Professional Documents
Culture Documents
Ictad-Sca 8 E&m
Ictad-Sca 8 E&m
SPECIFICATIONS FOR
ELECTRICAL AND MECHANICAL
WORKS ASSOCIATED WITH
BUILDING AND CIVIL ENGINEERING
SPECIFICATIONS FOR
ELECTRICAL AND MECHANICAL WORKS
ASSOCIATED WITH BUILDING AND
CIVIL ENGINEERING
i
PREFACE TO THE 1' EDITION
The Sri Lanka Construction Industry Training Project under the Ministry of Local Government,
Housing and Construction was established in January, 1981, and some of the objectives of this project
were to:
(a) Increase the effectiveness of work planning and supervision by training middle and upper
Management in Contract Procedures, Site Management and Quality Control.
(b) Improved and streamline the methods and procedures relating to the Construction Industry, to
meet the requirements of the National Development efforts.
This Project was implemented with the co-operation of the International Development Association of
the World Bank.
The Specification for Electrical and Mechanical Works Associated with Building and Civil Engineering
Sri Lanka has been prepared by this Project through a Working Group consisting of the following;
I thank all, those who contributed towards the publication of this specification document.
ii
'
PREFACE TO THE REVISED EDITION
The first edition of the Specifications for Electrical and Mechanical Works Associated with Building and
Civil Engineering has been in use since 1987 as a national guideline, by government organizations in
the implementation of their construction activities.
As a result of the developments, which took place in the Construction Industry, it was felt that a review
was needed. Hence this review was initiated in 1996 with the assistance of the IDA of the World Bank.
This review was carried out by Eng. MP Somaratne B.Sc (Eng), Hons, C Eng, MIE, (SL) Post Graduate
Diploma in Environmental Engineering and Management, under the guidance of a steering committee
and a sub committee appointed for the review of ICTAD publications. The steering committee consisted
of representatives of the following Professional and Policy making organizations:
The sub committee also consisted of professionals from the industry. This revised version of the
specification is intended to cover all aspects of Electrical and Mechanical Works Associated with
Building and Civil Engineering in Sri Lanka and to establish uniformity and consistency in the
procedure adopted and is now presented in a more readable manner with new texts and improved
terminology. Besides, the following changes have been made in this revised edition.
(i) This document originally in three parts has now been devided into four parts as follows;
Part I - General Requirements for Electrical and Mechanical Works
Part II - Electrical Installation
Part III - Air-Conditioning and Ventilation
Part IV - Lifts
(ii) Part I is the new part introduced to the document and has been prepared to generalize an acceptable
practice for all Electrical and Mechanical Installations and to avoid any repetition of it in each part
I wish to acknowledge with grateful thanks the services of Eng.MP Somaratne and all the members of
the steering committee and the sub committee. Meanwhile my special thanks are also due to Rear
Admiral K R L Perera, Mr. G J P Gunawardane, Prof. Lal Balasuirya, Archt. Vidura Sri Nammuni, Mr.
EM G de Zylva, Mr. HD Chandrasena, Mr. S A Karunaratne, Mr. Jayantha de Mel, Mr. AT de S
Gunasekera, Mr. N B M Ranatunga, Mr. K P W Rajasiri, Mrs. Vajira Ranasinghe and Mr. C
Amarakoon who contributed in numerous ways in the publication of this specification. I also wish to
appreciate the assistance rendered by Mrs. W L Lalitha Ranjani for the secretarial work.
I hope that this revised specification will be of use in activities related to Electrical and Mechanical
Works Associated with Building and Civil Engineering.
G �------
[
ma5ala de Silva
Chairman
iii
f
SPECIFICATIONS FOR ELECTRICAL AND MECHANICAL WORKS
ASSOCIATED WITH BUILDING AND CIVIL ENGINEERING
CONTENTS
Page
iv
PART -I
Any conflict in interpretation of the specification shall be referred to the Engineer for
clarifications.
Electrical installations shall comply with the latest requirements of the Ceylon Electricity
Board and the latest edition of the Regulations for Electrical Installations issued by the
Institution of Electrical Engineers - London (IEE Wiring Regulations).
3. Drawings
The Contractor shall prepare all necessary drawings diagrams and schedules for the following
purposes:-
(i) To illustrate in detail the arrangement of various sections of the contract works and to
identify or describe various components.
Part-I General Requirements for Electrical & Mechanical Works
(ii) To integrate the contract works properly with the detail of the building and with the
works of other trades and other services installations.
(iii) To furnish to other trades such information as is the responsibility of the contractor to
provide.
(iv) To locate and identify all necessary test points, access positions for the commissioning
routines.
Particular attention shall be made to the general accessibility to the site, the building and other
areas, so as to avoid any major structural alterations during the final installation of the plants
and systems.
7
Works
Part-I General Requirements for Electrical & Mechanical Works
The working drawings shall give all setting out details and dimensions of ductwork, pipework
th the
routes, details of supports and typical sections co-ordinating all services in congested areas to a
minimum scale of 1/50 with details at 1/20.
tor to
Signed and approved drawings shall not be deviated from unless a signed variation order or
site instruction is issued in writing by the Engineer.
onung
Amended or altered drawings shall show the nature of the amendment or alteration in a
revision block on the drawing, together with the revision number or letter and the date of the
revision.
.tions,
nally
The Contractor shall be responsible for any discrepancies, errors or omissions in the drawings
vICeS
and other particulars supplied by him whether such drawings and particulars have been
approved by the Engineer or not, provided that such discrepancies, errors, or omissions are not
due to inaccurate information or particulars furnished in writing to the Contractor by the
Engineer.
2ring.
to a
The Contractor shall prepare and submit to the Engineer within twenty one days of
r the
signing of the contract documents a timetable for the issue of all approved shop
ill be
drawings, piping drawings, equipment and plant layout drawings, general layout
ories
drawings and builder's work drawings.
shall
tplete
3.3 Builder's Work Drawings
Builder's work drawings shall give all structural details and finishes, with clear instructions as
to the level of finishes etc. The drawings shall indicate all work to be carried out by the builder
other
for the purpose of installing the equipment, plant, machinery, electrical switch gear, conduits,
lants
cables, distribution boards etc., and shall indicate sufficient details of any holes, openings,
chases, foundation ducts, trenches etc .. Drawings shall be to a minimum scale of 1/50 with
details at 1/20.
rking
In the preparation of the Builder's Work Drawings consideration shall be given to the extent of
hese
work that has been carried out by the builder at the item and the work proposed shall ensure
works
provisions for avoiding any cutting, defacing etc., of the finished work. Any special
instructions necessary, along with the proposed installation programme and procedure, shall
accompany the builder's work drawings so as to enable the builder to prepare himself for the
work.
