Detailed Quantity Surveying With Earthworks
Detailed Quantity Surveying With Earthworks
TOPICS COVERED:
● BILL OF QUANTITY
● TAKING OFF
● EARTHWORKS
BILL OF QUANTITY VS BILL OF MATERIALS
SECTION
PLAN
BOQ FORM:
EARTHWORKS
Takes place after clearing all obstructions at natural grade in the
construction site and staking.
3500
C1 C1
NGL
3000
1300
PLAN SECTION
EX 3. How much will it cost excavate 100 m³ using 10 men
at Php 327.00/day per man?
Given: 1 man can excavate 0.72 m³/day
EX 3. How much will it cost excavate 100 m³ using 10 men
at Php 327.00/day per man?
Given: 1 man can excavate 0.72 m³/day
Using 10 men:
Accomplishment/day = (Capability of 1 man per day) x (No. of men)
= (0.72 m³/day)(10 men)
= 7.20 m³/day
Number of days = Total volume of excavation / Accomplishment per day
= (100 m³) / (7.20 m³/day)
= 13.89 days = say 14 days
EX 3. How much will it cost excavate 100 m³ using 10 men
at Php 327.00/day per man?
Manpower cost:
Total Direct Cost = (Php 327/day/man)(10 men)(14 days)
= Php 45, 780.00
EX 4. How much will it cost backfill 85 m³ using 9 men
at Php 327.00/day per man?
Given: 1 man can compact 1.00 m³/day