Rep.
8 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB A2 MNB 313+766 LHS 14.25 VRC-SP/NH-71/STR-10289 10-Jun-22 22 Checked by AE Rep.
Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB A3 MNB 313+766 LHS VRC-SP/NH-71/STR-10272 08-Jun-22 22
Total Qty (Both Side) 0.060 Km.
Previous Qty. (Both Side) 0.060 Km.
Net Payable Qty (Both Side) 0.000 Km.
Approaches
1 Checking of Protection Work, Retaining Wall & Approach Slab in all manners of MNB MNB 309+955 RHS 0.500 VRC-SP/NH-71/STR-3834 22-Jan-21 5
2 Checking of Protection Work, Retaining Wall & Approach Slab in all manners of MNB MNB 309+955 LHS 0.500 VRC-SP/NH-71/STR-5865 23-Apr-21 8 Checked by AE Rep.
Apron balance/ Misc.
2 Checking of Protection Work, Retaining Wall & Approach Slab in all manners of MNB A3+A4 MNB 313698 LHS 0.300 VRC-SP/NH-71/STR-10971 30-Aug-22 25
Work
3 Checking Concrete Pouring for Approach Slab A3& A4 MNB 313+766 LHS 0.300 VRC-SP/NH-71/STR-11228 04-Oct-22 26

3 Checking Concrete Pouring for Approach Slab A1 MNB 313698 RHS VRC-SP/NH-71/STR-11448 09-Nov-22 27 Checked by AE Rep.
0.300
4 Checking Concrete Pouring for Approach Slab A2 MNB 313698 RHS VRC-SP/NH-71/STR-11441 08-Nov-22 27 Checked by AE Rep.
4 Checking Concrete Pouring for Approach Slab A1 MNB 313+766 RHS VRC-SP/NH-71/STR-11442 08-Nov-22 27 Checked by AE Rep.
0.300
5 Checking Concrete Pouring for Approach Slab A2 MNB 313+766 RHS VRC-SP/NH-71/STR-11449 09-Nov-22 27 Checked by AE Rep.
5 Checking of Protection Work, Retaining Wall & Approach Slab in all manners of MNB MNB 333137 RHS 0.500 VRC-SP/NH-71/STR-10571 06-Jul-22 23 Checked by AE Rep.
6 Checking of Protection Work, Retaining Wall & Approach Slab in all manners of MNB MNB 340867 LHS 0.500 VRC-SP/NH-71/STR-10630 21-Jul-22 23 Checked by AE Rep.

6 Checking of Approach Slab A-01 & A-02 side in all manners of MNB MNB 340867 RHS 0.300 VRC-SP/NH-71/STR-12576 25-Aug-23 36

7 Checking of Approach Slab A-01 & A-02 side in all manners of MNB MNB 331476 RHS 0.400 VRC-SP/NH-71/STR-12165 23-Mar-23 31 Checked by AE Rep.

7 Checking of Approach Slab A-01 & A-02 side in all manners of MNB MNB 333137 LHS 0.500 VRC-SP/NH-71/STR-12222 03-Apr-23 32 Checked by AE Rep.

8 Checking of Approach Slab A-01 & A-02 side in all manners of MNB MNB 331476 LHS 0.400 VRC-SP/NH-71/STR-12276 12-Apr-23 33 Checked by AE Rep.

Total Qty (Both Side) 4.800 No.


Previous Qty. (Both Side) 4.800 No.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
CHAINAGE
S No Description Side Quantity RFI NO Date SPS No. Remarks
MNPR Design
Net Payable Qty (Both Side) 0.000 No.
Deck slab
1 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 333+137 RHS 0.013 VRC -SP/NH-71/Str-9520 25-Mar-22 19 Checked by AE Rep.
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 340+867 RHS 0.008 VRC -SP/NH-71/Str-9559 28-Mar-22 19 Checked by AE Rep.
3 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 331+476 LHS 0.009 VRC -SP/NH-71/Str-10252 04-Jun-22 22 Checked by AE Rep
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 331+476 RHS 0.0088 VRC -SP/NH-71/Str-11500 21-Nov-22 27 Checked by AE Rep.
5 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 333+137 LHS 0.013 VRC -SP/NH-71/Str-11884 28-Jan-23 29 Checked by AE Rep.
6 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of MNB MNB 340+867 RHS 0.008 VRC -SP/NH-71/Str-12176 25-Mar-23 31 Checked by AE Rep.

Total Qty (Both Side) 0.060 No.


Previous Qty. (Both Side) 0.060 No.
Net Payable Qty (Both Side) 0.000 No.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Pile
Checking borrow depth & reinforcement for Pile Pouring of concrete
1 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6347 5/18/2021 12 Checked by AE Rep.
in A1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
2 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6405 5/22/2021 12 Checked by AE Rep.
in A1-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
3 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6244 5/11/2021 12 Checked by AE Rep.
in A1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
4 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6329 5/17/2021 12 Checked by AE Rep.
in A1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
5 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6228 5/10/2021 12
in A1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
6 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6436 5/24/2021 12
in A1-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
7 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6318 5/16/2021 12 Checked by AE Rep.
in A1-07
Checking borrow depth & reinforcement for Pile Pouring of concrete
8 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6389 5/21/2021 12 Checked by AE Rep.
in A1-08
Checking borrow depth & reinforcement for Pile Pouring of concrete
9 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6365 5/19/2021 12 Checked by AE Rep.
in A1-09
Checking borrow depth & reinforcement for Pile Pouring of concrete
10 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6207 5/9/2021 12 Checked by AE Rep.
in A1-10
Checking borrow depth & reinforcement for Pile Pouring of concrete
11 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6455 5/25/2021 12
in A2-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
12 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6303 5/15/2021 12 Checked by AE Rep.
in A2-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
13 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6258 5/12/2021 12 Checked by AE Rep.
in A2-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
14 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6304 5/15/2021 12
in A2-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
15 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6276 5/13/2021 12 Checked by AE Rep.
in A2-05
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


16 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6377 5/20/2021 12 Checked by AE Rep.
in A2-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
17 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6290 5/14/2021 12 Checked by AE Rep.
in A2-07
Checking borrow depth & reinforcement for Pile Pouring of concrete
18 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6330 5/17/2021 12
in A2-08
Checking borrow depth & reinforcement for Pile Pouring of concrete
19 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6319 5/16/2021 12 Checked by AE Rep.
in A2-09
Checking borrow depth & reinforcement for Pile Pouring of concrete
20 Pile 331+476 LHS 1 VRC-SP/NH-71/STR-6291 5/14/2021 12 Checked by AE Rep.
in A2-10

21 MNB A-2 side 1st pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10284 09-06-2022 5:30:PM 22

22 MNB A-2 side 2nd pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10294 10-06-2022 5:30:PM 22 Checked by AE Rep

23 MNB A-2 side 3rd pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10308 11-06-2022 5:30:PM 22

24 MNB A-2 side 4th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10321 12-06-2022 5:30:PM 22 Checked by AE Re

25 MNB A-2 side 5th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10326 13-06-2022 5:30:PM 22

26 MNB A-2 side 6th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10333 14-06-2022 5:30:PM 22 Checked by AE Rep

27 MNB A-2 side 7th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10348 17-06-2022 5:30:PM 22

28 MNB A-2 side 8th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10354 18-06-2022 5:30:PM 22 Checked by AE Rep

29 MNB A-1 side 1st pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10358 18-06-2022 5:30:PM 22

30 MNB A-2 side 9th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10365 19-06-2022 5:30:PM 22 Checked by AE Rep

31 MNB A-1 side 2nd pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10368 19-06-2022 5:30:PM 22
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

32 MNB A-2 side 10th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10379 21-06-2022 5:30:PM 22 Checked by AE Rep

33 MNB A-1 side 4th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10380 21-06-2022 5:30:PM 22

34 MNB A-1 side 3rd pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10382 21-06-2022 5:30:PM 22 Checked by AE Rep

35 MNB A-1 side 5th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10392 22-06-2022 5:30:PM 22

36 MNB A-1 side 6th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10394 22-06-2022 5:30:PM 22 Checked by AE Rep

37 MNB A-1 side 7th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10405 23-06-2022 5:30:PM 22

38 MNB A-1 side 8th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10407 23-06-2022 5:30:PM 22 Checked by AE Rep

39 MNB A-1 side 9th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10418 24-06-2022 5:30:PM 22

40 MNB A-1 side 10th pile boring, R/F & pouring Pile 333+137 LHS 1 VRC -SP/NH-71/Str-10435 25-06-2022 5:30:PM 22 Checked by AE Re

Checking borrow depth & reinforcement for Pile Pouring of concrete


41 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6617 6/3/2021 12 Checked by AE Rep.
in A2-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
42 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6670 6/6/2021 12 Checked by AE Rep.
in A2-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
43 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6684 6/7/2021 12 Checked by AE Rep.
in A2-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
44 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6703 6/8/2021 12 Checked by AE Rep.
in A2-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
45 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6723 6/9/2021 12 Checked by AE Rep.
in A2-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
46 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6741 6/10/2021 12 Checked by AE Rep.
in A2-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
47 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6759 6/11/2021 12 Checked by AE Rep.
in A2-07
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


48 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6783 6/12/2021 12
in A2-08
Checking borrow depth & reinforcement for Pile Pouring of concrete
49 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6799 6/13/2021 12 Checked by AE Rep.
in A2-09
Checking borrow depth & reinforcement for Pile Pouring of concrete
50 Pile 340+876 LHS 1 VRC-SP/NH-71/STR-6822 6/14/2021 12
in A2-10
Checking borrow depth & reinforcement for Pile Pouring of concrete VRC -SP/NH-71/Str-8682
51 Pile 340+876 LHS 1 12/22/2021 16 Checked by AE Rep.
in A1-08
Checking borrow depth & reinforcement for Pile Pouring of concrete VRC -SP/NH-71/STR-8689
52 Pile 340+876 LHS 1 12/23/2021 16 Checked by AE Rep.
in A1-09
Checking borrow depth & reinforcement for Pile Pouring of concrete VRC -SP/NH-71/STR-8698
53 Pile 340+876 LHS 1 12/24/2021 16
in A1-10
Checking borrow depth & reinforcement for Pile Pouring of concrete
54 Pile 340+867 LHS 1 VRC -SP/NH-71/STR-8422 11/24/2021 15 Checked by AE Rep.
in A1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
55 Pile 340+867 LHS 1 VRC -SP/NH-71/STR-8434 11/25/2021 15
in A1-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
56 Pile 340+867 LHS 1 VRC -SP/NH-71/STR-8444 11/26/2021 15 Checked by AE Rep.
in A1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
57 Pile 340+867 LHS 1 VRC -SP/NH-71/STR-8453 11/27/2021 15
in A1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
58 Pile 340+867 LHS 1 VRC -SP/NH-71/STR-8462 11/28/2021 15 Checked by AE Rep.
in A1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
59 Pile 340+867 LHS 1 VRC -SP/NH-71/STR-8463 11/29/2021 15
in A1-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
60 Pile 340+867 LHS 1 VRC -SP/NH-71/STR-8470 11/30/2021 15 Checked by AE Rep.
in A1-07
Checking borrow depth & reinforcement for Pile Pouring of concrete
61 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10454 6/26/2022 23 Checked by AE Rep.
in A1-01(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
62 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10469 6/27/2022 23
in A1-02(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
63 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10470 7/24/2022 23
in A1-03(SR)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


64 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10490 7/26/2022 23 Checked by AE Rep.
in A1-04(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
65 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10491 7/26/2022 23 Checked by AE Rep.
in A1-05(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
66 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10512 7/27/2022 23
in A1-06(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
67 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10513 7/28/2022 23 Checked by AE Rep.
in A1-07(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
68 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10538 7/29/2022 23
in A1-08(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
69 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10285 6/9/2022 23
in P1-01(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
70 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10286 6/9/2022 23 Checked by AE Rep.
in P1-02(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
71 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10296 6/10/2022 23
in P1-03(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
72 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10297 6/10/2022 23 Checked by AE Rep.
in P1-04(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
73 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10311 6/11/2022 23
in P1-05(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
74 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10312 6/11/2022 23 Checked by AE Rep.
in P1-06(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
75 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10387 6/21/2022 23
in A2-01(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
76 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10399 6/22/2022 23 Checked by AE Rep.
in A2-02(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
77 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10423 6/24/2022 23
in A2-03(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
78 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10437 6/25/2022 23 Checked by AE Rep.
in A2-04(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
79 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10452 6/26/2022 23
in A2-05(SR)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


80 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10467 6/27/2022 23 Checked by AE Rep.
in A2-06(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
81 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10488 6/28/2022 23
in A2-07(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
82 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10510 6/29/2022 23 Checked by AE Rep.
in A2-08(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
83 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-7706 8/12/2021 28
in A1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
84 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-8212 10/10/2021 28
in A1-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
85 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-8220 10/11/2021 28
in A1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
86 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-8225 10/12/2021 28
in A1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
87 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-8234 10/15/2021 28
in A1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
88 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-8280 10/20/2021 28
in A1-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
89 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9538 3/26/2022 28
in P1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
90 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9552 3/27/2022 28
in P1-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
91 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9563 3/28/2022 28
in P1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
92 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9576 3/29/2022 28
in P1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
93 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9589 3/30/2022 28
in P1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
94 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9601 3/31/2022 28
in P1-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
95 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9972 5/13/2022 28
in P2-01
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


96 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-9984 5/15/2022 28
in P2-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
97 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10065 5/20/2022 28
in P2-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
98 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10083 5/21/2022 28
in P2-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
99 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10098 5/22/2022 28
in P2-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
100 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-10113 5/23/2022 28
in P2-06

Total Qty LHS 100.000

Checking borrow depth & reinforcement for Pile Pouring of concrete


1 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9733 4/20/2022 20
in A1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
2 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9739 4/21/2022 20
in A1-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
3 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9758 4/23/2022 20
in A1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
4 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9759 4/23/2022 20 Checked by AE Rep.
in A1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
5 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9770 4/24/2022 20
in A1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
6 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9771 4/24/2022 20 Checked by AE Rep.
in A1-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
7 Pile 331+476 RHS 1 VRC -SP/NH-71/Str9785 4/25/2022 20
in A1-07
Checking borrow depth & reinforcement for Pile Pouring of concrete
8 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9786 4/25/2022 20 Checked by AE Rep.
in A1-08
Checking borrow depth & reinforcement for Pile Pouring of concrete
9 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9803 4/26/2022 20
in A1-09
Checking borrow depth & reinforcement for Pile Pouring of concrete
10 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9804 4/26/2022 20 Checked by AE Rep.
in A1-10
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


11 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9816 4/27/2022 20
in A2-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
12 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9817 4/27/2022 20
in A2-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
13 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9833 4/28/2022 20 Checked by AE Rep.
in A2-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
14 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9834 4/28/2022 20 Checked by AE Rep.
in A2-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
15 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9918 5/6/2022 21 Checked by AE Rep.
in A2-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
16 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-9936 5/9/2022 21 Checked by AE Rep.
in A2-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
17 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-10003 5/17/2022 21 Checked by AE Rep.
in A2-07
Checking borrow depth & reinforcement for Pile Pouring of concrete
18 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-10021 5/18/2022 21
in A2-08
Checking borrow depth & reinforcement for Pile Pouring of concrete
19 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-10045 5/19/2022 21
in A2-09
Checking borrow depth & reinforcement for Pile Pouring of concrete
20 Pile 331+476 RHS 1 VRC -SP/NH-71/Str-10058 5/20/2022 21 Checked by AE Rep.
in A2-10
Checking borrow depth & reinforcement for Pile Pouring of concrete
19 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5689 4/13/2021 12 Checked by AE Rep.
in A1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
20 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5747 4/16/2021 12 Checked by AE Rep.
in A1-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
21 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5670 4/12/2021 12 Checked by AE Rep.
in A1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
22 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5849 4/22/2021 12
in A1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
23 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5831 4/21/2021 12 Checked by AE Rep.
in A1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
24 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5709 4/14/2021 12 Checked by AE Rep.
in A1-06
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


25 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5728 4/15/2021 12 Checked by AE Rep.
in A1-07
Checking borrow depth & reinforcement for Pile Pouring of concrete
26 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5793 4/19/2021 12 Checked by AE Rep.
in A1-08
Checking borrow depth & reinforcement for Pile Pouring of concrete
27 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5881 4/23/2021 12 Checked by AE Rep.
in A1-09
Checking borrow depth & reinforcement for Pile Pouring of concrete
28 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5904 4/24/2021 12 Checked by AE Rep.
in A1-10
Checking borrow depth & reinforcement for Pile Pouring of concrete
29 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5906 4/24/2021 12
in A2-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
30 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-6000 4/28/2021 12 Checked by AE Rep.
in A2-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
31 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5981 4/27/2021 12 Checked by AE Rep.
in A2-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
32 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-6066 5/1/2021 12
in A2-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
33 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-6546 5/30/2021 12 Checked by AE Rep.
in A2-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
34 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-5930 4/25/2021 12 Checked by AE Rep.
in A2-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
35 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-6089 5/2/2021 12 Checked by AE Rep.
in A2-07
Checking borrow depth & reinforcement for Pile Pouring of concrete
36 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-6042 4/30/2021 12 Checked by AE Rep.
in A2-08
Checking borrow depth & reinforcement for Pile Pouring of concrete
37 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-6021 4/29/2021 12
in A2-09
Checking borrow depth & reinforcement for Pile Pouring of concrete
38 Pile 333+137 RHS 1 VRC-SP/NH-71/STR-6574 5/31/2021 12 Checked by AE Rep.
in A2-10

39 Checking of boring , reinforcement & pouring of pile no 01 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11238 10/6/2022 26

40 Checking of boring , reinforcement & pouring of pile no 02 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11241 10/8/2022 26
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

41 Checking of boring , reinforcement & pouring of pile no 03 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11248 10/9/2022 26

42 Checking of boring , reinforcement & pouring of pile no 04 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11251 10-10-2022 1:30:PM 26

43 Checking of boring , reinforcement & pouring of pile no 05 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11254 11-10-2022 1:30:PM 26

44 Checking of boring , reinforcement & pouring of pile no 05 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11255 12-10-2022 1:30:PM 26

45 Checking of boring , reinforcement & pouring of pile no 06 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11256 13-10-2022 1:30:PM 26

46 Checking of boring , reinforcement & pouring of pile no 07 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11265 14-10-2022 1:30:PM 26

47 Checking of boring , reinforcement & pouring of pile no 08 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11271 15-10-2022 1:30:PM 26

48 Checking of boring , reinforcement & pouring of pile no 09 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11278 16-10-2022 1:30:PM 26

49 Checking of boring , reinforcement & pouring of pile no 10 A-2 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11293 17-10-2022 5:30:PM 26

50 Checking of boring , reinforcement & pouring of pile no 01 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str- 11296 A 18-10-2022 5:30:PM 26

51 Checking of boring , reinforcement & pouring of pile no 02 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11322 20-10-2022 5:30:PM 26

52 Checking of boring , reinforcement & pouring of pile no 04 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11545 11/29/2022 27 Checked by AE Rep.

53 Checking of boring , reinforcement & pouring of pile no 05 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11530 11/26/2022 27 Checked by AE Rep.

54 Checking of boring , reinforcement & pouring of pile no 06 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11524 11/25/2022 27 Checked by AE Rep.

55 Checking of boring , reinforcement & pouring of pile no 07 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11514 11/24/2022 27 Checked by AE Rep.

56 Checking of boring , reinforcement & pouring of pile no 08 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11507 11/22/2022 27 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

57 Checking of boring , reinforcement & pouring of pile no 09 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11664 12/20/2022 28 Checked by AE Rep.

58 Checking of boring , reinforcement & pouring of pile no 10 A-1 side Pile 340+867 RHS 1 VRC -SP/NH-71/Str-11670 12/21/2022 28 Checked by AE Rep.

Checking borrow depth & reinforcement for Pile Pouring of concrete


59 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-8254 10/18/2021 23
in A1-01(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
60 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-8281 10/20/2021 23
in A1-02(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
61 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-8300 10/23/2021 23
in A1-03(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
62 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10453 6/26/2022 23
in A1-04(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
63 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10468 6/27/2022 23 Checked by AE Rep.
in A1-05(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
64 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10489 6/28/2022 23
in A1-06(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
65 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10511 6/29/2022 23 Checked by AE Rep.
in A1-07(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
66 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10537 6/30/2022 23 Checked by AE Rep.
in A1-08(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
67 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10298 6/10/2022 23 Checked by AE Rep.
in P1-01(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
68 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10313 6/11/2022 23
in P1-02(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
69 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10324 6/12/2022 23 Checked by AE Rep.
in P1-03(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
70 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10329 6/13/2022 23
in P1-04(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
71 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10330 6/13/2022 23 Checked by AE Rep.
in P1-05(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
72 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10337 6/14/2022 23
in P1-06(SR)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


73 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10331 6/13/2022 23 Checked by AE Rep.
in A2-01(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
74 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10338 6/14/2022 23
in A2-02(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
75 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10352 6/17/2022 23 Checked by AE Rep.
in A2-03(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
76 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10371 6/19/2022 23
in A2-04(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
77 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10375 6/20/2022 23 Checked by AE Rep.
in A2-05(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
78 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10398 6/22/2022 23
in A2-06(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
79 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10411 6/23/2022 23 Checked by AE Rep.
in A2-07(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
80 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10422 6/24/2022 23 Checked by AE Rep.
in A2-08(SR)
Checking borrow depth & reinforcement for Pile Pouring of concrete
81 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7641 8/4/2021 28
in A1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
82 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7642 8/4/2021 28
in A1-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
83 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7651 8/5/2021 28
in A1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
84 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7660 8/6/2021 28
in A1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
85 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7700 8/11/2021 28
in A1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
86 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7701 8/11/2021 28
in A1-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
87 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-9539 3/26/2022 28
in P1-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
88 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-9553 3/27/2022 28
in P1-02
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
A2- New Minor bridges (Length>6m and <60m)
0
S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking borrow depth & reinforcement for Pile Pouring of concrete


89 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-9564 3/28/2022 28
in P1-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
90 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-9577 3/29/2022 28
in P1-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
91 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-9589 3/30/2022 28
in P1-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
92 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-9723 4/19/2022 28
in P1-06
Checking borrow depth & reinforcement for Pile Pouring of concrete
93 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-9778 4/24/2022 28
in P2-01
Checking borrow depth & reinforcement for Pile Pouring of concrete
94 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10124 5/24/2022 28
in P2-02
Checking borrow depth & reinforcement for Pile Pouring of concrete
95 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10138 5/25/2022 28
in P2-03
Checking borrow depth & reinforcement for Pile Pouring of concrete
96 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10152 5/26/2022 28
in P2-04
Checking borrow depth & reinforcement for Pile Pouring of concrete
97 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10161 5/27/2022 28
in P2-05
Checking borrow depth & reinforcement for Pile Pouring of concrete
98 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-10175 5/28/2022 28
in P2-06
Total Qty RHS 100.000 Nos.
Total Qty (Both Side) 200.000 Nos.
Previous Qty. (Both Side) 200.000 Nos.
Net Payable Qty (Both Side) 0.000 Nos.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in
NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
A2- New Minor bridges (Length>6m and <60m)

S No Description Item CHAINAGE Side Quantity Nos. RFI NO Date SPS No. Remarks

Pile Cap
1 Checking reinforcement & shuttering for Pile Cap A2, Pouring of Concrete Pile cap 331+476 LHS 0.004 1.00 VRC-SP/NH-71/STR-7231 06-Jul-21 12 Checked by AE Rep.

2 Checking reinforcement & shuttering for Pile Cap A1, Pouring of Concrete Pile cap 331+476 LHS 0.004 1.00 VRC -SP/NH-71/Str-8637 19-Dec-21 16 Checked by AE Rep.

3 Checking reinforcement & shuttering for Pile Cap A1, Pouring of Concrete Pile cap 333+137 LHS 0.006 1.00 VRC -SP/NH-71/Str-11296 17-Oct-22 26

4 Checking reinforcement & shuttering for Pile Cap A2, Pouring of Concrete Pile cap 333+137 LHS 0.006 1.00 VRC -SP/NH-71/Str-11328 21-Oct-22 26

5 Checking reinforcement & shuttering for Pile Cap A2, Pouring of Concrete Pile cap 340+867 LHS 0.004 1.00 VRC -SP/NH-71/STR-8445 25-Nov-21 15

6 Checking reinforcement & shuttering for Pile Cap A1, Pouring of Concrete Pile cap 340+876 LHS 0.004 1.00 VRC -SP/NH-71/STR-8797 30-Dec-21 16 Checked by AE Rep.

7 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A1(SR) MNB+VUP 350+490 LHS 0.0063 1.00 VRC-SP/NH-71/STR-11505 22-Nov-22 27

8 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P1(SR) MNB+VUP 350+490 LHS 0.0063 1.00 VRC-SP/NH-71/STR-10514 29-Jun-22 23 Checked by AE Rep.

9 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A2(SR) MNB+VUP 350+490 LHS 0.0063 1.00 VRC-SP/NH-71/STR-10992 31-Aug-22 24 Checked by AE Rep.

10 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A1 MNB+VUP 350+490 LHS 0.0063 1.00 VRC-SP/NH-71/STR-9847 29-Apr-22 28

11 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P1 MNB+VUP 350+490 LHS 0.0063 1.00 VRC-SP/NH-71/STR-10424 22-Jun-22 28

12 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P2 MNB+VUP 350+490 LHS 0.0063 1.00 VRC-SP/NH-71/STR-10400 24-Jun-22 28

Total Qty LHS 0.0478 12.0000

1 Checking reinforcement & shuttering for Pile Cap A1, Pouring of Concrete Pile cap 333+137 RHS 0.006 1.00 VRC-SP/NH-71/STR-6784 12-Jun-21 12 Checked by AE Rep.

2 Checking reinforcement & shuttering for Pile Cap A2, Pouring of Concrete Pile cap 333+137 RHS 0.006 1.00 VRC -SP/NH-71/STR-7330 12.07.2021 12

3 Checking reinforcement & shuttering for Pile Cap A2, Pouring of Concrete Pile cap 331+476 RHS 0.004 1.00 VRC -SP/NH-71/STR-10160 28.06.2022 21 Checked by AE Rep.

4 Checking reinforcement & shuttering for Pile Cap A1, Pouring of Concrete Pile cap 331+476 RHS 0.004 1.00 VRC -SP/NH-71/STR-10420 24.06.2022 22 Checked by AE Rep.

5 Checking reinforcement & shuttering for Pile Cap A1, Pouring of Concrete Pile cap 340+867 RHS 0.004 1.00 VRC -SP/NH-71/STR-11727 29-Dec-22 28 Checked by AE Rep.

6 Checking reinforcement & shuttering for Pile Cap A2, Pouring of Concrete Pile cap 340+867 RHS 0.004 1.00 VRC -SP/NH-71/STR-11736 30-Dec-22 28 Checked by AE Rep.

7 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A2(SR) MNB+VUP 350+490 RHS 0.0063 1.00 VRC-SP/NH-71/STR-11537 27-Nov-22 27 Checked by AE Rep.

8 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P1(SR) MNB+VUP 350+490 RHS 0.0063 1.00 VRC-SP/NH-71/STR-10539 30-Jun-22 23

9 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A1(SR) MNB+VUP 350+490 RHS 0.0063 1.00 VRC-SP/NH-71/STR-10980 30-Aug-22 25 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in
NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
A2- New Minor bridges (Length>6m and <60m)

S No Description Item CHAINAGE Side Quantity Nos. RFI NO Date SPS No. Remarks

Pile Cap
10 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A1 MNB+VUP 350+490 RHS 0.006 1.00 VRC-SP/NH-71/STR-10492 28-Jun-22 28

11 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P2 MNB+VUP 350+490 RHS 0.006 1.00 VRC-SP/NH-71/STR-10438 25-Jun-22 28

12 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P1 MNB+VUP 350+490 RHS 0.0063 1.00 VRC-SP/NH-71/STR-12200 28-Mar-23 31 Checked by AE Rep.
Total Qty RHS 0.041 12.000
Total Qty (Both Side) 0.089 24.000
Previous Qty. (Both Side) 24.000
Net Payable Qty (Both Side) 0.000
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode
under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
A2- New Minor bridges (Length>6m and <60m)

S No Description Item CHAINAGE Side Quantity Nos. RFI NO Date SPS No. Remarks

Abutment / Pier
Checking of Reinforcement, Shuttering and Pouring of RCC in
1 Shaft 331+476 LHS 0.004 1.000 VRC -SP/NH-71/STR-7395 17-Jul-21 12 Checked by AE Rep.
Wall(Shaft) Final Lift A2 Side of Abutment
Checking reinforcement & shuttering for Abutment shaft final lift Checked by AE Rep.
2 Shaft 331+476 LHS 0.004 1.000 VRC -SP/NH-71/STR-8716 25-Dec-21 16
Pouring of concrete in Abutment shaft final lift A1
Checking of Reinforcement, Shuttering and Pouring of RCC in
3 Shaft 333+137 LHS 0.006 1.000 VRC -SP/NH-71/Str-11380 29-Oct-22 26
Wall(Shaft) Final Lift A1 Side of Abutment
Checking of Reinforcement, Shuttering and Pouring of RCC in
4 Shaft 333+137 LHS 0.006 1.000 VRC -SP/NH-71/Str-11381 29-Oct-22 26
Wall(Shaft) Final Lift A2 Side of Abutment
Checking of Reinforcement, Shuttering and Pouring of RCC in Checked by AE Rep.
5 Shaft 340+867 LHS 0.004 1.000 VRC -SP/NH-71/STR-8471 30-Nov-21 15
Wall(Shaft) Final Lift A2 Side of Abutment
Checking reinforcement & shuttering for Abutment Pouring of
6 Shaft 340+876 LHS 0.004 1.000 VRC -SP/NH-71/Str-9135 29-Jan-22 17 Checked by AE Rep.
concrete in Abutment A1 LHS
Checking of Reinforcement, Shuttering and Pouring of RCC in
7 Shaft 350+490 LHS 0.006 1.000 VRC-SP/NH-71/STR-10189 29-May-22 28
Wall(Shaft) Final Lift A1 Side of Abutment
Checking of Reinforcement, Shuttering and Pouring of RCC in
8 Shaft 350+490 LHS 0.006 1.000 VRC-SP/NH-71/STR-11890 28-Jan-23 29 Checked by AE Rep.
Wall(Shaft) Final Lift P2
Checking of Reinforcement, Shuttering and Pouring of RCC in
9 Shaft 350+490 LHS 0.006 1.000 VRC-SP/NH-71/STR-11564 04-Dec-22 29 Checked by AE Rep.
Wall(Shaft) Final Lift A1 SR
Checking of Reinforcement, Shuttering and Pouring of RCC in
10 Shaft 350+490 LHS 0.006 1.000 VRC-SP/NH-71/STR-11902 30-Jan-23 29 Checked by AE Rep.
Wall(Shaft) Final Lift A2 SR
Checking of Reinforcement, Shuttering and Pouring of RCC in
11 Shaft 350+490 LHS 0.006 1.000 VRC-SP/NH-71/STR-12240 06-Apr-23 32 Checked by AE Rep.
Wall(Shaft) Final Lift P1- SR

Total Qty LHS 0.060 11.000

Checking of Reinforcement, Shuttering and Pouring of RCC in


1 Shaft 333+137 RHS 0.006 1.000 VRC -SP/NH-71/STR-7375 16-Jul-21 12 Checked by AE Rep.
Wall(Shaft) Final Lift A1 Side of Abutment
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode
under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
A2- New Minor bridges (Length>6m and <60m)

S No Description Item CHAINAGE Side Quantity Nos. RFI NO Date SPS No. Remarks

Checking of Reinforcement, Shuttering and Pouring of RCC in


2 Shaft 333+137 RHS 0.006 1.000 VRC -SP/NH-71/STR-7365 15-Jul-21 12 Checked by AE Rep.
Wall(Shaft) Final Lift A2 Side of Abutment
Checking of Reinforcement, Shuttering and Pouring of RCC in
3 Shaft 331+476 RHS 0.004 1.000 VRC -SP/NH-71/Str-10637 22-Jul-22 23 Checked by AE Rep.
Wall(Shaft) Final Lift A2 Side of Abutment
MNB abutment shaft 2nd lift shuttering & steel fixing & casting A-
4 Shaft 331+476 RHS 0.004 1.000 VRC -SP/NH-71/Str-10828 20-Aug-22 24 Checked by AE Rep.
01 side
Checking of Reinforcement, Shuttering and Pouring of RCC in
5 Shaft 340+867 RHS 0.004 1.000 VRC -SP/NH-71/Str-11893 30-Jan-23 29 Checked by AE Rep.
Wall(Shaft) Final Lift A2 Side of Abutment
Checking reinforcement & shuttering for Abutment Pouring of
6 Shaft 340+876 RHS 0.004 1.000 VRC -SP/NH-71/Str-11899 29-Jan-23 29 Checked by AE Rep.
concrete in Abutment A1 LHS
Checking of Reinforcement, Shuttering and Pouring of RCC in
7 Shaft 350+490 RHS 0.006 1 VRC-SP/NH-71/STR-10940 28-Aug-22 28
Wall(Shaft) Final Lift A1 Side of Abutment
Checking of Reinforcement, Shuttering and Pouring of RCC in Checked by AE Rep.
8 Shaft 350+490 RHS 0.0063 1 VRC-SP/NH-71/STR-12205 29-Mar-23 31
Wall(Shaft) Final Lift A1 SR
Checking of Reinforcement, Shuttering and Pouring of RCC in
9 Shaft 350+490 RHS 0.006 1 VRC-SP/NH-71/STR-11616 12-Dec-22 29 Checked by AE Rep.
Wall(Shaft) Final Lift A2 SR
Checking of Reinforcement, Shuttering and Pouring of RCC in Checked by AE Rep.
10 Shaft 350+490 RHS 0.0063 1 VRC-SP/NH-71/STR-12215 31-Mar-23 31
Wall(Shaft) Final Lift P1 SR

Checking of Reinforcement,Shuttering & Pouring of concrete for


11 MNB+VUP 350+490 RHS 0.006 VRC-SP/NH-71/STR-12234 05-Apr-23
Abutment Cap A1 SR

Total Qty RHS 0.0209 10.000

Total Qty (Both Side) 21

Previous Qty. (Both Side) 21

Net Payable Qty (Both Side) 0


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode
under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
A2- New Minor bridges (Length>6m and <60m)

S No Description Item CHAINAGE Side Quantity Nos. RFI NO Date SPS No. Remarks

Pier Cap
Checking reinforcement & shuttering for Abutment cap A2 Pouring
1 Pier Cap 331+476 LHS 0.004 1.000 VRC -SP/NH-71/STR-8814 31-Dec-22 16 Checked by AE Rep.
of concrete in Abutment cap A2
Checking reinforcement & shuttering for Abutment Cap Pouring of
2 Pier Cap 331+476 LHS 0.004 1.000 VRC -SP/NH-71/Str-9023 18-Jan-22 17 Checked by AE Rep.
concrete in Abutment Cap A1 LHS
Checking reinforcement & shuttering for Abutment Cap Pouring of
3 Pier Cap 333+137 LHS 0.006 1.000 VRC -SP/NH-71/Str-11407 31-Oct-22 26
concrete in Abutment Cap A1 LHS
Checking reinforcement & shuttering for Abutment Cap Pouring of
4 Pier Cap 333+137 LHS 0.006 1.000 VRC -SP/NH-71/Str-11408 31-Oct-22 26
concrete in Abutment Cap A2 LHS
Checking reinforcement & shuttering for Abutment Cap Pouring of
5 Pier Cap 340+837 LHS 0.004 1.000 VRC -SP/NH-71/Str-9134 29-Jan-22 17 Checked by AE Rep.
concrete in Abutment Cap A2 LHS
Checking reinforcement & shuttering for Abutment Cap Pouring of
6 Pier Cap 340+837 LHS 0.004 1.000 VRC -SP/NH-71/Str-9183 08-Feb-22 18 Checked by AE Rep.
concrete in Abutment Cap A1 LHS
Checking of Reinforcement,Shuttering & Pouring of concrete for Checked by AE Rep.
7 MNB+VUP 350+490 LHS 0.006 1 VRC-SP/NH-71/STR-12187 27-Mar-23 31
Abutment Cap A1
Checking of Reinforcement,Shuttering & Pouring of concrete for Checked by AE Rep.
8 MNB+VUP 350+490 LHS 0.006 1 VRC-SP/NH-71/STR-12469 28-May-23 33
Abutment Cap A1 SR
Checking of Reinforcement,Shuttering & Pouring of concrete for Checked by AE Rep.
9 MNB+VUP 350+490 LHS 0.006 1 VRC-SP/NH-71/STR-12195 28-Mar-23 31
Abutment Cap A2 SR

Total Qty LHS 0.029 9.000


0
1 Checking reinforcement & shuttering for Abutment cap A1 Pier Cap 333+137 RHS 0.006 1.000 VRC -SP/NH-71/STR-8418 22-Nov-21 15

2 Checking reinforcement & shuttering for Abutment cap A2 Pier Cap 333+137 RHS 0.006 1.000 VRC -SP/NH-71/STR-8423 23-Nov-21 15 Checked by AE Rep.
Checking reinforcement & shuttering for Abutment cap A2 Pouring
3 Pier Cap 331+476 RHS 0.004 1.000 VRC -SP/NH-71/Str-10697 31-Jul-22 23 Checked by AE Rep.
of concrete in Abutment cap A2
MNB abutment shaft Cap shuttering & steel fixing & casting A-01
4 Pier Cap 331+476 RHS 0.004 1.000 VRC -SP/NH-71/Str-10878 25-Aug-22 24
side
Checking reinforcement & shuttering for Abutment Cap Pouring of
5 Pier Cap 340+837 RHS 0.004 1.000 VRC -SP/NH-71/Str-11906 31-Jan-23 29 Checked by AE Rep.
concrete in Abutment Cap A2 RHS
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode
under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
A2- New Minor bridges (Length>6m and <60m)