2
3
Part- I General Requirements for Electrical & Mechanical Works
At the completion of each section of the work, record drawing is to be prepared by the
Contractor for submission to the Engineer.
The record drawings shall show the position of every item of plant, all pipework, valves, drain
cocks and all items requiring access for maintenance or cleaning and any other item of
equipment forming part of the Services Installation. Where relevant, all sizes, capacities or
ratings of equipment shall be given. All items buried or otherwise concealed shall be precisely
located on the 'As Installed' drawings by means of dimensions taken on site from some readily
identifiable point (ie: main walls of building or finished floor levels). Where necessary, the
Contractor shall also produce sections, elevations and part plans.
5
When all record drawings have been submitted to the Engineer and have subsequently been
approved, the Contractor shall supply copies of these drawings in the following forms:
(ii) Manufacturer's catalogues for all items of equipment forming the installation.
I
Works
Part-I General Requirementsfor Electrical & Mechanical Works
(v) List of local suppliers and stockists of all items of equipment forming the services
y the installation.
5 Electricity Supply
, been Electricity supply to the premises will be 400 Volts, three phase, four wire or 230 Volts, two
wire at 50Hz. All equipment to be supplied under the contracts shall be designed to comply
with this supply.
The total power requirement for equipment shall be worked out and arrangements shall be
made by the contractor with the Engineer to have adequate capacities to be made available at
the services inlet to the premises well in advance of the period allocated for commissioning of
the plant and equipment.
6 Schedule of Rates
The bills of quantities attached to the tender document is intended to show the general sub-
This division of the items within the required supply and are not guaranteed to be complete. The
tenderer shall therefore ensure that all items of work and material required for the complete
installation are included in the prices quoted.
The rates quoted are to be used for evaluation of tender, and to calculate any variations of the
contract and price adjustments.
4 5
r
Part-I General Requirements for Electrical & Mechanical Works
---
10
. The bill of quantities will include quotation for the tenderer's charges for Inspections and
I
Testing of Work' in compliance with the ICTAD conditions and generally as per clause 16
under this part (part 1) of the specification and in Conditions of Contract - (SCA/I)
! I
published by ICTAD.
Materials shall conform to the appropriate Sri Lanka Standard or British Standard
Specifications where applicable and/or where specified.
The Engineer reserves the right to inspect the materials on the site at reasonable times and to
reject any materials not complying with the specification.
The cost of any dismantling and re-erection of the installation occasioned by the removal of
rejected materials shall be borne by the contractor concerned. This remedial work shall in no
way be allowed to delay the progress of the Contract.
Any modifications in the services installation arising as the works progress shall be noted in
detail by the contractor and any discrepancies resolved with the Engineer before installing any
part of the installation so affected. The Contractor shall include in his tender an allowance both
for the setting out of the works and any modifications that may arise.
13
4 9 Existing Services
Wherever possible the work shall be executed without affecting the existing services. Where
diversion of existing services is unavoidable details of diversion required shall be submitted to
the Engineer for co-ordination with those responsible for the existing service.
I
Works
Part-I General Requirements for Electrical & Mechanical Works
-----------------
Acceptance of Preceding Work
1s and
Before commencement of work in any section the work already performed by others to which the
1se 16
contract work adjoins shall be jointly inspected by the Engineer and the contractor and any
'A/I) deficiencies or delays in preceding work which would prevent satisfactory execution of work or
performance of his contract shall be notified in writing to the engineer and any modifications or
alterations to be integrated shall be mutually agreed between the Engineer and the Contractor.
Failure to comply with this requirement will be deemed as acceptance of preceding work for the
bed in purpose of Contract and any delays or extra work arising out of it shall remain the responsibility
nly to of the Contractor.
val by
Where it becomes necessary that the contractor shall complete any part of his work in advance of
his schedule inorder to complete any part of work of other trades he shall do so. No additional
val of payments will be made for complying with reasonable requests for such work.
mn no
The Contractor shall co-operate with the Engineer by complying with the requirement of Contract.
12 Builder's Works
ion to Except where specified and shown on drawings, provision of all holes, openings, chases, ducts etc.
required for the installation of equipment shall be undertaken by the contractor and required pipe
ducts, sleeves, bolts, sockets etc. shall be supplied. The Contractor shall be responsible for the
ted in accurate setting out of critical aspects of all such work and ensuring that all necessary provisions
g any are made and are adequate for the purpose. All such provisions shall be indicated and detailed on
e both the working drawings and/or Builder's Work Drawings.
6 7
Part -I General Requirements for Electrical & Mechanical Works
-
14 Water Proofing
Where any work pierces water proofing, including water proof concrete, methodology of work
shall be submitted for the approval by the Engineer before commencement of work. In wet
areas sleeves through floors shall be extended 30 mm above finished floor level. Where pipes
pass though water retaining structures they shall have puddle flanges of suitable size as
approved by the Engineer.
15 Accessibility
Wherever possible all equipment which must be serviced, operated and maintained shall be
located in fully accessible positions. Such equipment shall include but not be limited to,
control valves, motors, controllers, filters, pumps, electrical terminals, switchgear etc. When
direct access is not possible access panels shall be provided at suitable locations.
As far as practicable all equipment and fabrications shall be tested in the manufacturer's works
prior to delivery on site. All sections of the work completed shall be tested in accordance with
the appropriate regulations and codes during installation of the works to avoid the necessity for
disturbing the building programme at later stages. No pipes must be lagged, covered in or
otherwise made inaccessible before they have been tested.
Tests carried out shall include functioning of all controls, safety devices and mechanisms
under all conditions and circumstances, normal and abnormal. Measurements shall be made of
all critical dimensions and tolerances, including position alignment and performance of the 18
equipment.
All tests are to be recorded and signed by the Contractor's Senior Representative on site and as
far as possible witnessed by an Employer's Representative.
