LECTURE CONTENT SITUATION 3 - The table shown below tabulates the
activities for making a network diagram for a
✓ Basic Elements of Project Scheduling project together with duration and cost in normal ✓ Methods in Project Scheduling and accelerated conditions.
✓ Crashing of Project Network
Normal Conditions Accelerated ✓ Presidential Decree 1594 Activity Conditions ✓ Concrete Mix Design Duration Costs Duration Costs (Pesos) (Pesos) SITUATION 1 – The table below shows the schedule of 0-1 (A) 5 1000 3 1600 works necessary to carry out a construction 0-2 (B) 5 3000 4 4000 project. Critical Path Method is used for scheduling. 0-3 (D) 3 12000 2 12000 1-2 (C) 7 3000 5 3500 2-3 (E) 4 1000 3 1500 3-4 (F) 5 1000 3 1800
7. Determine the critical path.
A. A-C-E-F B. B-D-E-F C. A-B-E-F D. A-D-C-F 8. Determine the cost (in Pesos) if it is accelerated to the minimum duration. A. 21,700 B. 24,400 C. 22,500 D. 24,100 9. Determine which activity is the most cost effective in converting to the accelerated program. A. Activity A B. Activity D C. Activity C D. Activity F
SITUATION 4 – A project has been bid out by the
Department of Public Works and Highways. The Approved Agency Estimate is P 2,000,000. The result of responsive bids are as follows:
1. Determine the critical path for the project. Bidder A P 2,320,000
A. A-B-D-G-I-K B. A-C-H-J-K Bidder B P 2,600,000 C. A-B-E-I-K D. A-C-F-I-K Bidder C P 2,040,000 2. Determine the number of days required to carry Bidder D P 1,780,000 out the entire project A. 45 CD B. 65 CD Bidder E P 1,290,000 C. 55 CD D. 75 CD Bidder F P 1,650,000 3. Determine the total float of activity H. Bidder G P 2,440,000 A. 15 CD B. 25 CD Bidder H P 2,700,000 C. 20 CD D. 30 CD 4. Determine the free slack of activity F. 10. Determine which of the following are considered as responsive bidders. A. 18 CD B. 32 CD A. A,D,E,F B. C,D,F,G C. 27 CD D. 41 CD C. B,G,H D. A,C,D,E,F SITUATION 2 – The table below shows the schedule of 11. Which of the following most nearly gives the activities necessary for assembling computer. By value of Allowable Government Estimate? using Gantt Analysis, determine the following: A. P 1,911.667 B. P 2,051,250 C. P 1,908,000 D. P 1,880,000 12. Which of the following bidders should the project be awarded? B. Bidder A B. Bidder D C. Bidder C D. Bidder F
SITUATION 5 – The quantities and contract prices for
a government project are as follows:
Items Quantity Unit Price (Pesos)
AAE Contract Item 1 100 900 1,000 Item 2 50 12,000 10,000 Item 3 500 4,000 5,000 Item 4 60 7,500 6,000 Item 5 1,000 2,800 3,000 Item 6 400 2,000 1,500 5. Determine the number of days required to carry Item 7 3,000 2,100 2,000 out the entire project Item 8 20 20,000 25,000 A. A-C-F-G B. A-C-D-F-G C. A-B-E-F-G D. A-D-F-G 13. Which of the following most nearly gives the 6. Determine the critical path for the projects (in approved agency estimate (AAE)? weeks). C. P 13.95 M B. P 15.39 M A. 35 B. 41 C. P 14.34 M D. P 13.44 M C. 38 D. 44