S No Description Item CHAINAGE Side Quantity Nos. RFI NO Date SPS No. Remarks

Pier Cap
Checking reinforcement & shuttering for Abutment Cap Pouring of
6 Pier Cap 340+837 RHS 0.004 1.000 VRC -SP/NH-71/Str-11968 10-Feb-23 30 Checked by AE Rep.
concrete in Abutment Cap A1 RHS
Checking of Reinforcement,Shuttering & Pouring of concrete for
7 MNB+VUP 350+490 RHS 0.006 1.000 VRC-SP/NH-71/STR-12479 29-May-23 33 Checked by AE Rep.
Abutment Cap A1 SR
Checking of Reinforcement,Shuttering & Pouring of concrete for Checked by AE Rep.
8 MNB+VUP 350+490 RHS 0.006 1 VRC-SP/NH-71/STR-12183 26-Mar-23 31
Abutment Cap A1
Checking of Reinforcement,Shuttering & Pouring of concrete for Checked by AE Rep.
9 MNB+VUP 350+490 RHS 0.006 1 VRC-SP/NH-71/STR-12206 29-Mar-23 31
Abutment Cap A2 SR

Total Qty RHS 0.047 9.000


Total Qty (Both Side) 18.000
Previous Qty. (Both Side) 18.000
Net Payable Qty (Both Side) 0.000
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
A2- New Minor bridges (Length>6m and <60m)

S No Description type of Girder CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

1 Checking reinforcement & shuttering for Girder 01 Nos RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7750 8/19/2021 15
Checking reinforcement & shuttering for Girder 2nd Nos. Pouring
2 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7761 8/23/2021 15
of concrete in same
Checking reinforcement & shuttering for Girder 3rd Nos. Pouring of
3 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7769 8/25/2021 15
concrete in same
Checking reinforcement & shuttering for Girder 04 Pouring of
4 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7785 8/28/2021 15
concrete
Checking reinforcement & shuttering for Girder 05 Pouring of
5 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7846 8/31/2021 15
concrete
Checking reinforcement & shuttering for Girder 06 for MNB Checked by AE Rep.
6 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7877 9/2/2021 15
Pouring of concrete in same
Checking reinforcement & shuttering for Girder 07 for MNB Checked by AE Rep.
7 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7906 9/5/2021 15
Pouring of concrete in same
Checking reinforcement & shuttering for Girder 08 for MNB Checked by AE Rep.
8 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7925 9/7/2021 15
Pouring of concrete in same
Checking reinforcement & shuttering for Girder 09 Pouring of Checked by AE Rep.
9 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7969 9/11/2021 15
concrte in same
Checking reinforcement & shuttering for Girder-10 for MNB Checked by AE Rep.
10 RCC -Girder 331+476 1 VRC -SP/NH-71/STR-7989 9/14/2021 15
Pouring of concrete in same
Checking reinforcement & shuttering for Girder 01 Pouring of
11 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8073 9/26/2021 15
concrete in Girder 01
Chekcing reinforcement & shuttering for Girder 02 Pouring of
12 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8120 9/30/2021 15
concrete in same
Checking reinforcement & shuttering for Girder 03 Pouring of Checked by AE Rep.
13 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8179 10/7/2021 15
concrete in Girder 03
Checking reinforcement & shuttering for Girder 04 Pouring of Checked by AE Rep.
14 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8216 10/11/2021 15
concrete in Girder 04
Checking reinforcement & shuttering for Girder 05 Pouring of
15 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8261 10/18/2021 15
concrete in Girder 05
Checking reinforcement & shuttering for Girder 06 Pouring of Checked by AE Rep.
16 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8357 10/27/2021 15
concrete in Girder 06
S No Description type of Girder CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking reinforcement & shuttering for Girder 07 Pouring of


17 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8389 10/30/2021 15
concrete in Girder 07
Checking reinforcement & shuttering for Girder 08 Pouring of Checked by AE Rep.
18 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8394 11/2/2021 15
concrete in Girder 08
Checking reinforcement & shuttering for Girder 09 Pouring of
19 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8399 11/12/2021 15
concrete in Girder 09
Checking reinforcement & shuttering for Girder 10 Pouring of Checked by AE Rep.
20 Pre-Stressing Girder 333+137 1 VRC -SP/NH-71/STR-8405 11/16/2021 15
concrete in Girder 10
Checking reinforcement & shuttering for Girder 01 for MNB Checked by AE Rep.
21 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-7894 9/4/2021 15
Pouring of concrete in same
Checking reinforcement & shuttering for Girder 02 for MNB
22 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-7918 9/6/2021 15
Pouring of concrete in same
Checking reinforcement & shuttering for Girder 03 Pouring of Checked by AE Rep.
23 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-7946 9/9/2021 15
concrte in same
Checking reinforcement & shuttering for Girder 04 Pouring of
24 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-7968 9/11/2021 15
concrte in same
Checking reinforcement & shuttering for Girder-05 for MNB Checked by AE Rep.
25 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-8000 9/15/2021 15
Pouring of concrete in same
Checking reinforcement & shuttering for Girder-06 for MNB
26 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-8006 9/16/2021 15
Pouring of concrete in same
Chekcing reinforcement & shuttering for Girder 07 Pouring of Checked by AE Rep.
27 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-8098 9/28/2021 15
concrete in same
Chekcing reinforcement & shuttering for Girder 08 Pouring of
28 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-8102 9/29/2021 15
concrete in same
Checking reinforcement & shuttering for Girder 09 Pouring of Checked by AE Rep.
29 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-8139 10/3/2021 15
concrete in Girder 09
Checking reinforcement & shuttering for Girder 10 Pouring of
30 RCC -Girder 340+867 1 VRC -SP/NH-71/STR-8146 10/4/2021 15
concrete in Girder 10
Checking reinforcement,shuttering & Pouring of Concrete for
31 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11148 25-Sep-22 28
Girder 11
Checking reinforcement,shuttering & Pouring of Concrete for
32 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11157 26-Sep-22 28
Girder 12
Checking reinforcement,shuttering & Pouring of Concrete for
33 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11167 27-Sep-22 28
Girder 13
Checking reinforcement,shuttering & Pouring of Concrete for
34 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11168 27-Sep-22 28
Girder 14
Checking reinforcement,shuttering & Pouring of Concrete for
35 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11180 28-Sep-22 28
Girder 15
Checking reinforcement,shuttering & Pouring of Concrete for
36 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11256 12-Oct-22 28
Girder 16 & 17
Checking reinforcement,shuttering & Pouring of Concrete for
37 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11282 16-Oct-22 28
Girder 18 & 19
Checking reinforcement,shuttering & Pouring of Concrete for
38 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11313 19-Oct-22 28
Girder 20
Checking reinforcement,shuttering & Pouring of Concrete for
39 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11323 20-Oct-22 28
Girder 21 & 22
Checking reinforcement,shuttering & Pouring of Concrete for
40 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11330 21-Oct-22 28
Girder 23 & 24
S No Description type of Girder CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Checking reinforcement,shuttering & Pouring of Concrete for


41 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11336 22-Oct-22 28
Girder 25
Checking reinforcement,shuttering & Pouring of Concrete for
42 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11344 23-Oct-22 28
Girder 26 & 27
Checking reinforcement,shuttering & Pouring of Concrete for
43 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11548 29-Nov-22 28
Girder 28
Checking reinforcement,shuttering & Pouring of Concrete for
44 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11700 25-Dec-22 28 Checked by AE Rep.
Girder 29&30
Checking reinforcement,shuttering & Pouring of Concrete for
45 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11706 26-Dec-22 28 Checked by AE Rep.
Girder 31 (SR-1)
Checking reinforcement,shuttering & Pouring of Concrete for
46 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11752 31-Dec-22 29 Checked by AE Rep.
Girder 32
Checking reinforcement,shuttering & Pouring of Concrete for
47 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11877 26-Jan-23 29 Checked by AE Rep.
Girder 33&34
Checking reinforcement,shuttering & Pouring of Concrete for
48 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11896 29-Jan-23 29 Checked by AE Rep.
Girder 35&36
Checking reinforcement,shuttering & Pouring of Concrete for
49 RCC Girder 350+490 2 VRC-SP/NH-71/STR-11903 30-Jan-23 29 Checked by AE Rep.
Girder 37&38
Checking reinforcement,shuttering & Pouring of Concrete for
50 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11912 31-Jan-23 29 Checked by AE Rep.
Girder 39
Checking reinforcement,shuttering & Pouring of Concrete for
51 RCC Girder 350+490 1 VRC-SP/NH-71/STR-12159 22-Mar-23 31 Checked by AE Rep.
Girder 42
Checking reinforcement,shuttering & Pouring of Concrete for
52 RCC Girder 350+490 1 VRC-SP/NH-71/STR-12182 26-Mar-23 31 Checked by AE Rep.
Girder 43
Checking reinforcement,shuttering & Pouring of Concrete for
53 RCC Girder 350+490 1 VRC-SP/NH-71/STR-12186 27-Mar-23 31 Checked by AE Rep.
Girder 44
Checking reinforcement,shuttering & Pouring of Concrete for
54 RCC Girder 350+490 1 VRC-SP/NH-71/STR-12194 28-Mar-23 31 Checked by AE Rep.
Girder 45
Checking reinforcement,shuttering & Pouring of Concrete for
55 RCC Girder 350+490 1 VRC-SP/NH-71/STR-12202 29-Mar-23 31 Checked by AE Rep.
Girder 46

Total Qty (Both Side) 64 Nos.

Previous Qty. (Both Side) 64 Nos.

Net Payable Qty (Both Side) 0 Nos.


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under
Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023

0
A2- New Minor bridges (Length>6m and <60m)

S No Description Item CHAINAGE Side Quantity Nos. RFI NO Date SPS No. Remarks

Pier Cap
1 Fixing of Bearing A-1 side Bearing 331+476 LHS 0.004 5.000 VRC -SP/NH-71/STR-9250 22-Feb-22 18 Checked by AE Rep.
2 Fixing of Bearing A-2 side Bearing 331+476 LHS 0.004 5.000 VRC -SP/NH-71/STR-9250 22-Feb-22 18
3 Fixing of Bearing A-1 side Bearing 333+137 LHS 0.006 5.000 VRC -SP/NH-71/STR-11729 15-Dec-22 28 Checked by AE Rep.
4 Fixing of Bearing A-2 side Bearing 333+137 LHS 0.006 5.000 VRC -SP/NH-71/STR-11729 15-Dec-22 28 Checked by AE Rep.
5 Fixing of Bearing A-1 side Bearing 340+876 LHS 0.004 5.000
VRC -SP/NH-71/Str-9166 03-Feb-22 18 Checked by AE Rep.
6 Fixing of Bearing A-2 side Bearing 340+876 LHS 0.004 5.000
Total Qty LHS 0.02875 30.00000

1 Fixing of Bearing A-1 side Bearing 333+137 RHS 0.006 5.000 VRC -SP/NH-71/STR-9160 01-Feb-22 18 Checked by AE Rep.
2 Fixing of Bearing A-2 side Bearing 333+137 RHS 0.006 5.000 VRC -SP/NH-71/STR-9162 02-Feb-22 18 Checked by AE Rep.
3 Checking of fixing of Bearing A-2 side Bearing 331+477 RHS 0.006 5.000 VRC -SP/NH-71/Str-11120 22-Sep-22 25 Checked by AE Rep.
4 Checking of fixing of Bearing A-1 side Bearing 331+477 RHS 0.006 5.000 VRC -SP/NH-71/Str-11137 24-Sep-22 25
5 Fixing of Bearing A-01 & A-02 side Bearing 340+876 RHS 0.004 10.000 VRC -SP/NH-71/Str-11999 16-Feb-23 30 Checked by AE Rep.
Total Qty RHS 0.0250 30.0000
Total Qty (Both Side) 0.054 60.000
Previous Qty. (Both Side) 60.000
Net Payable Qty (Both Side) 0.000
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 27
Weightage bifrication for Underpass
Minor Bridges/ Underpasses/ Overpasses
B2- New Underpasses/ Overpasses
0
Stage for Payment Percentage Unit Unit Rate Total Amount Upto Date Previous Bill This Bill Remarks
Weightage Qty. (in Rs.) Qty. Amount Qty. Amount Qty. Amount
(in Rs.) (in Rs.) (in Rs.)
B2- New Underpasses/ Overpasses
(1) Foundation + Substructure 23.45% Km 1704516756 0.1775 302551724
(A) Foundation + Substructure ( Without Pile-69%) 69.01% 1704516756 0.1225 208803303 0.123 208803303 0.123 208803303 0.000 0

(B) Foundation + Substructure ( With Pile-31%) 30.99% 1704516756 0.055 93748422

(a) Pile { 49% of (1)} 49.00% No. 957015 48 45936727 48 45936727 48.0 45936726.6 - -
(b) Pile Cap { 25% of (1)} 25.00% Km 426129189 0.055 23437105 0.0481 20507467 0.0 20507467.2 - -
(c) Abutment / Pier { 15% of (1)} 15.00% Km 255677513 0.055 14062263 0.0275 7031132 0.0275 7031132 0.0000 0
(d) Abutment / Pier Cap { 9% of (1)} 9.00% Km 153406508 0.055 8437358 0 0
(e) Pedestal & Bearing { 2% of (1)} 2.00% Km 34090335 0.055 1874968 0 -
TOTAL 302551724 282278628 282278628 0

(1) Foundation + Substructure 23.45% Km 1704516756 0.178 302,551,724 0.166 282278628 0.166 282278628 0.00000 0

B2- New Underpasses/ Overpasses


(2) Super-Structure 18.10% Km 1315639799 0.1775 233526064
(A) Deck Slab Without Girder 69.01% 1315639799 0.1225 161165875 0.123 161165875 0.1225 161165875 0.0000 0
(B) Super-Structure With Girder 30.99% 1315639799 0.055 72360189
(a) Girder {47% of (2)} 47.00% No. 1133643 30 34009289 30 34009289 27 30608360 3.000 3400929
(b) Deck Slab {53% of (2)} 53.00% Km 697289093 0.055 38350900
TOTAL 195175164 191774235 3400929

(2) Super-Structure 18.10% Km 1315639799 0.1775 233,526,064 0.1483 195175164 0.1458 191774235 0.0026 3400929
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
Weightage bifrication for Underpass
0
Minor Bridges/ Underpasses/ Overpasses
B2- New Underpasses/ Overpasses

Stage for Payment Percentage Unit Unit Rate Total Amount Upto Date Previous Bill This Bill Remarks
Weightage Qty. (in Rs.) Qty. Amount Qty. Amount Qty. Amount
(in Rs.) (in Rs.) (in Rs.)
B2- New Underpasses/ Overpasses
(1) Foundation + Substructure 23.45% Km 2168829564 0.1395 302551724
(A) Foundation + Substructure ( Without Pile-69%) 87.81% 2168829564 0.1225 265681622 0.123 265681622 0.123 265681622 - -

(B) Foundation + Substructure ( With Pile-31%) 12.19% 2168829564 0.017 36870103

(a) Pile { 49% of (1)} 49.00% No. 1505529 12 18066350 12 18066350 12.0 18066350 - -
(b) Pile Cap { 25% of (1)} 25.00% Km 542207391 0.017 9217526 0.017 9217526 0.017 9217526 - -
(c) Abutment / Pier { 15% of (1)} 15.00% Km 325324435 0.017 5530515 0.017 5530515 0.0170 5530515 - -
(d) Abutment / Pier Cap { 9% of (1)} 9.00% Km 195194661 0.017 3318309 0.017 3318309 0.017 3318309 - -
(e) Pedestal & Bearing { 2% of (1)} 2.00% Km 36870 20 737402 0 0 - -
TOTAL 302551724 301814322 301814322 -

(1) Foundation + Substructure 23.45% Km 2168829564 0.1395 302,551,724 0.139 301814322 0.139 301814322 - -

B2- New Underpasses/ Overpasses


(2) Super-Structure 18.10% Km 1674021966 0.1395 233526064
(A) Deck Slab Without Girder 87.81% 1674021966 0.1225 205067691 0.1225 205067691 0.1225 205067691 - -
(B) Super-Structure With Girder 12.19% 1674021966 0.017 28458373
(a) Girder {47% of (2)} 47.00% No. 1337544 10 13375436 10 13375436 10 13375436 - -
(b) Deck Slab {53% of (2)} 53.00% Km 887231642 0.017 15082938
TOTAL 233526064 218443126 218443126 -

(2) Super-Structure 18.10% Km 1674021966 0.1395 233,526,064 0.1305 218443126 0.1305 218443126 - -
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode
under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
B2- New Underpasses/ Overpasses
0

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Pile
1 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-01 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-7264 7/8/2021 12 Checked by AE Rep.
2 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-02 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-7280 7/9/2021 12
3 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-03 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-7297 7/10/2021 12
4 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-04 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-7310 7/11/2021 12
5 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-05 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-7324 7/12/2021 12
6 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-06 Pile 350+490 LHS 1 VRC-SP/NH-71/STR-7355 7/14/2021 12

Total Qty LHS 6.000


1 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-01 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7265 7/8/2021 12 Checked by AE Rep.
2 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-02 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7281 7/9/2021 12 Checked by AE Rep.
3 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-03 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7298 7/10/2021 12 Checked by AE Rep.
4 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-04 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7311 7/11/2021 12 Checked by AE Rep.
5 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-05 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7325 7/12/2021 12
6 Checking borrow depth & reinforcement for Pile Pouring of concrete in A2-06 Pile 350+490 RHS 1 VRC-SP/NH-71/STR-7494 7/24/2021 12 Checked by AE Rep.

Total Qty RHS 6.000 Nos.


Total Qty (Both Side) 12.000 Nos.
Previous Qty. (Both Side) 12.000 Nos.
Net Payable Qty (Both Side) 0.000 Nos.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
B2- New Underpasses/ Overpasses

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Pile Cap
1 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A2 MNB/VUP 350+490 LHS 0.0085 VRC-SP/NH-71/STR-9843 4/28/2022 20 Checked by AE Rep.

Total Qty LHS 0.0085

2 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap A2 MNB/VUP 350+490 RHS 0.0085 VRC-SP/NH-71/STR-9824 4/27/2022 20 Checked by AE Rep.

Total Qty RHS 0.009 Km.


Total Qty (Both Side) 0.0170 Km.
Previous Qty. (Both Side) 0.0170 Km.
Net Payable Qty (Both Side) 0.0000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode
under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
B2- New Underpasses/ Overpasses

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Abutment / Pier

Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft)


1 Shaft 350+490 LHS 0.0085 VRC-SP/NH-71/STR-10918 27-Aug-22 24 Checked by AE Rep.
Final Lift A2 Side of Abutment

Total Qty LHS 0.0085


Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft)
1 Shaft 350+490 RHS 0.0085 VRC-SP/NH-71/STR-10703 31-Jul-22 23 Checked by AE Rep.
Final Lift A2 Side of Abutment

Total Qty RHS 0.0085 Km.

Total Qty (Both Side) 0.0170 Km.

Previous Qty. (Both Side) 0.0170 Km.

Net Payable Qty (Both Side) 0.0000 Km.


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work)
on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
Minor Bridges/ Underpasses/ Overpasses
B2- New Underpasses/ Overpasses

S No Description type of Girder CHAINAGE Quantity RFI NO Date SPS No. Remarks

Checking reinforcement,shuttering & Pouring of


1 RCC Girder 350+490 1 VRC-SP/NH-71/STR-10883 25-Aug-22 25
Concrete for Girder 01
Checking reinforcement,shuttering & Pouring of
2 RCC Girder 350+490 1 VRC-SP/NH-71/STR-10904 26-Aug-22 25 Checked by AE Rep.
Concrete for Girder 02
Checking reinforcement,shuttering & Pouring of
3 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11084 17-Sep-22 25 Checked by AE Rep.
Concrete for Girder 03
Checking reinforcement,shuttering & Pouring of
4 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11085 17-Sep-22 25 Checked by AE Rep.
Concrete for Girder 04
Checking reinforcement,shuttering & Pouring of Checked by AE Rep.
5 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11117 21-Sep-22 25
Concrete for Girder 05
Checking reinforcement,shuttering & Pouring of Checked by AE Rep.
6 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11130 23-Sep-22 25
Concrete for Girder 06
Checking reinforcement,shuttering & Pouring of Checked by AE Rep.
7 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11131 23-Sep-22 25
Concrete for Girder 07
Checking reinforcement,shuttering & Pouring of Checked by AE Rep.
8 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11141 24-Sep-22 25
Concrete for Girder 08
Checking reinforcement,shuttering & Pouring of Checked by AE Rep.
9 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11142 24-Sep-22 25
Concrete for Girder 09
Checking reinforcement,shuttering & Pouring of
10 RCC Girder 350+490 1 VRC-SP/NH-71/STR-11147 25-Sep-22 25
Concrete for Girder 10
S No Description type of Girder CHAINAGE Quantity RFI NO Date SPS No. Remarks

Total Qty (Both Side) 10 Nos.


Previous Qty. (Both Side) 10 Nos.
Net Payable Qty (Both Side) 0 Nos.
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 15
OTHER WORKS
RE PANEL CASTING

CHAINAGE
S No Description RFI NO Date SPS No. Remarks
From To
1 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 142.176 VRC-SP/NH-71/STR-470 9/26/2020 5
2 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 166.512 VRC-SP/NH-71/STR-554 9/30/2020 5 Checked by AE Rep.
3 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 128.208 VRC-SP/NH-71/STR-592 10/2/2020 5
4 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 229.824 VRC-SP/NH-71/STR-615 10/3/2020 5 Checked by AE Rep.
5 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 185.664 VRC-SP/NH-71/STR-635 10/4/2020 5
6 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 185.664 VRC-SP/NH-71/STR-661 10/5/2020 5 Checked by AE Rep.
7 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 206.544 VRC-SP/NH-71/STR-691 10/6/2020 5 Checked by AE Rep.
8 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 94.296 VRC-SP/NH-71/STR-714 10/7/2020 5
9 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 229.824 VRC-SP/NH-71/STR-794 10/10/2020 5 Checked by AE Rep.
10 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 182.472 VRC-SP/NH-71/STR-818 10/11/2020 5
11 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 206.544 VRC-SP/NH-71/STR-897 10/14/2020 5 Checked by AE Rep.
12 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 206.544 VRC-SP/NH-71/STR-919 10/15/2020 5 Checked by AE Rep.
13 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 206.544 VRC-SP/NH-71/STR-944 10/16/2020 5 Checked by AE Rep.
14 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 206.544 VRC-SP/NH-71/STR-956 10/17/2020 5 Checked by AE Rep.
15 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 140.976 VRC-SP/NH-71/STR-982 10/18/2020 5
16 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 169.968 VRC-SP/NH-71/STR-1000 10/19/2020 5 Checked by AE Rep.
17 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 130.872 VRC-SP/NH-71/STR-1026 10/20/2020 5
18 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 163.056 VRC-SP/NH-71/STR-1047 10/21/2020 5 Checked by AE Rep.
19 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 152.016 VRC-SP/NH-71/STR-1073 10/22/2020 5
20 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 202.152 VRC-SP/NH-71/STR-1203 10/28/2020 5 Checked by AE Rep.
21 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 171.432 VRC-SP/NH-71/STR-1212 10/29/2020 5
22 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 171.594 VRC-SP/NH-71/STR-1307 11/4/2020 5 Checked by AE Rep.
23 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 223.866 VRC-SP/NH-71/STR-1327 11/5/2020 5 Checked by AE Rep.
24 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 175.782 VRC-SP/NH-71/STR-1353 11/6/2020 5
25 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 147.888 VRC-SP/NH-71/STR-1378 11/7/2020 5
26 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 229.740 VRC-SP/NH-71/STR-1402 11/9/2020 5 Checked by AE Rep.
27 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 197.394 VRC-SP/NH-71/STR-1422 11/10/2020 5
28 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 199.224 VRC-SP/NH-71/STR-1427 11/11/2020 5 Checked by AE Rep.
29 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 111.720 VRC-SP/NH-71/STR-1436 11/12/2020 5
30 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 111.720 VRC-SP/NH-71/STR-1442 11/13/2020 5 Checked by AE Rep.
31 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 86.448 VRC-SP/NH-71/STR-1526 11/21/2020 5
32 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 44.952 VRC-SP/NH-71/STR-1550 11/23/2020 5
33 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 160.656 VRC-SP/NH-71/STR-1572 11/24/2020 5
34 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 160.656 VRC-SP/NH-71/STR-1616 11/27/2020 5 Checked by AE Rep.
35 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 160.656 VRC-SP/NH-71/STR-1627 11/28/2020 5 Checked by AE Rep.
36 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 158.430 VRC-SP/NH-71/STR-1720 12/2/2020 5
37 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 237.330 VRC-SP/NH-71/STR-1886 12/9/2020 5 Checked by AE Rep.
38 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 184.062 VRC-SP/NH-71/STR-1925 12/10/2020 5 Checked by AE Rep.
39 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 131.298 VRC-SP/NH-71/STR-1968 12/11/2020 5
40 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 168.804 VRC-SP/NH-71/STR-2025 12/12/2020 5 Checked by AE Rep.
41 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 186.492 VRC-SP/NH-71/STR-2081 12/14/2020 5 Checked by AE Rep.
42 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 186.492 VRC-SP/NH-71/STR-2126 12/15/2020 5
43 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 310.818 VRC-SP/NH-71/STR-2166 12/16/2020 5 Checked by AE Rep.
44 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 170.364 VRC-SP/NH-71/STR-2204 12/17/2020 5
45 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 191.112 VRC-SP/NH-71/STR-2318 12/19/2020 5 Checked by AE Rep.
46 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 291.300 VRC-SP/NH-71/STR-2363 12/21/2020 5 Checked by AE Rep.
47 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 167.748 VRC-SP/NH-71/STR-2498 12/23/2020 5
48 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 311.142 VRC-SP/NH-71/STR-2556 12/24/2020 5 Checked by AE Rep.
49 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 47.250 VRC-SP/NH-71/STR-2624 12/26/2020 5
50 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 350.976 VRC-SP/NH-71/STR-2695 12/28/2020 5 Checked by AE Rep.
51 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 71.988 VRC-SP/NH-71/STR-2803 12/29/2020 5
52 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 149.688 VRC-SP/NH-71/STR-2881 12/30/2020 5 Checked by AE Rep.
53 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 80.166 VRC-SP/NH-71/STR-2961 12/31/2020 5
54 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 81.180 VRC-SP/NH-71/STR-3010 1/2/2021 5 Checked by AE Rep.
55 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 137.556 VRC-SP/NH-71/STR-3064 1/4/2021 5 Checked by AE Rep.
56 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 43.164 VRC-SP/NH-71/STR-3141 1/5/2021 5
57 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 82.440 VRC-SP/NH-71/STR-3231 1/7/2021 5 Checked by AE Rep.
58 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 152.730 VRC-SP/NH-71/STR-3248 1/8/2021 5
59 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 88.286 VRC-SP/NH-71/STR-3290 1/9/2021 5 Checked by AE Rep.
60 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 190.422 VRC-SP/NH-71/STR-3325 1/11/2021 5
61 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 119.760 VRC-SP/NH-71/STR-3362 1/12/2021 5 Checked by AE Rep.
62 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 53.872 VRC-SP/NH-71/STR-3407 1/13/2021 5 Checked by AE Rep.
63 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 120.132 VRC-SP/NH-71/STR-3445 1/14/2021 5
64 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 50.304 VRC-SP/NH-71/STR-3478 1/15/2021 5 Checked by AE Rep.
65 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 123.756 VRC-SP/NH-71/STR-3524 1/16/2021 5
66 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 101.402 VRC-SP/NH-71/STR-3593 1/18/2021 5 Checked by AE Rep.
67 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 69.496 VRC-SP/NH-71/STR-3650 1/19/2021 5
68 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 103.338 VRC-SP/NH-71/STR-3695 1/20/2021 5 Checked by AE Rep.
69 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 128.866 VRC-SP/NH-71/STR-3768 1/21/2021 5
70 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 70.992 VRC-SP/NH-71/STR-3808 1/22/2021 5 Checked by AE Rep.
71 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 110.082 VRC-SP/NH-71/STR-3874 1/23/2021 5
72 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 130.572 VRC-SP/NH-71/STR-3922 1/24/2021 5 Checked by AE Rep.
73 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 145.266 VRC-SP/NH-71/STR-3969 1/25/2021 5
74 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 112.142 VRC-SP/NH-71/STR-4052 1/27/2021 5
75 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 126.606 VRC-SP/NH-71/STR-4127 1/28/2021 5
76 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 113.282 VRC-SP/NH-71/STR-4171 1/29/2021 5
77 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 173.798 VRC-SP/NH-71/STR-4225 1/30/2021 5
78 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 164.712 VRC-SP/NH-71/STR-4295 2/1/2021 6 Checked by AE Rep.
79 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 154.394 VRC-SP/NH-71/STR-4303 2/2/2021 6
80 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 92.506 VRC-SP/NH-71/STR-4330 2/3/2021 6 Checked by AE Rep.
81 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 82.422 VRC-SP/NH-71/STR-4356 2/4/2021 6
82 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 32.672 VRC-SP/NH-71/STR-4389 2/5/2021 6 Checked by AE Rep.
83 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 157.152 VRC-SP/NH-71/STR-4418 2/6/2021 6 Checked by AE Rep.
84 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 233.720 VRC-SP/NH-71/STR-4449 2/7/2021 6
85 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 218.560 VRC-SP/NH-71/STR-4488 2/8/2021 6 Checked by AE Rep.
86 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 96.792 VRC-SP/NH-71/STR-4527 2/9/2021 6
87 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 246.180 VRC-SP/NH-71/STR-4560 2/10/2021 6 Checked by AE Rep.
88 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 156.936 VRC-SP/NH-71/STR-4590 2/11/2021 6
89 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 253.992 VRC-SP/NH-71/STR-4602 2/12/2021 6 Checked by AE Rep.
90 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 215.658 VRC-SP/NH-71/STR-4646 2/13/2021 6 Checked by AE Rep.
91 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 262.872 VRC-SP/NH-71/STR-4676 2/14/2021 6
92 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 242.490 VRC-SP/NH-71/STR-4701 2/15/2021 6 Checked by AE Rep.
93 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 247.954 VRC-SP/NH-71/STR-4730 2/16/2021 6
94 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 221.706 VRC-SP/NH-71/STR-4758 2/17/2021 6 Checked by AE Rep.
95 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 153.782 VRC-SP/NH-71/STR-4786 2/18/2021 6
96 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 205.894 VRC-SP/NH-71/STR-4798 2/19/2021 6 Checked by AE Rep.
97 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 214.230 VRC-SP/NH-71/STR-4817 2/20/2021 6
98 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 259.316 VRC-SP/NH-71/STR-4827 2/21/2021 6 Checked by AE Rep.
99 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 260.510 VRC-SP/NH-71/STR-4841 2/22/2021 6
100 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 266.892 VRC-SP/NH-71/STR-4855 2/23/2021 6 Checked by AE Rep.
101 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 275.590 VRC-SP/NH-71/STR-4873 2/24/2021 6
102 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 184.200 VRC-SP/NH-71/STR-4885 2/25/2021 6 Checked by AE Rep.
103 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 96.354 VRC-SP/NH-71/STR-4895 2/26/2021 6
104 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 272.010 VRC-SP/NH-71/STR-4906 2/27/2021 6 Checked by AE Rep.
105 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 282.054 VRC-SP/NH-71/STR-4929 2/28/2021 6 Checked by AE Rep.
106 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 191.784 VRC-SP/NH-71/STR-4946 3/1/2021 7 Checked by AE Rep.
107 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 231.396 VRC-SP/NH-71/STR-4966 3/2/2021 7 Checked by AE Rep.
108 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 215.492 VRC-SP/NH-71/STR-4978 3/3/2021 7 Checked by AE Rep.
109 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 204.918 VRC-SP/NH-71/STR-4997 3/4/2021 7 Checked by AE Rep.
110 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 142.646 VRC-SP/NH-71/STR-5018 3/5/2021 7 Checked by AE Rep.
111 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 208.018 VRC-SP/NH-71/STR-5032 3/6/2021 7 Checked by AE Rep.
112 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 269.526 VRC-SP/NH-71/STR-5050 3/7/2021 7 Checked by AE Rep.
113 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 280.544 VRC-SP/NH-71/STR-5076 3/8/2021 7 Checked by AE Rep.
114 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 236.914 VRC-SP/NH-71/STR-5103 3/9/2021 7 Checked by AE Rep.
115 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 233.118 VRC-SP/NH-71/STR-5122 3/10/2021 7 Checked by AE Rep.
116 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 140.976 VRC-SP/NH-71/STR-5147 3/11/2021 7 Checked by AE Rep.
117 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 159.228 VRC-SP/NH-71/STR-5163 3/12/2021 7 Checked by AE Rep.
118 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 255.604 VRC-SP/NH-71/STR-5187 3/13/2021 7 Checked by AE Rep.
119 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 189.500 VRC-SP/NH-71/STR-5201 3/14/2021 7 Checked by AE Rep.
120 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 282.786 VRC-SP/NH-71/STR-5216 3/15/2021 7 Checked by AE Rep.
121 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 213.258 VRC-SP/NH-71/STR-5231 3/16/2021 7 Checked by AE Rep.
122 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 144.072 VRC-SP/NH-71/STR-5248 3/17/2021 7
123 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 241.254 VRC-SP/NH-71/STR-5269 3/18/2021 7 Checked by AE Rep.
124 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 261.672 VRC-SP/NH-71/STR-5312 3/20/2021 7
125 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 278.496 VRC-SP/NH-71/STR-5332 3/21/2021 7 Checked by AE Rep.
126 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 162.252 VRC-SP/NH-71/STR-5345 3/22/2021 7
127 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 277.932 VRC-SP/NH-71/STR-5368 3/23/2021 7 Checked by AE Rep.
128 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 141.444 VRC-SP/NH-71/STR-5377 3/24/2021 7
129 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 141.444 VRC-SP/NH-71/STR-5412 3/27/2021 7 Checked by AE Rep.
130 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 95.190 VRC -SP/NH-71/STR-5442 4/1/2021 8
131 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 51.174 VRC -SP/NH-71/STR-5451 4/2/2021 8
132 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 219.168 VRC -SP/NH-71/STR-5467 4/3/2021 8
133 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 157.159 VRC -SP/NH-71/STR-5481 4/4/2021 8
134 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 269.646 VRC -SP/NH-71/STR-5509 4/5/2021 8
135 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 187.123 VRC -SP/NH-71/STR-5541 4/6/2021 8
136 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 151.248 VRC -SP/NH-71/STR-5575 4/7/2021 8
137 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 137.616 VRC -SP/NH-71/STR-5594 4/8/2021 8
138 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 109.668 VRC -SP/NH-71/STR-5615 4/9/2021 8
139 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 196.473 VRC -SP/NH-71/STR-5630 4/10/2021 8
140 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 306.981 VRC -SP/NH-71/STR-5647 4/11/2021 8
141 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 144.768 VRC -SP/NH-71/STR-5666 4/12/2021 8
142 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 49.974 VRC -SP/NH-71/STR-5683 4/13/2021 8
143 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 275.236 VRC -SP/NH-71/STR-5703 4/14/2021 8
144 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 83.366 VRC-SP/NH-71/STR-6087 5/2/2021 9 Checked by AE Rep.
145 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 80.540 VRC-SP/NH-71/STR-6110 5/3/2021 9 Checked by AE Rep.
146 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 103.710 VRC-SP/NH-71/STR-6149 5/5/2021 9 Checked by AE Rep.
147 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 154.782 VRC-SP/NH-71/STR-6182 5/7/2021 9 Checked by AE Rep.
148 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 68.112 VRC-SP/NH-71/STR-6205 5/9/2021 9 Checked by AE Rep.
149 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 135.630 VRC-SP/NH-71/STR-6226 5/10/2021 9
150 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 119.670 VRC-SP/NH-71/STR-6242 5/11/2021 9 Checked by AE Rep.
151 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 136.992 VRC-SP/NH-71/STR-6256 5/12/2021 9 Checked by AE Rep.
152 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 172.750 VRC-SP/NH-71/STR-6288 5/14/2021 9 Checked by AE Rep.
153 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 47.880 VRC-SP/NH-71/STR-6301 5/15/2021 9 Checked by AE Rep.
154 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 47.880 VRC-SP/NH-71/STR-6316 5/16/2021 9
155 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 152.790 VRC-SP/NH-71/STR-6327 5/17/2021 9 Checked by AE Rep.
156 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 98.160 VRC-SP/NH-71/STR-6345 5/18/2021 9
157 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 96.142 VRC-SP/NH-71/STR-6363 5/19/2021 9 Checked by AE Rep.
158 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 142.482 VRC-SP/NH-71/STR-6418 5/23/2021 9 Checked by AE Rep.
159 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 70.224 VRC-SP/NH-71/STR-6434 5/24/2021 9 Checked by AE Rep.
160 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 158.766 VRC-SP/NH-71/STR-6495 5/28/2021 9 Checked by AE Rep.
161 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 62.875 VRC-SP/NH-71/STR-6518 5/29/2021 9
162 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 0.000 VRC-SP/NH-71/STR-6543 5/30/2021 9 Checked by AE Rep.
163 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 0.000 VRC-SP/NH-71/STR-6571 5/31/2021 9 Checked by AE Rep.
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 189.996 VRC -SP/NH-71/STR-6583 6/1/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 93.368 VRC -SP/NH-71/STR-6596 6/2/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 158.382 VRC -SP/NH-71/STR-6615 6/3/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 95.760 VRC -SP/NH-71/STR-6623 6/4/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 177.550 VRC -SP/NH-71/STR-6644 6/5/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 186.378 VRC -SP/NH-71/STR-6665 6/6/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 121.900 VRC -SP/NH-71/STR-6682 6/7/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 194.286 VRC -SP/NH-71/STR-6701 6/8/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 182.838 VRC -SP/NH-71/STR-6721 6/9/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 95.862 VRC -SP/NH-71/STR-6739 6/10/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 47.880 VRC -SP/NH-71/STR-6757 6/11/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 0.000 VRC -SP/NH-71/STR-6781 6/12/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 129.748 VRC -SP/NH-71/STR-6797 6/13/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 121.644 VRC -SP/NH-71/STR-6720 6/14/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 128.922 VRC -SP/NH-71/STR-6839 6/15/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 101.760 VRC -SP/NH-71/STR-6856 6/16/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 75.134 VRC -SP/NH-71/STR-6873 6/17/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 111.600 VRC -SP/NH-71/STR-6884 6/18/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 95.640 VRC -SP/NH-71/STR-6901 6/19/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 0.000 VRC -SP/NH-71/STR-6919 6/20/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 46.158 VRC -SP/NH-71/STR-6938 6/21/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 53.592 VRC -SP/NH-71/STR-6954 6/22/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 47.880 VRC -SP/NH-71/STR-6975 6/23/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 96.296 VRC -SP/NH-71/STR-7001 6/24/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 101.880 VRC -SP/NH-71/STR-7029 6/25/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 119.108 VRC -SP/NH-71/STR-7063 6/26/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 133.952 VRC -SP/NH-71/STR-7095 6/27/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 129.832 VRC -SP/NH-71/STR-7118 6/28/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 15.576 VRC -SP/NH-71/STR-7128 6/29/2021 10
Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 328150 Kila Zafargargh 129.144 VRC -SP/NH-71/STR-7149 6/30/2021 10
162 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 102.304 VRC-SP/NH-71/STR-311 9/16/2020 5 Checked by AE Rep.
163 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 102.304 VRC-SP/NH-71/STR-327 9/17/2020 5
164 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 100.839 VRC-SP/NH-71/STR-337 10/19/2020 5 Checked by AE Rep.
165 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 75.263 VRC-SP/NH-71/STR-370 9/21/2020 5
166 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 112.696 VRC-SP/NH-71/STR-383 9/22/2020 5 Checked by AE Rep.
167 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 119.090 VRC-SP/NH-71/STR-394 9/23/2020 5
168 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 119.090 VRC-SP/NH-71/STR-405 9/24/2020 5 Checked by AE Rep.
169 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 81.924 VRC-SP/NH-71/STR-425 9/25/2020 5
170 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 43.560 VRC-SP/NH-71/STR-456 9/26/2020 5
171 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 119.090 VRC-SP/NH-71/STR-493 9/28/2020 5 Checked by AE Rep.
172 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 119.090 VRC-SP/NH-71/STR-515 9/29/2020 5 Checked by AE Rep.
173 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 119.090 VRC-SP/NH-71/STR-586 10/2/2020 5 Checked by AE Rep.
174 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 103.105 VRC-SP/NH-71/STR-613 10/3/2020 5
175 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 119.090 VRC-SP/NH-71/STR-658 10/5/2020 5 Checked by AE Rep.
176 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 37.166 VRC-SP/NH-71/STR-683 10/6/2020 5
177 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 119.090 VRC-SP/NH-71/STR-709 10/7/2020 5 Checked by AE Rep.
178 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 75.530 VRC-SP/NH-71/STR-732 10/8/2020 5
179 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 78.727 VRC-SP/NH-71/STR-751 10/9/2020 5 Checked by AE Rep.
180 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 40.363 VRC-SP/NH-71/STR-779 10/10/2020 5
181 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 28.773 VRC-SP/NH-71/STR-1373 11/7/2020 5
182 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 95.910 VRC-SP/NH-71/STR-1394 11/9/2020 5 Checked by AE Rep.
183 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 89.516 VRC-SP/NH-71/STR-1419 11/10/2020 5
184 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 102.304 VRC-SP/NH-71/STR-1424 11/11/2020 5 Checked by AE Rep.
185 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 70.334 VRC-SP/NH-71/STR-1490 11/18/2020 5
186 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 56.348 VRC-SP/NH-71/STR-1496 11/19/2020 5
187 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 75.530 VRC-SP/NH-71/STR-1502 11/20/2020 5 Checked by AE Rep.
188 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 27.575 VRC-SP/NH-71/STR-1522 11/21/2020 5
189 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 112.696 VRC-SP/NH-71/STR-1545 11/23/2020 5 Checked by AE Rep.
190 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 54.349 VRC-SP/NH-71/STR-1565 11/24/2020 5
191 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 141.469 VRC-SP/NH-71/STR-1608 11/27/2020 5 Checked by AE Rep.
192 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 80.726 VRC-SP/NH-71/STR-1617 11/28/2020 5
193 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 89.516 VRC-SP/NH-71/STR-1673 12/1/2020 5 Checked by AE Rep.
194 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 92.980 VRC-SP/NH-71/STR-1731 12/3/2020 5
195 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 112.696 VRC-SP/NH-71/STR-1762 12/4/2020 5
196 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 191.423 VRC-SP/NH-71/STR-1791 12/5/2020 5 Checked by AE Rep.
197 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 145.864 VRC-SP/NH-71/STR-1827 12/7/2020 5
198 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 162.650 VRC-SP/NH-71/STR-1846 12/9/2020 5 Checked by AE Rep.
199 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 131.878 VRC-SP/NH-71/STR-1887 12/10/2020 5 Checked by AE Rep.
200 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 102.571 VRC-SP/NH-71/STR-1926 12/11/2020 5
201 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 75.530 VRC-SP/NH-71/STR-1970 12/12/2020 5
202 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 180.367 VRC-SP/NH-71/STR-2039 12/14/2020 5 Checked by AE Rep.
203 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 72.333 VRC-SP/NH-71/STR-2082 12/15/2020 5
204 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 92.980 VRC-SP/NH-71/STR-2127 12/16/2020 5 Checked by AE Rep.
205 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 62.742 VRC-SP/NH-71/STR-2168 12/17/2020 5
206 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 97.909 VRC-SP/NH-71/STR-2205 12/18/2020 5 Checked by AE Rep.
207 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 88.318 VRC-SP/NH-71/STR-2257 12/19/2020 5
208 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 85.121 VRC-SP/NH-71/STR-2320 12/21/2020 5
209 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 107.979 VRC-SP/NH-71/STR-2380 12/22/2020 5 Checked by AE Rep.
210 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 286.429 VRC-SP/NH-71/STR-2448 12/23/2020 5 Checked by AE Rep.
211 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 312.724 VRC-SP/NH-71/STR-2526 12/24/2020 5 Checked by AE Rep.
212 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 221.209 VRC-SP/NH-71/STR-2593 12/26/2020 5 Checked by AE Rep.
213 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 197.762 VRC-SP/NH-71/STR-2667 12/28/2020 5
214 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 224.940 VRC-SP/NH-71/STR-2756 12/29/2020 5 Checked by AE Rep.
215 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jaijaiwanti 32.264 VRC-SP/NH-71/STR-2855 12/30/2020 5
216 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-2989 1/2/2021 5 Checked by AE Rep.
217 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3030 1/4/2021 5
218 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3108 1/5/2021 5 Checked by AE Rep.
219 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3163 1/6/2021 5
220 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3195 1/7/2021 5 Checked by AE Rep.
221 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3228 1/8/2021 5
222 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3261 1/9/2021 5 Checked by AE Rep.
223 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3303 1/11/2021 5
224 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3341 1/12/2021 5 Checked by AE Rep.
225 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3380 1/13/2021 5
226 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3418 1/14/2021 5 Checked by AE Rep.
227 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3453 1/15/2021 5 Checked by AE Rep.
228 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3502 1/16/2021 5
229 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3554 1/18/2021 5 Checked by AE Rep.
230 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3615 1/19/2021 5
231 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3674 1/20/2021 5 Checked by AE Rep.
232 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3753 1/21/2021 5
233 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3829 1/22/2021 5 Checked by AE Rep.
234 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3861 1/23/2021 5
235 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3912 1/24/2021 5 Checked by AE Rep.
236 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-3995 1/25/2021 5 Checked by AE Rep.
237 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-4023 1/27/2021 5
238 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-4091 1/28/2021 5 Checked by AE Rep.
239 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-4156 1/29/2021 5
240 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC -SP/NH-71/STR-4205 1/30/2021 5 Checked by AE Rep.
241 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 151.736 VRC-SP/NH-71/STR-4245 1/31/2021 5 Checked by AE Rep.
242 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 119.147 VRC -SP/NH-71/STR-4280 2/1/2021 7 Checked by AE Rep.
243 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 122.971 VRC -SP/NH-71/STR-4297 2/2/2021 7
244 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 115.241 VRC -SP/NH-71/STR-4319 2/3/2021 7 Checked by AE Rep.
245 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 115.241 VRC -SP/NH-71/STR-4351 2/4/2021 7
246 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 126.521 VRC -SP/NH-71/STR-4380 2/5/2021 7 Checked by AE Rep.
247 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 135.462 VRC -SP/NH-71/STR-4409 2/6/2021 7
248 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 112.484 VRC -SP/NH-71/STR-4439 2/7/2021 7 Checked by AE Rep.
249 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 130.100 VRC -SP/NH-71/STR-4472 2/8/2021 7
250 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 145.595 VRC -SP/NH-71/STR-4509 2/9/2021 7 Checked by AE Rep.
251 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 138.920 VRC -SP/NH-71/STR-4546 2/10/2021 7
252 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 142.120 VRC -SP/NH-71/STR-4578 2/11/2021 7 Checked by AE Rep.
253 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 142.120 VRC -SP/NH-71/STR-4603 2/12/2021 7
254 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 143.075 VRC -SP/NH-71/STR-4636 2/13/2021 7 Checked by AE Rep.
255 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 127.993 VRC -SP/NH-71/STR-4664 2/14/2021 7
256 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 94.597 VRC -SP/NH-71/STR-4685 2/15/2021 7 Checked by AE Rep.
257 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 126.363 VRC -SP/NH-71/STR-4710 2/16/2021 7
258 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 121.065 VRC -SP/NH-71/STR-4733 2/17/2021 7 Checked by AE Rep.
259 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 143.484 VRC -SP/NH-71/STR-4761 2/18/2021 7
260 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 133.830 VRC -SP/NH-71/STR-4789 2/19/2021 7 Checked by AE Rep.
261 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 136.562 VRC -SP/NH-71/STR-4801 2/20/2021 7
262 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 135.761 VRC -SP/NH-71/STR-4820 2/21/2021 7 Checked by AE Rep.
263 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 133.670 VRC -SP/NH-71/STR-4832 2/22/2021 7
264 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 110.397 VRC -SP/NH-71/STR-4846 2/23/2021 7 Checked by AE Rep.
265 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 114.918 VRC -SP/NH-71/STR-4862 2/24/2021 7
266 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 114.918 VRC -SP/NH-71/STR-4880 2/25/2021 7 Checked by AE Rep.
267 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 98.472 VRC -SP/NH-71/STR-4891 2/26/2021 7
268 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 98.472 VRC -SP/NH-71/STR-4903 2/27/2021 7 Checked by AE Rep.
269 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 90.200 VRC -SP/NH-71/STR-4910 2/28/2021 7
270 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 90.200 VRC -SP/NH-71/STR-4933 3/1/2021 7 Checked by AE Rep.
271 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 96.441 VRC -SP/NH-71/STR-4952 3/2/2021 7
272 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 38.904 VRC -SP/NH-71/STR-4970 3/3/2021 7 Checked by AE Rep.
273 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 37.172 VRC -SP/NH-71/STR-4982 3/4/2021 7
274 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 37.172 VRC -SP/NH-71/STR-5000 3/5/2021 7 Checked by AE Rep.
275 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 37.172 VRC -SP/NH-71/STR-5021 3/6/2021 7
276 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 62.244 VRC -SP/NH-71/STR-5035 3/7/2021 7 Checked by AE Rep.
277 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 85.584 VRC -SP/NH-71/STR-5067 3/8/2021 7
278 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 82.224 VRC -SP/NH-71/STR-5091 3/9/2021 7 Checked by AE Rep.
279 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 82.224 VRC -SP/NH-71/STR-5116 3/10/2021 7
280 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 60.204 VRC -SP/NH-71/STR-5139 3/11/2021 7 Checked by AE Rep.
281 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 60.204 VRC -SP/NH-71/STR-5156 3/12/2021 7
282 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 60.204 VRC -SP/NH-71/STR-5176 3/13/2021 7 Checked by AE Rep.
283 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 37.284 VRC -SP/NH-71/STR-5194 3/14/2021 7
284 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 37.284 VRC -SP/NH-71/STR-5210 3/15/2021 7 Checked by AE Rep.
285 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 25.562 VRC -SP/NH-71/STR-5225 3/16/2021 7
286 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 26.562 VRC -SP/NH-71/STR-5244 3/17/2021 7 Checked by AE Rep.
287 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 28.049 VRC -SP/NH-71/STR-5263 3/18/2021 7
288 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 28.049 VRC -SP/NH-71/STR-5305 3/20/2021 7 Checked by AE Rep.
289 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 33.078 VRC -SP/NH-71/STR-5439 4/1/2021 8
290 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 33.078 VRC -SP/NH-71/STR-5447 4/2/2021 8
291 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 62.992 VRC -SP/NH-71/STR-5460 4/3/2021 8
292 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 49.990 VRC -SP/NH-71/STR-5478 4/4/2021 8
293 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 51.456 VRC -SP/NH-71/STR-5506 4/5/2021 8
294 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 86.912 VRC -SP/NH-71/STR-5536 4/6/2021 8
295 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 91.844 VRC -SP/NH-71/STR-5570 4/7/2021 8
296 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 91.844 VRC -SP/NH-71/STR-5589 4/8/2021 8
297 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 95.044 VRC -SP/NH-71/STR-5623 4/10/2021 8
298 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 89.652 VRC -SP/NH-71/STR-5644 4/11/2021 8
299 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 80.198 VRC -SP/NH-71/STR-5658 4/12/2021 8
300 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 27.427 VRC -SP/NH-71/STR-5679 4/13/2021 8
301 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 27.427 VRC -SP/NH-71/STR-5694 4/14/2021 8
302 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 27.427 VRC -SP/NH-71/STR-5714 4/15/2021 8
303 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 318500 Jai Jai wanti 24.696 VRC -SP/NH-7