8
' Works
Part- I General Requirements for Electrical & Mechanical Works
It is the Contractor's responsibility to see that tests are correctly carried out and that any
f work
remedial measures necessary are effected and a re-test carried out so that on completion of the
In wet
works each and every section has been satisfactorily tested and a complete set of certificates
pipes
forwarded to the Engineer.
ze as
The whole system is to be tested upon completion of building/works and defects are to be
rectified by the Contractor at his expense.
ose of
2rvices
17 Testing and Commissioning
he site
The Contractor shall upon completion, commission and test the system and submit two copies
of a comprehensive commissioning and test report to the Engineer for approval.
All test and commissioning records shall be bound into the operation and maintenance manual
when the system has been successfully completed and witnessed by the Engineer.
works
e with During final commissioning of the plant suitably qualified standby staff shall be provided from
ity for all trades in consultation with the Engineer so that all related services are available during
I in or commissioning.
Upon satisfactory commissioning, the Engineer shall authorise the taking over and will issue
nisms the appropriate certificates in accordance with the conditions of contract.
ade of
8 9
Part- I General Requirements for Electrical & Mechanical Works
------------------
Manufacturer's recommended spare parts lists together with any special tools required to
enable maintenance to be carried out are to be submitted for approval by the Engineer prior to
ordering and delivery. The Contractor shall hand over to the Engineer all agreed spares for
Chapt
19 Manufacturer's Data
I. I
Manufacturer's data sheets giving type references, performance characteristics, dimensions,
1.2
weights, installation instructions manuals, wiring diagrams, control circuits etc., shall be
1.3
provided for all equipment supplied.
1.3.1
1.3.2
20 Clearing of Site and Final Cleaning 1.4
All accumulated rubbish and unwanted materials shall be removed from the site as the work 1.5
proceeds. Materials, tools and equipment shall be stored in selected locations as agreed or in a 1.6
separate store provided for same. The site and working area shall be kept ciean and tidy. Any 1.7
rubbish and redundant material shall be regularly cleaned and removed from site. 1.8
1.9
Prior to handing over, all remaining equipment, tools etc., shall be removed from the site.
Chapt
21 Initial Servicing 2.1
All equipment shall be maintained and kept in full working order in accordance with the 2.2
Contract for the period of maintenance stated in the main Contract. 2.3
2.4
This service shall be extended to include regular examinations of the installation during normal 2.5
working hours at not less than monthly intervals. Such examinations shall be done by 2.5.1
competent personnel and shall include adjustment, cleaning, replenishment of consumables 2.5.2
and repairs of any defective installations. 2.5.3
An emergency call-back service shall be provided during both normal and after normal hours Chap
of work. 3.1
3.2
22 Defects Liability 3.2. l
Contractor shall make himself aware of the terms and conditions of clauses in the man 3.2.2
contract in this regard. Contractor shall take full responsibility of the services installation 3.2.3
during defect liability period. 3.2.4
3.2.5
10
Works
PART-II
ired to
ELECTRICAL INSTALLATIONS
prior to
ares for
CONTENTS
Page
Chapter 1 - General Requirements
I. I Introduction to the Specifications .. 18
nsions,
1.2 Scope of Work . 18
hall be
1.3 Drawings .. 18
1.3. I Tender Drawings .. .. .. .. .. .. .. .. .. . .. .. .. .. .. . . .. .. .. .. .. . .. .. .. .. . .. .. .. .. .. 18
1.8 Accessibility 20
al hours Chapter 3- Wiring Systems Using PVC Cables Enclosed in Conduit or Trunking
3.1 Wiring Systen1 .. 25
3.2 Steel Conduit and Conduit Fittings .. 25
. .
3.2.1 Protection against Corrosion .. 25
e main 3.2.2 Adaptable and Junction Boxes of Metal .. 25
tallation 3.2.3 Termination of Conduits , .. 26
3.2.4 Spacer Bar Saddles and Distance Saddles 26
3.2.5 Conduit Couplers and Bends 26
-------------------------------------
10 11
3.3 Rigid PVC and Conduit Fittings .. 26 Chapte
3.3.1 Boxes (Adaptable for Accessories) of Plastic Material 27
6.1
3.4 Adhesive Tape 27
j
6.2 l
3.5 Installation 27 1
6.3
•I
3.5.1 General 27
6.4
3.5.2 Trunking 28
j
6.5
6.6
I
t
Chapter 4 - Wiring System using Elastomer or PVC Insulated Multi Core Cables 6.7
4.1 General . 29 6.8
4.2 Elastomer - Insulated Cables Unarmoured : . 29 6.9
4.3 Elastomer - Insulated Cables - Wire Braided .. 29 6.10
4.4 PVC Insulated Cables - Unarmoured .. 29 6.11
4.5 PVC Insulated Cables - Armoured . 29 6.12
4.6 Cable Supports . 29 6.12.1
4.7 Cable Glands : . 30 6.12.2
4.8 Installation . 30 6.13
6.14
5.5 6.21
Distribution Boards 32
5.6 Consumers Control Units . . 32
5.7 Moulded Case Circuit Breakers and Enclosures .. 32 Chapte
----------------------·--------
12
---
LI
26 Chapter 6- Apparatus Including Wiring Accessories
27 6.1 Accessories ················································································································· 36
27 6.2 Switch Boxes, Socket Outlet Boxes ............................................................................... 36
27 6.3 Switch Plates and Sockets Outlet Plates .. 36
27 6.4 Switches . 36
28 6.5 Cord Operated Switches 36
32
32 Chapter 7-Lighting Fittings and Ancillary Equipment and Lamps
-·----- I3
12
7.6.2 Tube 42
10.8 Li
7.6.3 Fluorescent Fittings . 42 In
10.9
7.7 Flexible Cord 43
10.9.1 C
7.7.I Flexible Cords for use with Lighting Pendants and Electric Lighting Fittings............. 43
10.9.2 M
7.8 Flexible Steel Conduits and Adaptors 44
10.9.3 M
7.9 Flexible Non-Metallic Reinforced type Conduit . 44
10.9.4 A
7.10 Ceiling Fittings .. 44
Electrical Bell, Buzzer and Bell Indicator Board Accessories and Fittings
Electric Buzzer
..
..
47
47
48
11.3 .3
11.4 :
9.7 Bel! Indicator Boards 48 Chapter
9.8 Bell Pushes 48 12.1
9.8.1 Ordinary type 48 12.2 2
9.8.2 Flush type 48 12.3 E
9.8.3 Surface Conduit 48
a
T
i
10.2
10.3
10.4
Wiring Systen1
PVC Insulated Cables
Multi-Core Cables
.