14. Determine the complete list of the major items.
D. Items 2,5,7 B. Items 2,7 C. Items 5,7 D. Item 8 C. 0.681 B. 0.708 C. 0.693 D. 0.715 15. Which of the following need not be covered 24. Determine the required amount of cement in kN by a change order? for a 10 m3 concrete. D. 23.88 B. 36.79 A. Decrease in quantity from 50 to 37 for item C. 29.04 D. 41.35 2. 25. If the combined solid volume of cement, water, B. Decrease in quantity from 1000 to 750 for coarse aggregate, and entrapped air is 0.55 m3, item determine the weight of the dry sand (in kN). C. Increase in quantity from 500 to 625 for item D. Increase in quantity from 20 to 26 E. 11.65 B. 13.67 for item 8. C. 12.34 D. 14.52
SITUATION 9 – Section 426.12.2 of NSCP 2015 states
SITUATION 6 – The responsive bids for a government the provision for the frequency of testing for project with 8 bid items are as follows: concrete. It is required to determine the number of test sample per day for the following items: Item Qty AAE Bid A Bid B Bid C 1 100 1000 1000 500 800 Description Dimension Qty. 2 100 20000 27000 16000 19000 Column 1m x 1m x 3.50m 12 pcs. 3 500 5000 4000 3000 5000 Beam 1m x 1.7m x 6.0m 17 pcs. 4 60 6000 5000 6000 5000 Slab 6m x 6m x 0.20m 8 pcs. 5 1000 3000 2000 2500 3000 Shear Wall 6m x 3m x 0.30m 4 pcs. 6 400 1600 2000 1500 1200 26. Determine the required number of tests per day 7 3000 3000 3000 3500 2500 according to NSCP 2015. 8 20 25000 24000 12000 33000 F. 1 B. 3
16. Which of the following most nearly gives the C. 2 D. 4
total AAE? A. 64,600 B. 72,300 C. 71,500 D. 82,200 CONCEPTS 17. Determine the complete list of major items. B. Items 2,8 B. Items 2,4,8 Construction C. Item 2,4 D. Items 2,3,4,8 Is the mobilization and utilization of capital and 18. Determine the complete list of unbalanced bids. specialized personnel, materials, and equipment to A. Bid B B. Bids A,B,C assemble materials and equipment on a specific site C. Bids A,C D. Bids B,C in accordance with drawings, specifications, and contract documents prepared to serve the purpose of the client. SITUATION 7 – It is required to produce 25 cu. m. of Class B (1:2.5:5 mix) concrete using the below material properties. Assume 1 bag of cement has Construction Management volume of 0.028 cu. m. Use 26 liters of water per Is an arrangement whereby the tasks of planning, bag of cement. Determine the following: designing, and constructing may be integrated by a project team comprising the owner, the designer, consultants and the contractor working together at the construction stage of the project with the common objective of best serving the owner’s interest.
Basic Elements of Project Schedule
Activity on Arrow (AOA) 19. Number of bags of cement required. A project diagram in which activities are A. 143 B. 152 represented by arrows and are connected at points C. 148 D. 160 called nodes to illustrate activity sequencing. 20. The quantity of sand (cu. m.) required. A. 8.14 B. 10.38 C. 9.06 D. 11.45 21. The quantity of gravel (cu. m.) required. A. 17.18 B. 19.63 C. 18.44 D. 20.72 22. The quantity of water (liters) required. B. 3848 B. 3861 C. 3856 D. 3875 Event It denotes either the start or completion of an activity. Represents as nodes in network diagram. SITUATION 8 – The basic date for proportioning trial A. Successor Event – The event or events which batches for normal weight concrete with an average follow another event. compressive strength of 25 MPa at 28 days are as B. Predecessor Event – The event or events follows: which occur before another event.
Slump 75 mm to 100 mm Activity
Water-cement ratio by weight 0.48 It represents the distinct operation to be done as the project proceeds. An activity (except dummy S.G. of cement 3.15 activity) consumes time and resources as it S.G. of coarse aggregate 2.68 happens. It is represented by an arrow between two S.G. of fine aggregate 2.64 events in network diagram. Water (net mixing) 180 kg/m3 Dummy Activity Any activity which does not consume either any Entrapped air 1% resource or time (zero duration). It is an Unit weight of concrete 23.6 kN/m3 artificial activity represented by dotted line, which indicates that no succeeding activity shall 23. Determine the total solid volume (in m3) of commence until all previous activities are water, cement, coarse aggregates, and entrapped complete. air if the dry unit weight of coarse aggregate is 10.1 kN/m3. Duration (D) Estimated time it takes an activity Crashing of Project Network to be finished. It is when you shorten the duration of a project by reducing the time of one or more tasks. Early Start (ES) The earliest possible time an activity can start. Crashing is done by increasing the resources to the project, which helps make tasks take less time than Early Finish (EF) what they were planned for. The earliest possible time an activity can finish. EF = ES + D Of course, this also adds to the cost of the overall project. Therefore, the primary objective of project Late Start (LS) crashing is to shorten the project while also The latest possible time an activity can start keeping costs at a minimum. without delaying the project completion date. LS = LF - D Presidential Decree No.1594 PRESCRIBING POLICIES, GUIDELINES, RULES & REGULATIONS FOR Late Finish (LF) GOVERNMENT INFRASTRUCTURE CONTRACTS The latest possible time an activity can be A. Bids completed without delaying the overall project The implementing rules and regulation of P.D 1594 completion date. states that no award of contract shall be made to a Bidder whose bid price is higher than the allowable Backward Pass government estimate (AGE) or the Approved Agency The technique that determines the LATE START and Estimate (AAE) whichever is higher, or lower than LATE FINISH dates for each activity. seventy percent (70%) of the AGE.
