Answer: b
10. During reorder point planning, which time elements does the forward
scheduling procedure take into account when calculating the availability date?
There are 3 correct answers to this question.
a) Purchasing department processing time
b) Total shelf life
c) Goods receipt processing time
d) Planned delivery time
e) Goods issue processing time
Answer: a, c, d
ECC Questions
01. You want to maintain the settings for the 'default values for purchasing'
(EVO) parameter in SAP Materials Management.
Which document type can you assign for the order acknowledgment
requirement in the Indicator tab?
Please choose the correct answer.
a) Request for quotation
b) Scheduling agreement
c) Reservation
d) Purchase requisition
Answer: b
Answer: d
09. You want to post a goods issue from stock in quality inspection. In which
of the following cases is this possible?
There are 2 correct answers to this question.
a) Withdrawal for scrapping
b) Withdrawal for inspection sample
c) Withdrawal for a reservation
d) Withdrawal for a cost center
Answer: a, b
10. What does the item category specify in a purchasing document in SAP
Materials Management?
Please choose the correct answer.
a) Whether items without a material number are possible
b) Whether items without valuation are possible
c) Whether items with order acknowledgment are possible
d) Whether items with unlimited deliveries are possible
Answer: a
05. Occasionally a vendor delivers goods without a purchase order. You want
the system to create a purchase order for such deliveries automatically when a
goods receipt is posted.
What is a prerequisite for this scenario?
There are 2 correct answers to this question.
a) Automatic purchase order creation must be allowed for the movement type with
which you post the goods receipt.
b) Automatic purchase order creation must be allowed for the plant and storage
location to which you post the goods receipt.
c) A standard purchasing organization must be assigned to the company code to which
you post the goods receipt.
d) A reference purchasing organization must be assigned to the plant to which you post
the goods receipt.
Answer: a, c
06. In Customizing for Logistics Invoice Verification, the following values are
defined for the stochastic block:
- Threshold value: 10000
- Percentage: 40
You enter an invoice with a value of 7500.
What is the probability that the invoice will be blocked stochastically?
Please choose the correct answer.
a) 30%
b) 40%
c) 32.5%
d) 20%
Answer: a
07. Which of the following is a prerequisite for transfer postings between two
materials ("material to material")?
Please choose the correct answer.
a) The materials being transferred must have the same valuation class.
b) The materials being transferred must have the same material type.
c) The materials being transferred must have the same material group.
d) The materials being transferred must have the same base unit of measure.
Answer: d
08. What does the material type influence in the material master in SAP
Materials Management?
There are 2 correct answers to this question.
a) MRP type
b) Quantity and value update
c) Account group
d) Procurement type
Answer: b, d
09. Which of the following are SAP Solution Manager usage scenarios?
There are 2 correct answers to this question.
a) Legacy system data mapping
b) Implementation of SAP solutions
c) User productivity monitoring
d) Service desk
Answer: b, d
10. What is mandatory in a purchase order for a non-valuated material?
Please choose the correct answer.
a) Set the indicator for goods receipt.
b) Select an account assignment category and assign an account assignment object.
c) Set the indicator for non-valuated goods receipts.
d) Set the indicator for invoice receipt.
Answer: b
01. For which of the following objects can you use a standard movement type
to post a goods issue directly from the valuated stock?
There are 3 correct answers to this question.
a) Production order
b) Work center
c) Project (WBS element)
d) Profit center
e) Cost center
Answer: a, c, e
02. You have received an order confirmation from a vendor. What do you have
to do before you can enter the confirmed delivery date and confirmed quantity
in a purchase order item?
Please choose the correct answer.
a) Set the Goods Receipt indicator.
b) Set the Confirmation Received indicator in the header.
c) Use a confirmation control key in the relevant purchase order item.
d) Set the Acknowledgement Required indicator in the vendor master of the relevant
vendor.
Answer: c
03. In which of the following cases can invoices be released automatically?
There are 2 correct answers to this question.
a) The invoice was blocked due to a price variance. The buyer has now changed the
price in the purchase order to the invoice price
b) The invoice was blocked stochastically
c) The invoice was blocked manually because the invoice price was lower than the
order price. The buyer has now changed the price in the purchase order to the invoice
price
d) The invoice was blocked on the entry date due to date variance. The current date is
identical to the delivery date of the order item for which the invoice was blocked.
Answer: a, d
04. Which of the following objects can you reference when you enter an
invoice in Logistics Invoice Verification?
There are 2 correct answers to this question.
a) A service entry sheet
b) A material document
c) A vendor delivery note
d) A different invoice from the vendor
Answer: a, c
05. You want to generate purchase requisitions with the consignment item
category in material requirements planning (MRP). Which setting do you need
to make to do this?
Please choose the correct answer.
a) Enter a consignment contract item for the relevant material as a fixed source of
supply in the source list
b) Enter a consignment info record for the relevant material as a fixed source of supply
in the source list
c) Set the Regular Vendor indicator in a consignment info record for the relevant
material
d) Select Consignment as the special procurement type in the material master record
Answer: d
06. Which field attribute is given the highest priority in the field selection
control?
Please choose the correct answer.
a) Optional field
b) Required entry field
c) Suppress
d) Display
Answer: c Answer: c
07. You want to transfer materials between two plants using stock transport
orders. Which stock types can you use for postings with reference to stock
transport orders in these plants?
Please choose the correct answer.
a) Issuing plant: Unrestricted-use stock Receiving plant: Quality inspection stock or
blocked stock
b) Issuing plant: Unrestricted-use stock or quality inspection stock Receiving plant:
Unrestricted-use stock or quality inspection stock
c) Issuing plant: Unrestricted-use stock, quality inspection stock, or blocked stock
Receiving plant: Unrestricted-use stock, quality inspection stock, or blocked stock
d) Issuing plant: Unrestricted-use stock Receiving plant: Unrestricted-use stock, quality
inspection stock, or blocked stock
Answer: d
08. From which stock type can goods issues to cost centers be posted?
Please choose the correct answer.
a) Non-valuated blocked stock
b) Valuated blocked stock
c) Quality inspection stock
d) Unrestricted-use stock
Answer: d
09. When the procurement process is without a material master in SAP
Materials Management, which configuration element do you assign to the
valuation class?
Please choose the correct answer.
a) Item category
b) Material group
c) Valuation area
d) Material type
Answer: b
10. Which are the configuration options that can be defined to post unplanned
delivery costs?
There are 3 correct answers to this question.
a) The unplanned delivery costs are to be posted to separate G/L accounts
b) The unplanned delivery costs are to be distributed prorated to calculated invoice
items
c) The unplanned delivery costs can be posted by rules defined within a BAdI
d) The unplanned delivery costs are to be posted to a price difference account
e) The unplanned delivery costs are to be split in equal shares across the invoice items
Answer: a, b, c