.
49
49
49
13.3
Chapte
l
I 0.5 Mineral Insulated Cables 49 14.1
10.6 Conduits, Conduit Fittings and Terminal Boxes '.................. 49 14.2
I 0. 7 Apparatus (Fixed) 49 14.3
14
D L
42 Lighting Fittings .
10.8 50
42 Installation
10.9 50
43
10.9.1 Conduit . 50
43
10.9.2 Mineral Insulated Cables . 50
44 10.9.3 Multi- Core Cables . 50
44 I 0.9.4 Apparatus . 50
44
4.4
Chapter 11- The Protection of Structures Against Lightning
11.l General 51
11.2 Accessories and Fittings 51
46 11.2.1 Air Terminals (Finials) . 51
46 51
11.2.2 Roof Conductors
46 51
11.2.3 Down Conductors
11.2.4 Earth Terminals 51
11.2.5 Ridge Blocks and Wall Blocks :................................... 51
47 11.3 Installation . ·2
47 11.3.1 AirTerminals(Finials) . 2
47 11.3.2 Roof Conductors 52
47 11.3.3 Down Conductors 2
47 11.4 Earth Terminations and Text Points .. $3
48
48 Chapter 12- Earthing
48 54
12.1 General .
48 54
12.2 Earth Leakage Circuit Breakers (Residual Current Operated Circuit Breakers) .
48
12.3 Earth Electrode . 54
48
Chapter 13 -Testing
13.1 Testing by Contractor . 55
49 13.2 Testing for the Supply Authority .. 55
49 13.3 Tests & Certificates to IEE Wiring Regulations . 55
49
49
Chapter 14 - Electrical Equipment for Industrial Installations
49 14.1 General 56
49 14.2 Fixing 56
49 14.3 Painting 56
14 15
14.4 Earthing 57
14.11.
14.5 Conduits 57
14.11.
14.5. l Metal Conduits 57
I 4.11.
14.5.2 Rigid PVC Conduits .. 57
14.11.
14.5.3 Conduit Fittings . 58
l 4.11.
14.5.4 Wire Pulling 58
14.11.
14.6 Cable Ladder 58
14.11.
14.7 Cable Tray 59
14.11
14.8 Cable Trunking .. 59
14.11
14.9 Main and Submain Cabling . 60
14.11
14.9.1 General 60
14.1 I
14.9.2 Cable Supports . 60
14.12
14.9.3 Tray Ladder Run Cabling .. 60
14.12
14.9.4 Direct Buried Cabling . 6l
14.12
14.9.5 Ducted Cabling . 61
14.12
14.9.6 Cable Terminations 62
14.12
14.9.7 Cable Identification ····························································:······································· 62
14.1
14.10 Circuit Wiring . 62
14.12
14.10.1 General 62
"'
14.1,
14.10.2 Concealment 63
14.13'
14.10.3 Ring Subcircuits . 64
w
14.10.4 Terminations 64
14.15
14.10.5 Prohibited Installations . 64
14.10.6 Identification 65
14.11 Switch Boards 65
14.11.1 C:,eneral . 65
14.11.2 Construction . 65
14.11.3 Finish 67
14.11.4 Busbars 67
14.11.5 Switch Board Equipment . 68
14.11.5.1 Air Circuit Breakers 68
14.11.5.2 Miniature Circuit Breakers .. 69
14.11.5.3 Rotary Switches . 69
14.11.5.4 Locked Switch and Switchfuses 69
14.11.5.5 Ammeters and Voltmeters 69
14.11.5.6 Fuses 70
16
57 14.11.5.7 Contactors . 70
57 14.11.5.8 Thermal Overloads .. 70
57 14.11.5.9 Control Relays . 71
57 14.11.5.10 Time Switches . 71
58 14. l l.6 Supply Authority Metering . 71
58 14.11.7 Wiring, Connections, Terminations . 71
58
14.11.8 Distribution Boards . 73
59 14.11.9 Motor Starters and Controls . 73
59
14.11.10 Equipment Identification . 74
60
14.11.11 Inspection and Testing . 74
60
14.11.12 Tools and Spares . 75
60
14.12 Distribution Boards . 75
60
14.12.l General . 75
6l
14.12.2 General Construction . 75
61
14.12.3 Panel Board Equiptnent .' . 76
62
14.12.4 Finish 76
62
14.12.5 Wiring and Connections · .. 76
62
14.12.6 Equipment Identification . 76
62
14.12.7 Inspection . 77
63
14.13 Outlet Boxes • 77
64
14.14 Co1n1nissioning . 77
64
14.15 Record Drawings and Operating and Maintenance Instructions . 78
64
65
65
65
65
67
67
68
68
69
69
69
69
70
--·---
16 17
li
" CHAPTER 1
GENERAL REQUIREMENTS
This part of the specification should be read in conjunction with Part I (General Requirements)
of the specification the conditions of contract published by ICTAD and the particular
specification of the respective services installation and construed as a whole for the complete
specification.
Co-ordination with the electricity supply authority for obtaining the required power supply at
the premises and payment of all inspection and testing fees shall fall within the scope of work.
1.3 Drawings
Shall be generally as in Clause 3 of Part I of this specification. Only specific requirements
relevant for the electrical installations are indicated below.
The Tender drawings shall not necessarily indicate every required fitting, elbow, transition
box, junction box, pull box or similar items required for the complete installation.
18
Part II- Chapter I- General Requirements
Other than in areas of particular importance where branch circuits and associated cables and
conduit routing are shown, the Contractor shall provide all required branch circuit conduit and
cables as required to serve equipment and accessories in order to make the system functional.
1.6
The drawings shall be prepared to recognised drawing office standards, be properly labelled
and dated, with references for easy identification. The drawings and documents shall show 1.7
conduit and wireways, joints, pull boxes and all features and positions of other switch gear that
are to be installed.
All materials and work shall comply with the appropriate latest Sri Lanka Standard
Specification, British Standard Specification, the recommendations of the International
Electro-technical Commission, BS Codes of Practice or Sri Lanka Standard Code of Practice
for electrical installations. 1.9
Alternative specifications may be recognised where such represents a standard not less rigid
than that specified above subject to the approval of Engineer. In cases where there is a
conflict between standards, the Sri Lanka Standard shall apply.