Contractor's Representative Q.S. SQME Bridge Engineer Resident Engineer Team Leader
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 15
OTHER WORKS
RE PANEL CASTING

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
343 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1595 11/25/2020 5
344 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 168.840 1599 11/25/2020 5 Checked by AE Rep.
345 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1556 11/23/2020 5
346 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 28.410 1597 11/25/2020 5
347 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 5.360 1300 11/3/2020 5
348 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 85.230 1558 11/23/2020 5
349 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 199.680 1282 11/2/2020 5 Checked by AE Rep.
350 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 12.480 1302 11/3/2020 5
351 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 140.400 1293 11/3/2020 5 Checked by AE Rep.
352 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 28.410 1515 11/20/2020 5
353 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 168.840 1517 11/20/2020 5 Checked by AE Rep.
354 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 168.840 1560 11/23/2020 5 Checked by AE Rep.
355 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1513 11/20/2020 5 Checked by AE Rep.
356 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 5.120 1519 11/20/2020 5
357 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 12.480 1564 11/23/2020 5
358 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1577 11/24/2020 5 Checked by AE Rep.
359 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 12.480 1521 11/20/2020 5
360 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1535 11/21/2020 5
361 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 168.840 1581 11/24/2020 5 Checked by AE Rep.
362 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 28.410 1579 11/24/2020 5
363 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 30.304 2377 12/21/2020 5
364 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.400 2375 12/21/2020 5 Checked by AE Rep.
365 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 168.840 1539 11/21/2020 5 Checked by AE Rep.
366 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 28.410 1537 11/21/2020 5
367 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 18.940 2036 12/12/2020 5
368 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 31.200 1708 12/1/2020 5
369 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.400 1704 12/1/2020 5 Checked by AE Rep.
370 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 30.304 2554 12/18/2020 5 Checked by AE Rep.
371 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 31.200 2256 12/18/2020 5
372 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.400 2574 12/24/2020 5 Checked by AE Rep.
373 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 40.960 2445 12/22/2020 5
374 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 30.004 1706 12/1/2020 5
375 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.400 2034 12/12/2020 5 Checked by AE Rep.
376 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 31.200 2038 12/12/2020 5
377 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.400 2252 12/18/2020 5
378 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 936 10/15/2020 5
379 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 128.792 934 10/15/2020 5 Checked by AE Rep.
380 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 932 10/15/2020 5
381 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 31.200 2379 12/21/2020 5
382 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.400 2443 12/22/2020 5 Checked by AE Rep.
383 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 31.200 2447 12/22/2020 5
384 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 30.040 2576 12/24/2020 5
385 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 31.200 2578 12/24/2020 5
386 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 128.798 977 10/17/2020 5 Checked by AE Rep.
387 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 975 10/17/2020 5
388 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 12.480 979 10/17/2020 5
389 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 1097 10/22/2020 5
390 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1191 10/27/2020 5 Checked by AE Rep.
391 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 1016 10/19/2020 5 Checked by AE Rep.
392 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 128.792 1095 10/22/2020 5
393 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 3.120 1020 10/19/2020 5
394 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 12.480 1195 10/27/2020 5
395 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 28.410 1193 10/27/2020 5
396 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 128.792 1018 10/19/2020 5 Checked by AE Rep.
397 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 1043 10/20/2020 5 Checked by AE Rep.
398 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 1092 10/22/2020 5
399 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 906 10/14/2020 5 Checked by AE Rep.
400 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 841 10/11/2020 5 Checked by AE Rep.
401 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 85.230 1295 11/3/2020 5
402 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 128.792 839 10/11/2020 5 Checked by AE Rep.
403 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 837 10/11/2020 5
404 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 262.080 1249 10/30/2020 5 Checked by AE Rep.
405 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 222.440 1246 10/30/2020 5
406 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 5.120 1247 10/30/2020 5 Checked by AE Rep.
407 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 85.230 1243 10/30/2020 5
408 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1241 10/30/2020 5 Checked by AE Rep.
409 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 262.080 1226 10/29/2020 5 Checked by AE Rep.
410 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 85.230 1224 10/29/2020 5
411 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 115.200 1222 10/29/2020 5 Checked by AE Rep.
412 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.672 1041 10/20/2020 5 Checked by AE Rep.
413 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 222.720 1039 10/20/2020 5 Checked by AE Rep.
414 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 252.720 880 10/13/2020 5
415 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.672 878 10/13/2020 5 Checked by AE Rep.
416 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 222.720 876 10/13/2020 5
417 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 252.720 910 10/14/2020 5 Checked by AE Rep.
418 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 166.672 908 10/14/2020 5
419 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 252.720 815 10/10/2020 5 Checked by AE Rep.
420 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 90.912 813 10/10/2020 5 Checked by AE Rep.
421 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 811 10/10/2020 5
422 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 731 10/7/2020 5 Checked by AE Rep.
423 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 34.092 729 10/7/2020 5 Checked by AE Rep.
424 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 727 10/7/2020 5
425 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 726 10/7/2020 5 Checked by AE Rep.
426 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 15.152 706 10/6/2020 5
427 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 708 10/6/2020 5 Checked by AE Rep.
428 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 81.920 612 10/2/2020 5
429 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 81.920 632 10/3/2020 5 Checked by AE Rep.
430 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 653 10/4/2020 5
431 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 15.152 655 10/4/2020 5 Checked by AE Rep.
432 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 657 10/4/2020 5 Checked by AE Rep.
433 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 678 10/5/2020 5
434 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 15.152 680 10/5/2020 5
435 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 94.720 704 10/6/2020 5
436 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 190.320 682 10/5/2020 5 Checked by AE Rep.
437 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 286.040 VRC-SP-NH-71-Str-3023 1/2/2021 5
438 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 171.864 VRC-SP-NH-71-Str-3095 1/4/2021 5
439 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 171.864 VRC-SP-NH-71-Str-3550 1/16/2021 5
440 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 286.040 VRC-SP-NH-71-Str-3611 1/18/2021 5
441 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 286.040 VRC-SP-NH-71-Str-3670 1/19/2021 5
442 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 370.280 VRC-SP-NH-71-Str-3749 1/21/2021 5
443 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 370.280 VRC-SP-NH-71-Str-3857 1/22/2021 5
444 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 370.280 VRC-SP-NH-71-Str-3946 1/24/2021 5
445 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 379.480 VRC-SP-NH-71-Str-4019 1/25/2021 5
446 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 379.480 VRC-SP-NH-71-Str-4087 1/27/2021 5
447 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 379.480 VRC-SP-NH-71-Str-4152 1/28/2021 5
448 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 379.480 VRC-SP-NH-71-Str-4201 1/29/2021 5
449 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 379.480 VRC-SP-NH-71-Str-4242 1/30/2021 5
450 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 379.480 VRC-SP-NH-71-Str-4277 1/31/2021 5
451 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-4294 2/1/2021 8
452 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 154.872 VRC -SP/NH-71/STR-4318 2/2/2021 8
453 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 154.872 VRC -SP/NH-71/STR-4350 2/3/2021 8
454 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-4377 2/4/2021 8
455 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-4408 2/5/2021 8
456 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-4438 2/6/2021 8
457 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 152.032 VRC -SP/NH-71/STR-4508 2/8/2021 8
458 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 152.032 VRC -SP/NH-71/STR-4545 2/9/2021 8
459 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 152.032 VRC -SP/NH-71/STR-4577 2/10/2021 8
460 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-4602 2/11/2021 8
461 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-4635 2/12/2021 8
462 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-4663 2/13/2021 8
463 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 154.872 VRC -SP/NH-71/STR-4909 2/27/2021 8
464 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 154.872 VRC -SP/NH-71/STR-4932 2/28/2021 8
465 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 154.872 VRC -SP/NH-71/STR-5362 3/22/2021 8
466 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-5373 3/23/2021 8
467 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-5383 3/24/2021 8
468 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-5394 3/25/2021 8
469 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-5408 3/26/2021 8
470 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 157.992 VRC -SP/NH-71/STR-5418 3/27/2021 8
471 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.872 VRC -SP/NH-71/STR-5430 3/28/2021 8
472 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.872 VRC -SP/NH-71/STR-5446 4/1/2021 8
473 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 159.992 VRC -SP/NH-71/STR-5459 4/2/2021 8
474 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 159.992 VRC -SP/NH-71/STR-5477 4/3/2021 8
475 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 159.992 VRC -SP/NH-71/STR-5505 4/4/2021 8
476 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.872 VRC -SP/NH-71/STR-5535 4/5/2021 8
477 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.872 VRC -SP/NH-71/STR-5569 4/6/2021 8
478 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 162.552 VRC -SP/NH-71/STR-5607 4/8/2021 8
479 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 162.552 VRC -SP/NH-71/STR-5622 4/9/2021 8
480 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 162.552 VRC -SP/NH-71/STR-5643 4/10/2021 8
481 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5657 4/11/2021 8
482 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5693 4/13/2021 8
483 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 162.552 VRC -SP/NH-71/STR-5713 4/14/2021 8
484 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 162.552 VRC -SP/NH-71/STR-5771 4/17/2021 8
485 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5784 4/18/2021 8
486 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5797 4/19/2021 8
487 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5819 4/20/2021 8
488 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5840 4/21/2021 8
489 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5862 4/22/2021 8
490 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5895 4/23/2021 8
491 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-5919 4/24/2021 8
492 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 156.592 VRC -SP/NH-71/STR-6035 4/29/2021 8
493 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC -SP/NH-71/STR-6077 5/1/2021 9 Checked by AE Rep.
494 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6141 5/4/2021 9
495 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6200 5/8/2021 9 Checked by AE Rep.
496 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6222 5/9/2021 9
497 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6264 5/12/2021 9 Checked by AE Rep.
498 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC -SP/NH-71/STR-6313 5/15/2021 9 Checked by AE Rep.
499 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC -SP/NH-71/STR-6325 5/16/2021 9
500 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC -SP/NH-71/STR-6336 5/17/2021 9 Checked by AE Rep.
501 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC -SP/NH-71/STR-6357 5/18/2021 9
502 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6371 5/19/2021 9 Checked by AE Rep.
503 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6383 5/20/2021 9
504 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6399 5/21/2021 9 Checked by AE Rep.
505 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6414 5/22/2021 9
506 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6429 5/23/2021 9 Checked by AE Rep.
507 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6448 5/24/2021 9
508 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6463 5/25/2021 9 Checked by AE Rep.
509 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6479 5/26/2021 9
510 Checking of Reinforcement, Shuttering & Pouring of Concrete of RE Panel Casting 346500 Titoli 0.000 VRC-SP/NH-71/STR-6490 5/27/2021 9 Checked by AE Rep.
Total Qty : 68214 Sqm C=(A + B)/2
Previous Qty. : 0 Sqm D
Net Payable Qty : 68214 Sqm E=(C - D)

Contractor's Representative Q.S. SQME Bridge Engineer Resident Engineer Team Leader
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 09
OTHER WORKS
RE PANEL ERECTION

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
1 Pouring of Concrete in Coping beam for RE Wall No. W1 323930 323970 81.905 VRC -SP/NH-71/HW-2264 1/19/2021 5 Checked by AE Rep.
2 Pouring of Concrete in Coping beam for RE Wall No. W1 323970 324010 110.780 VRC -SP/NH-71/HW-2305 1/20/2021 5 Checked by AE Rep.
3 Pouring of Concrete in Coping beam for RE Wall No. W1 324010 324050 138.175 VRC -SP/NH-71/HW-2325 1/21/2021 5 Checked by AE Rep.
4 Pouring of Concrete in Coping beam for RE Wall No. W1 324050 324090 189.914 VRC -SP/NH-71/HW-2360 1/22/2021 5
5 Pouring of Concrete in Coping beam for RE Wall No. W1 324090 324180 512.455 VRC -SP/NH-71/HW-2407 1/23/2021 5 Checked by AE Rep.
6 Pouring of Concrete in Coping beam for RE Wall No. W1 324180 324240 385.860 VRC -SP/NH-71/HW-2626 2/2/2021 5 Checked by AE Rep.
7 Pouring of Concrete in Coping beam for RE Wall No. W1 324240 324282 254.221 VRC -SP/NH-71/HW-2655 2/3/2021 5
8 Pouring of Concrete in Coping beam for RE Wall No. W2 323930 324010 192.685 VRC -SP/NH-71/HW-2440 1/24/2021 5 Checked by AE Rep.
9 Pouring of Concrete in Coping beam for RE Wall No. W2 324010 324050 136.175 VRC -SP/NH-71/HW-2466 1/25/2021 5
10 Pouring of Concrete in Coping beam for RE Wall No. W2 324050 324130 346.925 VRC -SP/NH-71/HW-2530 1/28/2021 5 Checked by AE Rep.
11 Pouring of Concrete in Coping beam for RE Wall No. W2 324130 324200 452.390 VRC -SP/NH-71/HW-2628 2/2/2021 5
12 Pouring of Concrete in Coping beam for RE Wall No. W2 324200 324250 327.400 VRC -SP/NH-71/HW-2657 2/3/2021 5 Checked by AE Rep.
13 Pouring of Concrete in Coping beam for RE Wall No. W2 324250 324284.238 233.442 VRC -SP/NH-71/HW-2691 2/4/2021 5 Checked by AE Rep.
14 Pouring of Concrete in Coping beam for RE Wall No. W3 324289 324350 423.760 VRC -SP/NH-71/STR-5294 3/19/2021 7 Checked by AE Rep.
15 Pouring of Concrete in Coping beam for RE Wall No. W3 324350 324600 1849.075 VRC -SP/NH-71/STR-5314 3/20/2021 7 Checked by AE Rep.
16 Pouring of Concrete in Coping beam for RE Wall No. W3 324600 324722 770.260 VRC -SP/NH-71/STR-5336 3/21/2021 7
17 Pouring of Concrete in Coping beam for RE Wall No. W4 324296 324350 377.271 VRC -SP/NH-71/STR-5296 3/19/2021 7 Checked by AE Rep.
18 Pouring of Concrete in Coping beam for RE Wall No. W4 324350 324600 1849.092 VRC -SP/NH-71/STR-5316 3/20/2021 7 Checked by AE Rep.
19 Pouring of Concrete in Coping beam for RE Wall No. W4 324600 324722 770.260 VRC -SP/NH-71/STR-5338 3/21/2021 7 Checked by AE Rep.

Contractor's Representative Q.S. SQME Bridge Engineer Resident Engineer Team Leader
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 09
OTHER WORKS
RE PANEL ERECTION

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
20 Pouring of Concrete in Coping beam for RE Wall No. W5 324731 324850 659.506 VRC -SP/NH-71/STR-5275 3/18/2021 7 Checked by AE Rep.
21 Pouring of Concrete in Coping beam for RE Wall No. W5 324850 324950 496.800 VRC -SP/NH-71/STR-5298 3/19/2021 7 Checked by AE Rep.
22 Pouring of Concrete in Coping beam for RE Wall No. W5 324950 325130 573.493 VRC -SP/NH-71/STR-5318 3/20/2021 7
23 Pouring of Concrete in Coping beam for RE Wall No. W6 324731 324850 651.461 VRC -SP/NH-71/STR-5113 3/9/2021 7 Checked by AE Rep.
24 Pouring of Concrete in Coping beam for RE Wall No. W6 324850 324900 260.985 VRC -SP/NH-71/STR-5132 3/10/2021 7 Checked by AE Rep.
25 Pouring of Concrete in Coping beam for RE Wall No. W6 324900 325000 444.480 VRC -SP/NH-71/STR-5252 3/17/2021 7 Checked by AE Rep.
26 Pouring of Concrete in Coping beam for RE Wall No. W6 325000 325050 185.510 VRC -SP/NH-71/STR-5273 3/18/2021 7 Checked by AE Rep.
27 Pouring of Concrete in Coping beam for RE Wall No. W6 325050 325130 190.030 VRC -SP/NH-71/STR-5300 3/19/2021 7 Checked by AE Rep.
28 Pouring of Concrete in Coping beam for RE Wall No. W5 329455 329870 1827.012 VRC -SP/NH-71/STR-6532 10/3/2021 15
29 Pouring of Concrete in Coping beam for RE Wall No. W6 329455 329870 1828.806 VRC -SP/NH-71/STR-6533 10/3/2021 15
30 Pouring of Concrete in Coping beam for RE Wall No. W4 330834 331140 1212.412 VRC -SP/NH-71/STR-6544 10/5/2021 15
31 Pouring of Concrete in Coping beam for RE Wall No. W1 338633 339012 2242.918 VRC -SP/NH-71/STR-6545 10/5/2021 15
32 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-01 308+490 308+550 171.795 VRC-SP/NH-71/STR-7454 7/22/2021 15
33 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-01 308+550 308+600 228.125 VRC-SP/NH-71/STR-7474 7/23/2021 15
34 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-01 308+600 308+650 266.750 VRC-SP/NH-71/STR-7490 7/24/2021 15
35 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-01 308+650 308+700 296.755 VRC-SP/NH-71/STR-7636 8/4/2021 15
36 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-01 307+700 308+750 318.275 VRC-SP/NH-71/STR-7645 8/5/2021 15
37 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-01 308+750 308+805 364.603 VRC-SP/NH-71/STR-7656 8/6/2021 15
38 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 316+450 316+509 190.856 VRC-SP/NH-71/HW-8400 11/16/2021 15
39 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 322+484 322+500 177.127 VRC-SP/NH-71/STR-7316 7/12/2021 15
40 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 322+500 322+550 336.090 VRC-SP/NH-71/STR-7303 7/11/2021 15
41 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 322+550 322+600 321.630 VRC-SP/NH-71/STR-7287 7/10/2021 15
42 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 322+600 322+650 297.940 VRC-SP/NH-71/STR-7269 7/9/2021 15
43 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 322+650 322+700 236.680 VRC-SP/NH-71/STR-7249 7/8/2021 15
44 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 322+700 322+750 182.455 VRC-SP/NH-71/STR-7239 7/7/2021 15
45 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-03 322+750 322+800 109.705 VRC-SP/NH-71/STR-7204 7/5/2021 15

Contractor's Representative Q.S. SQME Bridge Engineer Resident Engineer Team Leader
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 09
OTHER WORKS
RE PANEL ERECTION

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
46 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+492 322+500 141.067 VRC-SP/NH-71/HW-7491 7/24/2021 15
47 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+500 322+550 390.575 VRC-SP/NH-71/STR-7455 7/22/2021 15
48 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+550 322+600 376.030 VRC-SP/NH-71/STR-7391 7/17/2021 15
49 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+600 322+650 352.340 VRC-SP/NH-71/STR-7286 7/10/2021 15
50 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+650 322+700 307.380 VRC-SP/NH-71/STR-7268 7/9/2021 15
51 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+700 322+750 237.155 VRC-SP/NH-71/STR-7248 7/8/2021 15
52 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+750 322+800 186.075 VRC-SP/NH-71/STR-7238 7/7/2021 15
53 Checking Shuttering, Level and Concrete Pouring for Copping Wall GA-04 322+800 322+850 112.870 VRC-SP/NH-71/STR-7203 7/5/2021 15
Total Qty : 25577.735 Sqm C=(A + B)/2
Previous Qty. : Sqm D
Net Payable Qty : 25577.735 Sqm E=(C - D)

Contractor's Representative Q.S. SQME Bridge Engineer Resident Engineer Team Leader
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km
9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No. : 15

OTHER WORKS

CRASH BARRIER

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Nos)

1 Checking erection of Fricton slab with crash barrier W5 329455 329870 0.167 VRC-SP/NH-71/STR-6528 10/1/2021 15

2 Checking erection of Fricton slab with crash barrier W6 329455 329870 0.167 VRC-SP/NH-71/STR-6553 10/6/2021 15

Total Qty : 0.333 Nos. C=(A + B)/2


Previous Qty. : Nos. D
Net Payable Qty : 0.333 Nos. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.01.23 31.01.23
SPS No.-37

0
B2- New Underpasses/ Overpasses
Foundation + Sub-Structure- VUP Abutment Cap

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Pier Cap
Checking of Reinforcement,Shuttering &
1 MNB+VUP 350+490 LHS 0.009 VRC-SP/NH-71/STR-11910 31-Jan-23 29 Checked by AE Rep.
Pouring of concrete for Abutment Cap A2
Total Qty LHS 0.009
Checking of Reinforcement,Shuttering &
1 MNB+VUP 350+490 RHS 0.009 VRC-SP/NH-71/STR-11740 30-Dec-22 29 Checked by AE Rep.
Pouring of concrete for Abutment Cap A2
Total Qty RHS 0.009

Total Qty (Both Side) 0.017

Previous Qty. (Both Side) 0.017

Net Payable Qty (Both Side) 0.000


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
B2- New Underpasses/ Overpasses
0
CHAINAGE
S No Description Side Quantity RFI NO Date SPS No. Remarks
VUP/CUP Design
SUBSTRUCTURE
1 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 308+818 RHS 5.250 VRC-SP/NH-71/STR-2328 21-Dec-20 4
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 308+818 LHS 5.250 VRC-SP/NH-71/STR-3564 18-Jan-21 5 Checked by AE Rep.
3 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 316+162 LHS 5.250 VRC-SP/NH-71/STR-4823 21-Feb-21 7
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 316+162 RHS 5.250 VRC-SP/NH-71/STR-1618 28-Nov-20 4
5 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 322+482 LHS 5.250 VRC-SP/NH71/STR-893 14-Oct-20 2 Checked by AE Rep.
6 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 322+482 RHS 5.250 VRC-SP/NH71/STR-689 06-Oct-20 2
7 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 324+287 LHS 5.250 VRC-SP/NH71/STR-756 09-Oct-20 2 Checked by AE Rep.
8 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 324+287 RHS 5.250 VRC-SP/NH71/STR-1661 30-Nov-20 3 Checked by AE Rep.
9 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass 324+727 LHS 3.500 VRC-SP/NH71/STR-1662 30-Nov-20 3 Checked by AE Rep.
10 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass CUP 324+727 RHS 3.500 VRC-SP/NH-71/STR-3371 12-Jan-21 5 Checked by AE Rep.
11 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass CUP 328+853 LHS 3.500 VRC-SP/NH-71/STR-4106 28-Jan-21 5 Checked by AE Rep.
12 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass CUP 328+853 RHS 3.500 VRC-SP/NH71/STR-917 15-Oct-20 2 Checked by AE Rep.
13 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 329+423 LHS 5.250 VRC-SP/NH71/STR-276 14-Sep-20 1
14 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 329+423 RHS 5.250 VRC-SP/NH71/STR-1119 24-Oct-20 2
15 LHS VRC-SP/NH71/STR-377 21-Sep-20 1 Checked by AE Rep.
Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass CUP 330+828 7.000
16 RHS VRC-SP/NH71/STR-518 29-Sep-20 1 Checked by AE Rep.
17 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 336+123 BHS 10.500 VRC-SP/NH71/STR-442 25-Sep-20 1 Checked by AE Rep.
18 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 338+994 LHS 5.250 VRC -SP/NH-71/Str-1665 30-Nov-20 4
19 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 338+994 RHS 5.250 VRC -SP/NH-71/Str-4104 28-Jan-21 5 Checked by AE Rep.
20 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 344+060 BHS 10.500 VRC-SP-NH-71-Str-4151 28-Jan-21 14
21 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 346+515 LHS 5.250 VRC-SP/NH71/STR-674 05-Oct-20 2
22 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass VUP 346+515 RHS 5.250 VRC-SP/NH71/STR-2373 21-Dec-20 4
23 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall Final Lift of Underpass CUP 353+305 BHS 7.000 VRC-SP/NH71/STR-649 04-Oct-20 2
Total Qty 0.123 Km.
Previous Qty 0.123 Km.
Net Payable Qty 0.000 Km.
SUPERSTRUCTURE
1 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 308+818 RHS 5.250 VRC-SP/NH-71/STR-2450 23-Dec-20 4
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Minor Bridges/ Underpasses/ Overpasses
B2- New Underpasses/ Overpasses
0
CHAINAGE
S No Description Side Quantity RFI NO Date SPS No. Remarks
VUP/CUP Design
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 308+818 LHS 5.250 VRC-SP/NH-71/STR-4030 27-Jan-21 4 Checked by AE Rep.
3 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 316+162 LHS 5.250 VRC-SP/NH-71/STR-5028 06-Mar-21 7 Checked by AE Rep.
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 316+162 RHS 5.250 VRC-SP/NH-71/STR-1642 30-Nov-20 4 Checked by AE Rep.
5 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 322+482 LHS 5.250 VRC-SP/NH71/STR-1145 26-Oct-20 2
6 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 322+482 RHS 5.250 VRC-SP/NH71/STR-1437 12-Nov-20 3 Checked by AE Rep.
7 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 324+287 LHS 5.250 VRC-SP/NH71/STR-895 14-Oct-20 2 Checked by AE Rep.
8 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 324+287 RHS 5.250 VRC-SP-NH-71-Str-2883 30-Dec-20 4
9 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass CUP 324+727 LHS 3.500 VRC-SP/NH-71/Str-2431 22-Dec-20 4
10 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass CUP 324+727 RHS 3.500 VRC-SP/NH-71/Str-3410 13-Jan-21 5 Checked by AE Rep.
11 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass CUP 328+853 LHS 3.500 VRC-SP/NH71/STR-4254 31-Jan-21 5 Checked by AE Rep.
12 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass CUP 328+853 RHS 3.500 VRC-SP/NH71/STR-1049 21-Oct-20 2 Checked by AE Rep.
13 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 329+423 LHS 5.250 VRC-SP/NH71/STR-436 22-Sep-20 1
14 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 329+423 RHS 5.250 VRC-SP/NH71/STR-1172 27-Oct-20 2 Checked by AE Rep.
15 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass CUP 330+828 LHS 3.500 VRC-SP/NH71/STR-391 22-Sep-20 1 Checked by AE Rep.
16 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass CUP 330+828 RHS 3.500 VRC-SP/NH71/STR-1024 20-Oct-20 2 Checked by AE Rep.
17 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 336+123 BHS 10.500 VRC-SP/NH71/STR-562 30-Sep-20 2
18 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 338+994 LHS 5.250 VRC-SP-NH-71-Str-2712 28-Dec-20 4
19 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 338+994 RHS 5.250 VRC -SP/NH-71/STR-4837 22-Feb-21 6 Checked by AE Rep.
20 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 344+060 BHS 10.500 VRC-SP/NH-71/STR-7956 09-Sep-21 14
21 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass VUP 346+515 BHS 10.500 VRC-SP-NH-71-Str-2901 30-Dec-20 4 Checked by AE Rep.
22 Checking of Reinforcement, Shuttering and Pouring of RCC in Slab of Underpass CUP 353+305 BHS 7.000 VRC-SP/NH71/STR-1220 29-Oct-20 2 Checked by AE Rep.
Total Qty (Both Side) 0.123 Km.
Previous Qty. (Both Side) 0.123 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Weightage bifrication for Underpass Approaches
New Underpasses/ Overpasses
B2- New Underpasses/ Overpasses
0
Upto Date Previous Bill This Bill Remarks
Percentage Scope Amount
Stage for Payment Unit Unit Rate Amount Amount Amount
Weightage Qty. (in Rs.) Qty. Qty. Qty.
(in Rs.) (in Rs.) (in Rs.) ###
B2- New Underpasses/ Overpasses
(3) VUP/CUP Approach after burification 30.08% Nos 388091934 ###
A- { RE Wall Work of Approach ( 60% of 3)} 18.05% 232855161

(i) RE Wall Casting & Erection { 60% of A} ( Erection


of VUP/CUP approaches shall be made on 10.83% Nos 9979507 14.0 139713096 13.85 138246109 13.85 138246109 - - ###
completion upto sub -grade top of half Stage

(ii) Other Work { 40% of A } 7.22% Nos 6653005 14.0 93142064 11.07 73662067 10.89 72457873 0.181 1,204,194 ###
B- { Highway Work of Approaches 40% of 3 } 12.03% 155236774 ###
(i) Earthwork up to top of the sub-grade {35.87% of ###
(B)}
4.32% km 4195399 13.273 55683431 12.43 52141885 12.43 52141885 - -

(ii) GSB,WMM { 17.54% of (B)} 2.11% km 2066760 13.175 27228530 11.60 23968154 11.60 23968154 - - ###
(iIi) DBM { 33.41% of (B)} 4.02% km 3936742 13.175 51864606 10.46 41192099 10.46 41192099 - - ###
(iv) BC {13.18% of (B)} 1.59% km 1521205 13.450 20460207 9.07 13797329 7.99 12154428 1.080 1,642,901 ###
TOTAL 343007643 340160547 2,847,095 ###
###
(3) Approach 30.08% Nos 27720852 14.000 388,091,934 12.374 343007643 12.271 340160547 0.103 2,847,095
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
1 Level & FDD Checking of Subgrade Top Layer in MCW 308350 308+490 LHS SG Top 140.000 VRC-SP/NH71/HW-6900 26-Nov-21 15 Checked by AE Rep.

