Professional Documents
Culture Documents
TALLER 51 - Revisión Del Intento
TALLER 51 - Revisión Del Intento
Pregunta 1 The ________ shows the total standard time required to produce one end product
Incorrecta in each work center required for its manufacture.
Puntúa como 1
Seleccione una:
La respuesta correcta es: Time saved at a non-bottleneck saves nothing and The
capacity of a system depends on the capacity of the bottleneck only
24/9/23, 11:30 TALLER 51: Revisión del intento
Pregunta 3 Planning the flow of work requires production activity control to:
Correcta I. be sure the material needed is available
Puntúa como 1 II. be sure the tooling needed is available
III. schedule the start and stop dates at each work center
IV. advise the plant supervisor of future orders
Seleccione una:
A. All of these
La respuesta correcta es: moving work to the next operation as a group of pieces
is completed
E. implementation
Pregunta 7 Which of the following are methods of reducing manufacturing lead time?
Correcta I. Subcontracting
Puntúa como 1 II. Forward scheduling
III. Operation overlapping
IV. Operation splitting
Seleccione una:
A. All of these
B. I and II
C. I and III
D. II and III
E. III and IV
Pregunta 8 All of the following are elements of manufacturing lead time EXCEPT:
Correcta
Puntúa como 1 Seleccione una:
A. design time
B. setup time
C. wait time
D. run time
E. move time
Seleccione una:
A. All of these
B. I and II
C. I and III
D. II and III
E. III and IV
C. If queue is reduced, the lead time and work in process will be reduced
D. All of these are true
E. None of these is true
Pregunta 11 Which file contains information on the efficiency and utilization of a work center?
Incorrecta
Puntúa como 1 Seleccione una:
Seleccione una:
Seleccione una:
A. I only
B. II and III only
C. II only
D. III only
E. I and II only
Seleccione una:
A. II and III
B. I and III
C. I and II
D. III and IV
E. I and IV
Pregunta 15 ________ is concerned with very short-term detailed planning of the flow of orders
Correcta through manufacturing.
Puntúa como 1
Seleccione una:
A. Master production scheduling
B. MRP
C. Master planning
D. Production planning
Pregunta 18 A scheduling system that assumes the required capacity will always be available
Correcta is called:
Puntúa como 1
Seleccione una:
A. forward scheduling
B. backward scheduling
C. infinite scheduling
D. finite scheduling
E. None of these
Pregunta 19 Which of the following files will contain information on manufacturing lead time
Correcta and quantity on hand?
Puntúa como 1
Seleccione una:
A. Shop order detail file
B. Industrial engineer's file
C. Work center file
D. Bill of material
E. Item master
Pregunta 20 A scheduling system in which the last operation on a routing is scheduled first
Correcta and for completion on the due date is called:
Puntúa como 1
Seleccione una:
A. forward scheduling
B. backward scheduling
C. infinite scheduling
D. finite scheduling
E. None of these
PRÓXIMA ACTIVIDAD
ACTIVIDAD PREVIA TALLER 52
Vdo 52: ToC