The electrical installation shall comply with the latest requirements of the Electricity Supply
Authority, standard specifications of the Sri Lanka Standards Institution and British Standards
Institution or the Regulations for Electrical Installation issued by the Institution of Electrical
Engineers, London (IEE Wiring Regulation), the current edition being the 16th.
19
rements
7 Part II- Chapter I- General Requirements
les and the neutral to earth at any other point is not allowed. The distribution system together with the
ional.
1.6 Materials and Samples
All materials and equipment supplied shall be new and in accordance with Clause 7 of Part 1
of this specification.
pies of
provide Whenever called for by the Engineer, sufficient number of samples of the material to be
supplied and the materials used in the installation shall be the same and/or identical to the
samples submitted and accepted by the Engineer.
abelled
ll show 1.7 Manufacturer's Data
ear that Manufacturer's data sheets giving type reference, performance characteristics, dimensions,
weights, installation instructions, wiring diagrams etc. shall be supplied for all equipment
supplied.
1.8 Accessibility
tandard Wherever possible all equipment and switchgear which must be serviced, operated and
ractice
1.9 Setting out of Work
The Contractor shall be responsible for the accurate setting out of the works, in relation to
ss rigid original points, lines and levels of reference given by the Engineer.
re is a
The dimensions given in the drawings shall be checked against actual site measurements and
exact relationship of the adjacent existing structures, services, or works to the proposed work
Supply shall be established. If any errors are found in positions, levels, dimensions, alignments etc.,
ectrical
Where the work of the contract involve installation in close proximity to the work of others
and where there is evidence that the work of the contract will interfere with the work of others,
the Contractor in consultation with the Engineer shall plan out a co-ordinating procedure to
wire at make satisfactory adjustments if necessary with respect to working space, point of connection
tion of etc. In which case necessary drawings shall be prepared and submitted to the Engineer for
approval.
19 20
Part II- Chapter I - General Requirements
If the installation within the contract is undertaken before co-ordinating with others and as
specified above or so as to cause interference with the work of others, necessary changes in the
work to correct conditions shall remain the sole responsibility of the Contractor.
2.1
2.2
2.3
2.4
2.5
2.5.1
21
irements
and as
CHAPTER 2
s in the WIRING SYSTEM USING PVC INSULATED OR
SHEATHED CABLES
2.5 Installation
Cabling shall run in conduits or cable traces, or on surfaces or structures. Routes shall be
approved by the Engineer.
Wiring above a horizontal ceiling shall be secured to the roof timbers with wiring clips and
pins spaced not more than 225 mm apart. In semi-permanent buildings or covered ways,
where no ceiling is provided, the wiring shall be the same as for wiring above the horizontal
ceiling.
21
- 22
J
Part II- Chapter 2 - Wiring System using PVC Insulated or Sheathed Cables
close joint light gauge steel oval conduit having protection against corrosion in
accordance with class 2.
light gauge steel conduit (Class A) complying with BS 31 (plain) or complying with
BS 4568 having protection against corrosion in accordance with Class 2.
Cables buried in concrete floors shall be protected throughout their entire buried
length by means of heavy gauge welded conduit (Class B) complying with Clause 3.2
or rigid PVC conduit complying with Clause 3.3.
Conduit buried in concrete shall have at least 35 mm. depth of cover over its entire
length. Conduit buried in plaster shall have at least 5 mm depth of cover over its entire
length.
Where conduit is buried in the carcass of a building or in the ground, all open ends
shall be temporarily plugged to prevent ingress of foreign matter, moisture or water
during and after construction.
23
d Cables Part II - Chapter 2- Wiring System using PVC Insulated or Sheathed Cables
Where conduit buried crosses an expansion joint in the concrete, it shall be wrapped
with water-proof building paper for a distance of 300 mm on either side of the joint.
Any alternative method of protecting the conduit against stresses due to expansion
shall be approved by the Engineer.
e of the
osion in
ing with
sulation
Bushes
buried
ause 3.2
ts entire
ts entire
en ends
r water
----------------------------------- 24
23
CHAPTER 3
WIRING SYSTEM USING PVC CABLES ENCLOSED
IN CONDUIT OR TRUNKING
Where other conduit systems are to be used they shall be to the approval of the Engineer.
PVC and metal conduits shall not be used together in the same installation. The wiring system
shall be such that the cables are fully protected. The conduits used shall be of adequate sections
to allow easy drawing 'in' and 'out' anyone of the cables or all cables in the conduit.
25
Part II- Chapter 3 - Wiring System using PVC Cables Enclosed in Conduit or Trunking
If runs of conduits must run from a danger area to a safe area, a sealing device or a stopper box
shall be provided at the point where conduit enter the safe area. These boxes shall conform to
BS 4662.
contact with the metal case with an internal hexagonal brass bush screwed into the socket from
inside the case and the two locked togethe;·. Plain slip or pingrip sockets shall not be used.
heavy gauge spacer bar saddles in such a manner that all the cables can be drawn in at any time
after the installations of the conduit pipes.
The spacing of supports shall be as given in Table 1IC of the IEE Wiring Regulations.
In addition, at bends, sets or boxes the conduit shall be fixed on either side.
On girders, the conduit and fittings shall be fixed by means of adjustable girder clips.
Radius of every conduit bend other than a bend complying with BS 4568 (Steel) or BS 4607
(PVC) shall be such as to allow compliance with Table 52C of I5th Edition of IEE Regulation
and in any event, the radius of the bend shall be not less than 2.5 times the outside diameter of
the conduit.
26
runking Part II- Chapter 3 - Wiring System using PVC Cables Enclosed in Conduit or Trunking
for earth continuity conductor. Other types of boxes sh al I be to the approval of the Engineer.
3.5 Installation
ny time The conduits shall be erected and completed before any cables are drawn in. The corners of
conduit pipes shall be turned by easy bends without altering the section. The use of
manufactured bends are not permitted. All metal or PVC boxes for mounting fittings shall be
Conduit systems not designed to be sealed shall be provided with suitable outlets to drain - off
cknuts.
All pipework shall be adequately supported by means of standard or purpose made clips so that
no movement or distortion of pipe takes place except that necessary to take up the expansion or
gulation
Flexible or pliable conduit shall not be used as protective conductor.
neter of
Conduits being installed in reinforced concrete floor slabs or columns shall be placed and
securely tied to the reinforcing steel prior to concrete being pored. All conduit ends shall be
completely sealed against the ingress of concrete and immediately following the pouring of
nted or
concrete shall be swabbed out and a pullwire installed prior to the ends being plugged.
ter tight
e used.