2 Level & FDD Checking of Subgrade Top Layer in MCW 308490 308+700 LHS SG Top 210.000 VRC-SP/NH71/HW-7549 18-Jan-22 17 Checked by AE Rep.

3 Level & FDD Checking of Subgrade Top Layer in MCW 308700 308+805 LHS SG Top 105.020 VRC-SP/NH71/HW-7571 20-Jan-22 17 Checked by AE Rep.

4 Level & FDD Checking of Subgrade Top Layer in MCW 308+817 309+200 LHS SG Top 383.08 VRC-SP/NH71/HW-7922 27-Feb-22 19

5 Level & FDD Checking of Subgrade Top Layer in MCW 309200 309+400 LHS SG Top 200.000 VRC-SP/NH71/HW-6973 4-Dec-21 17 Checked by AE Rep.

6 Level & FDD Checking of Subgrade Top Layer in MCW 315+620 315+950 LHS SG Top 330.00 VRC-SP/NH71/HW-8118 25-Mar-22 19 Checked by AE Rep.

7 Level & FDD Checking of Subgrade Top Layer in MCW 315+950 316+156 LHS SG Top 206.02 VRC-SP/NH71/HW-8726 24-May-22 22 Checked by AE Rep.
8 Level & FDD Checking of Subgrade Top Layer in MCW 316+168 316+510 LHS SG Top 342.02 VRC-SP/NH71/HW-9233 19-Jul-22 23 Checked by AE Rep.
9 Level & FDD Checking of Subgrade Top Layer in MCW 316510 316+650 LHS SG Top 140.000 VRC-SP/NH71/HW-7487 12-Jan-22 17

10 Level & FDD Checking of Subgrade Top Layer in MCW 321930 322+000 LHS SG Top 70.000 VRC-SP/NH71/HW-135 26-Aug-20 17

11 Level & FDD Checking of Subgrade Top Layer in MCW 322000 322+130 LHS SG Top 130.000 VRC-SP/NH71/HW-1457 3-Dec-20 17

12 Level & FDD Checking of Subgrade Top Layer in MCW 322130 322+480 LHS SG Top 350.000 VRC-SP/NH71/HW-7276 25-Dec-21 17 Checked by AE Rep.

13 Level & FDD Checking of Subgrade Top Layer in MCW 322484 322+800 LHS SG Top 316.000 VRC-SP/NH71/HW-6716 30.10.2021 15
14 Level & FDD Checking of Subgrade Top Layer in MCW 322800 322+890 LHS SG Top 90.000 VRC-SP/NH71/HW-1496 9-Dec-20 15
15 Level & FDD Checking of Subgrade Top Layer in MCW 322890 323+010 LHS SG Top 120.000 VRC-SP/NH71/HW-134 27-Aug-20 15
16 Level & FDD Checking of Subgrade Top Layer in MCW 328470 328+720 LHS SG Top 250.000 VRC -SP/NH-71/Hw-8192 6-Apr-22 20 Checked by AE Rep
17 Level & FDD Checking of Subgrade Top Layer in MCW 328720 328+843 LHS SG Top 123.000 VRC -SP/NH-71/Hw-8502 3-May-22 21 Checked by AE Rep.
18 Level & FDD Checking of Subgrade Top Layer in MCW 328851 329+060 LHS SG Top 209 VRC -SP/NH-71/Hw-9286 22-Jul-22 23
19 Laying & FDD checking of Sub Grade top layer W-03 329060 329+200 LHS SG Top 140 VRC -SP/NH-71/Hw-9384 18-Aug-22 24
20 Level & FDD Checking of Subgrade Top Layer in MCW 329200 329+432 LHS SG Top 232 VRC -SP/NH-71/Hw-9301 23-Jul-22 23 Checked by AE Rep.

21 Level & FDD Checking of Subgrade Top Layer in MCW 329432 330+110 LHS SG Top 678.000 VRC-SP/NH-71/STR-6343 7-Sep-21 15 Checked by AE Rep.
22 Level & FDD Checking of Subgrade Top Layer in MCW 330430 330+510 LHS SG Top 80.000 Done by earlier company 17
23 Level & FDD Checking of Subgrade Top Layer in MCW 330510 330+821 LHS SG Top 311.000 VRC -SP/NH-71/Hw-8507 4-May-22 21
24 Laying & level checking of Sub-grade Top W-03 330829 331+140 LHS SG Top 311.000 VRC -SP/NH-71/Hw-8072 21-Mar-22 19
25 Level & FDD Checking of Subgrade Top Layer in MCW 331420 331+500 LHS SG Top 80.000 VRC -SP/NH-71/Hw-9350 28-Jul-22 23 Checked by AE Rep.
26 Level & FDD Checking of Subgrade Top Layer 335+580 335830 LHS SG Top 250.000 VRC -SP/NH-71/Hw-8480 29-04-2022

27 Level & FDD Checking of Subgrade Top Layer 335830 336126 LHS SG Top 295.504 VRC-SP/NH-71/HW-7689 31-Jan-22 17 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
28 Level & FDD Checking of Subgrade Top Layer in MCW 336126 336+400 LHS SG Top 274.496 VRC-SP/NH-71/HW-5846 31-Jul-21 15
29 Level & FDD Checking of Subgrade Top Layer in MCW 336400 336+520 LHS SG TOP 120.000 VRC-SP/NH71/HW-255 2-Sep-20 15
30 Level & FDD Checking of Subgrade Top Layer in MCW 336520 336+710 LHS SG TOP 190.000 VRC-SP/NH71/HW-221 1-Sep-20 15
31 Level & FDD Checking of Subgrade Top Layer in MCW 338430 338490 LHS SG Top 60.000 VRC -SP/NH-71/HW-3258 25-Feb-21 16

32 Level & FDD Checking of Subgrade Top Layer in MCW 338490 338550 LHS SG Top 60.000 VRC -SP/NH-71/HW-5427 9-Jul-21 16
33 Laying & level checking of sub- grade top layer W-1 338550 339+005 LHS SG Top 455.000 VRC -SP/NH-71/Hw-7995 4-Mar-22 19
34 Laying & level checking of sub- grade top layer W-3 339017 339+370 LHS SG Top 353.000 VRC -SP/NH-71/Hw-8001 5-Mar-22 19 Checked by AE Rep.
35 Level & FDD Checking of Subgrade Top Layer in MCW 339370 339580 LHS SG Top 210.000 VRC -SP/NH-71/HW-6773 16-Nov-21 17 Checked by AE Rep.

36 Level & FDD Checking of Subgrade Top Layer in MCW 343380 343450 LHS SG Top 70.000 VRC-SP/NH71/HW-182 31-Aug-20 16

37 Level & FDD Checking of Subgrade Top Layer in MCW 343450 343540 LHS SG TOP 90.000 Done by earlier company 16

38 Level & FDD Checking of Subgrade Top Layer in MCW 343540 344076 LHS SG TOP 536.000 VRC-SP/NH-71/HW-10365 28-Feb-23 30 Checked by AE Rep.

39 Level & FDD Checking of Subgrade Top Layer in MCW 344076 344450 LHS SG TOP 374.000 VRC-SP/NH-71/HW-10349 26-Feb-23 30 Checked by AE Rep.

40 Level & FDD Checking of Subgrade Top Layer in MCW 344450 344540 LHS SG TOP 90.000 Done by earlier company 16

41 Level & FDD Checking of Subgrade Top Layer in MCW 344540 344680 LHS SG TOP 140.000 VRC-SP/NH-71/HW-10136 31-Jan-23 30

42 Level & FDD Checking of Subgrade Top Layer in MCW 345810 345870 LHS SG TOP 60.000 Done by earlier company 16

43 Level & FDD Checking of Subgrade Top Layer in MCW 345870 345900 LHS SG TOP 30.000 VRC-SP/NH71/HW-159 28-Aug-20 16 Checked by AE Rep.

44 Level & FDD Checking of Subgrade Top Layer in MCW 345900 345940 LHS SG TOP 40.000 VRC-SP/NH71/HW-146 28-Aug-20 16

45 Level & FDD Checking of Subgrade Top Layer in MCW 345940 346070 LHS SG TOP 130.000 VRC-SP/NH71/HW-246 2-Sep-20 16 Checked by AE Rep.
46 Level & FDD Checking of Subgrade Top Layer in MCW 346+070 346+520 LHS SG TOP 450 VRC-SP/NH-71/HW-9637 30-Sep-22 25
47 Level & FDD Checking of Subgrade Top Layer in MCW 346+520 347+030 LHS SG TOP 510.00 VRC-SP/NH-71/HW-9322 26-Jul-22 23 Checked by AE Rep.

48 Level & FDD Checking of Subgrade Top Layer in MCW 347030 347120 LHS SG TOP 90.000 VRC-SP/NH71/HW-499 21-Sep-20 16 Checked by AE Rep.
49 Level & FDD Checking of Subgrade Top Layer in MCW 352900 353+300 LHS SG Top 400.000 VRC-SP/NH-71/HW-5270 29-Jun-21 15 Checked by AE Rep.
50 Level & FDD Checking of Subgrade Top Layer in MCW 353+300 353+710 LHS SG Top 410.000 VRC-SP/NH-71/HW-8277 18-Apr-22
51 Level & FDD Checking of Subgrade Top Layer in MCW 323+870 324+278 LHS SG Top 408 12 Checked by AE Rep.

52 Level & FDD Checking of Subgrade Top Layer in MCW 324+296 324+720 LHS SG Top 424.25 12
53 Level & FDD Checking of Subgrade Top Layer in MCW 324+734 325+130 LHS SG Top 396 12 Checked by AE Rep.
0
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
Total Qty LHS 12462.390 m
1 Level & FDD Checking of Subgrade Top Layer in MCW 308350 308+510 RHS SG Top 160.000 VRC-SP/NH71/HW-373 9-Sep-20 15
2 Level & FDD Checking of Subgrade Top Layer in MCW 308510 308+805 RHS SG Top 295.000 VRC-SP/NH71/HW-6947 1-Dec-21 15 Checked by AE Rep.

3 Level & FDD Checking of Subgrade Top Layer in MCW 308816.98 309+200 RHS SG Top 383.020 VRC-SP/NH71/HW-7662 30-Jan-22 17 Checked by AE Rep.

4 Level & FDD Checking of Subgrade Top Layer in MCW 309200 309+300 RHS SG Top 100.000 VRC-SP/NH71/HW-1380 25-Nov-20 15
5 Level & FDD Checking of Subgrade Top Layer in MCW 309300 309+400 RHS SG Top 100.000 VRC-SP/NH71/HW-837 11-Oct-20 15
6 Level & FDD Checking of Subgrade Top Layer in MCW 315620 315+660 RHS SG Top 40.000 VRC-SP/NH71/HW-569 26-Sep-20 15
7 Level & FDD Checking of Subgrade Top Layer in MCW 315660 315+760 RHS SG Top 100.000 VRC-SP/NH71/HW-635 29-Sep-20 15
8 Level & FDD Checking of Subgrade Top Layer in MCW 315760 315+960 RHS SG Top 200.000 VRC-SP/NH71/HW-7377 2-Jan-22 17

9 Level & FDD Checking of Subgrade Top Layer in MCW 315960 316+156 RHS SG Top 196.02 VRC-SP/NH71/HW-8673 21-May-22 21 Checked by AE Rep.

10 Level & FDD Checking of Subgrade Top Layer in MCW 316+168 316+460 RHS SG Top 292.02 VRC-SP/NH71/HW-9015 25-Jun-22 22 Checked by AE Rep
11 Level & FDD Checking of Subgrade Top Layer in MCW 316460 316+550 RHS SG Top 90.000 VRC-SP/NH71/HW-953 21-Oct-20 15
12 Level & FDD Checking of Subgrade Top Layer in MCW 316550 316+650 RHS SG Top 100.000 VRC-SP/NH71/HW-827 10-Oct-20 15
13 Level & FDD Checking of Subgrade Top Layer in MCW 321930 322+000 RHS SG Top 70.000 VRC-SP/NH71/HW-135 27-Aug-20 17
14 Level & FDD Checking of Subgrade Top Layer in MCW 322000 322+110 RHS SG Top 110.000 VRC-SP/NH71/HW-1456 3-Dec-20 17

15 Level & FDD Checking of Subgrade Top Layer in MCW 322110 322+350 RHS SG Top 240.000 VRC-SP/NH71/HW-7274 21-Dec-22 17

16 Level & FDD Checking of Subgrade Top Layer in MCW 322350 322+471 RHS SG Top 121.000 VRC-SP/NH71/HW-7573 20-Jan-22 17 Checked by AE Rep.

17 Level & FDD Checking of Subgrade Top Layer in MCW 322484 322+600 RHS SG Top 116.000 VRC-SP/NH71/HW-5453 11-Jul-21 15
18 Level & FDD Checking of Subgrade Top Layer in MCW 322600 322+800 RHS SG Top 200.000 VRC-SP/NH71/HW-5436 10-Jul-21 15 Checked by AE Rep.
19 Level & FDD Checking of Subgrade Top Layer in MCW 322800 322+890 RHS SG Top 90.000 VRC-SP/NH71/HW-1509 10-Dec-20 15
20 Level & FDD Checking of Subgrade Top Layer in MCW 322890 323+000 RHS SG Top 110.000 VRC-SP/NH71/HW-134 27-Aug-20 15
21 Level & FDD Checking of Subgrade Top Layer in MCW 328470 328+560 RHS SG Top 90.000 VRC -SP/NH-71/HW-73 23-Aug-20 16 Checked by AE Rep.
22 Level & FDD Checking of Subgrade Top Layer in MCW 328560 328+720 RHS SG Top 160.000 VRC -SP/NH-71/Hw-8202 7-Apr-22 20
23 Level & FDD Checking of Subgrade Top Layer in MCW 328+720 328+854 RHS SG Top 134.000 VRC -SP/NH-71/Hw-8511 5-May-22 21 Checked by AE Rep.
24 Level & FDD Checking of Subgrade Top Layer in MCW 328+863 328+900 RHS SG Top 37 VRC -SP/NH-71/Hw-8952 19-Jun-22 26
25 Laying & FDD checking of Sub Grade Top layer W-04 328900 329+178 RHS SG Top 278.000 VRC -SP/NH-71/Hw-9520 8-Sep-22 25 Checked by AE Rep.
26 Level & FDD Checking of Subgrade Top Layer in MCW 329432 330+110 RHS SG Top 678.000 VRC-SP/NH-71/STR-6344 7-Sep-21 15 Checked by AE Rep.
27 Laying & FDD checking of Sub Grade Top layer W-04 329186 329+432 RHS SG Top 246.000 VRC -SP/NH-71/Hw-9507 6-Sep-22 25 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
28 Level & FDD Checking of Subgrade Top Layer in MCW 330+430 330+826 RHS SG Top 396.000 VRC -SP/NH-71/Hw-8569 13-May-22 21 Checked by AE Rep.
29 Level & FDD Checking of Subgrade Top Layer in MCW 330+834 331+000 RHS SG Top 206.000 VRC -SP/NH-71/Hw-8624 18-May-22 21 Checked by AE Rep.
30 Level & FDD Checking of Subgrade Top Layer in MCW 331+000 331+080 RHS SG Top 80.000 VRC -SP/NH-71/Hw-8856 5-Jun-22 22

31 Level & FDD Checking of Subgrade Top Layer in MCW 331+080 331+140 RHS SG Top 60.000 VRC -SP/NH-71/Hw-10680 15-Jun-23 34 Checked by AE Rep.
32 Level & FDD Checking of Subgrade Top Layer in MCW 335580 335+830 RHS SG Top 250.000 VRC -SP/NH-71/Hw-8481 29-Apr-22 20 Checked by AE Rep.
33 Level & FDD Checking of Subgrade Top Layer 335830 336119 RHS SG Top 288.702 VRC-SP/NH-71/HW-7690 31-Jan-22 17
34 Level & FDD Checking of Subgrade Top Layer in MCW 336119 336+400 RHS SG Top 281.298 VRC-SP/NH-71/HW-5847 31-Jul-21 15 Checked by AE Rep.
35 Level & FDD Checking of Subgrade Top Layer in MCW 336400 336+520 RHS SG TOP 120.000 VRC-SP/NH71/HW-254 2-Sep-20 15
36 Level & FDD Checking of Subgrade Top Layer in MCW 336520 336+710 RHS SG TOP 190.000 VRC-SP/NH71/HW-222 1-Sep-20 15
37 Level & FDD Checking of Subgrade Top Layer in MCW 338+430 338+490 RHS SG Top 60.000 VRC -SP/NH-71/HW-4604 14-May-22 16
38 Laying & level checking of sub- grade top layer W-2 338+490 339+012 RHS SG Top 522.000 VRC -SP/NH-71/Hw-7996 3/4/2022 19
39 Laying & level checking of sub- grade top layer W-4 339+024 339+370 RHS SG Top 346.000 VRC -SP/NH-71/Hw-8002 3/5/2022 19
40 Level & FDD Checking of Subgrade Top Layer in MCW 339+370 339+580 RHS SG Top 210.000 VRC -SP/NH-71/HW-6806 19-Nov-21 17 Checked by AE Rep.

41 Level & FDD Checking of Subgrade Top Layer in MCW 343380 343500 RHS SG TOP 120 VRC-SP/NH-71/HW-10408 11-Mar-23 31 Checked by AE Rep.

42 Level & FDD Checking of Subgrade Top Layer in MCW 343+500 343+700 RHS SG TOP 200.000 VRC-SP/NH-71/HW-10366 28-Feb-23 30 Checked by AE Rep.

43 Level & FDD Checking of Subgrade Top Layer in MCW 343700 344060 RHS SG TOP 360 VRC-SP/NH-71/HW-10471 29-Mar-23 31 Checked by AE Rep.

44 Level & FDD Checking of Subgrade Top Layer in MCW 344060 344180 RHS SG TOP 120 VRC-SP/NH-71/HW-10448 23-Mar-23 31 Checked by AE Rep.

45 Level & FDD Checking of Subgrade Top Layer in MCW 344+180 344+520 RHS SG TOP 340.000 VRC-SP/NH-71/HW-10350 26-Feb-23 30 Checked by AE Rep.

46 Level & FDD Checking of Subgrade Top Layer in MCW 344520 344680 RHS SG TOP 160 VRC-SP/NH-71/HW-10465 27-Mar-23 31 Checked by AE Rep.
47 Level & FDD Checking of Subgrade Top Layer in MCW 345+810 346+520 RHS SG TOP 710 VRC-SP/NH-71/HW-9638 30-Sep-22 25 Checked by AE Rep.
48 Level & FDD Checking of Subgrade Top Layer in MCW 346+520 347+120 RHS SG TOP 600 VRC-SP/NH-71/HW-9323 27-Jul-22 23 Checked by AE Rep.
49 Level & FDD Checking of Subgrade Top Layer in MCW 352+900 353+300 RHS SG Top 400.000 VRC-SP/NH-71/HW-5271 29-Jun-21 15 Checked by AE Rep.
50 Level & FDD Checking of Subgrade Top Layer in MCW 353300 353+710 RHS SG Top 410.000 VRC -SP/NH-71/Hw-8278 18-Apr-22 20 Checked by AE Rep.
51 Level & FDD Checking of Subgrade Top Layer in MCW 323+870 324+278 RHS SG Top 408 12 Checked by AE Rep.

52 Level & FDD Checking of Subgrade Top Layer in MCW 324+296 324+720 RHS SG Top 424.25 12
53 Level & FDD Checking of Subgrade Top Layer in MCW 324+734 325+130 RHS SG Top 396 12 Checked by AE Rep.
0
0
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
Total Qty RHS 12394.310 m
Total Qty (Both Side) 12.428 Km.
Previous Qty. (Both Side) 12.428 Km.
Net Payable Qty (Both Side) 0.000 Km.
Non Bituminious Base
MEASUREMENT SHEET WMM
Chainage Quantity
Sl. No. Description Side Layer No.
(MTR)
RFI No. Date SPS No. Remarks
From To
1 Level & FDD Checking of WMM Top Layer in MCW 308350 308+490 LHS WMM Top 140.000 VRC-SP/NH71/HW-6937 30-Nov-21 15 Checked by AE Rep.

2 Level & FDD Checking of WMM Top Layer in MCW 308+490 308+805 LHS WMM Top 315 VRC-SP/NH71/HW-8051 13-Mar-22 19

3 Level & FDD Checking of WMM Top Layer in MCW 308+820 309+200 LHS WMM Top 380.000 VRC-SP/NH71/HW-8182 5-Apr-22 20 Checked by AE Rep.
4 Level & FDD Checking of WMM Top Layer in MCW 309200 309+400 LHS WMM Top 200.000 VRC-SP/NH71/HW-7001 6-Dec-22 17 Checked by AE Rep.

5 Level & FDD Checking of WMM Top Layer in MCW 315620 315+950 LHS WMM Top 330.000 VRC-SP/NH71/HW-8175 4-Apr-22 20

6 Level & FDD Checking of WMM Top Layer in MCW 315950 316+153 LHS WMM Top 202.520 VRC-SP/NH71/HW-9479 30-Aug-22 27 Checked by AE Rep.

7 Level & FDD Checking of WMM Top Layer in MCW 316+171 316+500 LHS WMM Top 328.580 VRC-SP/NH71/HW-9421 26-Aug-22 27 Checked by AE Rep.

8 Level & FDD Checking of WMM Top Layer in MCW 316+500 316+650 LHS WMM Top 150 VRC-SP/NH71/HW-9421 26-Aug-22 24

9 Level & FDD Checking of WMM Top Layer in MCW 321+930 322+100 LHS WMM Top 170 VRC-SP/NH71/HW-8733 24-May-22 21 Checked by AE Rep.

10 Level & FDD Checking of WMM Top Layer in MCW 322+300 322+350 LHS WMM Top 50.000 VRC-SP/NH71/HW-7731 7-Feb-22 18

11 Level & FDD Checking of WMM Top Layer in MCW 322350 322482 LHS WMM Top 131.600 VRC-SP/NH71/HW-7612 24-Jan-22 17 Checked by AE Rep.

12 Level & FDD Checking of WMM Top Layer in MCW 322494 322+800 LHS WMM Top 306.500 VRC-SP/NH71/HW-6763 12-Nov-21 15 Checked by AE Rep.
13 Level & FDD Checking of WMM Top Layer in MCW 322800 323+010 LHS WMM Top 210.000 VRC-SP/NH71/HW-5455 11-Jul-21 15 Checked by AE Rep.
14 Level & FDD Checking of WMM Top Layer in MCW 328460 328+660 LHS WMM Top 200.000 VRC-SP/NH71/HW-9165 2-Jul-22 23 Checked by AE Rep.
15 Laying & FDD checking of WMM top layer W-01 328660 328+720 LHS WMM Top 60.000 VRC -SP/NH-71/Hw-9368 8-Aug-22 24
16 Laying & FDD checking of WMM Top layer W-01 328720 328+843 LHS WMM Top 123.000 VRC -SP/NH-71/Hw-9580 19-Sep-22 25 Checked by AE Rep.
17 Laying & FDD checking of WMM Top layer W-03 328851 329+178 LHS WMM Top 327.000 VRC -SP/NH-71/Hw-9579 19-Sep-22 25 Checked by AE Rep.
18 Laying & FDD checking of WMM Top layer W-03 329186 329+432 LHS WMM Top 246.000 VRC -SP/NH-71/Hw-9585 20-Sep-22 25 Checked by AE Rep.
19 Level & FDD Checking of WMM Top Layer in MCW 329+432 329+870 LHS WMM Top 438.000 VRC-SP/NH71/HW-7909 26-Feb-22 18 Checked by AE Rep.
20 Level & FDD Checking of WMM Top Layer in MCW 329870 330+110 LHS WMM Top 240.000 VRC-SP/NH71/HW-2382 22-Jan-21 15
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
21 Laying & FDD checking of WMM top layer W-03 330430 330+600 LHS WMM Top 170.000 VRC -SP/NH-71/Hw-9378A 18-Aug-22 24
22 Laying & FDD checking of WMM Top layer W-01 330600 330+821 LHS WMM Top 221.000 VRC -SP/NH-71/Hw-9503 4-Sep-22 25 Checked by AE Rep.
23 Laying & FDD checking of WMM top layer W-03 330829 331+140 LHS WMM Top 311.000 VRC -SP/NH-71/Hw-9377 14-Aug-22 24
24 Level & FDD Checking of WMM Top Layer in MCW 335580 335830 LHS WMM Top 250.000 VRC-SP/NH-71/HW-9911 26-Dec-22 30 Checked by AE Rep.
25 Level & FDD Checking of WMM Top Layer in MCW 335830 336+120 LHS WMM Top 290.000 VRC-SP/NH71/HW-9316 24-Jul-22 23
26 Level and FDD Checking of WMM Top Layer 336120 336135 LHS WMM Top 15.000 VRC-SP/NH-71/HW-7409 4-Jan-22 17 Checked by AE Rep.
27 Level & FDD Checking of WMM Top Layer in MCW 336135 336+400 LHS WMM Top 265.000 VRC-SP/NH-71/HW-6691 27-Oct-21 15 Checked by AE Rep.
28 Level & FDD Checking of WMM Top Layer in MCW 336400 336+710 LHS WMM TOP 310.000 VRC-SP/NH71/HW-484 20-Sep-20 15
29 Level & FDD Checking of WMM Top Layer in MCW 338430 338+490 LHS WMM TOP 60.000 VRC -SP/NH-71/HW-3293 28-Feb-21 16
30 Level and FDD Checking of WMM Top Layer W-1 338490 339+005 LHS WMM TOP 515.000 VRC -SP/NH-71/Hw-8014 07-Mar-22 19
31 Level & FDD Checking of WMM Top Layer in MCW 339370 339+580 LHS WMM TOP 210.000 VRC -SP/NH-71/HW-6806 19-Nov-21 17 Checked by AE Rep.
32 Level & FDD Checking of WMM Top Layer in MCW 343380 343+760 LHS WMM Top 380.000 VRC-SP/NH-71/HW-10559 31-May-23 33 Checked by AE Rep.
33 Level & FDD Checking of WMM Top Layer in MCW 344060 344+250 LHS WMM Top 190.000 VRC-SP/NH-71/HW-10553 30-May-23 33
34 Level & FDD Checking of WMM Top Layer in MCW 344250 344450 LHS WMM Top 200 VRC-SP/NH-71/HW-10488 31-Mar-23 31
35 Level & FDD Checking of WMM Top Layer in MCW 344450 344+540 LHS WMM TOP 90.000 Done by earlier company 16

36 Level & FDD Checking of WMM Top Layer in MCW 344540 344+550 LHS WMM Top 10.000 VRC-SP/NH-71/HW-10514 16-May-23 33

37 Level & FDD Checking of WMM Top Layer in MCW 345810 346+000 LHS WMM TOP 190.000 VRC-SP/NH71/HW-339 7-Sep-20 16 Checked by AE Rep.

38 Level & FDD Checking of WMM Top Layer in MCW 346000 346+500 LHS WMM Top 500.000 VRC-SP/NH-71/HW-10053 18-Jan-23 29

39 Level & FDD Checking of WMM Top Layer in MCW 346500 347+030 LHS WMM Top 530.000 VRC-SP/NH-71/HW-10054 18-Jan-23 29 Checked by AE Rep.

40 Level & FDD Checking of WMM Top Layer in MCW 347030 347+120 LHS WMM TOP 90.000 VRC-SP/NH71/HW-654 29-Sep-20 16 Checked by AE Rep.
41 Level & FDD Checking of WMM Top Layer in MCW 352+900 353+300 LHS WMM TOP 400 VRC-SP/NH-71/HW-8096 23-Mar-22 19 Checked by AE Rep.
42 Level & FDD Checking of WMM Top Layer in MCW 353300 353710 LHS WMM Top 410 VRC-SP/NH-71/HW-10474 30-Mar-23 31 Checked by AE Rep.
43 Level & FDD Checking of WMM Top Layer in MCW 323+870 324+278 LHS WMM TOP 408 12 Checked by AE Rep.

44 Level & FDD Checking of WMM Top Layer in MCW 324+296 324+720 LHS WMM TOP 424.25 12
45 Level & FDD Checking of WMM Top Layer in MCW 324+734 325+130 LHS WMM TOP 396 12 Checked by AE Rep.
0 0

Total Qty LHS 11383.450 m A


0
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
1 Level & FDD Checking of WMM Top Layer in MCW 308350 308+480 RHS WMM Top 130.000 VRC-SP/NH71/HW-5512 14-Jul-21 15
2 Level & FDD Checking of WMM Top Layer in MCW 308480 308+805 RHS WMM Top 325.000 VRC-SP/NH71/HW-6974 4-Dec-22 17 Checked by AE Rep.

3 Level & FDD Checking of WMM Top Layer in MCW 308+817 309+200 RHS WMM Top 383.1 VRC-SP/NH71/HW-8081 22-Mar-22 19 Checked by AE Rep.

4 Level & FDD Checking of WMM Top Layer in MCW 309+200 309+400 RHS WMM Top 200 VRC-SP/NH71/HW-9016 25-Jun-22 22 Checked by AE Rep
5 Level & FDD Checking of WMM Top Layer in MCW 315620 315+750 RHS WMM Top 130 VRC-SP/NH71/HW-8172 3-Apr-22 21 Checked by AE Rep.

6 Level & FDD Checking of WMM Top Layer in MCW 315750 315+900 RHS WMM Top 150.000 VRC-SP/NH71/HW-6995 5-Jan-22 17

7 Level & FDD Checking of WMM Top Layer in MCW 315+900 316+153 RHS WMM Top 252.52 VRC-SP/NH71/HW-8731 24-May-22 22 Checked by AE Rep.
8 Level & FDD Checking of WMM Top Layer in MCW 316+171 316+300 RHS WMM Top 128.52 VRC-SP/NH71/HW-8854 5-Jun-22 22 Checked by AE Rep
9 Level & FDD Checking of WMM Top Layer in MCW 316+300 316+650 RHS WMM Top 350 VRC-SP/NH71/HW-9099 28-Jun-22 22 Checked by AE Rep
10 Level & FDD Checking of WMM Top Layer in MCW 339+017 339+370 RHS WMM Top 353 VRC-SP/NH71/HW-9053 26-Jun-22 22

11 Level & FDD Checking of WMM Top Layer in MCW 321930 322+100 RHS WMM Top 170 VRC-SP/NH71/HW-8714 23-May-22 21

12 Level & FDD Checking of WMM Top Layer in MCW 322+300 322+350 RHS WMM Top 50 VRC-SP/NH71/HW-8579 14-May-22 24

13 Level & FDD Checking of WMM Top Layer in MCW 322+460 322+475 RHS WMM Top 14.6 VRC-SP/NH71/HW-8579 (A) 14-May-22 NCR 350 TO 460

14 Level & FDD Checking of WMM Top Layer in MCW 322494 322+500 RHS WMM Top 6.500 VRC-SP/NH71/HW-6639 21-Oct-21 15
15 Level & FDD Checking of WMM Top Layer in MCW 322500 322+700 RHS WMM Top 200.000 VRC-SP/NH71/HW-6720 30-Oct-21 15 Checked by AE Rep.

16 Level & FDD Checking of WMM Top Layer in MCW 322+700 322+800 RHS WMM Top 100 VRC-SP/NH71/HW-8026 9-Mar-22 25 Checked by AE Rep.
17 Level & FDD Checking of WMM Top Layer in MCW 322800 323+000 RHS WMM Top 200.000 VRC-SP/NH71/HW-5454 11-Jul-21 15 Checked by AE Rep.
18 Level & FDD Checking of WMM Top Layer in MCW 328470 328560 RHS WMM Top 90.000 VRC-SP/NH71/HW-596 27-Sep-20 17
19 Level & FDD Checking of WMM Top Layer in MCW 328560 328710 RHS WMM Top 150.000 VRC-SP/NH71/HW-9161 1-Jul-22 23 Checked by AE Rep.
20 Laying & FDD checking of WMM top layer W-02 328710 328+854 RHS WMM Top 144.000 VRC -SP/NH-71/Hw-9482 30-Aug-22 24 Checked by AE Rep.
21 Laying & FDD checking of WMM Top layer W-04 328863 329+178 RHS WMM Top 315.000 VRC -SP/NH-71/Hw-9725 11-Nov-22 27 Checked by AE Rep.
22 Laying & FDD checking of WMM Top layer W-04 329186 329+432 RHS WMM Top 246.000 VRC -SP/NH-71/Hw-9596 24-Sep-22 25
23 Level & FDD Checking of WMM Top Layer in MCW 329+432 329+870 RHS WMM Top 438.000 VRC-SP/NH71/HW-7909 26-Feb-22 18 Checked by AE Rep.
24 Level & FDD Checking of WMM Top Layer in MCW 329870 330+110 RHS WMM Top 240.000 VRC-SP/NH71/HW-3724 24-Mar-21 15
25 Laying & FDD checking of WMM top layer W-02 330430 330+826 RHS WMM Top 396.000 VRC -SP/NH-71/Hw-9394 21-Aug-22 24 Checked by AE Rep.
26 Laying & FDD checking of WMM Top layer W-04 330834 331+050 RHS WMM Top 216.000 VRC -SP/NH-71/Hw-9391 20-Aug-22 24 Checked by AE Rep.
27 Laying & FDD checking of WMM Top layer W-04 331050 331+096 RHS WMM Top 46.000 VRC -SP/NH-71/Hw-9391 20-Aug-22 34 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
28 Level & FDD Checking of WMM Top Layer in MCW 335580 335830 RHS WMM Top 250.000 VRC-SP/NH-71/HW-9912 25-Dec-22 30 Checked by AE Rep.
29 Level & FDD Checking of WMM Top Layer in MCW 335830 336+120 RHS WMM Top 290.000 VRC-SP/NH71/HW-9317 24-Jul-22 23 Checked by AE Rep.
30 Level and FDD Checking of WMM Top Layer 336120 336135 RHS WMM Top 15.000 VRC-SP/NH-71/HW-7410 4-Jan-22 17
31 Level & FDD Checking of WMM Top Layer in MCW 336135 336+400 RHS WMM Top 265.000 VRC-SP/NH-71/HW-6692 27-Oct-21 15 Checked by AE Rep.
32 Level & FDD Checking of WMM Top Layer in MCW 336400 336+710 RHS WMM TOP 310.000 VRC-SP/NH71/HW-346 7-Sep-20 15
33 Level & FDD Checking of WMM Top Layer in MCW 338+430 338+490 RHS WMM TOP 60.000 VRC -SP/NH-71/HW-4655 17-May-22 16

34 Level and FDD Checking of WMM Top Layer W-2 338+490 339+012 RHS WMM TOP 522.000 VRC -SP/NH-71/Hw-8021 08-Mar-22 19 Checked by AE Rep.

