Create and Implement Requirements Iso - Fsms 22000 - 2018
Create and Implement Requirements Iso - Fsms 22000 - 2018
VERSION / 001
01/AUGUST/2023
VERSION HISTORY
REVISION
VERSION APPROVED BY DATE DESCRIPTION OF CHANGE AUTHOR
Create project management plan for create and
001 CEO Aug 1, 2023 Yasser Abdelbaset
implement ISO/ FSMS 22000:2028
PREPARED
BY Yasser Abdelbaset TITLE QA& Food Safety Manager DATE Aug 1, 2023
APPROVED
BY
TITLE CEO DATE
Page 1 of 21
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY ........................................................................................................................ 3
Page 2 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
1. EXECUTIVE SUMMARY
Use the project charter to summarize the purpose of the project. Detail goals and objectives.
The purpose of this project is to create and implement a Food Safety Management System (FSMS) in
accordance with the requirements of the ISO 22000:2018 standard across our YASSER Company. The
goal is to systematically manage all aspects of food safety, ensuring that our products are safe for
consumption and meet the highest international standards.
Training and Education: Provide comprehensive training to all relevant staff members on the FSMS
and ISO 22000:2018 requirements. This will ensure that all employees understand their roles and
responsibilities in maintaining food safety and are competent to carry out those roles.
Continuous Improvement: Establish mechanisms for continuous improvement of the FSMS. This
includes monitoring and measurement of processes, internal audits, management review, and taking
corrective actions as needed.
In fulfilling these objectives, we aim to enhance our operational efficiency, improve customer
satisfaction, comply with regulatory requirements, and strengthen our market positioning. The successful
completion of this project will mark a significant milestone in our commitment to food safety and
quality, reinforcing our reputation as a trusted provider in the food industry.
Page 3 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
• All kitchens and restaurants that are operated by the YASSER company.
• Development of a Food Safety Management System compliant with ISO 22000 standards.
• Training of all staff at all restaurant and kitchen chain locations regarding ISO 22000
standards, based on food safety management system.
• Regular audits to ensure compliance with ISO 22000 across all locations.
• Obtaining ISO 22000 certification for all restaurant and kitchen chain locations.
• Developing and implementing procedures and SOP’s for (operation restaurants and kitchen
process, HR process, MCR SOP, Marketing SOP, Supply chain SOP, maintenance
Procedures, continuous improvement and maintenance of the ISO 22000 standard SOP’s,
Procedures and HACCP system.
1.2 DELIVERABLES
• A documented Food Safety Management System compliant with ISO 22000 requirements,
such as FSMS Procedures, Food Safety Management System Procedures:
1. Quality manual File
2. Prerequisites Program Systems (PRP's)
3. PRP's Procedures
4. Forms and Records Template File
5. HACCP Plan and Manual
6. Checklist and Internal Audit System
7. Non-conforming System
8. Meeting Management Review File
9. Training File with PPT File
• Training programs for staff at all levels on ISO 22000 standards and procedures.
• Regular audit reports demonstrating compliance with ISO 22000.
• ISO 22000 certification for all restaurant and kitchen chain locations.
Page 4 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
This WBS is a high-level overview and can be expanded to include more specific tasks and subtasks.
For example, under "FSMS Development", you might include specific tasks for developing each part
of the FSMS (such as a hazard analysis plan, a control measure plan, a verification plan, etc.).
Similarly, under "Training and Education", you might include tasks for developing different training
modules, scheduling, and conducting training sessions and evaluating training effectiveness.
7. Implementation of FSMS
3.1 Implement FSMS SOP and procedures in all kitchens and restaurants
3.2 Monitor and measure the effectiveness of FSMS
3.3 Adjust and improve processes as necessary
8. Continuous Improvement
4.1 Develop a system for continuous monitoring and improvement
4.2 Conduct regular internal audits
4.3 Implement corrective actions based on audit results
4.4 Conduct management reviews and make necessary adjustments.
9. Certification
5.1 Prepare for certification audit
5.2 Successfully complete an audit by a recognized certification body
5.3 Obtain ISO 22000:2018 certification for all locations.
Page 5 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
Identifying and understanding the stakeholders is crucial for the success of the project. Stakeholders,
in this context, are individuals or groups who have an interest in the project, are affected by the
project, or can influence its outcome. Below is a basic analysis of the key stakeholders for the Food
Safety Management System (FSMS) implementation project:
1. Management Team: The management team of YASSER Company has a vested interest in
the success of this project as it directly affects the company's reputation, customer
satisfaction, and regulatory compliance. They are responsible for providing resources and
strategic direction for the project.
2. Employees: All employees, especially those in the kitchens and restaurants, will be directly
affected by the implementation of the FSMS. They will need to be trained on the new system
and will be responsible for adhering to the new policies and procedures.