26
27
Part II - Chapter 3 - Wiring System using PVC Cables Enclosed in Conduit or Trunking
The metal conduit shall be bonded to earth to keep the electrical resistance of the conduit with
the earthing lead measured from the connection with the electrode to any other position in the
completed installation not to exceed I ohm. The ends of every earth continuity conductor
whether stranded or solid shall be connected to the conduit pipe by screwed or grip joints to
enable it to give ample and permanent electrical conductivity and mechanical rigidity.
3.5.2 Trunking
Trunking shall be to BS 4678 and be securely fixed and adequately protected against possible
mechanical damages.
Every entry to finished trunking shall be so placed as to prevent the ingress of water or be
protected against such ingress.
Spacing of supports for fixing trunking shall be in accordance with Table 11 D of Appendix 11.
The cable capacities of trunking shall be as given in Table 12E and l 2F of Appendix 12 of
IEE Regulations.
4.3
In every vertical trunking containing cables or conductors internal barriers shall be provided so
as to prevent the air at the top of the trunking from attaining an excessively high temperature.
The distance between barriers shall be distance between floor or Sm which ever is lesser.
4.4
4.5
4.6
28
- --
Trunking
duit with
CHAPTER 4
on in the
WIRING SYSTEM USING ELASTOMER OR PVC
onductor
joints to INSULATED MULTI- CORE CABLES
4.1 General
The details of installations given in the Appendix 9 of the IEE Regulations are to be
possible observed. PVC insulated cables shall be used in all wiring systems unless otherwise specified.
ndix 1H. Butyl rubber and ethylene propylene rubber materials shall be used as insulation where
fix 12 of temperature does not exceed 80'€.
armouring shall be used if the ground is liable to subsidence, to prevent cables from breaking.
If physical damage from stones or workmen's tools is expected steel tape armouring shall be
used.
Whenever XLPE cables are used BS 5467 shall apply.
28
-- the IEE Regulation.
29
Part II- Chapter 4 - Wiring System using Elastomer or PVC Insulated Multi - Core Cables
4.8 Installation
Cables shall be supported by means of insulators, cleats or saddles and clips when used 5.1
indoors.
Unarmoured cables in ground shall be enclosed in metal or rigid PVC conduit.
5.2
Joints of cables to BS 6004 shall in general be made in a joint box or in an accessory. Joints
will not be permitted in BS 6346 cables. Where joints are unavoidable all U.G. joints shall be
made in a resin type joint box. Joints above ground shall be to the approval of the Engineer.
All terminations for BS 6346 cables shall be provided with a cable gland. In BS 6004 cables,
the sheath should enter the fitting or the accessory.
5.3
5.4
30
e Cables
CHAPTER 5
installed
SWITCHGEAR, DISTRIBUTION BOARDS, CIRCUIT BREAKERS,
CONTACTORS AND BUSBAR CHAMBERS
5.2 Enclosures
y. Joints Enclosures shall be provided to protect all equipment against external influences and to have a
ineer.
For factory built equipment this requirement is considered to be satisfied if the equipment
Enclosures provided during erection shall comply with Regulations 412-3 to 412-6 of the
Wiring Regulations. Further they shall provide a degree of protection appropriate to the
environment where they are used.
Enclosure for outdoor use shall provide a degree of protection not less than JP 54 conforming
5.3 Fuses
Semi - enclosed rewirable fuses shall comply with BS 3036: 1958. Cartridge type fuses shall
comply with BS 88:Part II : 1975 or BS 1361: 1971 or the latest.
5.4 Switchgear
Circuit breakers shall be of the air-break type and comply with BS 3871, BS 4572- Part I and
!EC 157-1.
Air break switches, disconnectors, fuse switches, switch fuses etc., shall comply with BS 5419.
All equipment shall be designed to carry the rated currents continuously and the utilization
category shall be AC 22 unless otherwise specified.
----------------------
31
30
Part IH- Chapter - Switchgear, Distribution Boards, Circuit Breakers, Contactors Busbar Chambers
---
All switchgear shall be fitted with a reliable indicating device, indicating the position of the
moving contacts if the contact separation is not externally visible.
Fuse distribution boards shall generally comply with the requirements of BS 5486: Part II.
5.10
5.7 Moulded Case Circuit Breakers and Enclosures
MCCBs shall comply with BS 4752 Part I or BS 3871 : Part 11 or IEC 157-1 and the enclosures
shall meet the requirements of clause 5.2. MCCB's shall be fitted with magnetic over load and
thermal circuit protection.
5.11
5.8 Miniature Circuit Breakers
MCBs shall comply with BS 3871: Part I and be provided with thermal overload and magnetic
short circuit protection with time lag features.
These shall be rust protected and provided with removable end, top and bottom plates.
The busbars shall be of copper or aluminium of adequate cross section and the design shall be
such that connection can be made by clamping without the necessity for drilling.
--------
32
I
ambers
of the - Part II- Chapter 5 - Switchgear, Distribution Boards, Circuit Breakers, Contactors & Busbar Chambers
The busbars shall be of tinned copper or aluminium alloy coloured in their respective phase
colour or encapsulated in insulation.
Busbars shall, in addition to being spaced at such intervals to give the necessary air clearance
for the voltage rating, be completely insulated in an approved manner. Primary busbars,
connections and their supports shall be capable of carrying the short time current associated
I I.
with their short circuit ratings for a period of 3 seconds.
The connections from busbars in individual units shall have a continuous current rating of not
Primary busbars shall be clearly marked and shall be displaced for standard phase sequence
and shall be readily extensible. Busbars where installed shall be rated to withstand at any
position the full fault level related to the largest protective fuse that could be used with the
coming
main isolator.
All cables that terminates on the switchgear assembly shall be provided with cable glands,
All conduits, trunking, ducts etc., shall be terminated on the switchgear structure without
impairing the degree of protection provided by the enclosure.
All switchgear shall be ridigly fixed or mounted on DIN rails and should be able to withstand
shall be
the normal thermal & mechanicai stresses and dynamic stresses due to switchgear operation.
33
Part II- Chapter 5 - Switchgear, Distribution Boards, Circuit Breakers, Contactors & Busbar Chambers F
Site built assemblies of main switchgear shall generally comply with the above requirements
and shall be to the approval of the Engineer.