35 Laying & FDD checking of WMM Top layer W-4 339+024 339+370 RHS WMM TOP 346.000 VRC -SP/NH-71/Hw-8214 9-Apr-22 20 Checked by AE Rep.

36 Level & FDD Checking of WMM Top Layer in MCW 339370 339+580 RHS WMM TOP 210.000 VRC -SP/NH-71/HW-6807 19-Nov-21 17 Checked by AE Rep.
37 Level & FDD Checking of WMM Top Layer in MCW 343380 343+760 RHS WMM Top 380.000 VRC-SP/NH-71/HW-10558 31-May-23 33 Checked by AE Rep.
38 Level & FDD Checking of WMM Top Layer in MCW 344290 344520 RHS WMM Top 230 VRC-SP/NH-71/HW-10479 30-Mar-23 31 Checked by AE Rep.
39 Level & FDD Checking of WMM Top Layer in MCW 344520 344680 RHS WMM Top 160 VRC-SP/NH-71/HW-10494 2-Apr-23 32 Checked by AE Rep.
40 Level & FDD Checking of WMM Top Layer in MCW 345810 346+500 RHS WMM Top 490.000 VRC-SP/NH-71/HW-10056 18-Jan-23 29 200M Length NCR
41 Level & FDD Checking of WMM Top Layer in MCW 346000 346200 RHS WMM Top 200 VRC-SP/NH-71/HW-10110 28-Jan-23 31 Checked by AE Rep.
42 Level & FDD Checking of WMM Top Layer in MCW 346500 347+120 RHS WMM Top 620.000 VRC-SP/NH-71/HW-10057 18-Jan-23 29
43 Level & FDD Checking of WMM Top Layer in MCW 352+900 353+300 RHS WMM TOP 400 VRC-SP/NH-71/HW-8097 23-Mar-22 19 Checked by AE Rep.

44 Level & FDD Checking of WMM Top Layer in MCW 353300 353710 RHS WMM Top 410 VRC-SP/NH-71/HW-10475 30-Mar-23 31 Checked by AE Rep.
45 Level & FDD Checking of WMM Top Layer in MCW 323+870 324+278 RHS WMM TOP 408 12 Checked by AE Rep.

46 Level & FDD Checking of WMM Top Layer in MCW 324+296 324+720 RHS WMM TOP 424.25 12
47 Level & FDD Checking of WMM Top Layer in MCW 324+734 325+130 RHS WMM TOP 396 12 Checked by AE Rep.
0
Total Qty RHS 11810.490 m B
Total Qty (Both Side) 11.597 Km. (A+B)/2000
Previous Qty. (Both Side) 11.597 Km.
Net Payable Qty (Both Side) 0.000 Km.
Bituminous Base Course
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
(MTR)
From To
1 Level Checking of DBM Top Layer in MCW 308+350 308+490 LHS DBM Top 140.00 VRC-SP/NH71/HW-7930 27-Feb-22 18
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)

2 Level Checking of DBM Top Layer in MCW 308+490 308+802 LHS DBM Top 311.52 VRC-SP/NH71/HW-9239 19-Jul-22 23 Checked by AE Rep.

3 Level Checking of DBM Top Layer in MCW 308+820 309+200 LHS DBM Top 379.58 VRC-SP/NH71/HW-9709 5-Nov-22 27 Checked by AE Rep.

4 Level Checking of DBM Top Layer in MCW 309+200 309+400 LHS DBM Top 200.00 VRC-SP/NH71/HW-7962 28-Feb-22 27 Checked by AE Rep.

5 Level Checking of DBM Top Layer in MCW 315+620 316+153 LHS DBM Top 532.52 VRC-SP/NH71/HW-10287 20-Feb-23 30 Checked by AE Rep.

6 Level Checking of DBM Top Layer in MCW 316+171 316+550 LHS DBM Top 378.58 VRC-SP/NH71/HW-10309 22-Feb-23 30 Checked by AE Rep.

7 Level Checking of DBM Top Layer in MCW 316+550 316+650 LHS Top 100.00 VRC-SP/NH71/HW-8284 18-Apr-22
20
Checked by AE Rep.

8 Level Checking of DBM Top Layer in MCW 321+930 322+300 LHS DBM Top 370.00 VRC-SP/NH71/HW-9576 19-Sep-22
30
Checked by AE Rep.

9 Level Checking of DBM Top Layer in MCW 322+300 322+480 LHS DBM Top 180.10 VRC-SP/NH71/HW-8014 7-Mar-22 19 Checked by AE Rep.

10 Level Checking of DBM Top Layer in MCW 322+492 323+000 LHS DBM Top 508.00 VRC-SP/NH71/HW-8036 10-Mar-22 19
11 Level Checking of DBM Top Layer in MCW 323+870 324+278 LHS DBM 408.00 VRC -SP/NH-71/HW-3583 20-Mar-21 12 Checked by AE Rep.
12 Level Checking of DBM Top Layer in MCW 324+296 324+720 LHS DBM 424.25 VRC -SP/NH-71/HW-6173 26-Aug-21 12
13 Level Checking of DBM Top Layer in MCW 324+734 325+200 LHS DBM 466.00 VRC -SP/NH-71/HW-4474 7-May-21 12 Checked by AE Rep.
14 Checking Laying of DBM Top Layer 328+470 328+843 LHS Top 373.00 VRC -SP/NH-71/Hw-10088 25-Jan-23 29 Checked by AE Rep.
15 Checking Laying of DBM Top Layer 328+851 329+432 LHS Top 581.00 VRC -SP/NH-71/Hw-10089 25-Jan-23 29 Checked by AE Rep.
16 Level Checking of DBM Top Layer in MCW 329+432 329+870 LHS DBM 438.00 VRC -SP/NH-71/HW-7972 28-Feb-22 18
17 Level Checking of DBM Top Layer in MCW 329+870 330+110 LHS Top 240.00 VRC-SP/NH-71/HW-3580 20-Mar-21 15
18 Checking Laying of DBM Top Layer 330+430 330+821 LHS Top 391.00 VRC -SP/NH-71/Hw-10126 31-Jan-23 29 Checked by AE Rep.
19 Spraying of tack coat & laying of DBM Top layer W-03 330+829 331+140 LHS Top 311.00 VRC -SP/NH-71/Hw-9433 27-Aug-22 24
20 Checking Laying of DBM Top Layer 335+580 335+850 LHS Top 270.00 VRC-SP/NH-71/HW-9961 29-Dec-22 29
21 Checking Laying of DBM Top Layer 335+850 336+120 LHS Top 270.00 VRC-SP/NH-71/HW-9897 24-Dec-22 28 Checked by AE Rep.
22 Level Checking of DBM Top Layer in MCW 336+120 336+500 LHS Top 380.00 VRC-SP/NH-71/HW-7670 31-Jan-22 17 Checked by AE Rep.
23 Level Checking of DBM Top Layer in MCW 336+500 336+710 LHS Top 210.00 VRC-SP/NH-71/HW-4842 30-May-21 15 Checked by AE Rep.
24 Level and level Checking of DBM Top Layer W-1 338+430 338+490 LHS Top 60.00 VRC -SP/NH-71/Hw-8331 21-Apr-22 20
25 Level and level Checking of DBM Top Layer W-1 338+490 339+005 LHS Top 515.00 VRC -SP/NH-71/Hw-8109 24-Mar-22 19
26 Checking Laying of DBM Top Layer 339+017 339+580 LHS Top 563.00 VRC -SP/NH-71/Hw-10119 30-Jan-23 29 Checked by AE Rep.
27 Checking Laying of DBM Top Layer 345+810 346+140 LHS Top 330.00 VRC-SP/NH-71/HW-10877 27-Aug-23 36 Checked by AE Rep.
28 Checking Laying of DBM Top Layer 346+140 347+030 LHS Top 890.00 VRC-SP/NH-71/HW-10133 31-Jan-23 29 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)

29 Checking Laying of DBM Top Layer 347+030 347+120 LHS Top 90.00 VRC-SP/NH-71/HW-5226 27-Jun-21 16
30 Checking Laying of DBM Top Layer 352+900 353+300 LHS Top 400.00 VRC-SP/NH-71/HW-8124 25-Mar-22 19 Checked by AE Rep.
31 Checking Laying of DBM Top Layer 353+300 353+710 LHS Top 410.00 VRC-SP/NH-71/HW-10560 31-May-23 33 Checked by AE Rep.
0
Total Qty LHS 11120.550 m
0 0

1 Checking of DBM Top Layer in MCW 308+350 308+805 RHS DBM Top 455.00 VRC-SP/NH71/HW-7967 28-Feb-22 18

2 Level Checking of DBM Top Layer in MCW 308+820 309+200 RHS DBM Top 380.00 VRC-SP/NH71/HW-9239 23-Jul-22 23 Checked by AE Rep.

3 Level Checking of DBM Top Layer in MCW 309+200 309+370 RHS DBM Top 170.00 VRC-SP/NH71/HW-9193 8-Jul-22 25 Checked by AE Rep.

4 Level Checking of DBM Top Layer in MCW 309+370 309+400 RHS DBM Top 30.00 VRC-SP/NH71/HW-10335 25-Feb-23 30

5 Level Checking of DBM Top Layer in MCW 315+620 316+153 RHS DBM Top 532.58 VRC-SP/NH71/HW-10325 24-Feb-23 30

6 Level Checking of DBM Top Layer in MCW 316+171 316+650 RHS DBM Top 478.52 VRC-SP/NH71/HW-9494 31-Aug-22 24 Checked by AE Rep.

7 Level Checking of DBM Top Layer in MCW 321+930 322+300 RHS DBM Top 370.00 VRC-SP/NH71/HW-10361 28-Feb-23 30

8 Level Checking of DBM Top Layer in MCW 322+300 322+350 RHS DBM Top 50.00 VRC-SP/NH71/HW-8926 16-Jun-22 24 Checked by AE Rep.

9 Level Checking of DBM Top Layer in MCW 322+350 322+465 RHS DBM Top 115.10 VRC-SP/NH71/HW-8926(A) 16-Jun-22 27 Checked by AE Rep.

10 Checking Laying of DBM Top Layer 322+484 322+800 RHS DBM Top 316.00 VRC-SP/NH71/HW-8034 10-Mar-22 19

11 Level Checking of DBM Top Layer in MCW 322+800 323+000 RHS DBM Top 200.00 VRC-SP/NH71/HW-7677 31-Jan-22 17
12 Laying of DBM Layer 323+870 324+278 RHS DBM 408.00 VRC -SP/NH-71/HW-3584 20-Mar-21 12 Checked by AE Rep.
13 Laying of DBM Layer 324+296 324+720 RHS DBM 424.25 VRC -SP/NH-71/HW-6170 25-Aug-21 12
14 Laying of DBM Layer 324+734 325+200 RHS DBM 466.00 VRC -SP/NH-71/HW-4475 7-May-21 12
15 Checking Laying of DBM Top Layer 328+470 328+854 RHS Top 384.00 VRC -SP/NH-71/Hw-10084 24-Jan-23 29 Checked by AE Rep.
16 Checking Laying of DBM Top Layer 328+863 329+432 RHS Top 569.00 VRC -SP/NH-71/Hw-10085 24-Jan-23 29 Checked by AE Rep.
17 Checking Tack coat spraying & DBM Top Layer in MCW 329+432 329+870 RHS Top 438.00 VRC -SP/NH-71/Hw-8093 23-Mar-22 19
18 Checking Laying of DBM Top Layer 329+870 330+110 RHS Top 240.00 VRC -SP/NH-71/HW-4722 21-May-21 15
19 Checking Laying of DBM Top Layer 330+430 330+826 RHS Top 396.00 VRC -SP/NH-71/Hw-10125 31-Jan-23 29 Checked by AE Rep.
20 Checking Laying of DBM Top Layer 330+834 331+140 RHS Top 306.00 VRC -SP/NH-71/Hw-10127 31-Jan-23 29 Checked by AE Rep.
21 Checking Laying of DBM Top Layer 335+580 335+830 RHS Top 250.00 VRC-SP/NH-71/HW-9960 29-Dec-22 29
22 Checking Laying of DBM Top Layer 335+830 336+120 RHS Top 290.00 VRC-SP/NH-71/HW-9898 24-Dec-22 28 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)
23 Checking Laying of DBM Top Layer 336+120 336+500 RHS Top 380.00 VRC-SP/NH-71/HW-7687 31-Jan-22 17
24 Checking Laying of DBM Top Layer 336+500 336+710 RHS Top 210.00 VRC-SP/NH-71/HW-4844 30-May-21 15 Checked by AE Rep.
25 Level and level Checking of DBM Top Layer W-2 338+430 338+490 RHS Top 60.00 VRC -SP/NH-71/Hw-8332 21-Apr-22 20
26 Level and level Checking of DBM Top Layer W-2 338+490 339+012 RHS Top 522.00 VRC -SP/NH-71/Hw-8107 24-Mar-22 19
27 Level and level Checking of DBM Top Layer W-4 339+024 339+580 RHS Top 556.00 VRC -SP/NH-71/Hw-8389 24-Apr-22 20 Checked by AE Rep
28 Checking Laying of DBM Top Layer 352+900 353+300 RHS Top 400 VRC-SP/NH-71/HW-8125 25-Mar-22 19 Checked by AE Rep.
29 Checking Laying of DBM Top Layer 353+300 353+710 RHS Top 410 VRC-SP/NH-71/HW-10561 31-May-23 33

Total Qty RHS 9806.450 m


Total Qty (Both Side) 10.4635 Km.
Previous Qty. (Both Side) 10.4635 Km.
Net Payable Qty (Both Side) 0.0000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01-09-2023 30-09-2023
SPS No.-37
B2- New Underpasses/ Overpasses
0
MEASUREMENT SHEET Earthwork
Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (MTR)

Wearing Course
Quantity
Sl. No. Description Chainage Side Layer No. RFI No. Date SPS No. Remarks
(MTR)
1 Level Checking of BC Layer in MCW 321+930 322+470 LHS BC Top 540 VRC-SP/NH-71/HW-10889 3-Sep-23 37

2 Level Checking of BC Layer in MCW 322+470 323+010 LHS BC Top 540 VRC-SP/NH-71/HW-10894 6-Sep-23 37
Total Qty LHS 9020.000 m 37
1 Level Checking of BC Layer in MCW 321930 322+500 RHS BC Top 570 VRC-Sp/NH-71/HW-10904 9-Sep-23 37
2 Level Checking of BC Layer in MCW 322500 323+010 RHS BC Top 510 VRC-Sp/NH-71/HW-10900 8-Sep-23 37

Total Qty RHS 9120.000 m


Total Qty (Both Side) 9.0700 Km.
Previous Qty. (Both Side) 7.9900 Km. 0
Net Payable Qty (Both Side) 1.0800 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of
NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of
Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA


Contractor : M/s VRC-SPIDPL (JV)
Authority's Engineer : M/s ICT Private Limited in association with VESPL
SPS No.-37

Reinforced Earth Panel Erection

Quantity
Descriptions Unit Remarks
(Erection)

a As per Cost Estimate Scope Quantity of RE Panel Sqm 85232

b As per Schedule-H Scope Quantity Nos. 14

c Work Done Quantity of RE Panel Sqm 84337

d Work Done Quantity of RE Panel Nos. 13.85 d = (b x c) / a

Friction Slab Crash Barrier

a As per Cost Estimate Scope Quantity of Friction Slab Crash Barrier Rm 20199

b As per Schedule-H Scope Quantity Rm 14

c Work Done Quantity of Friction Slab Crash Barrier Rm 15974

d Work Done Quantity of Friction Slab Crash Barrier Nos 11.07 d = (b x c) / a


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
Checking Shuttering, Level and Concrete Pouring for
1 308+490 308+550 145.390 VRC-SP/NH-71/STR-7454 7/22/2021 15 Checked by AE Rep.
Copping Wall GA-01

2 Checking Shuttering & Concrete Pouring for Coping 308+490 308+550 145.390 4-Jan-22 17 Checked by AE Rep.
for RE Wall GA-02 VRC-SP/NH-71/STR-8869
Checking Shuttering, Level and Concrete Pouring for
3 308+550 308+600 193.062 VRC-SP/NH-71/STR-7474 7/23/2021 15
Copping Wall GA-01

4 Checking Shuttering & Concrete Pouring for Coping 308+550 308+600 193.062 5-Jan-22 17
for RE Wall GA-02 VRC-SP/NH-71/STR-8886
Checking Shuttering, Level and Concrete Pouring for
5 308+600 308+650 225.751 VRC-SP/NH-71/STR-7490 7/24/2021 15 Checked by AE Rep.
Copping Wall GA-01

6 Checking Shuttering & Concrete Pouring for Coping 308+600 308+650 225.751 6-Jan-22 17 Checked by AE Rep.
for RE Wall GA-02 VRC-SP/NH-71/STR-8899
Checking Shuttering, Level and Concrete Pouring for
7 308+650 308+700 251.144 VRC-SP/NH-71/STR-7636 8/4/2021 15
Copping Wall GA-01

8 Checking Shuttering & Concrete Pouring for Coping 308+650 308+700 251.203 7-Jan-22 17
for RE Wall GA-02 VRC-SP/NH-71/STR-8908
Checking Shuttering, Level and Concrete Pouring for
9
Copping Wall GA-01
308+700 308+750 269.356 VRC-SP/NH-71/STR-7645 8/5/2021 17

10 Checking Shuttering & Concrete Pouring for Coping 308+700 308+750 269.356 18-Jan-22 17 Checked by AE Rep.
for RE Wall GA-02 VRC-SP/NH-71/STR-9022
Checking Shuttering, Level and Concrete Pouring for
11 308+750 308+805 308.563 VRC-SP/NH-71/STR-7656 8/6/2021 15 Checked by AE Rep.
Copping Wall GA-01

12 Checking Shuttering & Concrete Pouring for Coping 308+750 308+800 280.223 19-Jan-22 17
for RE Wall GA-02 VRC-SP/NH-71/STR-9029
13 Checking Shuttering & Concrete Pouring for Coping 308+800 308+805 28.340 20-Jan-22 17 Checked by AE Rep.
for RE Wall GA-02 VRC-SP/NH-71/STR-9040
14 Checking Shuttering & Concrete Pouring for Coping 308+816 308+960 857.502 27-Jan-22 17 Checked by AE Rep.
for RE Wall GA-03 VRC-SP/NH-71/STR-9099
15 Checking Shuttering & Concrete Pouring for Coping for 308+816 309+200 1714.533 27-Feb-22 18 Checked by AE Rep.
RE Wall GA-04 VRC-SP/NH-71/STR-9315
16 Checking Shuttering & Concrete Pouring for Coping 308+960 309+200 857.200 28-Jan-22 17
for RE Wall GA-03 VRC-SP/NH-71/STR-9112
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)

17 Checking Shuttering & Concrete Pouring for Coping 315+788 315+800 21.944 2-Jan-22 17 Checked by AE Rep.
for RE Wall GA-01 VEC-SP/NH-/STR-8841
18 Checking Shuttering & Concrete Pouring for Coping 315+788 315+870 204.690 28-Jan-22 17
for RE Wall GA-02 VEC-SP/NH-/STR-9114
19 Checking Shuttering & Concrete Pouring for Coping 315+800 315+900 287.480 3-Jan-22 17 Checked by AE Rep.
for RE Wall GA-01 VEC-SP/NH-/STR-8852
20 Checking Shuttering & Concrete Pouring for Coping for 315870 316156.02 1507.611 25-May-22 21
RE Wall GA-02 VEC-SP/NH-/STR-10127
21 Checking Shuttering & Concrete Pouring for Coping 315+900 316+156 1402.877 26-Apr-22 20
for RE Wall GA-01 VEC-SP/NH-/STR-9801
22 Checking Shuttering & Concrete Pouring for Coping for 316167 316430 1209.607 25-May-22 21
RE Wall GA-03 VEC-SP/NH-/STR-10128
23 Checking Shuttering & Concrete Pouring for Coping 316167.98 316509.55 1439.611 30-Jun-22 22 Checked by AE Rep
for RE Wall GA-04 VRC-SP/NH-71/STR-10533
24 Checking Shuttering & Concrete Pouring for Coping 316+430 316+510 230.004 16-Nov-21 17 Checked by AE Rep.
for RE Wall GA-03 VRC-SP/NH-71/STR-8400
25 Checking Shuttering & Concrete Pouring for Coping 322+050 322+100 108.546 5-Jan-22 17
for RE Wall GA-02 VRC-SP/NH-71/STR-8880
Checking Shuttering & Concrete Pouring for Coping
26 322+100 322+150 149.596 VRC-SP/NH-71/STR-8863 4-Jan-22 17 Checked by AE Rep.
for RE Wall GA-02
Checking Shuttering & Concrete Pouring for Coping
27 322+110 322+150 47.630 VRC-SP/NH-71/STR-8838 2-Jan-22 17 Checked by AE Rep.
for RE Wall GA-01
Checking Shuttering & Concrete Pouring for Coping
28 322+160 322+330 646.214 VRC-SP/NH-71/STR-8838 2-Jan-22 17 Checked by AE Rep.
for RE Wall GA-01
Checking Shuttering & Concrete Pouring for Coping
29 322+160 322+210 209.497 VRC-SP/NH-71/STR-8863 4-Jan-22 17 Checked by AE Rep.
for RE Wall GA-02
30 Checking Shuttering & Concrete Pouring for Coping 322+210 322+255 198.360 27-Dec-21 17
for RE Wall
Checking GA-02 & Concrete Pouring for Coping
Shuttering VRC-SP/NH-71/STR-8739
31 for RE Wall GA-02 322+255 322+300 280.244 VRC-SP/NH-71/STR-8757 28-Dec-21 17 Checked by AE Rep.

32 Checking Shuttering & Concrete Pouring for Coping 322+300 322+350 308.925 29-Dec-21 17
for RE Wall GA-02 VRC-SP/NH-71/STR-8779
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)

33 Checking Shuttering & Concrete Pouring for Coping 322+330 322+471 763.533 17-Dec-21 17
for RE Wall GA-01 VRC-SP/NH-71/STR-8615
34 Checking Shuttering & Concrete Pouring for Coping 322+350 322+400 329.625 30-Dec-21 17 Checked by AE Rep.
for RE Wall GA-02 VRC-SP/NH-71/STR-8796
35 Checking Shuttering & Concrete Pouring for Coping 322+400 322+450 342.476 31-Dec-21 17
for RE Wall GA-02 VRC-SP/NH-71/STR-8813
36 Checking Shuttering & Concrete Pouring for Coping 322+450 322+480 208.643 1-Jan-22 17 Checked by AE Rep.
for RE Wall GA-02 VRC-SP/NH-71/STR-8829
Checking Shuttering, Level and Concrete Pouring for
37 322+484 322+500 149.902 VRC-SP/NH-71/STR-7316 7/12/2021 15
Copping Wall GA-03
Checking Shuttering, Level and Concrete Pouring for
38 322+492 322+500 119.385 VRC-SP/NH-71/HW-7491 7/24/2021 15 Checked by AE Rep.
Copping Wall GA-04
Checking Shuttering, Level and Concrete Pouring for
39 322+500 322+550 284.433 VRC-SP/NH-71/STR-7303 7/11/2021 15 Checked by AE Rep.
Copping Wall GA-03
Checking Shuttering, Level and Concrete Pouring for
40 322+500 322+550 330.544 VRC-SP/NH-71/STR-7455 7/22/2021 15
Copping Wall GA-04
Checking Shuttering, Level and Concrete Pouring for
41 322+550 322+600 272.195 VRC-SP/NH-71/STR-7287 7/10/2021 15
Copping Wall GA-03
Checking Shuttering, Level and Concrete Pouring for
42 322+550 322+600 318.234 VRC-SP/NH-71/STR-7391 7/17/2021 15 Checked by AE Rep.
Copping Wall GA-04
Checking Shuttering, Level and Concrete Pouring for
43 322+600 322+650 252.147 VRC-SP/NH-71/STR-7269 7/9/2021 15 Checked by AE Rep.
Copping Wall GA-03
Checking Shuttering, Level and Concrete Pouring for
44 322+600 322+650 298.185 VRC-SP/NH-71/STR-7286 7/10/2021 15
Copping Wall GA-04
Checking Shuttering, Level and Concrete Pouring for
45 322+650 322+700 200.302 VRC-SP/NH-71/STR-7249 7/8/2021 15
Copping Wall GA-03
Checking Shuttering, Level and Concrete Pouring for
46 322+650 322+700 260.136 VRC-SP/NH-71/STR-7268 7/9/2021 15 Checked by AE Rep.
Copping Wall GA-04
Checking Shuttering, Level and Concrete Pouring for
47 322+700 322+750 154.412 VRC-SP/NH-71/STR-7239 7/7/2021 15 Checked by AE Rep.
Copping Wall GA-03
Checking Shuttering, Level and Concrete Pouring for
48 322+700 322+750 200.704 VRC-SP/NH-71/STR-7248 7/8/2021 15
Copping Wall GA-04
Checking Shuttering, Level and Concrete Pouring for
49 322+750 322+800 92.843 VRC-SP/NH-71/STR-7204 7/5/2021 15
Copping Wall GA-03
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
Checking Shuttering, Level and Concrete Pouring for
50 322+750 322+800 157.475 VRC-SP/NH-71/STR-7238 7/7/2021 15 Checked by AE Rep.
Copping Wall GA-04
Checking Shuttering, Level and Concrete Pouring for
51 322+800 322+850 95.522 VRC-SP/NH-71/STR-7203 7/5/2021 15
Copping Wall GA-04
Left quantity of Pouring of Concrete in Coping beam for RE
52 323+930 325+130 1959.000 VRC -SP/NH-71/Str-9402 3/10/2022 19 Checked by AE Rep.
Wall No. W1,2,3,4,5 &6
53 Pouring of Concrete in Coping beam for RE Wall No. W1 323+930 323+970 69.316 VRC -SP/NH-71/HW-2264 1/19/2021 5 Checked by AE Rep.

54 Pouring of Concrete in Coping beam for RE Wall No. W2 323+930 324+010 163.069 VRC -SP/NH-71/HW-2440 1/24/2021 5 Checked by AE Rep.

55 Pouring of Concrete in Coping beam for RE Wall No. W1 323+970 324+010 93.753 VRC -SP/NH-71/HW-2305 1/20/2021 5 Checked by AE Rep.

56 Pouring of Concrete in Coping beam for RE Wall No. W1 324+010 324+050 116.938 VRC -SP/NH-71/HW-2325 1/21/2021 5 Checked by AE Rep.

57 Pouring of Concrete in Coping beam for RE Wall No. W2 324+010 324+050 115.245 VRC -SP/NH-71/HW-2466 1/25/2021 5

58 Pouring of Concrete in Coping beam for RE Wall No. W1 324+050 324+090 160.724 VRC -SP/NH-71/HW-2360 1/22/2021 5

59 Pouring of Concrete in Coping beam for RE Wall No. W2 324+050 324+130 293.603 VRC -SP/NH-71/HW-2530 1/28/2021 5 Checked by AE Rep.

60 Pouring of Concrete in Coping beam for RE Wall No. W1 324+090 324+180 433.691 VRC -SP/NH-71/HW-2407 1/23/2021 5 Checked by AE Rep.

61 Pouring of Concrete in Coping beam for RE Wall No. W2 324+130 324+200 382.858 VRC -SP/NH-71/HW-2628 2/2/2021 5

62 Pouring of Concrete in Coping beam for RE Wall No. W1 324+180 324+240 326.553 VRC -SP/NH-71/HW-2626 2/2/2021 5 Checked by AE Rep.

63 Pouring of Concrete in Coping beam for RE Wall No. W2 324+200 324+250 277.079 VRC -SP/NH-71/HW-2657 2/3/2021 5 Checked by AE Rep.

64 Pouring of Concrete in Coping beam for RE Wall No. W1 324+240 324+282 215.147 VRC -SP/NH-71/HW-2655 2/3/2021 5

65 Pouring of Concrete in Coping beam for RE Wall No. W2 324+250 324+284 197.562 VRC -SP/NH-71/HW-2691 2/4/2021 5 Checked by AE Rep.

66 Pouring of Concrete in Coping beam for RE Wall No. W3 324+289 324+350 358.628 VRC -SP/NH-71/STR-5294 3/19/2021 7 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)

67 Pouring of Concrete in Coping beam for RE Wall No. W4 324+296 324+350 319.284 VRC -SP/NH-71/STR-5296 3/19/2021 7 Checked by AE Rep.

68 Pouring of Concrete in Coping beam for RE Wall No. W3 324+350 324+600 1564.872 VRC -SP/NH-71/STR-5314 3/20/2021 7 Checked by AE Rep.

69 Pouring of Concrete in Coping beam for RE Wall No. W4 324+350 324+600 1564.887 VRC -SP/NH-71/STR-5316 3/20/2021 7 Checked by AE Rep.

70 Pouring of Concrete in Coping beam for RE Wall No. W3 324+600 324+722 651.871 VRC -SP/NH-71/STR-5336 3/21/2021 7

71 Pouring of Concrete in Coping beam for RE Wall No. W4 324+600 324+722 651.871 VRC -SP/NH-71/STR-5338 3/21/2021 7 Checked by AE Rep.

72 Pouring of Concrete in Coping beam for RE Wall No. W5 324+731 324+850 558.140 VRC -SP/NH-71/STR-5275 3/18/2021 7 Checked by AE Rep.

73 Pouring of Concrete in Coping beam for RE Wall No. W6 324+731 324+850 551.331 VRC -SP/NH-71/STR-5113 3/9/2021 7 Checked by AE Rep.

74 Pouring of Concrete in Coping beam for RE Wall No. W5 324+850 324+950 420.442 VRC -SP/NH-71/STR-5298 3/19/2021 7 Checked by AE Rep.

75 Pouring of Concrete in Coping beam for RE Wall No. W6 324+850 324+900 220.872 VRC -SP/NH-71/STR-5132 3/10/2021 7 Checked by AE Rep.

76 Pouring of Concrete in Coping beam for RE Wall No. W6 324+900 325+000 376.163 VRC -SP/NH-71/STR-5252 3/17/2021 7 Checked by AE Rep.

77 Pouring of Concrete in Coping beam for RE Wall No. W5 324+950 325+130 485.347 VRC -SP/NH-71/STR-5318 3/20/2021 7

78 Pouring of Concrete in Coping beam for RE Wall No. W6 325+000 325+050 156.997 VRC -SP/NH-71/STR-5273 3/18/2021 7 Checked by AE Rep.

79 Pouring of Concrete in Coping beam for RE Wall No. W6 325+050 325+130 160.822 VRC -SP/NH-71/STR-5300 3/19/2021 7 Checked by AE Rep.
Checking erection of RE Wall upto coping beam RE Wall
80 328+510 328+740 787.217 VRC -SP/NH-71/STR-8699 12/24/2021 16 Checked by AE Rep.
no.02
Checking erection of RE Wall upto coping beam RE Wall
81 328+530 328+700 365.991 VRC -SP/NH-71/STR-8690 12/23/2021 16 Checked by AE Rep.
no.01
Erection of RE wall below 1 mtr from coping beam RE Wall
82 328+700 328+843 549.248 VRC -SP/NH-71/STR-8691 12/23/2021 16 Checked by AE Rep.
no.01
Checking erection of RE Wall upto coping beam RE Wall
83 328+740 328+854 577.302 VRC -SP/NH-71/STR-8700 12/24/2021 16
no.02
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)

84 Pouring of Concrete in Coping beam for RE Wall No. W3 328+851 329+000 742.40 VRC -SP/NH-71/Str-10269 6/6/2022 22 Checked by AE Rep

Checking erection of RE Wall upto coping beam RE Wall


85 329+000 329+200 1643.310 VRC -SP/NH-71/STR-8717 12/25/2021 16 Checked by AE Rep.
no.03
Checking erection of RE Wall upto coping beam RE Wall
86 329+200 329+444 1540.045 VRC -SP/NH-71/STR-8718 12/25/2021 16 Checked by AE Rep.
no.03
87 Pouring of Concrete in Coping beam for RE Wall No. W5 329+455 329+870 1601.721 VRC -SP/NH-71/STR-6532 10/3/2021 15 Checked by AE Rep.

88 Pouring of Concrete in Coping beam for RE Wall No. W6 329+455 329+870 1601.721 VRC -SP/NH-71/STR-6533 10/3/2021 15

89 Pouring of Concrete in Coping beam for RE Wall No. W1 330+430 330+715 VRC -SP/NH-71/Str-9507 3/24/2022 19 Checked by AE Rep.
627.523
Checking erection of RE Wall upto coping beam RE Wall
90 330+430 330+826 1758.282 VRC -SP/NH-71/STR-8758 12/28/2021 16 Checked by AE Rep.
no.02
91 Pouring of Concrete in Coping beam for RE Wall No. W1 330+715 330+821 731.12 VRC -SP/NH-71/Str-10246 6/3/2022 22 Checked by AE Rep

92 Pouring of Concrete in Coping beam for RE Wall No. W3 330+829 330+834 21.935 VRC -SP/NH-71/Str-9671 4/12/2022 20

93 Pouring of Concrete in Coping beam for RE Wall No. W3 330+834 330+900 350.021 VRC -SP/NH-71/STR-6543 10/5/2021 15 Checked by AE Rep.

94 Pouring of Concrete in Coping beam for RE Wall No. W4 330+834 330+900 324.658 VRC -SP/NH-71/STR-6544 10/5/2021 15

95 Pouring of Concrete in Coping beam for RE Wall No. W3 330+900 331+140 775.660 VRC -SP/NH-71/Str-9680 4/13/2022 20 Checked by AE Rep.

96 Pouring of Concrete in Coping beam for RE Wall No. W4 330+900 330+950 273.90 VRC -SP/NH-71/Str-9898 5/2/2022 21 Checked by AE Rep.

97 Pouring of Concrete in Coping beam for RE Wall No. W4 330+950 331+080 564.09 VRC -SP/NH-71/Str-10261 6/5/2022 22

98 Pouring of Concrete in Coping beam for RE Wall No. W4 331+080 331+140 VRC -SP/NH-71/Str-12507 6/1/2023 34 Qty Paid 1162.65 Sqm
Checking Erection of RE Wall No. W1 (below Copping top -
99 335+604 336+113 1318.336 VRC -SP/NH-71/STR-8384 10/30/2021 15
1.50 Mtr.)
100 Pouring of Concrete in Coping beam for RE Wall No. W1 335604 335836 887.67 VRC-SP/NH-71/STR-9878 4/30/2021 20 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
Checking Erection of RE Wall No. W2 (below Copping top
101 335+775 336+106 833.782 VRC -SP/NH-71/STR-8385 10/30/2021 15
- 1.50 Mtr.)
102 Pouring of Concrete in Coping beam for RE Wall No. W2 335775 335836 -162.00 VRC-SP/NH-71/STR-9879 4/30/2021 20 Checked by AE Rep.

103 Pouring of Concrete in Coping beam for RE Wall No.W2 335+836 336+113 372.283 VRC-SP/NH-71/STR-9034 1/19/2022 17

104 Pouring of Concrete in Coping beam for RE Wall No.W2 335+836 336+106 363.142 VRC-SP/NH-71/STR-9046 1/20/2022 17 Checked by AE Rep.

105 Pouring of Concrete in Coping beam for RE Wall No.W4 336+119 336+477 1599.070 VRC -SP/NH-71/STR-7539 7/27/2021 15

106 Pouring of Concrete in Coping beam for RE Wall No. W3 336+126 336+478 1842.540 VRC -SP/NH-71/STR-7565 7/29/2021 15 Checked by AE Rep.
107 Pouring of Concrete in Coping beam for RE Wall No. W2 338+550 338+633 200 VRC -SP/NH-71/Str-9374 3/8/2022 19 Checked by AE Rep.

108 Checking erection of RE Wall upto coping beam RE Wall no.01 338+610.000 338+652.000 3/9/2022 19 Checked by AE Rep.
90 VRC -SP/NH-71/Str-9391
Left quantity of Pouring of Concrete in Coping beam for RE 3/11/2022
109 Wall No. W-2 338+633 339+012 19
402.980 VRC -SP/NH-71/Str-9410
110 Pouring of Concrete in Coping beam for RE Wall No. W2 338+633 339+012 1758.320 VRC -SP/NH-71/STR-6545 10/5/2021 15 Checked by AE Rep.
Left quantity of Pouring of Concrete in Coping beam for RE VRC -SP/NH-71/Str-9411 3/11/2022 Checked by AE Rep.
111 Wall No. W-1 338+652.128 339+005.531 19
284.07
Checking erection of RE Wall upto coping beam RE Wall
112 338+652.128 339+005.531 1725.818 VRC -SP/NH-71/STR-8759 12/28/2021 16 Checked by AE Rep.
no.01
113 Coping beam R/F, Shuttering fixing & casting W-3 339+024 339+150 855.52 VRC -SP/NH-71/Str-9482 3/22/2022 19 Checked by AE Rep.