3. Customers: As the end consumers of the products, customers have a high interest in food
safety. While they do not have direct involvement in the project, the main goal of
implementing FSMS and achieving ISO 22000:2018 certification is to ensure customer
confidence and satisfaction.
4. Regulatory Bodies: Entities such as the local health department and food safety inspectors
are external stakeholders who will verify the company's compliance with food safety
regulations. Achieving ISO 22000:2018 certification will show these bodies that the company
is committed to maintaining high food safety standards.
5. ISO Certification Body: This external organization will conduct the audit for ISO
22000:2018 certification. Their role is crucial in validating the company's adherence to the
ISO standard.
6. Suppliers: Suppliers are a key part of the company's operations. They need to be aware of the
company's food safety policies to ensure the raw materials supplied meet the required safety
standards.
Page 6 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
Page 7 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
A Change Management Plan guides how changes to the project will be managed and controlled. It is
crucial to ensure that changes are beneficial, consistent, and approved in order to prevent scope creep
and to keep the project on track.
For our FSMS implementation project, we will follow a structured change control process.
Change Submission: Anyone involved in the project can submit a change request, including team
members, stakeholders, suppliers, or even customers. Requests should be in writing and should
include a detailed description of the change, the reasons for the change, the potential impacts on the
project, and any other relevant information.
Change Evaluation: Once a change request is received, it will be reviewed by the project manager
to assess its validity and potential impact on the project. This includes assessing the impact on the
project's scope, schedule, cost, and quality.
Change Approval: If the change is deemed to be substantial and impactful, it will be escalated to the
top management for review. which consists of key stakeholders, will decide whether to approve,
reject, or defer the change based on its potential benefits and drawbacks.
Change Implementation: If a change is approved, the project manager will update the project plan,
schedule, and other relevant documentation. The project team will then implement the change.
Change Tracking and Communication: All changes, regardless of whether they are approved or
rejected, will be tracked in a change log. This log will include information on the change request, the
Page 8 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
decision made, and any actions taken. Changes will be communicated to all relevant stakeholders
through regular project updates.
While this process is intended to be comprehensive, it is also designed to be flexible. The nature of
changes can vary significantly, and as such, the process may need to be adapted depending on the
specifics of the change being considered.
Please note that this project will adhere to the organization's standard change management policies
and procedures, where applicable. If there are any conflicts between the project's Change
Management Plan and the organization's policies, the organization's policies will take precedence.
The project scope management plan is a critical part of our project to implement ISO/FSMS
22000:2018. It outlines how the project's scope will be defined, validated, and controlled.
Scope Management Authority: The Project Manager, who is responsible for overseeing the
implementation of ISO/FSMS 22000:2018, has the authority to manage the project scope. This
includes ensuring that all work completed aligns with the project's aim to meet the ISO/FSMS
22000:2018 standards.
Scope Measurement: The project scope will be measured based on the requirements outlined by
ISO/FSMS 22000:2018. This includes developing an FSMS, training staff, implementing the FSMS,
continuous improvement and obtaining certification. The Work Breakdown Structure (WBS) and the
ISO/FSMS 22000:2018 requirements will serve as the key reference points for scope measurement.
Scope Verification and Approval: The Change Control Board (CCB), which includes key
stakeholders, will approve any changes to the project scope. Changes must be reviewed and approved
through the established change management process (see section 1.7, Change Management Plan).
Page 9 of 21
2. COMMUNICATION MANAGEMENT PLAN
A communication plan defines who needs information and updates on the project, what information they need, how frequently those people must
be updated, and how they will be updated. A communication management plan is often used in tandem with a stakeholder list. Outline the plan
here or link to a separate document.
NAME TITLE EMAIL OFFICE PHONE
MESSAGE
COMMUNICATION TYPE DESCRIPTION FREQUENCY DELIVERABLE DELIVERABLE OWNER
DISTRIBUTION
Discuss project
In-person/Online
Project Meetings progress, issues, and Weekly Meeting minutes Project Manager
Meetings
updates
Detailed project updates Every 2
Project Reports Email Project status report Project Manager
and changes weeks
High-level project
Email/In-person
Executive Updates updates, risks, and Monthly Executive update report Project Manager
meetings
major changes
Information about
Training schedule and
Training Communications upcoming training As needed Email/Intranet Training Coordinator
materials
sessions and materials
Information related to
Supplier Communications product changes and As needed Email/Phone Supplier update report Supply Chain Manager
requirements
Communication related
Audit schedule and Quality Assurance
Audit Communications to audit schedules and As needed Email/Official letters
documentation Manager
required documentation
Page 10 of 21
3. RESOURCE MANAGEMENT PLAN
Procurement management can include all resources equipment and supplies. Also, detail whether goods or
services will be purchased or rented.