5.14
Within panels adequate labelling shall be provided using white letterset "Helvetica Medium 24
PT" labelling shall be capital letters on the trunking lids coated with hard varnish for all fuses,
relays, control equipment etc. Such labelling shall correspond in detail with item numbers for
Where the operation of switch gear and control gear cannot be obtained by the operator and
where this might cause a danger, a suitable indicator, complying with BS 4099 where
Protective devices shall be arranged and identified so that the circuit protected may be easily
recognised; for this purpose it may be convenient to group them in distribution boards.
the type of composition of circuits (Points of utilisation served, number and size of
conductors type of wiring, and
the information necessary for the identification of devices performing the function of
Every item of equipment or enclosure within which a voltage exceeding 250 volts exists and
where the pressure of such a voltage would not normally be expected, shall be so arranged that
before access is gained to live parts a warning of the maximum voltage present is clearly
visible.
34
umbers Part II - Chapter 5 - Switchgear, Distribution Boards, Circuit Breakers, Contactors & Busbar Chambers
ments Access should be restricted by an appropriate transparent material on which the voltage
requirements.
2 easily
g to BS
size of
ction of
ists and
ged that
s clearly
34 ------------------------ 35
CHAPTER 6
APPARATUS INCLUDING WIRING ACCESSORIES
6.1 Accessories
All accessories if not made in accordance with the requirements of other British Standards
shall comply with the requirements of BS 5733.
The wooden boxes shall be of Halmilla or Teak or other approved hard wood, square or
rectangular in shape, with a fully covered back having a wall thickness of 10 mm all round and
be suitable to accommodate flush type switches, bell pushes, socket outlets etc.,
For steel conduit wiring systems the boxes shall be of cast iron or steel.
For PVC conduit wiring system the boxes shall be of moulded plastic, steel or cast iron.
6.4 Switches
Switches shall comply with BS 3676 or SLS 1000 and of the quick-break, quick make type.
Switches shall generally be of the all insulated pattern unless associated with a metallic conduit
system.
36
Part II- Chapter 6 - Apparatus including Wiring Accessories
6.12
6.8 Socket Outlets and Plugs
These shall conform to BS 1778, BS 4343 Parts 2,5 and 15 or SLS 948: Part 1. Socket outlets
and plugs of the shuttered type shall conform to BS 546 or to the equivalent Sri Lanka
Standard.
13A socket outlets and plugs shall conform to BS 1363 (SLS 734:1986)
The ceiling fans shall be three bladed type 1400 mm sweep if not otherwise specified. The
motor shall be smgle phase 220/230 V, 50 Hz, totally enclosed capacitor type, with grease
packed ball bearing. The fan to be supplied with an insulated shackle, canopy, specified length 6.14
of down rod and a choke type speed regulator. The terminal block on the fan as well as the
capacitor and the fan hook shall be provided with removable covers. The speed regulator shall
be provided with an off position and five running positions and should be capable of regulating
down to 35% full speed.
37
essories Part II- Chapter 6 - Apparatus including Wiring Accessories
The fan hook should be rust protected and subject to the approval of the Engineer. The down
lamp to rod shall be of adequate mechanical strength and the internal diameter shall not be less than 16
mm.
Ceiling fans shall be suspended at a minimum height of 2750 mm from the floor unless
cent or otherwise specified in the design/ bill of quantities.
t outlets use in 230V, 50 Hz, AC supply with grease packed ball bearing having an easily accessible
Lanka lubricator. It shall be controlled by a regulator designed for regulation of speed down to 60 to
70 percent of full speed and the regulator shall be of the series choke type having four speeds
and off positions or shall be controlled off a switch socket outlet. The regulator unless fully
insulated shall be earthed, complete with all necessary connections and fixtures.
gle pole
.s of BS 6.12.1 Light Proof Cowls
I
These shall have louvres of robust material, fitted by means of fixing rings and nuts, so as to
restrict entry of light fully but to allow easy flow of exhaust air and fitted to the body of the
exhaust fan by screws.
ox with
ed. The shower. In rooms other than bathrooms socket outlets complying with BS 4573 shall be used.
grease
d length 6.14 Cooker Control Unit
11 as the These shall comprise of a double pole switch of not less than 30A rating complying with BS
tor shall 3676 and a 15A switch socket-outlet having fuse protection or 13A socket-outlets and a pilot
gulating lamp or a mechanical indicator to show weather the supply is 'on' or 'off' and shall be of the
all insulated pattern.
37
Part II- Chapter 6 - Apparatus including Wiring Accessories
In toilet area where a fixed bath or a shower is used the switch shall be installed outside and
immediately adjacent to the normal access door of the room, or to be operated by an insulated
6.20
cord.
All socket-outlets except in a toilet, kitchen or operating theatre etc., shall be mounted at a
minimum height of 150 mm from the finished floor level or 150 mm above a working surface
(e.g. in a kitchen, laboratory etc., unless otherwise specified).
6.21
In a room where a shower or a fixed bath is installed only shaver socket is permissible to be
installed.
No two socket-outlets fed from two different phases shall be installed within 2m from each
other. Continuity conductor used shall be 4.0 mm" unless otherwise specified. All 15A socket-
outlets shall be wired of a 2.5 mm of 250 V grade if it is wired of one way of a distribution
board protected by a rewirable fuse.
39
ssories Part II - Chapter 6 - Apparatus including Wiring Accessories
-------------�----------'----�-
All switches and socket-outlets shall be installed on suitable wooden or conduit boxes
Their direction of rotation should be such as to extract air from the room. Their positioning is
important to get maximum efficiency. Cooker control units shall be of approved manufacture
and be installed by an approved method at position shown in the layout drawing. The rate
witches
for the installation shall include the necessary length of earth wire and the necessary length of
s for an
wire required for installation in accordance with type of wiring specified in the bill of
quantities.
zuit at a
Engine & Governor BS 5514 and BS 6514 respectively.
l in the
The sound level of the generator should be within the specified limits of environmental
requirements.
side and
sulated
6.20 Power Factor Correction/ Harmonic Filters
Power Factor Correction should be done to compensate reactive power in LY /HY installation.