114 Checking erection of RE Wall upto coping beam Wall no-04 339+024 339+370 1157.976 VRC -SP/NH-71/Str-9086 1/25/2022 17 Checked by AE Rep.
115 Coping beam R/F, Shuttering fixing & casting W-3 339+150 339+260 564.36 VRC -SP/NH-71/Str-9471 3/21/2022 19 Checked by AE Rep.
116 Coping beam R/F, Shuttering fixing & casting W-3 339+260 339+300 153.32 VRC -SP/NH-71/Str-9464 3/16/2022 19 Checked by AE Rep.
117 Coping beam R/F, Shuttering fixing & casting W-3 339+300 339+370 195.61 VRC -SP/NH-71/Str-9456 3/15/2022 19
118 Checking Erection of RE Wall No. W2 343511 344040 651.30 VRC-SP/NH-71/STR-11165 27-Sep-22 25 Checked by AE Rep
Checking Erection of RE Wall No. W1 (below Copping top -
119
1.50 Mtr.)
343534 344061 1587.38 VRC-SP/NH-71/STR-10220 5/31/2022 21 Checked by AE Rep.
120 Checking Erection of RE Wall No. W2 343+590 344+542 870.000 VRC-SP/NH-71/STR-11900 1/30/2023 29
121 Checking Erection of RE Wall No. W2 343+590 344+542 649.690 VRC-SP/NH-71/STR-11950 2/6/2023 31 Checked by AE Rep
122 Checking Erection of RE Wall No. W4 344055 344521 591.44 VRC-SP/NH-71/STR-11166 27-Sep-22 25
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)

123 Checking Erection of RE Wall No. W4 344055 344521 1380.02 VRC-SP/NH-71/STR-11720 12/28/2022 28

124 Checking Erection of RE Wall No. W3 344076 344542 1197.99 VRC-SP/NH-71/STR-10704 7/31/2022 23 Checked by AE Rep.
125 Checking Erection of RE Wall No. W3 344076 344542 951.00 VRC-SP/NH-71/STR-10517 6/29/2022 22 Checked by AE Rep
126 Checking Erection of RE Wall No. W3 344076 344542 952.16 VRC-SP/NH-71/STR-11708 12/26/2022 28
127 Erection for RE Wall No.W1 346+131 346+230 225.286 VRC-SP/NH-71/STR-9106 1/25/2022 17 Checked by AE Rep.
128 Checking Erection of RE Wall No. W2 346134 346200 133.94 VRC-SP/NH-71/STR-10208 5/30/2022 21 Checked by AE Rep.
Checking Erection of RE Wall No. W2 (below Copping top -
129
1.50 Mtr.)
346200 346501 1076.48 VRC-SP/NH-71/STR-10208 5/30/2022 21 Checked by AE Rep.
130 Checking Erection of RE Wall No. W2 346200 346501 377.13 VRC-SP/NH-71/STR-10976 8/30/2022 24 Checked by AE Rep.
131 Erection for RE Wall No.W1(Upto 3M Hight) 346+230 346+450 562.078 VRC-SP/NH-71/STR-9088 1/27/2022 17 Checked by AE Rep.
132 Checking Erection of RE Wall No. W1 346260 346516 672.88 VRC-SP/NH-71/STR-10705 7/31/2022 23
133 Checking Erection of RE Wall No. W4 346514 346919 1754.17 VRC-SP/NH-71/STR-10457 6/26/2022 22
134 Checking Erection of RE Wall No. W3 346529 346945 712.73 VRC-SP/NH-71/STR-10456 6/26/2022 22 Checked by AE Rep
Checking Erection of RE Wall No. W3 (below Copping top
135 346+529 346+945 1007.123 VRC -SP/NH-71/STR-8267 10/19/2021 15
- 1.50 Mtr.)
136 Pouring of Concrete in Coping beam for RE Wall No. W1 352+965 353+298 1283.146 VRC-SP/NH-71/STR-7139 6/29/2021 15 Checked by AE Rep.

137 Pouring of Concrete in Coping beam for RE Wall No.W2 352+965 353+294 1260.569 VRC-SP/NH-71/STR-7108 6/27/2021 15
Pouring of Concrete in Coping beam for RE Wall No. W1
138 352965 353298 5.15 VRC-SP/NH-71/STR-10197 5/29/2022 21
(Balance Qty)
Pouring of Concrete in Coping beam for RE Wall No.W2
139 352965 353294 5.03 VRC-SP/NH-71/STR-10197 5/29/2022 21
(Balance Qty)
Checking Erection of RE Wall No. W4 (below Copping top
140 353+302 353+630 713.108 VRC-SP/NH-71/STR-8354 6/30/2021 15
- 1.50 Mtr.)
141 Pouring of Concrete in Coping beam for RE Wall No. W3 353302 353630 77.907 VRC-SP/NH-71/STR-9706 4/17/2022 20 Checked by AE Rep.
Checking Erection of RE Wall No. W3 (below Copping top
142 353+306 353+630 815.289 VRC-SP/NH-71/STR-8353 10/27/2021 15
- 1.00 Mtr.)
143 Pouring of Concrete in Coping beam for RE Wall No. W4 353306 353630 445.87 VRC-SP/NH-71/STR-9791 4/25/2022 20 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
0

CHAINAGE Quantity
S No Description RFI NO Date SPS No. Remarks
From To (Sqm)
Pouring of Concrete in Coping beam for RE Wall No.W4
144
(Balance Qty)
353306 353630 101.52 VRC-SP/NH-71/STR-10205 5/30/2022 21 Checked by AE Rep.
Checking of Steel & Shuttering of copying beam & casting
145 328+863 329+178 1540.074 VRC -SP/NH-71/Str-11025 9/6/2022 25
W-04
146 Copying Beam shuttering & steel fixing & casting W-04 329+250 329+444 1311.780 VRC -SP/NH-71/Str-10710 8/2/2022 24 Checked by AE Rep.

Total Qty : 84336.610 Sqm 31

Previous Qty. : 84336.610 Sqm 31 D

Net Payable Qty : 0.000 Sqm 31 E=(C - D)


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS

0
Friction Slab Crash Barrier
Quantity
S No Description CHAINAGE Side RFI NO Date SPS No. Remarks
(Rm)

1 Checking for erection of Friction Slab 343610 343700 RHS 90 VRC -SP/NH-71/Str-12588 9/11/2023 37

2 Checking for erection of Friction Slab 344280 344450 RHS 170 VRC -SP/NH-71/Str-12590 9/16/2023 37

Total Qty : 15974 Rm 31 C=(A + B)/2


Previous Qty. : 15714 Rm 31 D
Net Payable Qty : 260 Rm 31 E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

Flyover
C2- New Elevated section/ Flyovers/ Grade Separators
0
Stage for Payment Percentag Unit Unit Rate Total Amount Upto Date Previous Bill This Bill Remarks
e Qty. (in Rs.) Qty. Amount Qty. Amount Qty. Amount
Weightage (in Rs.) (in Rs.) (in Rs.)
C2- New Elevated section/ Flyovers/ Grade Separators
(1) Foundation 13.75% Km 382406298 0.070 26,768,441
(a) Pile { 66% of (1)} 9.08% Nos. 184033 96.000 17,667,171 96 17667171 96.00 17667171 - -
(b) Pile Cap { 34% of (1)} 4.68% Km. 130018141 0.070 9,101,270 0.070 9101270 0.07 9101269.9 - -
TOTAL 26768441 26768441 -

(1) Foundation 13.75% Km 382406298 0.070 26,768,441 0.070 26768441 0.070 26768441 - -

(2) Substructure 23.07% Km 641608240 0.070 44,912,577


(a) Abutment/ Pier { 62% of (2) } 14.30% Km 397797109 0.070 27,845,798 0.070 27845798 0.07 27845798 - -
(b) Abutment/ Pier Cap { 25% of (2) } 5.77% Km 160402060 0.070 11,228,144 0.070 11228144 0.07 11228144 - -
(c) Pedestal & Bearing { 13% of (2) } 3.00% Km 83409071 0.070 5,838,635 0.045 3753408 0.045 3753408.2 - -
TOTAL 42827350 42827350 -
(2) Substructure 23.07% Km 641608239.985714 0.070 44,912,577 0.067 42827350 0.067 42827350 - -

(3) Superstructure 33.60% Km 934461936 0.070 65,412,336


(a) Girder {47% of (2)} 15.79% Km 1024793 30.000 30,743,798 30.000 30743798 30 30743798 - -
(b) Deck Slab {53% of (2)} 17.81% Km 495264826 0.070 34,668,538 0.030 14857945 0.03 14857945 - -

Total 45601742.5 45601742 -


(3) Superstructure 33.60% Km 934461936 0.070 65,412,336 0.049 45601742 0.049 45601742 - -
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
Flyover

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Pile
1 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.1) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6785 6/12/2021 12
2 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.2) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6805 6/13/2021 12 Checked by AE Rep.
3 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.3) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6829 6/14/2021 12
4 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.4) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6846 6/15/2021 12 Checked by AE Rep.
5 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.5) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6864 6/16/2021 12
6 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.6) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6889 6/18/2021 12 Checked by AE Rep.
7 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.7) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6906 6/19/2021 12
8 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.8) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6928 6/20/2021 12 Checked by AE Rep.
9 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.9) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6958 6/22/2022 12
10 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.10) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6988 6/23/2022 12 Checked by AE Rep.
11 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.11) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-7018 6/24/2022 12
12 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.12) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-7047 6/25/2022 12 Checked by AE Rep.
13 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.1) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6426 5/23/2021 12 Checked by AE Rep.
14 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.2) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6444 5/24/2021 12
15 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.3) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6476 5/26/2021 12 Checked by AE Rep.
16 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.4) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6486 5/27/2021 12
17 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.5) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6500 5/28/2021 12
18 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.6) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6532 5/29/2021 12 Checked by AE Rep.
19 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.7) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6558 5/30/2021 12
20 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.8) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6579 5/31/2021 12 Checked by AE Rep.
21 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.9) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6589 6/1/2021 12
22 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.10) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6599 6/2/2021 12 Checked by AE Rep.
23 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.11) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6619 6/3/2021 12
24 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.12) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6628 6/4/2021 12 Checked by AE Rep.
25 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.1) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7632 8/3/2021 12
26 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.2) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7653 8/5/2021 12
27 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.3) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7668 8/7/2021 12 Checked by AE Rep.
28 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.4) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7695 8/11/2021 12 Checked by AE Rep.
29 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.5) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7713 8/13/2021 13
30 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.6) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7720 8/14/2021 13
31 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.7) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7738 8/17/2021 13
32 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.8) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7751 8/19/2021 13
33 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.9) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7765 8/24/2021 13
34 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.10) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7780 8/27/2021 13
35 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.11) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7814 8/29/2021 13
36 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.12) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8069 9/26/2021 13
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
Flyover

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks
Checking of Borehole,Reinforcement & Pouring of concrete for Pile
37 Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8683 12/22/2021 16
(P2-No.1)
Checking of Borehole,Reinforcement & Pouring of concrete for Pile
38 Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8702 12/24/2021 16
(P2-No.2)
Checking of Borehole,Reinforcement & Pouring of concrete for Pile
39 Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8719 12/25/2021 16
(P2-No.3)
40 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.4) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8720 12/25/2021 16
41 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.5) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8730 12/26/2021 16 Checked by AE Rep.
42 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.6) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8731 12/26/2021 16
43 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.7) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8744 12/27/2021 16 Checked by AE Rep.
44 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.8) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8745 12/27/2021 16 Checked by AE Rep.
45 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.9) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8764 12/28/2021 16 Checked by AE Rep.
46 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.10) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8765 12/28/2021 16 Checked by AE Rep.
47 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.11) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8784 12/29/2021 17 Checked by AE Rep.
48 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.12) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8785 12/29/2021 17
Total Qty LHS 48.000
1 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.1) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6786 6/12/2021 12
2 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.2) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6806 6/13/2021 12 Checked by AE Rep.
3 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.3) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6830 6/14/2021 12
4 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.4) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6847 6/15/2021 12 Checked by AE Rep.
5 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.5) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6878 6/17/2021 12
6 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.6) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6905 6/19/2021 12 Checked by AE Rep.
7 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.7) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6927 6/20/2021 12
8 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.8) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6945 6/21/2021 12 Checked by AE Rep.
9 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.9) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-6987 6/23/2022 12
10 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.10) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-7017 6/24/2022 12 Checked by AE Rep.
11 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.11) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-7046 6/25/2022 12
12 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A1-No.12) Pile 355+055 A1 1.000 VRC-SP/NH-71/STR-7078 6/26/2022 12 Checked by AE Rep.
13 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.1) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6427 5/23/2021 12
14 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.2) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6445 5/24/2021 12 Checked by AE Rep.
15 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.3) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6460 5/25/2021 12
16 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.4) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6477 5/26/2021 12 Checked by AE Rep.
17 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.5) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6487 5/27/2021 12 Checked by AE Rep.
18 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.6) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6501 5/28/2021 12 Checked by AE Rep.
19 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.7) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6533 5/29/2021 12
20 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.8) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6559 5/30/2021 12 Checked by AE Rep.
21 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.9) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6580 5/31/2021 12
22 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.10) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6590 6/1/2021 12 Checked by AE Rep.
23 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.11) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6600 6/2/2021 12
24 Checking of Reinforcement & Pouring of concrete Borehole for Pile (A2-No.12) Pile 355+055 A2 1.000 VRC-SP/NH-71/STR-6620 6/3/2021 12 Checked by AE Rep.
25 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.1) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7633 8/5/2021 12 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala
(Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
Flyover

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

26 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.2) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7866 9/1/2021 13
27 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.3) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-7878 9/2/2021 13
28 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.4) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8002 9/15/2021 13
29 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.5) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8072 9/26/2021 13
30 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.6) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8081 9/27/2021 13
31 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.7) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8086 9/28/2021 13
32 Checking of Reinforcement & Pouring of concrete Borehole for Pile (P1-No.8) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8096 9/28/2021 13
33 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P1-No.9) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8235 15-Oct-21 14
34 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P1-No.10) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8238 16-Oct-21 14
35 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P1-No.11) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8240 16-Oct-21 14
36 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P1-No.12) Pile 355+055 P1 1.000 VRC-SP/NH-71/STR-8308 24-Oct-21 14
Checking of Borehole,Reinforcement & Pouring of concrete for Pile
37 Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8724 25-Dec-21 16
(P2-No.1)
Checking of Borehole,Reinforcement & Pouring of concrete for Pile
38 Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8725 25-Dec-21 16
(P2-No.2)
Checking of Borehole,Reinforcement & Pouring of concrete for Pile
39 Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8733 26-Dec-21 16
(P2-No.3)
40 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.4) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8734 26-Dec-21 16 Checked by AE Rep.
41 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.5) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8747 27-Dec-21 16 Checked by AE Rep.
42 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.6) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8748 27-Dec-21 16 Checked by AE Rep.
43 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.7) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8772 28-Dec-21 16 Checked by AE Rep.
44 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.8) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-8773 28-Dec-21 17
45 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.9) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-9035 19-Jan-22 17 Checked by AE Rep.
46 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.10) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-9036 19-Jan-22 17
47 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.11) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-9056 21-Jan-22 17 Checked by AE Rep.
48 Checking of Borehole,Reinforcement & Pouring of concrete for Pile (P2-No.12) Pile 355+055 P2 1.000 VRC-SP/NH-71/STR-9067 22-Jan-22 17 Checked by AE Rep.
Total Qty RHS 48.000
Total Qty (Both Side) 96.000
Previous Qty. (Both Side) 96.000
Net Payable Qty (Both Side) 0.000
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under
Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
Flyover

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Pile Cap
1 Checking of Reinforcement & Pouring of concrete for Pile Cap (A1 LHS) Pile cap 355+055 A1 0.009 VRC-SP/NH-71/STR-7141 6/29/2021 12 Checked by AE Rep.
2 Checking of Reinforcement & Pouring of concrete for Pile Cap (A2 LHS) Pile cap 355+055 A2 0.009 VRC-SP/NH-71/STR-7107 6/27/2021 12
3 Checking of Reinforcement & Pouring of concrete for Pile Cap (A1 RHS) Pile cap 355+055 A1 0.009 VRC-SP/NH-71/STR-7161 6/30/2021 12 Checked by AE Rep.
4 Checking of Reinforcement & Pouring of concrete for Pile Cap (A2 RHS) Pile cap 355+055 A2 0.009 VRC-SP/NH-71/STR-7124 6/28/2021 12 Checked by AE Rep.
5 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P1 ( LHS ) Pile cap 355+055 P1 0.009 VRC-SP/NH-71/STR-8566 12/11/2021 16 Checked by AE Rep.
6 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P1 ( RHS ) Pile cap 355+055 P1 0.009 VRC-SP/NH-71/STR-8640 12/19/2021 16 Checked by AE Rep.
7 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P2 ( RHS ) Pile cap 355+055 P2 0.00875 VRC-SP/NH-71/STR-10136 5/26/2022 21 Checked by AE Rep.
8 Checking of Reinforcement,Shuttering & Pouring of concrete for Pile Cap P2 ( LHS ) Pile cap 355+055 P2 0.00875 VRC-SP/NH-71/STR-10150 5/25/2022 21

Total Qty 0.070 Km.


Previous Qty. (Both Side) 0.070 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left
out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

0
Flyover

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Abutment / Pier
1 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft) Final Lift A1 Side of Abutment Shaft 355+055 LHS 0.009 VRC-SP/NH-71/STR-8126 30-Sep-21 13
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft) Final Lift A2 Side of Abutment Shaft 355+055 LHS 0.009 VRC-SP/NH-71/STR-8070 26-Sep-21 13
3 Checking of Reinforcement,Shuttering & Pouring of concrete for Wall Final Lift P1 Shaft 355+055 LHS 0.009 VRC-SP/NH-71/STR-9080 24-Jan-22 17 Checked by AE Rep.
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft) Final Lift P2 Shaft 355+055 LHS 0.009 VRC-SP/NH-71/STR-10701 31-Jul-22 23 Checked by AE Rep.
Total Qty LHS 0.0350

1 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft) Final Lift A1 Side of Abutment Shaft 355+055 RHS 0.009 VRC-SP/NH-71/STR-8127 30-Sep-21 13
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft) Final Lift A2 Side of Abutment Shaft 355+055 RHS 0.009 VRC-SP/NH-71/STR-8071 26-Sep-21 13
3 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft) Final Lift P1 Side of Abutment Shaft 355+055 RHS 0.009 VRC-SP/NH-71/STR-8807 30-Dec-21 16
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Wall(Shaft) Final Lift P2 Shaft 355+055 RHS 0.009 VRC-SP/NH-71/STR-10702 31-Jul-22 23
Total Qty RHS 0.0350 Km.
Total Qty (Both Side) 0.0700 Km.
Previous Qty. (Both Side) 0.070 Km.
Net Payable Qty (Both Side) 0.0000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

C2- New Elevated section/ Flyovers/ Grade Separators


Flyover

S No Description Item CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

Abutment / Pier
Checking of Reinforcement, Shuttering and Pouring of RCC in Abutment Cap
1 Abutment Cap 355+055 LHS 0.00875 VRC-SP/NH-71/STR-11171 27-Sep-22 25 Checked by AE Rep.
A1

2 Checking of Reinforcement, Shuttering and Pouring of RCC in Pier Cap P1 Pier Cap 355+055 LHS 0.00875 VRC-SP/NH-71/STR-10977 30-Aug-22 24 Checked by AE Rep.

3 Checking of Reinforcement, Shuttering and Pouring of RCC in Pier Cap P2 Pier Cap 355+055 LHS 0.00875 VRC-SP/NH-71/STR-11363 27-Oct-22 26
Checking of Reinforcement, Shuttering and Pouring of RCC in Abutment Cap
4 Abutment Cap 355+055 LHS 0.00875 VRC-SP/NH-71/STR-11413 31-Oct-22 26
A2

Total Qty LHS 0.0350


Checking of Reinforcement, Shuttering and Pouring of RCC in Abutment Cap
1 Abutment Cap 355+055 RHS 0.00875 VRC-SP/NH-71/STR-11184 28-Sep-22 25 Checked by AE Rep.
A1
2 Checking of Reinforcement, Shuttering and Pouring of RCC in Pier Cap P1 Pier Cap 355+055 RHS 0.00875 VRC-SP/NH-71/STR-11198 29-Sep-22 25
3 Checking of Reinforcement, Shuttering and Pouring of RCC in Pier Cap P2 Pier Cap 355+055 RHS 0.00875 VRC-SP/NH-71/STR-11375 28-Sep-22 26
4 Checking of Reinforcement, Shuttering and Pouring of RCC in Pier Cap P2 Pier Cap 355+055 RHS 0.00875 VRC-SP/NH-71/STR-11521 25-Nov-22 27 Checked by AE Rep.

Total Qty RHS 0.0350 Km.


Total Qty (Both Side) 0.0700 Km.
Previous Qty. (Both Side) 0.0700 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

C2- New Elevated section/ Flyovers/ Grade Separators


(3) Superstructure(a) Girder

CHAINA Quantit
S No Description type of Girder RFI NO Date SPS No. Remarks
GE y

1 Checking reinforcement,shuttering & Pouring of Concrete for Girder 01 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-10882 25-Aug-22 24 Checked by AE Rep.

2 Checking reinforcement,shuttering & Pouring of Concrete for Girder 02 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11123 22-Sep-22 25 Checked by AE Rep.
3 Checking reinforcement,shuttering & Pouring of Concrete for Girder 03 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11143 24-Sep-22 25 Checked by AE Rep.
4 Checking reinforcement,shuttering & Pouring of Concrete for Girder 04 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11197 29-Sep-22 25 Checked by AE Rep.
5 Checking reinforcement,shuttering & Pouring of Concrete for Girder 05 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11209 30-Sep-22 25
6 Checking reinforcement,shuttering & Pouring of Concrete for Girder 06 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11331 21-Oct-22 26
7 Checking reinforcement,shuttering & Pouring of Concrete for Girder 07 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11345 23-Oct-22 26
8 Checking reinforcement,shuttering & Pouring of Concrete for Girder 08 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11360 27-Oct-22 26
9 Checking reinforcement,shuttering & Pouring of Concrete for Girder 09 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11371 28-Oct-22 26
10 Checking reinforcement,shuttering & Pouring of Concrete for Girder 10 Pre-Stressing Girder 355+055 1 VRC-SP/NH-71/STR-11397 30-Oct-22 26

11 Checking reinforcement,shuttering & Pouring of Concrete for Girder 01 RCC Girder 355+055 1 VRC-SP/NH-71/STR-10903 26-Aug-22 24

12 Checking reinforcement,shuttering & Pouring of Concrete for Girder 02 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11100 19-Sep-22 25 Checked by AE Rep.
13 Checking reinforcement,shuttering & Pouring of Concrete for Girder 03 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11101 19-Sep-22 25 Checked by AE Rep.
14 Checking reinforcement,shuttering & Pouring of Concrete for Girder 04 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11122 22-Sep-22 25 Checked by AE Rep.
15 Checking reinforcement,shuttering & Pouring of Concrete for Girder 05 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11158 26-Sep-22 25 Checked by AE Rep.
16 Checking reinforcement,shuttering & Pouring of Concrete for Girder 06 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11169 27-Sep-22 25
17 Checking reinforcement,shuttering & Pouring of Concrete for Girder 07 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11170 27-Sep-22 25
18 Checking reinforcement,shuttering & Pouring of Concrete for Girder 08 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11182 28-Sep-22 25
19 Checking reinforcement,shuttering & Pouring of Concrete for Girder 09 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11183 28-Sep-22 25
20 Checking reinforcement,shuttering & Pouring of Concrete for Girder 10 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11195 29-Sep-22 25 Checked by AE Rep.
21 Checking reinforcement,shuttering & Pouring of Concrete for Girder 11 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11543 28-Nov-22 27 Checked by AE Rep.
22 Checking reinforcement,shuttering & Pouring of Concrete for Girder 12 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11623 13-Dec-22 28 Checked by AE Rep.
22 Checking reinforcement,shuttering & Pouring of Concrete for Girder 13 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11549 29-Nov-22 27 Checked by AE Rep.
23 Checking reinforcement,shuttering & Pouring of Concrete for Girder 15 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11551 30-Nov-22 27 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on
EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

C2- New Elevated section/ Flyovers/ Grade Separators


(3) Superstructure(a) Girder

CHAINA Quantit
S No Description type of Girder RFI NO Date SPS No. Remarks
GE y
24 Checking reinforcement,shuttering & Pouring of Concrete for Girder 14 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11609 11-Dec-22 28 Checked by AE Rep.
25 Checking reinforcement,shuttering & Pouring of Concrete for Girder 16 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11643 17-Dec-22 28 Checked by AE Rep.
26 Checking reinforcement,shuttering & Pouring of Concrete for Girder 17 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11666 20-Dec-22 28 Checked by AE Rep.
27 Checking reinforcement,shuttering & Pouring of Concrete for Girder 18 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11680 22-Dec-22 28 Checked by AE Rep.
28 Checking reinforcement,shuttering & Pouring of Concrete for Girder 19 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11715 27-Dec-22 28 Checked by AE Rep.
29 Checking reinforcement,shuttering & Pouring of Concrete for Girder 20 RCC Girder 355+055 1 VRC-SP/NH-71/STR-11746 31-Dec-22 28 Checked by AE Rep.

Total Qty 30 Nos.


Previous Paid Qty 30 Nos.
This Bill Qty. 0 Nos.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

C2- New Elevated section/ Flyovers/ Grade Separators


(3) Superstructure(b) Slab

CHAINAG
S No Description Type Side Quantity RFI NO Date SPS No. Remarks
E

Checking of Reinforcement, Shuttering and Pouring of RCC


1 Slab 355+055 LHS 0.0075 VRC-SP/NH-71/STR-12213 31-Mar-23 31 Checked by AE Rep.
in Slab of A2

Checking of Reinforcement, Shuttering and Pouring of RCC


2 Slab 355+055 RHS 0.0075 VRC-SP/NH-71/STR-12209 30-Mar-23 31 Checked by AE Rep.
in Slab of A2

Checking of Reinforcement, Shuttering and Pouring of RCC


3 Slab 355+055 RHS 0.015 VRC-SP/NH-71/STR-12578 27-Aug-23 36 Checked by AE Rep.
in Slab of P-01 to P-02 span

Total Qtyy (Both Side) 0.030 Nos.


Previous Paid Qtyy. (Both Side) 0.030 Nos.
This Bill Qty. (Both Side) 0.000 Nos.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work) on EPC
Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

C2- New Elevated section/ Flyovers/ Grade Separators


(2-C) Superstructure(b) Bearing

S No Description Type CHAINAGE Side Quantity RFI NO Date SPS No. Remarks

1 Checking of Fixing of Bearing A2-P2 Bearing 355+055 LHS 0.0075 VRC-SP/NH-71/STR-12041 22-Feb-23 31 Checked by AE Rep.

2 Checking of Fixing of Bearing A2-P2 Bearing 355+055 RHS 0.0075 VRC-SP/NH-71/STR-12003 16-Feb-23 31 Checked by AE Rep.

3 Checking of Fixing of Bearing P1-P2 Bearing 355+055 LHS 0.015 VRC-SP/NH-71/STR-12189 27-Mar-23 31

4 Checking of Fixing of Bearing P1-P2 Bearing 355+055 RHS 0.015 VRC-SP/NH-71/STR-12198 27-Mar-23 31

Total Qty (Both Side) 0.045 Nos.

Previous Paid Qty . (Both Side) 0.045 Nos.

This Bill Qty. (Both Side) 0.000 Nos.


Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

Other works
(i) Toll Plaza
0
Stage for Payment Percentage Unit Unit Rate Total Amount Upto Date Previous Bill This Bill Remarks
Weightage Qty. (in Rs.) Qty. Amount Qty. Amount Qty. Amount
(in Rs.) (in Rs.) (in Rs.)
(i) Toll Plaza 18.69% No. 120903370.938 1 120,903,371
(a) Road Works { 70% of (i) } 13.08% Km. 141053933 0.600 84,632,360
(1) Earthwork up to top of the sub- 1.05% Km. 11284315 0.600 6,770,589 0.600 6770589 0.600 6770589 - -
grade { 8% of (a) }
(2) Sub-Base Course { 10% of (a) } 1.31% Km. 14105393 0.600 8,463,236 0.600 8463236 0.600 8463236 - -
(3) DLC { 12% of (a) } 1.57% Km. 16926472 0.600 10,155,883 0.580 9817354 0.580 9817354 - -
(4) PQC { 45% of (a) } 5.89% Km. 63474270 0.600 38,084,562 0.545 34593477 0.545 34593477 - -
(5) Other Works { 25% of (a) } 3.27% Km. 35263483 0.600 21,158,090
5.61% No.

Including Toll
Building
Construction, RCC
(b) Building Works { 30% of (i) } 36271011 1 36,271,011 0.442 16031787 0.442 16,031,787 Drain, Canopy and
Balance PQC Work
(Details attached
as Annex-1)

TOTAL 75676442 59644655 16,031,787

(i) Toll Plaza 18.69% No. 120903371 1 120,903,371 0.626 75676442 0.493 59644655 0.133 16,031,787
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance Work)
on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
Other works
0
(1) Earthwork up to top of the sub-grade

Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

1 Level & FDD Checking of Subgrade Top Layer 341+020 341+075 LHS SG TOP 0 VRC-SP/NH71/HW-7990 02.03.2022 19 Checked by AE Rep.

2 Level & FDD Checking of Subgrade Top Layer 341+075 341+200 LHS SG TOP 125 VRC-SP/NH71/HW-2734 05.02.2021 12

3 Level & FDD Checking of Subgrade Top Layer 341+200 341+440 LHS SG TOP 240 VRC-SP/NH71/HW-2307 20.01.2021 12 Checked by AE Rep.

4 Level & FDD Checking of Subgrade Top Layer 341+440 341+660 LHS SG TOP 220 VRC-SP/NH71/HW-2348 21.01.2021 12 Checked by AE Rep.

5 Level & FDD Checking of Subgrade Top Layer 341+660 341+675 LHS SG TOP 15 VRC-SP/NH71/HW-4333 29.04.2021 12
Total Qty LHS 600 m
1 Level & FDD Checking of Subgrade Top Layer 341+020 341+075 RHS SG TOP 0 VRC-SP/NH71/HW-7989 02.03.2022 19 Checked by AE Rep.
2 Level & FDD Checking of Subgrade Top Layer 341+075 341+300 RHS SG TOP 225 VRC-SP/NH71/HW-5622 18.07.2021 12
3 Level & FDD Checking of Subgrade Top Layer 341+300 341+400 RHS SG TOP 100 VRC-SP/NH71/HW-8013 07.03.2022 19 Checked by AE Rep.
4 Level & FDD Checking of Subgrade Top Layer 341+400 341+480 RHS SG TOP 80 VRC -SP/NH-71/Hw-8166 01.04.2022 20 Checked by AE Rep.
5 Level & FDD Checking of Subgrade Top Layer 341+480 341+675 RHS SG TOP 195 VRC -SP/NH-71/Hw-9996 02.01.2023 29 Checked by AE Rep.
Total Qty RHS 600 m
Total Qty (Both Side) 0.600 Km.
Previous Qty. (Both Side) 0.600 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

Other works
0
(2) Sub-Base Course

Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

1 Level and FDD Checking of GSB Top Layer 341+020 341+075 LHS GSB TOP 0 VRC-SP/NH71/HW-8023 08.03.2022 19
2 Level and FDD Checking of GSB Top Layer 341+075 341+200 LHS GSB TOP 125 VRC-SP/NH71/HW-2866 9.02.2021 12
3 Level and FDD Checking of GSB Top Layer 341+200 341+400 LHS GSB TOP 200 VRC-SP/NH71/HW-2794 7.02.2021 12 Checked by AE Rep.

4 Level and FDD Checking of GSB Top Layer 341+400 341+660 LHS GSB TOP 260 VRC-SP/NH71/HW-2829 8.02.2021 12
5 Level and FDD Checking of GSB Top Layer 341+660 341+675 LHS GSB TOP 15 VRC-SP/NH71/HW-4349 30.04.2021 12
Total Qty LHS 600 m
1 Level and FDD Checking of GSB Top Layer 341+020 341+075 RHS GSB TOP 0 VRC-SP/NH71/HW-8022 08.03.2022 19
2 Level and FDD Checking of GSB Top Layer 341+075 341+300 RHS GSB TOP 225 VRC-SP/NH71/HW-5641 19.07.2021 12 Checked by AE Rep.
3 Level and FDD Checking of GSB Top Layer 341+300 341+400 RHS GSB TOP 100 VRC-SP/NH71/HW-8044 11.03.2022 19 Checked by AE Rep.
4 Level and FDD Checking of GSB Top Layer 341+400 341+470 RHS GSB TOP 70 VRC -SP/NH-71/Hw-8173 03.04.2022 20 Checked by AE Rep.
4 Level and FDD Checking of GSB Top Layer 341+470 341+675 RHS GSB TOP 205 VRC -SP/NH-71/Hw-10002 05.01.2023 29 Checked by AE Rep.
Total Qty RHS 600 m
Total Qty (Both Side) 0.600 Km.
Previous Qty. (Both Side) 0.600 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

Other works
0
(2) Sub-Base Course

Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

1 Laying of DLC Layer at Toll Plaza 341+075 341+675 LHS DLC 600 VRC-SP/NH-71/HW-5601 17-Jul-21 12 Checked by AE Rep.
Total Qty LHS 600 m
1 Laying of DLC Layer at Toll Plaza 341+075 341+180 RHS DLC 105 VRC -SP/NH-71/HW-9895 24-Dec-22 28 Checked by AE Rep.
2 Laying of DLC Layer at Toll Plaza 341+180 341+230 RHS DLC 50 VRC -SP/NH-71/Hw-8204 07-Apr-22 20
3 Laying of DLC Layer at Toll Plaza 341+230 341+300 RHS DLC 70 VRC -SP/NH-71/HW-9320 27-Feb-22 18
4 Laying of DLC Layer at Toll Plaza 341+300 341+350 RHS DLC 50 VRC -SP/NH-71/HW-9772 28-Nov-22 27 Checked by AE Rep.
5 Laying of DLC Layer at Toll Plaza 341+350 341+400 RHS DLC 50 VRC -SP/NH-71/Hw-8211 08-Apr-22 20 Checked by AE Rep.
6 Laying of DLC Layer at Toll Plaza 341+400 341+455 RHS DLC 55 VRC -SP/NH-71/Hw-7994 03-Mar-22 19 Checked by AE Rep.
7 Laying of DLC Layer at Toll Plaza 341+455 341+675 RHS DLC 180 VRC -SP/NH-71/Hw-10330 24-Feb-23 30 40 mtr deduction
Total Qty RHS 560 m
Total Qty (Both Side) 0.580 Km.
Previous Qty. (Both Side) 0.580 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A
(Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

Other works
0
PQC

Chainage Quantity
Sl. No. Description Side Layer No. RFI No. Date SPS No. Remarks
From To (m)

