MEPF , Building , Equipment and Fitout Program March

Mo Tu We Th Fr Sa Su Mo Tu We
4 5 6 7 8 9 10 11 12 13
Scope of work

Sunken Bar
Stainless Steel Sink work Remodel
Beer taps
soft drinks mixer

Handover
Installation of water mixers
Installation of drainage pipes
Installation Equipments
Smoke Detectors / Manual call points
Handover
Pool Bar
MEP Main incomer power supply cable
MEP Installation of new switch board
MEP Installation of all cables with Breaker
MEP Installation of all Gas equipments
MEP Installation of all electrical Equipments
MEP Installation of Exdaust fans
MEP Installation of fresh air Fans
MEP Installation of power outlets
MEP Installation of led linear Lights
MEP Installation of sport led lights
MEP Installation of table ceiling lights
MEP Installation of area lights
MEP Installation of feature lights
BD Installation of ceiling fixing
BD Installation of ceiling fixing
Painter Undercoat paint ceiling
Painter One coat of finish paint
Pioneer Installation of smoke detectors
Pioneer Installation of manual call point
Pioneer Installation of MC detector board
Fit Fitout for complete bar area stones tops
FIT Fitout of all timber finsh
FIT Fitout feature wall
FIT Fitout any hardware for feature wall
BD Fitout of all ceiling
FIT Fitout of all feature ceiling items
Tile Fitout of any tiles which is outstanding
FIT Fitout of door and hardware
SM Fitout of all equipments for bar
SM Fitout of all Equipments for Kitchen Cold
SM Fitout of all equipment for hot kitchen
SM Fitout of items for dishwasher area
SM Fitout of equipment for Pizza Kitchen
Painter Paint finshing or stain Finshing
All General Check up work through
Landscape works
All Defect works or any remodel works
IT Fitout of all IT Items
All Inspection
Anil Handover

whiskey bar
MEP Main incomer power supply cable
MEP Installation of new switch board
MEP Installation of all cables with Breaker
MEP Installation of all electrical Equipments
MEP Installation of fresh air fans
MEP Installation of air conditioning
MEP Installation of exduest fan toilets
MEP Installation of power outlets
MEP Installation of led linear Lights
MEP Installation of led liner feature lights
MEP Installation of sport led lights
MEP Installation of table ceiling lights
MEP Installation of area lights
MEP Installation of wall feature lights
MEP Installation of ceiling feature lights
MEP Installation of down lights
Builder Installation of ceiling fixing
Builder Installation of ceiling feature fixing
Builder Installation of all ceiling and wall millwork
Painter Undercoat paint ceiling
Painter One coat of finish paint
MEP Installation of smoke detectors
MEP Installation of manual call point
MEP Installation of sprinkler heads
Builder Fitout for complete bar area stones tops
Builder Fitout of all timber finsh jointer
Builder Fitout feature wall jointer
Builder Fitout any hardware for feature wall
Builder Fitout of all ceiling art jointer
Builder Fitout of all feature met ceiling jointer
Builder Fitout of any tiles which is outstanding
Builder Fitout of door and hardware
Builder Installation new wall glass soundproof This need to be ordered
MEP Fitout of all equipments for bar
Builder Fitout of hardware for bar
MEP Fitout of taps ,sinks and drainage
MEP Fitout of dishwasher and drainage
Painter Paint finshing or stain Finshing
installation of toilet fitout male
Installation of toilets female
Fitout of projector
Fitout of projector screen
Fitout for guest network
Fitout the phone
Fitout for sound system Cables
Fitout for the unit
Fitout for DJ equipment
Fitout for DJ light control
Fitout for DJ sound control
Fitout point of sale unit
Fitout beerunits and taps
Fitout soft drink mixer
General Check up work through = for any changers which can address
Back area Landscape works
Defect works or any remodel works
Fitout of all IT Items
Inspection
FF&E set up
Handover

Resort HV system
EFL main incomer 11KVA new line
Switch Gear connection EFL side
Switch Gear connection Generator
Fransformer Connection south wing side
Fransformer Connection North wing side
Interm connection for the old board to New
North wing
Generator Connection1 &2
Fransformer stepup connection 1 & 2
Removing of the old generators
Guest Wings
South Wing 28 rooms
North Wing 60rooms
Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3

Handover
Handover
Handover
April
Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Th Fr Sa Su
25 26 27 28
Handover Handover
Handover