PLT GBA-8 Time Estimation
PLT GBA-8 Time Estimation
Shut-in mode
1 RIH PLT to 9615 + spinner calibration 4/27/2024 9:30 4/27/2024 16:28 0
2 Log up 30 fpm 4/27/2024 16:28 4/27/2024 18:16 9615
3 RIH back to 9615 4/27/2024 18:16 4/27/2024 19:32 6825
4 Log up 60 fpm 4/27/2024 19:32 4/27/2024 20:33 9615
5 RIH back to 9615 4/27/2024 20:33 4/27/2024 21:49 6825
6 Log up 90 fpm 4/27/2024 21:49 4/27/2024 22:35 9615
7 RIH back to 9615 4/27/2024 22:35 4/27/2024 23:50 6825
8 POH & Station Log 4/27/2024 23:50 4/28/2024 4:29 9615
9 L/D Lubricator + Change Tractor + Rehead 4/28/2024 4:29 4/28/2024 7:29
10 Clean up well 4/28/2024 7:29 4/28/2024 13:29
Flowing Mode
11 RIH PLT to 9615 + spinner calibration 4/28/2024 15:29 4/28/2024 21:36 0
12 Log up 30 fpm 4/28/2024 21:36 4/28/2024 23:24 9615
13 RIH back to 9615 4/28/2024 23:24 4/29/2024 2:12 6825
14 Log up 60 fpm 4/29/2024 2:12 4/29/2024 3:13 9615
15 RIH back to 9615 4/29/2024 3:13 4/29/2024 5:47 6825
16 Log up 90 fpm 4/29/2024 5:47 4/29/2024 6:33 9615
18 POH & Station Log 4/29/2024 6:33 4/29/2024 10:30 6825
19 L/D Lubricator 4/29/2024 10:30 4/29/2024 13:30
20 Demob Tractor
Initial Tractoring End Tractoring Target Depth No Station Log Duration (hrs)