1 Checking PQC Laying at Toll Plaza 341+075 341+355 LHS PQC 280 VRC -SP/NH-71/HW-7647 28-Jan-22 17 Checked by AE Rep.

2 Checking PQC Laying at Toll Plaza 341+395 341+675 LHS PQC 280 VRC -SP/NH-71/HW-7628 25-Jan-22 17
Total Qty LHS 560 m

1 Checking PQC Laying at Toll Plaza 341+075 341+130 RHS PQC 55 VRC -SP/NH-71/HW-9969 30-Dec-22 28 Checked by AE Rep.
2 Checking PQC Laying at Toll Plaza 341+130 341+170 RHS PQC 40 VRC -SP/NH-71/HW-9959 29-Dec-22 28 Checked by AE Rep.
3 Checking PQC Laying at Toll Plaza 341+170 341+230 RHS PQC 60 VRC -SP/NH-71/HW-9869 18-Dec-22 28 Checked by AE Rep.
4 Checking PQC Laying at Toll Plaza 341+230 341+300 RHS PQC 70 VRC -SP/NH-71/HW-9325 28-Feb-22 18
5 Checking PQC Laying at Toll Plaza 341+300 341+320 RHS PQC 20 VRC -SP/NH-71/Hw-10100 27-Jan-23 29 Checked by AE Rep.
9 Checking PQC Laying at Toll Plaza 341+390 341+400 RHS PQC 10 VRC -SP/NH-71/Hw-10389 04-Mar-23 31 Checked by AE Rep.
6 Checking PQC Laying at Toll Plaza 341+400 341+455 RHS PQC 55 VRC -SP/NH-71/Hw-8057 14-Mar-22 19
11 Checking PQC Laying at Toll Plaza 341+455 341+530 RHS PQC 75 VRC -SP/NH-71/Hw-10484 31-Mar-23 31 Checked by AE Rep.
10 Checking PQC Laying at Toll Plaza 341+530 341+580 RHS PQC 50 VRC -SP/NH-71/Hw-10452 24-Mar-23 31 Checked by AE Rep.
7 Checking PQC Laying at Toll Plaza 341+580 341+600 RHS PQC 20 VRC -SP/NH-71/Hw-10363 25-Feb-23 30 Checked by AE Rep.
8 Checking PQC Laying at Toll Plaza 341+600 341+675 RHS PQC 75 VRC -SP/NH-71/Hw-10339 28-Feb-23 30
Total Qty RHS 530 m
Total Qty (Both Side) 0.545 Km.
Previous Qty. (Both Side) 0.545 Km.
Net Payable Qty (Both Side) 0.000 Km.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
1 Road Side Drain 308350 308380 LHS 30 VRC-SP/NH-71/STR-3118 1/5/2021 5 Checked by AE Rep.
2 Road Side Drain 308380 308410 LHS 30 VRC-SP/NH-71/STR-3157 1/6/2021 5
3 Road Side Drain 308410 308440 LHS 30 VRC-SP/NH-71/STR-3189 1/7/2021 5 Checked by AE Rep.
4 Road Side Drain 308440 308470 LHS 30 VRC-SP/NH-71/STR-3223 1/8/2021 5
5 Road Side Drain 308470 308480 LHS 10 VRC-SP/NH-71/STR-3256 1/9/2021 5 Checked by AE Rep.
6 Road Side Drain 308480 308500 LHS 20 VRC-SP/NH-71/STR-2462 12/23/2020 4 Checked by AE Rep.
7 Road Side Drain 308500 308530 LHS 30 VRC-SP/NH-71/STR-2509 12/24/2020 4
8 Road Side Drain 308530 308560 LHS 30 VRC-SP/NH-71/STR-2585 12/26/2020 4 Checked by AE Rep.
9 Road Side Drain 308560 308590 LHS 30 VRC-SP/NH-71/STR-2650 12/28/2020 4
10 Road Side Drain 308590 308610 LHS 20 VRC-SP/NH-71/STR-2741 12/29/2020 4 Checked by AE Rep.
11 Road Side Drain 308610 308640 LHS 30 VRC-SP/NH-71/STR-2912 12/31/2020 4
12 Road Side Drain 308640 308660 LHS 20 VRC-SP/NH-71/STR-2983 1/2/2021 5
13 Road Side Drain 308660 308690 LHS 30 VRC-SP/NH-71/STR-3024 1/4/2021 5 Checked by AE Rep.
14 Road Side Drain 308690 308720 LHS 30 VRC-SP/NH-71/STR-3452 1/15/2021 5
15 Road Side Drain 308720 308750 LHS 30 VRC-SP/NH-71/STR-3501 1/16/2021 5 Checked by AE Rep.
16 Road Side Drain 308750 308780 LHS 30 VRC-SP/NH-71/STR-3567 1/18/2021 5
17 Road Side Drain 308780 308810 LHS 30 VRC-SP/NH-71/STR-3614 1/19/2021 5 Checked by AE Rep.
18 Road Side Drain 308810 308860 LHS 50 VRC-SP/NH-71/STR-11455 11/11/2022 27 Checked by AE Rep.
19 Road Side Drain 308860 308900 LHS 40 VRC-SP/NH-71/STR-5041 3/7/2021 7 Checked by AE Rep.
20 Road Side Drain 309000 309030 LHS 30 VRC-SP/NH-71/STR-5097 3/9/2021 7 Checked by AE Rep.
21 Road Side Drain 309030 309050 LHS 20 VRC-SP/NH-71/STR-2653 12/28/2020 4 Checked by AE Rep.
22 Road Side Drain 309050 309070 LHS 20 VRC-SP/NH-71/STR-2832 12/30/2020 4
23 Road Side Drain 309070 309100 LHS 30 VRC-SP/NH-71/STR-2914 12/31/2020 4 Checked by AE Rep.
24 Road Side Drain 309100 309130 LHS 30 VRC-SP/NH-71/STR-3037 1/4/2021 5
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
25 Road Side Drain 309130 309170 LHS 40 VRC-SP/NH-71/STR-3198 1/7/2021 5 Checked by AE Rep.
26 Road Side Drain 309170 309200 LHS 30 VRC-SP/NH-71/STR-3504 1/16/2021 5
27 Road Side Drain 309200 309230 LHS 30 VRC-SP/NH-71/STR-3572 1/18/2021 5 Checked by AE Rep.
28 Road Side Drain 309230 309260 LHS 30 VRC-SP/NH-71/STR-3617 1/19/2021 5
29 Road Side Drain 309260 309290 LHS 30 VRC-SP/NH-71/STR-3673 1/20/2021 5 Checked by AE Rep.
30 Road Side Drain 309290 309310 LHS 20 VRC-SP/NH-71/STR-3752 1/21/2021 5
31 Road Side Drain 309310 309340 LHS 30 VRC-SP/NH-71/STR-3828 1/22/2021 5 Checked by AE Rep.
32 Road Side Drain 315620 315640 LHS 20 VRC-SP/NH-71/STR-2661 12/28/2020 4
33 Road Side Drain 315640 315660 LHS 20 VRC-SP/NH-71/STR-2750 12/29/2020 4 Checked by AE Rep.
34 Road Side Drain 315660 315680 LHS 20 VRC-SP/NH-71/STR-2835 12/30/2020 4
35 Road Side Drain 315680 315700 LHS 20 VRC-SP/NH-71/STR-3174 1/6/2021 5
36 Road Side Drain 315700 315740 LHS 40 VRC-SP/NH-71/STR-3456 1/15/2021 5 Checked by AE Rep.
37 Road Side Drain 315740 315770 LHS 30 VRC-SP/NH-71/STR-3510 1/16/2021 5
38 Road Side Drain 315770 315800 LHS 30 VRC-SP/NH-71/STR-3553 1/18/2021 5 Checked by AE Rep.
39 Road Side Drain 315800 315820 LHS 20 VRC-SP/NH-71/STR-3623 1/19/2021 5
40 Road Side Drain 315820 315850 LHS 30 VRC-SP/NH-71/STR-3679 1/20/2021 5 Checked by AE Rep.
41 Road Side Drain 315850 315870 LHS 20 VRC-SP/NH-71/STR-3836 1/22/2021 5
42 Road Side Drain 315870 315910 LHS 40 VRC-SP/NH-71/STR-3860 1/23/2021 5 Checked by AE Rep.
43 Road Side Drain 315910 315940 LHS 30 VRC-SP/NH-71/STR-4090 1/28/2021 5
44 Road Side Drain 315940 315980 LHS 40 VRC-SP/NH-71/STR-4324 2/3/2021 6 Checked by AE Rep.
45 Road Side Drain 315980 316010 LHS 30 VRC-SP/NH-71/STR-5698 4/14/2021 8
46 Road Side Drain 316010 316040 LHS 30 VRC-SP/NH-71/STR-3911 1/24/2021 5 Checked by AE Rep.
47 Road Side Drain 316040 316080 LHS 40 VRC-SP/NH-71/STR-5699 4/14/2021 8
48 Road Side Drain 316080 316100 LHS 20 VRC-SP/NH-71/STR-5717 4/15/2021 8 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
49 Road Side Drain 316280 316320 LHS 40 VRC-SP/NH-71/STR-5992 4/28/2021 8
50 Road Side Drain 316320 316360 LHS 40 VRC-SP/NH-71/STR-5966 4/27/2021 8 Checked by AE Rep.
51 Road Side Drain 316360 316400 LHS 40 VRC-SP/NH-71/STR-5942 4/26/2021 8
52 Road Side Drain 316400 316440 LHS 40 VRC-SP/NH-71/STR-5098 3/9/2021 7 Checked by AE Rep.
53 Road Side Drain 316440 316480 LHS 40 VRC-SP/NH-71/STR-3862 1/23/2021 5
54 Road Side Drain 316480 316510 LHS 30 VRC-SP/NH-71/STR-3913 1/24/2021 5 Checked by AE Rep.
55 Road Side Drain 316510 316540 LHS 30 VRC-SP/NH-71/STR-4666 2/14/2021 6
56 Road Side Drain 316540 316580 LHS 40 VRC-SP/NH-71/STR-3868 1/23/2021 5
57 Road Side Drain 316580 316620 LHS 40 VRC-SP/NH-71/STR-5047 3/7/2021 7 Checked by AE Rep.
58 Road Side Drain 316620 316650 LHS 30 VRC-SP/NH-71/STR-5099 3/9/2021 7 Checked by AE Rep.
59 Road Side Drain 321930 321960 LHS 30 VRC-SP/NH-71/STR-2099 12/15/2020 4 Checked by AE Rep.
60 Road Side Drain 321960 321990 LHS 30 VRC-SP/NH-71/STR-2140 12/16/2020 4
61 Road Side Drain 321990 322020 LHS 30 VRC-SP/NH-71/STR-2179 12/17/2020 4 Checked by AE Rep.
62 Road Side Drain 322020 322060 LHS 40 VRC-SP/NH-71/STR-2278 12/19/2020 4
63 Road Side Drain 322060 322100 LHS 40 VRC-SP/NH-71/STR-2339 12/21/2020 4
64 Road Side Drain 322100 322130 LHS 30 VRC-SP/NH-71/STR-2594 12/26/2020 4 Checked by AE Rep.
65 Road Side Drain 322130 322160 LHS 30 VRC-SP/NH-71/STR-3511 1/16/2021 5 Checked by AE Rep.
66 Road Side Drain 322160 322190 LHS 30 VRC-SP/NH-71/STR-3573 1/18/2021 5
67 Road Side Drain 322190 322220 LHS 30 VRC-SP/NH-71/STR-3622 1/19/2021 5 Checked by AE Rep.
68 Road Side Drain 322220 322250 LHS 30 VRC-SP/NH-71/STR-3680 1/20/2021 5
69 Road Side Drain 322250 322280 LHS 30 VRC-SP/NH-71/STR-3837 1/22/2021 5 Checked by AE Rep.
70 Road Side Drain 322280 322320 LHS 40 VRC-SP/NH-71/STR-3867 1/23/2021 5 Checked by AE Rep.
71 Road Side Drain 322320 322350 LHS 30 VRC-SP/NH-71/STR-4097 1/28/2021 5
72 Road Side Drain 322350 322370 LHS 20 VRC-SP/NH-71/STR-3994 1/25/2021 5 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
73 Road Side Drain 322370 322400 LHS 30 VRC-SP/NH-71/STR-3917 1/24/2021 5
74 Road Side Drain 322400 322440 LHS 40 VRC-SP/NH-71/STR-4155 1/29/2021 5 Checked by AE Rep.
75 Road Side Drain 322440 322470 LHS 30 VRC-SP/NH-71/STR-4209 1/30/2021 5
76 Road Side Drain 322520 322560 LHS 40 VRC-SP/NH-71/STR-4744 2/17/2021 6 Checked by AE Rep.
77 Road Side Drain 322560 322590 LHS 30 VRC-SP/NH-71/STR-5664 4/12/2021 8 Checked by AE Rep.
78 Road Side Drain 322590 322610 LHS 20 VRC-SP/NH-71/STR-3512 1/16/2010 5 Checked by AE Rep.
79 Road Side Drain 322610 322640 LHS 30 VRC-SP/NH-71/STR-2405 12/22/2020 4 Checked by AE Rep.
80 Road Side Drain 322640 322650 LHS 10 VRC-SP/NH-71/STR-2180 12/17/2020 4
81 Road Side Drain 322650 322680 LHS 30 VRC-SP/NH-71/STR-2059 12/14/2020 4 Checked by AE Rep.
82 Road Side Drain 322680 322720 LHS 40 VRC-SP/NH-71/STR-1991 12/12/2020 4
83 Road Side Drain 322720 322750 LHS 30 VRC-SP/NH-71/STR-2102 12/15/2020 4 Checked by AE Rep.
84 Road Side Drain 322750 322780 LHS 30 VRC-SP/NH-71/STR-2536 12/24/2020 4 Checked by AE Rep.
85 Road Side Drain 322780 322800 LHS 20 VRC-SP/NH-71/STR-2666 12/28/2020 4
86 Road Side Drain 322800 322830 LHS 30 VRC-SP/NH-71/STR-3185 1/6/2021 5
87 Road Side Drain 322830 322870 LHS 40 VRC-SP/NH-71/STR-3873 1/23/2021 5 Checked by AE Rep.
88 Road Side Drain 322870 322900 LHS 30 VRC-SP/NH-71/STR-5872 4/23/2021 8
89 Road Side Drain 322900 322940 LHS 40 VRC-SP/NH-71/STR-5927 4/25/2021 8 Checked by AE Rep.
90 Road Side Drain 322940 322980 LHS 40 VRC-SP/NH-71/STR-5941 4/26/2021 8
91 Road Side Drain 322980 323010 LHS 30 VRC-SP/NH-71/STR-5965 4/27/2021 8 Checked by AE Rep.
92 Road Side Drain 323870 323900 LHS 30 VRC -SP/NH-71/STR-819 10/11/2020 4
93 Road Side Drain 323900 324000 LHS 100 VRC -SP/NH-71/STR-848 10/12/2020 4
94 Road Side Drain 324000 324100 LHS 100 VRC-SP/NH/-71/Str-857 10/13/2020 4
95 Road Side Drain 324100 324277 LHS 177 VRC-SP/NH/-71/Str-887 10/14/2020 4
96 Road Side Drain 324277 324297 LHS 20 VRC-SP/NH-71/STR-4597 2/11/2021 6 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
97 Road Side Drain 324297 324310 LHS 13 VRC -SP/NH-71/STR-920 10/15/2020 4
98 Road Side Drain 324310 324320 LHS 10 VRC-SP/NH-71/Str-400 9/23/2020 1
99 Road Side Drain 324320 324380 LHS 60 VRC-SP/NH-71/Str-503 9/28/2020 1
100 Road Side Drain 324380 324440 LHS 60 VRC-SP/NH-71/STR-957 10/17/2020 4
101 Road Side Drain 324440 324460 LHS 20 VRC-SP/NH-71/Str-376 9/21/2020 1 Checked by AE Rep.
102 Road Side Drain 324460 324470 LHS 10 VRC-SP/NH-71/Str-390 9/22/2020 1
103 Road Side Drain 324470 324480 LHS 10 VRC-SP/NH-71/Str-397 9/23/2020 1 Checked by AE Rep.
104 Road Side Drain 324480 324490 LHS 10 VRC-SP/NH-71/Str-411 9/24/2020 1 Checked by AE Rep.
105 Road Side Drain 324490 324510 LHS 20 VRC-SP/NH-71/Str-433 9/25/2020 1 Checked by AE Rep.
106 Road Side Drain 324510 324520 LHS 10 VRC-SP/NH-71/Str-500 9/28/2020 1 Checked by AE Rep.
107 Road Side Drain 324520 324530 LHS 10 VRC-SP/NH-71/STR-529 9/29/2020 1 Checked by AE Rep.
108 Road Side Drain 324530 324540 LHS 10 VRC-SP/NH-71/STR-823 10/11/2020 4
109 Road Side Drain 324540 324550 LHS 10 VRC-SP/NH-71/STR-550 9/30/2020 1
110 Road Side Drain 324550 324570 LHS 20 VRC-SP/NH-71/STR-4598 2/11/2021 6
111 Road Side Drain 324570 324580 LHS 10 VRC-SP/NH-71/Str-461 9/26/2020 1
112 Road Side Drain 324580 324590 LHS 10 VRC-SP/NH-71/Str-501 9/28/2020 1 Checked by AE Rep.
113 Road Side Drain 324590 324600 LHS 10 VRC-SP/NH-71/STR-530 9/29/2020 1
114 Road Side Drain 324600 324610 LHS 10 VRC-SP/NH-71/STR-983 10/18/2020 4
115 Road Side Drain 324610 324620 LHS 10 VRC-SP/NH-71/STR-551 9/30/2020 1 Checked by AE Rep.
116 Road Side Drain 324620 324640 LHS 20 VRC-SP/NH-71/STR-575 10/1/2020 1 Checked by AE Rep.
117 Road Side Drain 324640 324660 LHS 20 VRC-SP/NH-71/STR-602 10/2/2020 1 Checked by AE Rep.
118 Road Side Drain 324660 324717 LHS 57 VRC-SP/NH-71/STR-1001 10/19/2020 4
119 Road Side Drain 324717 324737 LHS 20 VRC-SP/NH-71/STR-4599 2/11/2021 6 Checked by AE Rep.
120 Road Side Drain 324737 324900 LHS 163 VRC-SP/NH-71/STR-1078 10/22/2020 4
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
121 Road Side Drain 324900 325000 LHS 100 VRC-SP/NH-71/STR-1185 10/27/2020 4
122 Road Side Drain 325000 325100 LHS 100 VRC-SP/NH-71/STR-1107 10/23/2020 4
123 Road Side Drain 325100 325200 LHS 100 VRC-SP/NH-71/STR-824 10/11/2020 4
124 Road Side Drain 328470 328500 LHS 30 VRC-SP-NH-71-Str-3220 1/7/2021 5 Checked by AE Rep.
125 Road Side Drain 328500 328550 LHS 50 VRC-SP-NH-71-Str-3241 1/8/2021 5 Checked by AE Rep.
126 Road Side Drain 328550 328600 LHS 50 VRC-SP-NH-71-Str-3245 1/8/2021 5
127 Road Side Drain 328600 328650 LHS 50 VRC-SP-NH-71-Str-3400 1/13/2021 5 Checked by AE Rep.
128 Road Side Drain 328650 328700 LHS 50 VRC-SP-NH-71-Str-3404 1/13/2021 5
129 Road Side Drain 328700 328750 LHS 50 VRC-SP-NH-71-Str-3471 1/15/2021 5 Checked by AE Rep.
130 Road Side Drain 328750 328800 LHS 50 VRC-SP-NH-71-Str-3590 1/18/2021 5
131 Road Side Drain 328800 328850 LHS 50 VRC-SP-NH-71-Str-3766 1/21/2021 5 Checked by AE Rep.
132 Road Side Drain 328850 328900 LHS 50 VRC-SP-NH-71-Str-3647 1/19/2021 5
133 Road Side Drain 328900 328950 LHS 50 VRC-SP-NH-71-Str-3806 1/22/2021 5 Checked by AE Rep.
134 Road Side Drain 328950 329000 LHS 50 VRC-SP-NH-71-Str-2869 12/30/2020 4
135 Road Side Drain 329000 329050 LHS 50 VRC-SP-NH-71-Str-2955 12/31/2020 4
136 Road Side Drain 329050 329100 LHS 50 VRC-SP/NH-71/STR-4138 1/28/2021 5
137 Road Side Drain 329100 329150 LHS 50 VRC-SP/NH-71/STR-4066 1/27/2021 5 Checked by AE Rep.
138 Road Side Drain 329150 329200 LHS 50 VRC-SP/NH-71/STR-3976 1/25/2021 5
139 Road Side Drain 329200 329250 LHS 50 VRC-SP/NH-71/STR-4139 1/28/2021 5 Checked by AE Rep.
140 Road Side Drain 329250 329300 LHS 50 VRC-SP/NH-71/STR-4190 1/29/2021 5
141 Road Side Drain 329300 329350 LHS 50 VRC-SP/NH-71/STR-3933 1/24/2021 5 Checked by AE Rep.
142 Road Side Drain 329350 329400 LHS 50 VRC -SP/NH-71/Str-1910 12/10/2020 4
143 Road Side Drain 329400 329440 LHS 40 VRC-SP/NH-71/STR-4392 2/5/2021 6
144 Road Side Drain 329440 329500 LHS 60 VRC -SP/NH-71/Str-1837 12/7/2020 4 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
145 Road Side Drain 329500 329570 LHS 70 VRC-SP/NH-71/Str-2001 12/12/2020 4 Checked by AE Rep.
146 Road Side Drain 329570 329580 LHS 10 VRC-SP/NH-71/STR-4393 2/5/2021 6 Checked by AE Rep.
147 Road Side Drain 329580 329630 LHS 50 VRC-SP/NH-71/Str-2107 12/15/2020 4 Checked by AE Rep.
148 Road Side Drain 329630 329680 LHS 50 VRC-SP/NH-71/Str-2150 12/16/2020 4 Checked by AE Rep.
149 Road Side Drain 329680 329730 LHS 50 VRC-SP/NH-71/Str-2196 12/17/2020 4 Checked by AE Rep.
150 Road Side Drain 329730 329760 LHS 30 VRC-SP/NH-71/Str-2315 12/19/2020 4 Checked by AE Rep.
151 Road Side Drain 329760 329800 LHS 40 VRC-SP/NH-71/Str-2357 12/21/2020 4 Checked by AE Rep.
152 Road Side Drain 329800 329850 LHS 50 VRC-SP/NH-71/Str-2494 12/23/2020 4 Checked by AE Rep.
153 Road Side Drain 329850 329900 LHS 50 VRC-SP-NH-71-Str-2620 12/26/2020 4 Checked by AE Rep.
154 Road Side Drain 329900 329950 LHS 50 VRC-SP-NH-71-Str-2691 12/28/2020 4 Checked by AE Rep.
155 Road Side Drain 329950 330000 LHS 50 VRC-SP-NH-71-Str-2797 12/29/2020 4
156 Road Side Drain 330000 330015 LHS 15 VRC-SP/NH-71/STR-4394 2/5/2021 6
157 Road Side Drain 330015 330110 LHS 95 VRC-SP-NH-71-Str-2877 12/30/2020 4
158 Road Side Drain 330430 330480 LHS 50 VRC-SP/NH-71/Str-2061 12/14/2020 4 Checked by AE Rep.
159 Road Side Drain 330480 330530 LHS 50 VRC-SP/NH-71/Str-2109 12/15/2020 4
160 Road Side Drain 330530 330580 LHS 50 VRC-SP/NH-71/Str-2359 12/21/2020 4 Checked by AE Rep.
161 Road Side Drain 330580 330600 LHS 20 VRC-SP/NH-71/Str-2496 12/23/2020 4 Checked by AE Rep.
162 Road Side Drain 330600 330620 LHS 20 VRC-SP/NH-71/Str-4428 2/6/2021 6
163 Road Side Drain 330620 330720 LHS 100 VRC-SP/NH-71/Str-2801 12/29/2020 4 Checked by AE Rep.
164 Road Side Drain 330720 330760 LHS 40 VRC-SP/NH-71/Str-4429 2/6/2021 6
165 Road Side Drain 330760 330810 LHS 50 VRC -SP/NH-71/STR-6172 5/6/2021 10 Checked by AE Rep.
166 Road Side Drain 330810 330830 LHS 20 VRC-SP/NH-71/Str-4530 2/9/2021 6
167 Road Side Drain 330830 330900 LHS 70 VRC-SP/NH-71/Str-1814 12/5/2020 4 Checked by AE Rep.
168 Road Side Drain 330900 330950 LHS 50 VRC-SP/NH-71/Str-4430 2/6/2021 6
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
169 Road Side Drain 330950 331000 LHS 50 VRC -SP/NH-71/STR-6173 5/6/2021 10
170 Road Side Drain 331000 331050 LHS 50 VRC-SP/NH-71/Str-4531 2/9/2021 6
171 Road Side Drain 331050 331100 LHS 50 VRC -SP/NH-71/Str-9607 01.04.2022 20 Checked by AE Rep.
172 Road Side Drain 331100 331140 LHS 40 VRC-SP/NH-71/Str-4532 2/9/2021 6
173 Road Side Drain 335580 335670 LHS 90 VRC-SP/NH-71/STR-8328 10/25/2021 16 Checked by AE Rep.
174 Road Side Drain 335670 335760 LHS 90 VRC-SP/NH-71/STR-8343 10/26/2021 16 Checked by AE Rep.
175 Road Side Drain 335760 335800 LHS 40 VRC-SP/NH-71/STR-8673 12/26/2021 16 Checked by AE Rep.
176 Road Side Drain 335800 335880 LHS 80 VRC-SP/NH-71/STR-8760 12/28/2021 16 Checked by AE Rep.
177 Road Side Drain 335880 335950 LHS 70 VRC-SP/NH-71/STR-8761 12/28/2021 16 Checked by AE Rep.
178 Road Side Drain 335950 336000 LHS 50 VRC-SP/NH-71/STR-8589 12/14/2021 16 Checked by AE Rep.
179 Road Side Drain 336000 336040 LHS 40 VRC-SP/NH-71/STR-8573 12/13/2021 16
180 Road Side Drain 336140 336220 LHS 80 VRC-SP/NH-71/STR-6424 5/23/2021 9 Checked by AE Rep.
181 Road Side Drain 336220 336310 LHS 90 VRC-SP/NH-71/STR-6443 5/24/2021 9 Checked by AE Rep.
182 Road Side Drain 336310 336400 LHS 90 VRC-SP/NH-71/STR-6458 5/25/2021 9 Checked by AE Rep.
183 Road Side Drain 336400 336450 LHS 50 VRC-SP-NH-71-Str-4080 1/27/2021 5
184 Road Side Drain 336450 336500 LHS 50 VRC-SP-NH-71-Str-4145 1/28/2021 5
185 Road Side Drain 336500 336550 LHS 50 VRC-SP-NH-71-Str-4147 1/28/2021 5 Checked by AE Rep.
186 Road Side Drain 336550 336600 LHS 50 VRC-SP-NH-71-Str-4194 1/29/2021 5
187 Road Side Drain 336600 336650 LHS 50 VRC-SP-NH-71-Str-5838 4/21/2021 8
188 Road Side Drain 336650 336710 LHS 60 VRC-SP/NH-71/STR-7152 6/30/2021 10 Checked by AE Rep.
189 Road Side Drain 338430 338500 LHS 70 VRC-SP-NH-71-Str-3879 1/23/2021 5
190 Road Side Drain 338500 338540 LHS 40 VRC-SP/NH-71/Str-2009 12/12/2020 4 Checked by AE Rep.
191 Road Side Drain 338540 338560 LHS 20 VRC-SP-NH-71-Str-2564 12/24/2020 4 Checked by AE Rep.
192 Road Side Drain 338560 338580 LHS 20 VRC -SP/NH-71/STR-4398 2/5/2021 6 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
193 Road Side Drain 338580 338600 LHS 20 VRC-SP-NH-71-Str-2632 12/26/2020 4 Checked by AE Rep.
194 Road Side Drain 338600 338700 LHS 100 VRC-SP/NH-71/Str-2105 12/15/2020 4 Checked by AE Rep.
195 Road Side Drain 338700 338750 LHS 50 VRC-SP-NH-71-Str-3329 1/11/2021 5 Checked by AE Rep.
196 Road Side Drain 338750 338800 LHS 50 VRC-SP-NH-71-Str-3366 1/12/2021 5 Checked by AE Rep.
197 Road Side Drain 338800 338850 LHS 50 VRC-SP-NH-71-Str-3331 1/11/2021 5
198 Road Side Drain 338850 338900 LHS 50 VRC-SP-NH-71-Str-3482 1/15/2021 5 Checked by AE Rep.
199 Road Side Drain 338900 338950 LHS 50 VRC-SP-NH-71-Str-3364 1/12/2021 5
200 Road Side Drain 338950 339000 LHS 50 VRC-SP-NH-71-Str-3365 1/12/2021 5 Checked by AE Rep.
201 Road Side Drain 339000 339050 LHS 50 VRC-SP-NH-71-Str-3368 1/12/2021 5 Checked by AE Rep.
202 Road Side Drain 339050 339100 LHS 50 VRC-SP-NH-71-Str-3369 1/12/2021 5
203 Road Side Drain 339100 339150 LHS 50 VRC-SP-NH-71-Str-3878 1/23/2021 5 Checked by AE Rep.
204 Road Side Drain 339150 339200 LHS 50 VRC-SP/NH-71/STR-3930 1/24/2021 5 Checked by AE Rep.
205 Road Side Drain 339200 339250 LHS 50 VRC-SP/NH-71/STR-4062 1/27/2021 5 Checked by AE Rep.
206 Road Side Drain 339250 339300 LHS 50 VRC-SP/NH-71/STR-3973 1/25/2021 5
207 Road Side Drain 339300 339350 LHS 50 VRC-SP/NH-71/STR-4230 1/30/2021 5
208 Road Side Drain 339350 339400 LHS 50 VRC-SP/NH-71/STR-4184 1/29/2021 5
209 Road Side Drain 339400 339450 LHS 50 VRC-SP/NH-71/STR-4063 1/27/2021 5 Checked by AE Rep.
210 Road Side Drain 339450 339500 LHS 50 VRC-SP/NH-71/STR-3974 1/25/2021 5 Checked by AE Rep.
211 Road Side Drain 339500 339580 LHS 80 VRC-SP/NH-71/STR-3931 1/24/2021 5 Checked by AE Rep.
212 Road Side Drain 343380 343480 LHS 100 VRC-SP/NH-71/STR-9290 2/24/2022 19
213 Road Side Drain 343480 343570 LHS 90 VRC-SP/NH-71/STR-7102 6/27/2021 10
214 Road Side Drain 343570 343660 LHS 90 VRC-SP/NH-71/STR-7134 6/29/2021 10
215 Road Side Drain 343660 343750 LHS 90 VRC-SP/NH-71/STR-7012 6/24/2021 10 Checked by AE Rep.
216 Road Side Drain 343750 343840 LHS 90 VRC-SP/NH-71/STR-6986 6/23/2021 10 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
217 Road Side Drain 343840 343930 LHS 90 VRC-SP/NH-71/STR-6863 6/16/2021 10 Checked by AE Rep.
218 Road Side Drain 343930 343980 LHS 50 VRC-SP/NH-71/STR-7038 6/25/2021 10
219 Road Side Drain 343980 344050 LHS 70 VRC-SP/NH-71/STR-10551 6/30/2022 22 Checked by AE Rep
220 Road Side Drain 344085 344120 LHS 35 VRC-SP/NH-71/STR-11542 11/28/2022 27 Checked by AE Rep.
221 Road Side Drain 344120 344200 LHS 80 VRC-SP/NH-71/STR-7603 7/31/2021 11 Checked by AE Rep.
222 Road Side Drain 344200 344230 LHS 30 VRC-SP/NH-71/STR-11546 11/29/2022 27 Checked by AE Rep.
223 Road Side Drain 344230 344350 LHS 120 VRC-SP/NH-71/STR-6524 5/29/2021 9 Checked by AE Rep.
224 Road Side Drain 344350 344380 LHS 30 VRC-SP/NH-71/STR-11547 11/29/2022 27 Checked by AE Rep.
225 Road Side Drain 344380 344410 LHS 30 VRC-SP/NH-71/STR-6526 5/29/2021 9
226 Road Side Drain 344410 344500 LHS 90 VRC-SP-NH-71-Str-6051 4/30/2021 8
227 Road Side Drain 344500 344580 LHS 80 VRC-SP/NH-71/STR-6552 5/30/2021 9 Checked by AE Rep.
228 Road Side Drain 344580 344680 LHS 100 VRC-SP/NH-71/STR-6576 5/31/2021 9 Checked by AE Rep.
229 Road Side Drain 345810 345900 LHS 90 VRC-SP/NH-71/STR-7583 7/30/2021 11 Checked by AE Rep.
230 Road Side Drain 345900 345950 LHS 50 VRC-SP/NH-71/STR-9598 3/31/2022 19 Checked by AE Rep.
231 Road Side Drain 345950 346020 LHS 70 VRC-SP/NH-71/STR-7584 7/30/2021 11 Checked by AE Rep.
232 Road Side Drain 346020 346080 LHS 60 VRC-SP/NH-71/STR-8125 9/30/2021 13
233 Road Side Drain 346080 346160 LHS 80 VRC-SP/NH-71/STR-9140 1/29/2022 17 Checked by AE Rep.
234 Road Side Drain 346160 346180 LHS 20 VRC-SP/NH-71/STR-9599 3/31/2022 19 Checked by AE Rep.
235 Road Side Drain 346180 346250 LHS 70 VRC-SP/NH-71/STR-7154 6/30/2021 10
236 Road Side Drain 346250 346320 LHS 70 VRC-SP/NH-71/STR-7155 6/30/2021 10
237 Road Side Drain 346320 346380 LHS 60 VRC-SP/NH-71/STR-6556 5/30/2021 9 Checked by AE Rep.
238 Road Side Drain 346380 346400 LHS 20 VRC-SP/NH-71/STR-9600 3/31/2022 19 Checked by AE Rep.
239 Road Side Drain 346400 346500 LHS 100 VRC-SP/NH-71/STR-8130 9/30/2021 13
240 Road Side Drain 346580 346660 LHS 80 VRC-SP-NH-71-Str-4014 1/25/2021 5 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
241 Road Side Drain 346660 346750 LHS 90 VRC-SP-NH-71-Str-4196 1/29/2021 5 Checked by AE Rep.
242 Road Side Drain 346750 346820 LHS 70 VRC-SP/NH-71/STR-7549 7/28/2021 11 Checked by AE Rep.
243 Road Side Drain 346820 346910 LHS 90 VRC-SP-NH-71-Str-5986 4/27/2021 8
244 Road Side Drain 346910 347000 LHS 90 VRC-SP-NH-71-Str-6006 4/28/2021 8 Checked by AE Rep.
245 Road Side Drain 347000 347060 LHS 60 VRC-SP/NH-71/STR-8108 9/29/2021 13
246 Road Side Drain 347060 347120 LHS 60 VRC-SP/NH-71/STR-8110 9/29/2021 13
247 Road Side Drain 352900 352950 LHS 50 VRC-SP/NH-71/STR-9551 3/27/2022 19 Checked by AE Rep.
248 Road Side Drain 352950 353000 LHS 50 VRC-SP/NH-71/STR-9486 3/22/2022 19 Checked by AE Rep.
249 Road Side Drain 353000 353060 LHS 60 VRC-SP/NH-71/STR-9500 3/23/2022 19 Checked by AE Rep.
250 Road Side Drain 353060 353150 LHS 90 VRC-SP/NH-71/STR-8314 10/24/2021 14
251 Road Side Drain 353150 353200 LHS 50 VRC-SP/NH-71/STR-8344 10/26/2021 14
252 Road Side Drain 353200 353280 LHS 80 VRC-SP/NH-71/STR-8075 9/27/2021 13
253 Road Side Drain 353330 353370 LHS 40 VRC-SP/NH-71/STR-9592 3/30/2022 20
254 Road Side Drain 353370 353400 LHS 30 VRC-SP/NH-71/STR-8052 9/24/2021 13
255 Road Side Drain 353400 353450 LHS 50 VRC-SP/NH-71/STR-8046 9/23/2021 13
256 Road Side Drain 353450 353530 LHS 80 VRC-SP/NH-71/STR-8040 9/22/2021 13
257 Road Side Drain 353530 353570 LHS 40 VRC-SP/NH-71/STR-8022 9/19/2021 13
258 Road Side Drain 353570 353650 LHS 80 VRC-SP/NH-71/STR-10168 5/27/2021 21
259 Road Side Drain 353650 353700 LHS 50 VRC-SP/NH-71/STR-10194 5/29/2021 21 Checked by AE Rep.
260 Road Side Drain 353700 353710 LHS 10 VRC-SP/NH-71/STR-10479 6/27/2022 22
0
Total Qty LHS 11885 m 0 A
1 Road Side Drain 308350 308380 RHS 30 VRC-SP/NH-71/STR-2463 12/23/2020 4 Checked by AE Rep.
2 Road Side Drain 308380 308440 RHS 60 VRC-SP/NH-71/STR-1938 12/11/2020 4
3 Road Side Drain 308440 308480 RHS 40 VRC-SP/NH-71/STR-1987 12/12/2020 4 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
4 Road Side Drain 308480 308530 RHS 50 VRC-SP/NH-71/STR-2056 12/14/2020 4
5 Road Side Drain 308530 308560 RHS 30 VRC-SP/NH-71/STR-2138 12/16/2020 4 Checked by AE Rep.
6 Road Side Drain 308560 308590 RHS 30 VRC-SP/NH-71/STR-2178 12/17/2020 4 Checked by AE Rep.
7 Road Side Drain 308590 308610 RHS 20 VRC-SP/NH-71/STR-2221 12/18/2020 4 Checked by AE Rep.
8 Road Side Drain 308610 308630 RHS 20 VRC-SP/NH-71/STR-2276 12/19/2020 4 Checked by AE Rep.
9 Road Side Drain 308630 308650 RHS 20 VRC-SP/NH-71/STR-2222 12/18/2020 4
10 Road Side Drain 308650 308690 RHS 40 VRC-SP/NH-71/STR-4809 2/20/2021 6
11 Road Side Drain 308690 308720 RHS 30 VRC-SP/NH-71/STR-2337 12/21/2020 4 Checked by AE Rep.
12 Road Side Drain 308720 308750 RHS 30 VRC-SP/NH-71/STR-2393 12/22/2020 4 Checked by AE Rep.
13 Road Side Drain 308750 308770 RHS 20 VRC-SP/NH-71/STR-2464 12/23/2020 4 Checked by AE Rep.
14 Road Side Drain 308770 308800 RHS 30 VRC-SP/NH-71/STR-2651 12/28/2020 4 Checked by AE Rep.
15 Road Side Drain 308800 308830 RHS 30 VRC-SP/NH-71/STR-6128 5/4/2021 9 Checked by AE Rep.
16 Road Side Drain 308830 308850 RHS 20 VRC-SP/NH-71/STR-6144 5/5/2021 9
17 Road Side Drain 308850 308860 RHS 10 VRC-SP/NH-71/STR-6203 5/9/2021 9 Checked by AE Rep.
18 Road Side Drain 308860 308890 RHS 30 VRC-SP/NH-71/STR-2586 12/26/2020 4
19 Road Side Drain 308890 308910 RHS 20 VRC-SP/NH-71/STR-2743 12/29/2020 4 Checked by AE Rep.
20 Road Side Drain 308910 308940 RHS 30 VRC-SP/NH-71/STR-2919 12/31/2020 4
21 Road Side Drain 308940 308980 RHS 40 VRC-SP/NH-71/STR-3041 1/4/2021 5 Checked by AE Rep.
22 Road Side Drain 308980 309020 RHS 40 VRC-SP/NH-71/STR-3121 1/5/2021 5
23 Road Side Drain 309020 309050 RHS 30 VRC-SP/NH-71/STR-3168 1/6/2021 5 Checked by AE Rep.
24 Road Side Drain 309050 309080 RHS 30 VRC-SP/NH-71/STR-3264 1/9/2021 5
25 Road Side Drain 309080 309100 RHS 20 VRC-SP/NH-71/STR-3298 1/11/2021 5 Checked by AE Rep.
26 Road Side Drain 309100 309130 RHS 30 VRC-SP/NH-71/STR-3378 1/13/2021 5
27 Road Side Drain 309130 309150 RHS 20 VRC-SP/NH-71/STR-3755 1/21/2021 5 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
28 Road Side Drain 309150 309160 RHS 10 VRC-SP/NH-71/STR-3461 1/15/2021 5
29 Road Side Drain 309160 309200 RHS 40 VRC-SP/NH-71/STR-3509 1/16/2021 5 Checked by AE Rep.
30 Road Side Drain 309200 309230 RHS 30 VRC-SP/NH-71/STR-3624 1/19/2021 5
31 Road Side Drain 309230 309260 RHS 30 VRC-SP/NH-71/STR-3676 1/20/2021 5 Checked by AE Rep.
32 Road Side Drain 309260 309300 RHS 40 VRC-SP/NH-71/STR-3830 1/22/2021 5
33 Road Side Drain 309300 309330 RHS 30 VRC-SP/NH-71/STR-4323 2/3/2021 6 Checked by AE Rep.
34 Road Side Drain 309330 309370 RHS 40 VRC-SP/NH-71/STR-4549 2/10/2021 6
35 Road Side Drain 309370 309400 RHS 30 VRC-SP/NH-71/STR-4580 2/11/2021 6 Checked by AE Rep.
36 Road Side Drain 315620 315660 RHS 40 VRC-SP/NH-71/STR-5969 4/27/2021 8 Checked by AE Rep.
37 Road Side Drain 315660 315700 RHS 40 VRC-SP/NH-71/STR-5995 4/28/2021 8 Checked by AE Rep.
38 Road Side Drain 315700 315740 RHS 40 VRC-SP/NH-71/STR-6015 4/29/2021 8 Checked by AE Rep.
39 Road Side Drain 315740 315780 RHS 40 VRC-SP/NH-71/STR-6037 4/30/2021 8
40 Road Side Drain 315780 315810 RHS 30 VRC-SP/NH-71/STR-6058 5/1/2021 9 Checked by AE Rep.
41 Road Side Drain 315810 315840 RHS 30 VRC-SP/NH-71/STR-6079 5/2/2021 9
42 Road Side Drain 315840 315880 RHS 40 VRC-SP/NH-71/STR-6104 5/3/2021 9 Checked by AE Rep.
43 Road Side Drain 315880 315920 RHS 40 VRC-SP/NH-71/STR-6127 5/4/2021 9
44 Road Side Drain 315920 315960 RHS 40 VRC-SP/NH-71/STR-6143 5/5/2021 9 Checked by AE Rep.
45 Road Side Drain 315960 316000 RHS 40 VRC-SP/NH-71/STR-6204 5/9/2021 9
46 Road Side Drain 316000 316020 RHS 20 VRC-SP/NH-71/STR-6342 5/18/2021 9 Checked by AE Rep.
47 Road Side Drain 316020 316050 RHS 30 VRC-SP/NH-71/STR-2920 12/31/2020 4 Checked by AE Rep.
48 Road Side Drain 316050 316080 RHS 30 VRC-SP/NH-71/STR-3044 1/4/2021 5 Checked by AE Rep.
49 Road Side Drain 316080 316100 RHS 20 VRC-SP/NH-71/STR-3390 1/13/2021 5
50 Road Side Drain 316100 316120 RHS 20 VRC-SP/NH-71/STR-2839 12/30/2020 4
51 Road Side Drain 316120 316150 RHS 30 VRC-SP/NH-71/STR-3171 1/6/2021 5 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
52 Road Side Drain 316150 316190 RHS 40 VRC-SP/NH-71/STR-7488 7/24/2021 11 Checked by AE Rep.
53 Road Side Drain 316190 316250 RHS 60 VRC-SP/NH-71/STR-1939 12/11/2020 4
54 Road Side Drain 316250 316300 RHS 50 VRC-SP/NH-71/STR-1988 12/12/2020 4
55 Road Side Drain 316300 316350 RHS 50 VRC-SP/NH-71/STR-2055 12/14/2020 4
56 Road Side Drain 316350 316390 RHS 40 VRC-SP/NH-71/STR-2098 12/15/2020 4 Checked by AE Rep.
57 Road Side Drain 316390 316430 RHS 40 VRC-SP/NH-71/STR-2139 12/16/2020 4 Checked by AE Rep.
58 Road Side Drain 316430 316460 RHS 30 VRC-SP/NH-71/STR-2223 12/18/2020 4 Checked by AE Rep.
59 Road Side Drain 316460 316490 RHS 30 VRC-SP/NH-71/STR-2933 12/31/2020 4 Checked by AE Rep.
60 Road Side Drain 316490 316500 RHS 10 VRC-SP/NH-71/STR-2525 12/24/2020 4
61 Road Side Drain 316500 316530 RHS 30 VRC-SP/NH-71/STR-2338 12/21/2020 4 Checked by AE Rep.
62 Road Side Drain 316530 316560 RHS 30 VRC-SP/NH-71/STR-3045 1/4/2021 5
63 Road Side Drain 316560 316590 RHS 30 VRC-SP/NH-71/STR-2394 12/22/2020 4 Checked by AE Rep.
64 Road Side Drain 316590 316620 RHS 30 VRC-SP/NH-71/STR-2475 12/23/2020 4 Checked by AE Rep.
65 Road Side Drain 316620 316650 RHS 30 VRC-SP/NH-71/STR-2590 12/26/2020 4
66 Road Side Drain 321930 321940 RHS 10 VRC-SP/NH-71/STR-4022 1/27/2021 5 Checked by AE Rep.
67 Road Side Drain 321940 321980 RHS 40 VRC-SP/NH-71/STR-4100 1/28/2021 5
68 Road Side Drain 321980 322010 RHS 30 VRC-SP/NH-71/STR-4160 1/29/2021 5 Checked by AE Rep.
69 Road Side Drain 322010 322040 RHS 30 VRC-SP/NH-71/STR-4210 1/30/2021 5
70 Road Side Drain 322040 322080 RHS 40 VRC-SP/NH-71/STR-4386 2/5/2021 6
71 Road Side Drain 322080 322120 RHS 40 VRC-SP/NH-71/STR-4605 2/12/2021 6 Checked by AE Rep.
72 Road Side Drain 322120 322160 RHS 40 VRC-SP/NH-71/STR-4638 2/13/2021 6
73 Road Side Drain 322160 322200 RHS 40 VRC-SP/NH-71/STR-4716 2/16/2021 6 Checked by AE Rep.
74 Road Side Drain 322200 322240 RHS 40 VRC-SP/NH-71/STR-3462 1/15/2021 5 Checked by AE Rep.
75 Road Side Drain 322240 322280 RHS 40 VRC-SP/NH-71/STR-3574 1/18/2021 5
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
76 Road Side Drain 322280 322310 RHS 30 VRC-SP/NH-71/STR-3633 1/19/2021 5 Checked by AE Rep.
77 Road Side Drain 322310 322340 RHS 30 VRC-SP/NH-71/STR-3842 1/22/2021 5
78 Road Side Drain 322340 322370 RHS 30 VRC-SP/NH-71/STR-3918 1/24/2021 5 Checked by AE Rep.
79 Road Side Drain 322370 322410 RHS 40 VRC-SP/NH-71/STR-3871 1/23/2021 5
80 Road Side Drain 322410 322430 RHS 20 VRC-SP/NH-71/STR-4741 2/17/2021 6
81 Road Side Drain 322430 322470 RHS 40 VRC-SP/NH-71/STR-4715 2/16/2021 6 Checked by AE Rep.
82 Road Side Drain 322470 322500 RHS 30 VRC-SP/NH-71/STR-4667 2/14/2021 6 Checked by AE Rep.
83 Road Side Drain 322570 322600 RHS 30 VRC-SP/NH-71/STR-2287 12/19/2020 4 Checked by AE Rep.
84 Road Side Drain 322600 322630 RHS 30 VRC-SP/NH-71/STR-2395 12/22/2020 4 Checked by AE Rep.
85 Road Side Drain 322630 322650 RHS 20 VRC-SP/NH-71/STR-2476 12/23/2020 4
86 Road Side Drain 322650 322680 RHS 30 VRC-SP/NH-71/STR-2533 12/24/2020 4 Checked by AE Rep.
87 Road Side Drain 322680 322710 RHS 30 VRC-SP/NH-71/STR-3115 1/5/2021 5 Checked by AE Rep.
88 Road Side Drain 322710 322750 RHS 40 VRC-SP/NH-71/STR-4204 1/30/2021 5
89 Road Side Drain 322750 322780 RHS 30 VRC-SP/NH-71/STR-4387 2/5/2021 6
90 Road Side Drain 322780 322810 RHS 30 VRC-SP/NH-71/STR-2840 12/30/2020 4 Checked by AE Rep.
91 Road Side Drain 322810 322840 RHS 30 VRC-SP/NH-71/STR-2935 12/31/2020 4 Checked by AE Rep.
92 Road Side Drain 322840 322870 RHS 30 VRC-SP/NH-71/STR-3102 1/5/2021 5 Checked by AE Rep.
93 Road Side Drain 322870 322900 RHS 30 VRC-SP/NH-71/STR-3186 1/6/2021 5
94 Road Side Drain 322900 322930 RHS 30 VRC-SP/NH-71/STR-3279 1/9/2021 5 Checked by AE Rep.
95 Road Side Drain 322930 322960 RHS 30 VRC-SP/NH-71/STR-3316 1/11/2021 5
96 Road Side Drain 322960 323000 RHS 40 VRC-SP/NH-71/STR-3463 1/15/2021 5 Checked by AE Rep.
97 Road Side Drain 323000 323010 RHS 10 VRC-SP/NH-71/STR-5048 3/7/2021 7 Checked by AE Rep.
98 Road Side Drain 323870 323960 RHS 90 VRC-SP/NH-71/STR-825 10/11/2020 4
99 Road Side Drain 323960 323980 RHS 20 VRC-SP/NH-71/STR-645 10/4/2020 1
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
100 Road Side Drain 323980 324000 RHS 20 VRC-SP/NH-71/STR-625 10/3/2020 1
101 Road Side Drain 324000 324020 RHS 20 VRC-SP/NH-71/STR-601 10/2/2020 1 Checked by AE Rep.
102 Road Side Drain 324020 324040 RHS 20 VRC-SP/NH-71/STR-576 10/1/2020 1 Checked by AE Rep.
103 Road Side Drain 324040 324060 RHS 20 VRC-SP/NH-71/STR-548 9/30/2020 1 Checked by AE Rep.
104 Road Side Drain 324060 324080 RHS 20 VRC-SP/NH-71/STR-525 9/29/2020 1 Checked by AE Rep.
105 Road Side Drain 324080 324110 RHS 30 VRC-SP/NH-71/STR-577 10/1/2020 1 Checked by AE Rep.
106 Road Side Drain 324110 324130 RHS 20 VRC-SP/NH-71/STR-549 9/30/2020 1 Checked by AE Rep.
107 Road Side Drain 324130 324150 RHS 20 VRC-SP/NH-71/STR-526 9/29/2020 1 Checked by AE Rep.
108 Road Side Drain 324150 324170 RHS 20 VRC-SP/NH71/Str-497 9/28/2020 1 Checked by AE Rep.
109 Road Side Drain 324170 324190 RHS 20 VRC-SP/NH71/Str-460 9/26/2020 1
110 Road Side Drain 324190 324200 RHS 10 VRC-SP/NH-71/STR-960 10/17/2020 4
111 Road Side Drain 324200 324220 RHS 20 VRC-SP/NH71/Str-200 9/7/2020 1 Checked by AE Rep.
112 Road Side Drain 324220 324240 RHS 20 VRC-SP/NH71/Str-292 9/15/2020 1
113 Road Side Drain 324240 324250 RHS 10 VRC-SP/NH-71/STR-1052 10/21/2020 4
114 Road Side Drain 324250 324260 RHS 10 VRC-SP/NH71/Str-350 9/20/2020 1 Checked by AE Rep.
115 Road Side Drain 324260 324297 RHS 37 VRC-SP/NH-71/STR-4600 2/11/2021 6 Checked by AE Rep.
116 Road Side Drain 324297 324310 RHS 13 VRC-SP/NH-71/STR-1150 10/26/2020 4
117 Road Side Drain 324310 324330 RHS 20 VRC-SP/NH71/Str-410 9/24/2020 1 Checked by AE Rep.
118 Road Side Drain 324330 324350 RHS 20 VRC-SP/NH71/Str-430 9/25/2020 1 Checked by AE Rep.
119 Road Side Drain 324350 324370 RHS 20 VRC-SP/NH71/Str-498 9/28/2020 1 Checked by AE Rep.
120 Road Side Drain 324370 324390 RHS 20 VRC-SP/NH-71/STR-1109 10/23/2020 4
121 Road Side Drain 324390 324400 RHS 10 VRC-SP/NH-71/STR-527 9/29/2020 1 Checked by AE Rep.
122 Road Side Drain 324400 324440 RHS 40 VRC-SP/NH-71/STR-1186 10/27/2020 4
123 Road Side Drain 324440 324460 RHS 20 VRC-SP/NH71/Str-293 9/15/2020 1 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
124 Road Side Drain 324460 324480 RHS 20 VRC-SP/NH-71/STR-1126 10/24/2020 4
125 Road Side Drain 324480 324510 RHS 30 VRC-SP/NH71/Str-342 9/19/2020 1
126 Road Side Drain 324510 324530 RHS 20 VRC-SP/NH-71/STR-949 10/16/2020 4
127 Road Side Drain 324530 324540 RHS 10 VRC-SP/NH71/Str-374 9/21/2020 1 Checked by AE Rep.
128 Road Side Drain 324540 324550 RHS 10 VRC-SP/NH-71/STR-1032 10/20/2020 4
129 Road Side Drain 324550 324570 RHS 20 VRC-SP/NH71/Str-412 9/24/2020 1
130 Road Side Drain 324570 324590 RHS 20 VRC-SP/NH71/Str-431 9/25/2020 1 Checked by AE Rep.
131 Road Side Drain 324590 324610 RHS 20 VRC-SP/NH71/Str-499 9/28/2020 1 Checked by AE Rep.
132 Road Side Drain 324610 324640 RHS 30 VRC-SP/NH-71/STR-1083 10/22/2020 4
133 Road Side Drain 324640 324660 RHS 20 VRC-SP/NH-71/STR-528 9/29/2020 1
134 Road Side Drain 324660 324680 RHS 20 VRC-SP/NH-71/STR-552 9/30/2020 1 Checked by AE Rep.
135 Road Side Drain 324680 324700 RHS 20 VRC-SP/NH-71/STR-578 10/1/2020 1 Checked by AE Rep.
136 Road Side Drain 324700 324737 RHS 37 VRC-SP/NH-71/STR-4601 2/11/2021 6
137 Road Side Drain 324737 324920 RHS 183 VRC-SP/NH-71/STR-950 10/16/2020 4
138 Road Side Drain 324920 324930 RHS 10 VRC-SP/NH71/Str-201 9/7/2020 1 Checked by AE Rep.
139 Road Side Drain 324930 324990 RHS 60 VRC-SP/NH-71/STR-1006 10/19/2020 4
140 Road Side Drain 324990 325010 RHS 20 VRC-SP/NH71/Str-313 9/16/2020 1 Checked by AE Rep.
141 Road Side Drain 325010 325100 RHS 90 VRC-SP/NH-71/STR-1012 10/19/2020 4
142 Road Side Drain 325100 325200 RHS 100 VRC-SP/NH-71/STR-1204 10/28/2020 4
143 Road Side Drain 328470 328500 RHS 30 VRC-SP/NH-71/Str-3218 1/7/2021 5 Checked by AE Rep.
144 Road Side Drain 328500 328550 RHS 50 VRC-SP/NH-71/Str-3243 1/8/2021 5 Checked by AE Rep.
145 Road Side Drain 328550 328600 RHS 50 VRC-SP/NH-71/Str-3281 1/9/2021 5
146 Road Side Drain 328600 328650 RHS 50 VRC-SP/NH-71/Str-3402 1/13/2021 5 Checked by AE Rep.
147 Road Side Drain 328650 328700 RHS 50 VRC-SP/NH-71/Str-3406 1/13/2021 5 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
148 Road Side Drain 328700 328750 RHS 50 VRC-SP/NH-71/Str-3473 1/15/2021 5
149 Road Side Drain 328750 328800 RHS 50 VRC-SP/NH-71/Str-3592 1/18/2021 5 Checked by AE Rep.
150 Road Side Drain 328800 328850 RHS 50 VRC-SP/NH-71/Str-3767 1/21/2021 5
151 Road Side Drain 328850 328900 RHS 50 VRC-SP/NH-71/Str-3649 1/19/2021 5 Checked by AE Rep.
152 Road Side Drain 328900 328950 RHS 50 VRC-SP/NH-71/Str-3807 1/22/2021 5 Checked by AE Rep.
153 Road Side Drain 328950 329000 RHS 50 VRC-SP/NH-71/Str-3880 1/23/2021 5 Checked by AE Rep.
154 Road Side Drain 329000 329050 RHS 50 VRC-SP/NH-71/Str-3805 1/22/2021 5
155 Road Side Drain 329050 329100 RHS 50 VRC-SP/NH-71/Str-3881 1/23/2021 5
156 Road Side Drain 329100 329150 RHS 50 VRC-SP/NH-71/STR-3932 1/24/2021 5 Checked by AE Rep.
157 Road Side Drain 329150 329200 RHS 50 VRC-SP/NH-71/STR-4064 1/27/2021 5 Checked by AE Rep.
158 Road Side Drain 329200 329240 RHS 40 VRC-SP/NH-71/Str-2805 12/29/2020 4
159 Road Side Drain 329240 329250 RHS 10 VRC-SP/NH-71/STR-4137 1/28/2021 5 Checked by AE Rep.
160 Road Side Drain 329250 329300 RHS 50 VRC-SP/NH-71/Str-2959 12/31/2020 4
161 Road Side Drain 329300 329350 RHS 50 VRC-SP/NH-71/STR-3975 1/25/2021 5 Checked by AE Rep.
162 Road Side Drain 329350 329400 RHS 50 VRC-SP/NH-71/Str-1947 12/11/2020 4
163 Road Side Drain 329400 329440 RHS 40 VRC-SP/NH-71/STR-4395 2/5/2021 6 Checked by AE Rep.
164 Road Side Drain 329440 329500 RHS 60 VRC-SP/NH-71/Str-1839 12/7/2020 4
165 Road Side Drain 329500 329570 RHS 70 VRC-SP/NH-71/Str-2003 12/12/2020 4
166 Road Side Drain 329570 329630 RHS 60 VRC-SP/NH-71/STR-4065 1/27/2021 5 Checked by AE Rep.
167 Road Side Drain 329630 329680 RHS 50 VRC-SP/NH-71/Str-2148 12/16/2020 4
168 Road Side Drain 329680 329730 RHS 50 VRC-SP/NH-71/Str-2194 12/17/2020 4
169 Road Side Drain 329730 329780 RHS 50 VRC-SP/NH-71/Str-2313 12/19/2020 4
170 Road Side Drain 329780 329830 RHS 50 VRC-SP/NH-71/Str-2492 12/23/2020 4
171 Road Side Drain 329830 329880 RHS 50 VRC-SP-NH-71-Str-2618 12/26/2020 4
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
172 Road Side Drain 329880 329920 RHS 40 VRC-SP-NH-71-Str-2689 12/28/2020 4
173 Road Side Drain 329920 329950 RHS 30 VRC-SP/NH-71/STR-4462 2/7/2021 6
174 Road Side Drain 329950 330000 RHS 50 VRC-SP/NH-71/STR-4396 2/5/2021 6 Checked by AE Rep.
175 Road Side Drain 330000 330050 RHS 50 VRC-SP/NH-71/STR-4463 2/7/2021 6
176 Road Side Drain 330050 330100 RHS 50 VRC-SP/NH-71/STR-4397 2/5/2021 6 Checked by AE Rep.
177 Road Side Drain 330100 330110 RHS 10 VRC-SP/NH-71/STR-4464 2/7/2021 6
178 Road Side Drain 330430 330480 RHS 50 VRC-SP/NH-71/Str-2063 12/14/2020 4
179 Road Side Drain 330480 330530 RHS 50 VRC-SP/NH-71/Str-2152 12/16/2020 4
180 Road Side Drain 330530 330580 RHS 50 VRC-SP/NH-71/Str-2317 12/19/2020 4
181 Road Side Drain 330580 330610 RHS 30 VRC-SP/NH-71/Str-2361 12/21/2020 4
182 Road Side Drain 330610 330640 RHS 30 VRC-SP/NH-71/Str-4533 2/9/2021 6 Checked by AE Rep.
183 Road Side Drain 330640 330750 RHS 110 VRC-SP/NH-71/Str-1780 12/4/2020 4
184 Road Side Drain 330750 330780 RHS 30 VRC-SP-NH-71-Str-2693 12/28/2020 4
185 Road Side Drain 330780 330800 RHS 20 VRC-SP-NH-71-Str-4534 2/9/2021 6 Checked by AE Rep.
186 Road Side Drain 330800 330860 RHS 60 VRC -SP/NH-71/Str-9613 02.04.2022 20
187 Road Side Drain 330860 330900 RHS 40 VRC-SP-NH-71-Str-2957 12/31/2020 4
188 Road Side Drain 330900 330950 RHS 50 VRC -SP/NH-71/Str-9625 04.04.2022 20 Checked by AE Rep
189 Road Side Drain 330950 331000 RHS 50 VRC-SP/NH-71/STR-4535 2/9/2021 6
190 Road Side Drain 331+000 331+050 RHS 50 VRC -SP/NH-71/Str-10419 6/24/2022 22 Checked by AE Rep.
191 Road Side Drain 331050 331100 RHS 50 VRC-SP/NH-71/STR-4536 2/9/2021 6 Checked by AE Rep.
192 Road Side Drain 331100 331140 RHS 40 VRC-SP/NH-71/STR-12570 7/21/2023 35 Checked by AE Rep.
193 Road Side Drain 335580 335700 RHS 120 VRC-SP/NH-71/STR-8269 10/19/2021 14
194 Road Side Drain 335700 335760 RHS 60 VRC-SP/NH-71/STR-8247 10/17/2021 14
195 Road Side Drain 335760 335810 RHS 50 VRC-SP/NH-71/STR-9808 4/26/2022 20
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
196 Road Side Drain 335870 335930 RHS 60 VRC-SP/NH-71/STR-7536 7/27/2021 11
197 Road Side Drain 335930 336000 RHS 70 VRC-SP/NH-71/STR-7548 7/28/2021 11
198 Road Side Drain 336000 336060 RHS 60 VRC-SP/NH-71/STR-7560 7/29/2021 11
199 Road Side Drain 336140 336220 RHS 80 VRC-SP/NH-71/STR-6548 5/30/2021 9
200 Road Side Drain 336220 336300 RHS 80 VRC-SP/NH-71/STR-6550 5/30/2021 9
201 Road Side Drain 336300 336360 RHS 60 VRC-SP-NH-71-Str-6049 4/30/2021 8 Checked by AE Rep.
202 Road Side Drain 336360 336430 RHS 70 VRC-SP-NH-71-Str-6031 4/29/2021 8
203 Road Side Drain 336430 336500 RHS 70 VRC-SP-NH-71-Str-6008 4/28/2021 8 Checked by AE Rep.
204 Road Side Drain 336500 336580 RHS 80 VRC-SP-NH-71-Str-5988 4/27/2021 8
205 Road Side Drain 336580 336650 RHS 70 VRC-SP-NH-71-Str-5961 4/26/2021 8 Checked by AE Rep.
206 Road Side Drain 336650 336710 RHS 60 VRC-SP/NH-71/STR-7153 6/30/2021 10 Checked by AE Rep.
207 Road Side Drain 338430 338500 RHS 70 VRC-SP/NH-71/STR-4131 1/28/2021 5
208 Road Side Drain 338500 338540 RHS 40 VRC-SP/NH-71/STR-4185 1/29/2021 5 Checked by AE Rep.
209 Road Side Drain 338540 338560 RHS 20 VRC-SP/NH-71/STR-4567 2/10/2021 6
210 Road Side Drain 338560 338580 RHS 20 VRC-SP/NH-71/STR-4704 2/15/2021 6 Checked by AE Rep.
211 Road Side Drain 338580 338600 RHS 20 VRC-SP/NH-71/STR-4649 2/13/2021 6
212 Road Side Drain 338600 338650 RHS 50 VRC-SP/NH-71/STR-4181 1/29/2021 5 Checked by AE Rep.
213 Road Side Drain 338650 338700 RHS 50 VRC-SP/NH-71/STR-4231 1/30/2021 5 Checked by AE Rep.
214 Road Side Drain 338700 338750 RHS 50 VRC-SP/NH-71/STR-4705 2/15/2021 6 Checked by AE Rep.
215 Road Side Drain 338750 338800 RHS 50 VRC-SP/NH-71/STR-4650 2/13/2021 6
216 Road Side Drain 338800 338850 RHS 50 VRC-SP/NH-71/STR-4706 2/15/2021 6 Checked by AE Rep.
217 Road Side Drain 338850 338900 RHS 50 VRC-SP/NH-71/STR-4132 1/28/2021 5 Checked by AE Rep.
218 Road Side Drain 338900 338950 RHS 50 VRC-SP/NH-71/STR-4186 1/29/2021 5 Checked by AE Rep.
219 Road Side Drain 338950 339000 RHS 50 VRC-SP/NH-71/STR-4709 2/15/2021 6
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
220 Road Side Drain 339000 339050 RHS 50 VRC-SP/NH-71/STR-4182 1/29/2021 5
221 Road Side Drain 339050 339100 RHS 50 VRC-SP/NH-71/STR-4568 2/10/2021 6 Checked by AE Rep.
222 Road Side Drain 339100 339150 RHS 50 VRC-SP/NH-71/STR-4707 2/15/2021 6 Checked by AE Rep.
223 Road Side Drain 339150 339200 RHS 50 VRC-SP/NH-71/STR-4651 2/13/2021 6 Checked by AE Rep.
224 Road Side Drain 339200 339250 RHS 50 VRC-SP/NH-71/STR-4183 1/29/2021 5 Checked by AE Rep.
225 Road Side Drain 339250 339300 RHS 50 VRC-SP/NH-71/STR-4708 2/15/2021 6 Checked by AE Rep.
226 Road Side Drain 339300 339350 RHS 50 VRC-SP/NH-71/STR-4652 2/13/2021 6 Checked by AE Rep.
227 Road Side Drain 339350 339400 RHS 50 VRC-SP/NH-71/STR-4229 1/30/2021 5 Checked by AE Rep.
228 Road Side Drain 339400 339450 RHS 50 VRC-SP/NH-71/STR-4569 2/10/2021 6 Checked by AE Rep.
229 Road Side Drain 339450 339500 RHS 50 VRC-SP/NH-71/STR-4133 1/28/2021 5 Checked by AE Rep.
230 Road Side Drain 339500 339580 RHS 80 VRC-SP/NH-71/STR-4187 1/29/2021 5 Checked by AE Rep.
231 Road Side Drain 343810 343900 RHS 90 VRC-SP/NH-71/STR-10527 6/29/2022 22 Checked by AE Rep
232 Road Side Drain 343900 343910 RHS 10 VRC-SP/NH-71/STR-10206 5/30/2021 21
233 Road Side Drain 343910 344000 RHS 90 VRC-SP/NH-71/STR-9705 4/17/2021 20 Checked by AE Rep.
234 Road Side Drain 344060 344100 RHS 40 VRC-SP/NH-71/STR-7851 8/31/2021 12 Checked by AE Rep.
235 Road Side Drain 344100 344170 RHS 70 VRC-SP/NH-71/STR-7559 7/29/2021 11 Checked by AE Rep.
236 Road Side Drain 343380 343450 RHS 70 VRC-SP/NH-71/STR-10699 7/31/2022 23 Checked by AE Rep.
237 Road Side Drain 343450 343500 RHS 50 VRC-SP/NH-71/STR-10691 7/30/2022 23 Checked by AE Rep.
238 Road Side Drain 343500 343550 RHS 50 VRC-SP/NH-71/STR-10700 7/31/2022 23 Checked by AE Rep.
239 Road Side Drain 343550 343600 RHS 50 VRC-SP/NH-71/STR-10686 7/29/2022 23 Checked by AE Rep.
240 Road Side Drain 343600 343650 RHS 50 VRC-SP/NH-71/STR-10677 7/28/2022 23 Checked by AE Rep.
241 Road Side Drain 343650 343700 RHS 50 VRC-SP/NH-71/STR-10667 7/27/2022 23
242 Road Side Drain 343700 343750 RHS 50 VRC-SP/NH-71/STR-10668 7/27/2022 23
243 Road Side Drain 343750 343810 RHS 60 VRC-SP/NH-71/STR-10656 7/26/2022 23 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
244 Road Side Drain 344170 344250 RHS 80 VRC-SP/NH-71/STR-7582 7/30/2021 11 Checked by AE Rep.
245 Road Side Drain 344250 344300 RHS 50 VRC-SP/NH-71/STR-7601 7/30/2021 11
246 Road Side Drain 344300 344350 RHS 50 VRC-SP/NH-71/STR-7850 8/31/2021 12 Checked by AE Rep.
247 Road Side Drain 344350 344400 RHS 50 VRC-SP/NH-71/STR-7602 7/31/2021 11
248 Road Side Drain 344400 344490 RHS 90 VRC-SP/NH-71/STR-7825 8/30/2021 12 Checked by AE Rep.
249 Road Side Drain 344490 344590 RHS 100 VRC-SP/NH-71/STR-7826 8/30/2021 12
250 Road Side Drain 344590 344680 RHS 90 VRC-SP/NH-71/STR-7827 8/30/2021 12
251 Road Side Drain 345810 345900 RHS 0 VRC-SP/NH-71/STR-9278 2/23/2022 18
252 Road Side Drain 345810 345835 RHS 25 VRC-SP/NH-71/STR-10207 5/30/2022 22
253 Road Side Drain 345835 345900 RHS 65 VRC-SP/NH-71/STR-11532 11/27/2022 27 Checked by AE Rep.
254 Road Side Drain 345900 345980 RHS 80 VRC-SP/NH-71/STR-9120 1/28/2022 17 Checked by AE Rep.
255 Road Side Drain 345980 346030 RHS 50 VRC-SP/NH-71/STR-9138 1/29/2022 17 Checked by AE Rep.
256 Road Side Drain 346030 346070 RHS 40 VRC-SP/NH-71/STR-10550 5/30/2022 22
257 Road Side Drain 346070 346100 RHS 30 VRC-SP/NH-71/STR-11533 11/27/2022 27 Checked by AE Rep.
258 Road Side Drain 346100 346180 RHS 80 VRC-SP/NH-71/STR-9291 2/24/2022 18 Checked by AE Rep.
259 Road Side Drain 346180 346260 RHS 80 VRC-SP/NH-71/STR-9297 2/25/2022 18 Checked by AE Rep.
260 Road Side Drain 346260 346320 RHS 60 VRC-SP/NH-71/STR-9311 2/26/2022 18 Checked by AE Rep.
261 Road Side Drain 346320 346400 RHS 80 VRC-SP/NH-71/STR-9318 2/27/2022 18 Checked by AE Rep.
262 Road Side Drain 346400 346470 RHS 70 VRC-SP/NH-71/STR-9395 3/9/2022 19 Checked by AE Rep.
263 Road Side Drain 346470 346500 RHS 30 VRC-SP/NH-71/STR-11534 11/27/2022 27 Checked by AE Rep.
264 Road Side Drain 346550 346590 RHS 40 VRC-SP/NH-71/STR-11535 11/27/2022 27 Checked by AE Rep.
265 Road Side Drain 346590 346650 RHS 60 VRC-SP/NH-71/STR-9424 3/12/2022 19 Checked by AE Rep.
266 Road Side Drain 346650 346700 RHS 50 VRC-SP/NH-71/STR-9394 3/9/2022 19
267 Road Side Drain 346700 346760 RHS 60 VRC-SP/NH-71/STR-9319 2/27/2022 18 Checked by AE Rep.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71
to Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana
Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period
Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(ii) Road side drains
Quantity
tatement No. SPS-23Description
& COS-1 (RA-7) (10%)
CHAINAGE Side RFI NO Date SPS No. Remarks
(m)
268 Road Side Drain 346760 346820 RHS 60 VRC-SP/NH-71/STR-9312 2/26/2022 18 Checked by AE Rep.
269 Road Side Drain 346820 346900 RHS 80 VRC-SP/NH-71/STR-9298 2/25/2022 18 Checked by AE Rep.
270 Road Side Drain 346900 346980 RHS 80 VRC-SP/NH-71/STR-8703 12/24/2021 17 Checked by AE Rep.
271 Road Side Drain 346980 347060 RHS 80 VRC-SP/NH-71/STR-8704 12/24/2021 17 Checked by AE Rep.
272 Road Side Drain 347060 347120 RHS 60 VRC-SP/NH-71/STR-8123 9/30/2021 13
273 Road Side Drain 352900 352950 RHS 50 VRC-SP/NH-71/STR-9862 4/29/2021 20 Checked by AE Rep.
274 Road Side Drain 352950 353040 RHS 90 VRC-SP/NH-71/STR-9475 3/21/2022 19 Checked by AE Rep.
275 Road Side Drain 353040 353130 RHS 90 VRC-SP/NH-71/STR-9487 3/22/2022 19
276 Road Side Drain 353130 353190 RHS 60 VRC-SP/NH-71/STR-9511 3/24/2022 19 Checked by AE Rep.
277 Road Side Drain 353190 353290 RHS 100 VRC-SP/NH-71/STR-9522 3/25/2022 19
278 Road Side Drain 353300 353390 RHS 90 VRC-SP/NH-71/STR-9838 28-04-2022 20 Checked by AE Rep.
279 Road Side Drain 353390 353480 RHS 90 VRC-SP/NH-71/STR-9839 28-04-2022 20 Checked by AE Rep.
280 Road Side Drain 353480 353560 RHS 80 VRC-SP/NH-71/STR-9855 29-04-2022 20 Checked by AE Rep.
281 Road Side Drain 353560 353650 RHS 90 VRC-SP/NH-71/STR-10153 5/26/2021 21
282 Road Side Drain 353650 353710 RHS 60 VRC-SP/NH-71/STR-10167 5/27/2021 21 Checked by AE Rep.