Forward Pass For the purpose of these implementing rules and
The technique to determine the EARLY START and EARLY regulations, the AGE shall be equal to one-half the FINISH dates for each activity. sum of the AAE and the average of all responsive bids. Free Slack (FS) or Free Float (FF) The amount of time an activity can be delayed without For purpose of determining the average of all delaying the early start of any immediately following responsible bids, bids higher than One Hundred activity. Twenty Percent (120%) of the AAE or lower than FS or FF = ES NEXT ACTIVITY – EF CURRENT ACITIVITY sixty percent (60%) of the AAE shall not be considered. Total Slack (TS) or Total Float (TF) The amount of time an activity can be delayed from B. Unbalanced Bids its early start without delaying the planned project The implementing rules of PD 1594 defines an completion date. unbalanced bid as a bid containing one or more pay TF = LS – ES = LF – EF items that are 30% higher than the unit allowable government estimate (AGE) in respect to major items Methods in Project Scheduling whereas other pay items are priced lower than the 1. Gantt Analysis (GA) unit AGE. It is created by Henry Gantt during World War I for scheduling work in factories. Major items are defined as pay items representing at least 20% of the AAE or the first two items It is a technique that utilizes bar charts that having the highest percentage of the AAE or those illustrates a project schedule. It can show indicated or specified in the instruction to dependencies among activities and current schedule bidders. of those activities. C. Change Order GA lists the tasks in a chart to be performed on the The implementing rules and regulations of PD 1594 vertical axis, and time intervals on the horizontal states that for a unit price contract, quantity axis. The width of the horizontal bars in the graph overruns or underruns of not more than fifteen shows the duration of each activity. (15%) percent of the estimates per major pay item and twenty-five percent (25%) per minor pay item in It illustrates the start and finish dates of the the Bill of Quantities need not be covered by a Change Order provided that the same is authorized terminal elements and summary elements of a project. by the Approving Authority for the contract. However, they do not show relationships and dependencies between tasks as network diagrams do. Concrete Mix Design 2. Critical Path Method (CPM) For designing concrete mix, ABSOLUTE VOLUME METHOD It is a deterministic technique that requires is used. It calculates mix proportions by basis of mapping out every key task that is necessary to volume of components. complete a project. 𝑊𝑙𝑜𝑜𝑠𝑒 It includes identifying the amount of time necessary 𝑉𝑎𝑏𝑠𝑜𝑙𝑢𝑡𝑒 = to finish each activity and the dependencies of each 𝛾𝑏𝑢𝑙𝑘 activity on any others. 𝛾𝑙𝑜𝑜𝑠𝑒 = 𝛾𝑛𝑎𝑡𝑢𝑟𝑎𝑙 𝛾𝑏𝑢𝑙𝑘 It is used to set a realistic deadline for a project and to track its progress along the way. = 𝑆. 𝐺.× 𝛾𝑤𝑎𝑡𝑒𝑟
3. Program Evaluation & Review Technique (PERT)
A network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual duration estimates.
It uses probabilistic time estimates – estimates of
activity duration using optimistic, most likely and pessimistic estimates of activity duration. Thus, it attempts to address the risk associated with duration estimates. 𝑂𝑇 + 4 × 𝑀𝐿𝑇 + 𝑃𝑇 The table above is true, on the assumption that the 𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑇𝑖𝑚𝑒 = cement paste enters the void of the sand and at the 6 same instance, the composition of these two materials fill the voids of the gravel and thereafter, form a solid mass called concrete equivalent to 1 cubic meter. Frequency of Testing 426.12.2.1 Compliance Requirements: a. Samples for preparing strength test specimens of each concrete mixture placed each day shall be taken in accordance with (1) through (3):
1. At least once a day;
2. At least once for each 110 m3 of concrete; 3. At least once for each 460 m2 of surface area for slabs or walls.
b. On a given project, if total volume of
concrete is such that frequency of testing would provide fewer than five strength tests for a given concrete mixture, strength test specimens shall be made from at least five randomly selected batches or from each batch if fewer than five batches are used;
c. If the total quantity of a given concrete
mixture is less than 38 m3, strength tests are not required if evidence of satisfactory strength is submitted to and approved by the building official.
Correlational Relationship of Nursing Professional Subjects and Board Exam Performance of Isabela State University-Echague November 2022 Nursing Licensure Examination Takers
International Journal of Innovative Science and Research Technology