1. Human Resources:
• Project Manager: Responsible for overseeing the project, making key decisions, and coordinating
with stakeholders.
• ISO/FSMS Advisor: An external consultant contracted to provide expert advice, create an initial
assessment report, and assist in developing the FSMS in compliance with ISO 22000:2018
standards.
• Training Coordinator: Responsible for organizing and conducting training sessions for
employees.
• Quality Assurance Manager: Ensures compliance with ISO 22000:2018 standards and prepares
for the certification audit.
2. Non-Human Resources:
Þ ISO/FSMS 22000:2018 Standard: The organization needs to purchase the latest version of the
ISO 22000:2018 standard. This will serve as the main guideline for developing the FSMS.
Þ FSMS and HACCP Training Materials: These include training materials for FSMS and HACCP
levels 2, 3, and 4. They could be developed in-house or purchased from a reputable provider.
Þ ISO Training Material: Training materials specific to ISO 22000:2018 will also need to be
procured.
Þ Audit and Certification Services: The organization will need to contract with an ISO-accredited
body to conduct the certification audit.
3. Resource Procurement:
- Purchasing: The ISO/FSMS 22000:2018 standard and training materials will be purchased
following the organization's purchasing policies. The Project Manager will work with the
procurement department to ensure these resources are acquired in a timely manner.
- Contracting: Contracts will be established with an ISO consultation office for advisory services
and with an ISO-accredited body for audit and certification services. These contracts will be
managed by the Project Manager, in consultation with the legal and procurement teams.
Resources will be allocated based on the project schedule and individual task requirements. The Project
Manager will monitor resource usage throughout the project to ensure effective utilization and to prevent
any resource conflicts.
Page 11 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
Human Resources:
• Project Manager: Responsible for overseeing the project, making key decisions, and coordinating
with stakeholders.
• ISO/FSMS Advisor: An external consultant contracted to provide expert advice, create an initial
assessment report, and assist in developing the FSMS in compliance with ISO 22000:2018
standards.
• Training Coordinator: Responsible for organizing and conducting training sessions for
employees.
• Quality Assurance Manager: Ensures compliance with ISO 22000:2018 standards and prepares
for the certification audit.
Page 12 of 21
4.1 PROJECT STAFF LIST
NAME TITLE EMAIL PHONE
Page 13 of 21
4.2 RESOURCE REQUIREMENT CALENDAR
A resource calendar details key resources for the project. It describes what resources will be needed when and for how long. Note that not
all resources will necessarily be required for the duration. Complete this calendar or link to an external document.
Page 14 of 21
5. SCHEDULE MANAGEMENT PLAN
Explain methods for developing the schedule and what tools will be used to record and post the schedule and
any changes.
The Schedule Management Plan outlines the process and tools for developing, tracking, and managing
the project schedule for implementing the ISO/FSMS 22000:2018 Food Safety Management System
(FSMS).
Schedule Development:
The project schedule will be developed using the Work Breakdown Structure (WBS), taking into
consideration the phases and requirements of ISO 22000:2018 implementation:
• Task Identification: Based on the WBS, project tasks will be identified. This will include tasks
such as acquiring the ISO/FSMS 22000:2018 standard, contracting with the ISO consultation
office and ISO-accredited body, developing or procuring the necessary training materials, and
conducting training.
• Task Sequencing: Tasks will be sequenced based on their dependencies and the requirements of
the ISO 22000:2018 standard. For example, the procurement of the ISO standard and contracting
with the consultation office must occur before the assessment report can be created.
• Duration Estimation: The duration of each task will be estimated based on the resources
allocated, the complexity of the task, and the requirements of the ISO 22000:2018 standard.
Schedule Tools:
A variety of tools will be used to manage the project schedule:
• Project Management Software: Software like Microsoft Project, Asana, or Trello will be used
to develop, track, and update the project schedule. These tools facilitate collaboration, allow for
easy tracking of task status, and provide visual representations of the project timeline.
• Gantt Chart: A Gantt chart will be developed using the project management software. This will
provide a visual representation of the project schedule, showing when each task is scheduled to
start and end, the duration of each task, and the dependencies between tasks.
• Change Log: A change log will be maintained to record any changes to the schedule, including
what the change was, why it was made, and the impact on the project schedule.
Schedule Control:
The project schedule will be continuously monitored and controlled throughout the project:
• Regular Reviews: The project schedule will be reviewed regularly, typically at project team
meetings. If tasks are falling behind schedule, the team will identify why this is happening and
develop a plan to get back on track.
• Change Management: If changes to the schedule are necessary, they will undergo a change
management process. This will include evaluating the impact of the change, gaining the
necessary approvals, and updating the project schedule and change log.