Total Qty RHS 12210 m B


Total Qty (Both Side) 12.048 Km. C=(A + B)/2
Previous Qty. (Both Side) 12.048 Km. D
Net Payable Qty (Both Side) 0.000 Km. E=(C - D)
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-
71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37
OTHER WORKS
(Viii) Utility duct
S No. Description Chainage Road Side item Nos RFI Date SPS No
1 Checking Pipe Laying for Utility Duct 308+805 BHS Utility Duct 1.000 VRC-SP/NH-71/HW-4689 2/15/2021 17
2 Checking of Utility Pipe Laying 312+650 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9295 2/25/2022 18
3 Checking Pipe Laying for Utility Duct 322+484 BHS Utility Duct 1.000 VRC-SP/NH-71/HW-4283 2/1/2021 17 Checked by AE Rep.
4 Checking Pipe Laying for Utility Duct 324+421 BHS Utility Duct 1.000 VRC -SP/NH-71/STR-6211 09-May-21 11
5 Checking Pipe Laying for Utility Duct 324+740 BHS Utility Duct 1.000 VRC -SP/NH-71/STR-6212 09-May-21 11
6 Checking Pipe Laying for Utility Duct 328+900 RHS Utility Duct 0.500 VRC -SP/NH-71/STR-8401 16-Nov-21 15 Checked by AE Rep.
7 Checking Pipe Laying for Utility Duct 328+900 LHS Utility Duct 0.500 VRC -SP/NH-71/STR-9165 02-Feb-22 18 Checked by AE Rep.
8 Checking Pipe Laying for Utility Duct 334+820 RHS Utility Duct 0.500 VRC -SP/NH-71/STR-8402 16-Nov-21 15
9 Checking Pipe Laying for Utility Duct 334+800 LHS Utility Duct 0.500 VRC -SP/NH-71/STR-8377 29-Oct-21 14
10 Checking Pipe Laying for Utility Duct 339+700 LHS Utility Duct 0.500 VRC -SP/NH-71/STR-8279 20-Oct-21 14
11 Checking Pipe Laying for Utility Duct 339+700 RHS Utility Duct 0.500 VRC -SP/NH-71/STR-8500 04-Dec-22 16 Checked by AE Rep.
12 Checking Pipe Laying for Utility Duct 341+020 LHS Utility Duct 0.500 VRC -SP/NH-71/STR-8284 21-Oct-21 14
13 Checking Pipe Laying for Utility Duct 341+020 RHS Utility Duct 0.500 VRC -SP/NH-71/Str-9006 16-Jan-22 17 Checked by AE Rep.
14 Checking Pipe Laying for Utility Duct 341+700 RHS Utility Duct 0.500 VRC -SP/NH-71/STR-11737 30-Dec-22 28 Checked by AE Rep.
15 Checking Pipe Laying for Utility Duct 341+800 LHS Utility Duct 0.500 VRC -SP/NH-71/STR-8290 22-Oct-21 14
16 Checking for Pipe Laying of Utility Duct 348+950 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9239 2/16/2022 18
17 Checking for Pipe Laying of Utility Duct 349+000 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9240 2/16/2022 18
18 Checking for Pipe Laying of Utility Duct 350+000 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9272 2/23/2022 18
19 Checking for Pipe Laying of Utility Duct 350+950 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9273 2/23/2022 18 Checked by AE Rep.
20 Checking for Pipe Laying of Utility Duct 351+450 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9274 2/23/2022 18 Checked by AE Rep.
21 Checking for Pipe Laying of Utility Duct 353+750 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9275 2/23/2022 18 Checked by AE Rep.
22 Checking for Pipe Laying of Utility Duct 354+500 BHS Utility Duct 1.000 VRC-SP/NH-71/STR-9285 2/23/2022 18

Total Qty (Both Side) 17.000 Nos.


Previous Qty. (Both Side) 17.000 Nos.
Net Payable Qty (Both Side) 0.000 Nos.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to
Km 9.400 of NH-71A (Balance Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL 01.09.2023 30.09.2023
SPS No.-37

OTHER WORKS (Junction)

0
Type of
S No. Description Chainage Road Side Nos RFI Date SPS No
Junction

Checked by AE
1 Major Junction 320600 RHS Y 1 VRC-SP/NH-71/HW-8963 6/21/2022 22
Rep

2 Major Junction 326+375 BHS Y 1 VRC -SP/NH-71/HW-6303 03-Sep-21 13


3 Minor Junction 326+575 RHS T 1 37
4 Minor Junction 327+045 LHS T 1 37
5 Minor Junction 331+090 RHS T 1 37
6 Minor Junction 331+570 RHS T 1 37
7 Minor Junction 338+900 LHS X 1 37
8 Minor Junction 338+900 RHS X 1 37

Total Qty (Both Side) 8.000 Nos.


Previous Qty. (Both Side) 2.000 Nos.
Net Payable Qty (Both Side) 6.000 Nos.
Four Laning of Rohtak - Jind Section from Km 307.000 to Km 347.800 of NH-71 and connecting link from Km 347.800 of NH-71 to Km 9.400 of NH-71A (Balance
Work) on EPC Mode under Bharatmala (Left out in NHDP) in the state of Haryana

Client : NATIONAL HIGHWAYS AUTHORITY OF INDIA Period


Contractor : M/s VRC-SPIDPL (JV) From To
Authority's Engineer : M/s ICT Private Limited in association with VESPL : 01-09-2023 to 30-09-2023
SPS No.-37
OTHER WORKS- Plantation work
0
Chainage Quantity
S No. Description Chainage To side RFI Date SPS No
From (Km)
1 Checking of median plantation work 323000 323800 BHS 800 VRC -SP/NH-71/Hw-10128 1/31/2023 29
2 Checking of median plantation work 325300 326250 BHS 950 VRC -SP/NH-71/Hw-10129 1/31/2023 29
3 Checking of median plantation work 326700 328460 BHS 1760 VRC -SP/NH-71/Hw-10130 1/31/2023 29
4 Checking of median plantation work 331600 332700 BHS 1100 VRC -SP/NH-71/Hw-10131 1/31/2023 29
5 Checking of median plantation work 333500 334700 BHS 1200 VRC -SP/NH-71/Hw-10132 1/31/2023 29
Total Qty (Both Side) 5.81
Hold Qty (Both Side) 2.905
Total Recommended Qty (Both Side) 2.905
Previous Qty. (Both Side) 2.905
Net Payable Qty (Both Side) 0