This Schedule Management Plan is designed to ensure that the ISO/FSMS 22000:2018 project stays on
track and that any deviations from the schedule are promptly addressed. The plan will be reviewed and
updated as needed throughout the project.
Page 15 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
The Quality Management Plan outlines the approach towards ensuring the quality of all deliverables and
processes in line with the ISO/FSMS 22000:2018 project requirements.
Quality Standards:
The primary quality standard for this project is ISO 22000:2018. All deliverables, including the Food
Safety Management System (FSMS), training materials, and processes, will need to adhere to the
requirements outlined in this standard.
Quality Governance:
Quality governance will be implemented through the following mechanisms:
• Quality Assurance: The Project Manager and Quality Assurance Manager will be responsible
for ensuring that all project deliverables meet the quality standards set out in ISO 22000:2018.
• Quality Audits: Regular internal audits will be conducted to ensure compliance with ISO
22000:2018 and to identify areas for improvement. The results of these audits will be shared with
the project team and key stakeholders.
Quality Metrics:
Quality metrics will be used to measure the effectiveness of the FSMS and the project's adherence to ISO
22000:2018. These metrics could include:
• Compliance rate with ISO 22000:2018: This measures the extent to which the organization's
FSMS complies with the ISO 22000:2018 standard.
• Number of non-compliance issues identified in audits: This measures the number of instances
where the organization's FSMS does not comply with ISO 22000:2018.
• Employee training completion rate: This measures the percentage of employees who have
completed the necessary ISO/FSMS and HACCP training.
Page 16 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
The Risk Management Plan outlines the processes for identifying, analyzing, prioritizing, tracking, and
responding to project risks in the implementation of the ISO/FSMS 22000:2018 Food Safety
Management System (FSMS).
Risk Identification:
Risk identification will be a continuous process throughout the project. The project team will use a
variety of methods to identify potential risks, including brainstorming sessions, historical data analysis,
and consultation with experts. Risks could include things like delays in procuring the ISO 22000:2018
standard, resistance to change within the organization, or issues with the ISO-accredited body.
Risk Tracking:
All identified risks will be recorded in a risk register. The risk register will include details about each
risk, including its description, its potential impact on the project, its likelihood of occurrence, and the
planned response strategy. The risk register will be reviewed and updated regularly.
Contingency Planning:
Contingency plans will be developed for high-impact, high-likelihood risks. These plans will outline the
steps that will be taken if the risk event occurs. For example, if there is a risk that the ISO-accredited
body is not available when needed for the audit, a contingency plan could involve identifying and
reaching out to alternate ISO-accredited bodies.
The Risk Management Plan is designed to ensure that potential threats to the successful implementation
of the ISO/FSMS 22000:2018 project are identified, analyzed, and addressed in a timely and effective
manner. This plan will be reviewed and updated as needed throughout the project.
Page 17 of 21
Project Plan/ Create and Implement Requirements ISO / FSMS-22000:2018
The risk log (also known as a risk register) provides a structured way to record and manage project
risks. Here is an example of a risk log for the ISO/FSMS 22000:2018 project:
Implement a
Conduct
change
additional
Resistance to management
training and
R2 change within High Medium High process and
communication
the organization engage
to address
stakeholders
resistance
early
Regular
communication
Have a list of
Issues with the with the ISO-
alternate ISO-
R3 ISO-accredited Low High Medium accredited body
accredited
body and monitor
bodies
their
performance
Detailed
Inadequate
resource Adjust project
resources for
R4 Medium High High planning and scope or
project
regular timeline
implementation
monitoring
Seek expert
Non-compliance Regular internal
advice and
with ISO audits and
R5 Low High Medium implement
22000:2018 training for
corrective
requirements employees
actions
This risk log provides a comprehensive overview of the potential risks facing the ISO/FSMS
22000:2018 project, along with strategies for mitigating these risks and contingency plans in case the
risks materialize. The risk log will be a living document, updated throughout the project as new risks
emerge and existing risks are managed.
Page 18 of 21
8. COST BASELINE
Detail the cost baseline for the project. This information provides the basis for tracking, reporting, and managing costs. Complete this table or
link to an external document.
PROJECT PHASE BUDGETED TOTAL COMMENTS
9. QUALITY BASELINE
Define the quality baseline for the project, which includes any tolerances or standards. Complete this table or link to an external document.
ITEM ACCEPTABLE LEVEL COMMENTS
Page 19 of 21
10. APPENDICES
Attach or link to separate plan documents or other reference documents. Optional.
ATTACHMENT NAME LOCATION / LINK
Page 20 of 21
11. AUTHORIZATION SIGNATURES
PREPARED BY
Signature Date
Yasser Abdelbaset
RECOMMENDED BY
Signature Date
APPROVED BY
CEO
Project Sponsor Name and Title
Page 21 of 21