Capacitor banks and switchgear shall be in compliance with IEC 70, IEC 947 : Part I.
ted at a
Harmonic filters provided, if any, shall comply with IEC 146 or IEC 1000/4.
surface
m each
Dry Type (Cast Resin) Transformers IEC720
socket-
tribution
39 40
CHAPTER 7
LIGHTING FITTINGS AND ANCILLARY EQUIPMENT AND LAMPS
particular specification shall be as follows. The lamp holders shall comply with BS 5042 and
be to customer's choice. Provisions for earthing should be made available appropriately.
A plastic or glass bell shaped shade having a depth not less than 200 mm and bottom
diameter not less than 160 mm shall be used complete with all necessary accessories and
fixtures and be provided with lamps of 75 watts, maximum.
These shall be mounted on a suitable size mounting block or on a conduit box depending on
the type of wiring complete with all necessary wiring connections, accessories and fixtures.
7.2 Lighting Fittings for Use with Mercury Electric Discharge Lamps
Each fitting shall consist of an outdoor type mercury vapour lamp with choke and capacitor
housed in a steel box. The lamp shall be complete with a gallery and shade mounted on a
suitable bracket which shall be fixed to the wall or to a pole by means of suitable clamps as
specified in design/ bill of quantities as per clients choice. Earthing and power factor
correction should be provided.
41
Part II- Chapter 7 - Lighting Fittings & Ancillary Equipment & Lamps
For lamps of wattage above 200W, approved Edison Screw type lamp holders complying with
BS 5042. Part II shall be used.
Al! bright metal parts shall be chromium plated or the reflector of glass silver mirrored and
rigidly mounted to the frame. The lamps for both sets shall be of such a wattage as to give 450
to 600 foot candles on the operating table at a distance of 1250 mm from table.
7.7
7.6 Pendants
7.6.1 Plain
A plain pendant shall comprise a ceiling rose, a length of flexible wire, a suspension type
bayonet lamp holder, a translucent plastic shade of diameter not less than 200 mm and depth
l
of 125 mm together with associated wiring and fixtures. It shall be controlled by a SA switch
and wired with copper conductor of cross sectional area 1 mm2 unless otherwise specified.
7.7.1
j
7.6.2 Tube ]
A tube pendant shall be generally as described above except that the lamp is a suspension type
fluorescent fitting suspended by chains to suit the specified mounting height.
b
42
Lamps Part II- Chapter 7 - Lighting Fittings & Ancillary Equipment & Lamps
starting. Starter or starters used shall be normal or glow type having a radio interference
e shall
suppressor and a power correcting capacitor incorporated in the system. Each fitting shall be
ungers
complete with reflector, fluorescent tubes having bi-pin lamp caps and bi-pin lamp holders all
rouds.
wired internally. The fitting shall be suitable for the use with 230V, 50Hz normal supply.
Suspensions of tubes shall be by rigid tubes or chains fixed to hooks screwed into plugs buried
g with
in the ceiling or any other approved method. Thickness of the sheet metal of the reflector shall
be not less than SWG24.
Batten type fitting shall be fixed direct on to the support by the end of plugs or any other
r three
approved method. The colour of the tube shall be warm white or day light unless specified in
the bill of quantities.
ion type The applications shall be as given in Table IO B of the same regulations.
d depth
A switch 7.7.1 Flexible Cords for use with Lighting Pendants and Electric Lighting Fittings
2
ied.
Flexible cords for pendants and fluorescent fittings shall be of minimum size of 0.5 mm ,
ion type Where a flexible cord supports or partly supports a luminaire the maximum mass supported
by the cord shall not exceed the appropriate value indicated below.
e, 20 or
to assist
---
42 --------------------------:3
4
Part II- Chapter 7- Lighting Fittings & Ancillary Equipment & Lamps
(i) an awkward short run under floor from main conduit line to a light fitting or
(ii) in the connections between motor starter and motor.
Brass adaptors connecting water tight flexible conduit pipes threaded internally to the pitch of
the flexible tube screwed onto the two ends of the flexible pipe shall be used.
Fittings shall be not less than 300 mm in diameter and 100 mm in depth and shall be so
designed to prevent ingress of water when mounted in exposed positions.
44
& Lamps Part II- Chapter 7- Lighting Fittings & Ancillary Equipment & Lamps
Pendant lamps and fluorescent fittings shall be suspended at a height of 2500 mm from
finished floor level and shall be wired off a ceiling rose with appropriate flexible cords.
The installation shall be complete with all wiring inclusive of switches etc., depending on type
of wiring.
The operating theatre lamps shall be wired off a separate way of the distribution board and
controlled off a SA switch installed as specified in the design of light fittings. Specially if
ter-tight flush mounted and totally enclosed or required to be provided with heat-resisting insulation
suitable for the temperatures likely to be encountered, heat resisting sleeves shall be fitted over
the individual cores to prevent a short circuit between conductors or an earth fault. Similar
method should be used for accessories and appliances which are subject to such conditions.
pitch of
ble non-
amps to
ecessary
all be so
g blocks
1ed floor
: used to
44 45
CHAPTER 8
PERFORATED METAL CABLE TRAYS AND ACCESSORIES
8.3 Installation
Cable trays may be suspended from the ceiling, roof girders or fixed to the walls by means of
brackets. At the point of support the bracket or the support shall extend the full width of the
cable tray.
Each bracket shall be fixed to the tray by at least two screws. Connections between lengths of
cable tray shall be subject to the approval of the Engineer. At joints the earth continuity shall
be secured by means of adequate bonds.
46
CHAPTER 9
BELL AND AUDIBLE WIRING SYSTEMS
9.3 Cables
Cables used for wiring shall be 1.0 mm2 PVC insulated and sheathed cables of 250 V grade
along with an earth wire, unless otherwise specified.
9.4 Transformers
Transformers shall comply with BS 3535 and have the primary and secondary coils wound
separate with earth protection. One terminal of the secondary shall be arranged for earthing.
Two fused tapping shall be arranged on the secondary giving a voltage of 12. The transformer
shall be mounted on a bakelite case and cover fastened. by screws. The primary coil shall be
wound for 230V, 50 Hz, single phase AC supply and the secondary for 12V giving an output of
1 OVA for a single bell and 60 to 100 VA when used with indicator boards.
9.5 Electrical Bell, Buzzer And Bell Indicator Board Accessories and Fittings
These can be either electronic or electro-mechanical type. In case of an electro-mechanical
device metal bell and the gong should be electroplated.
These shall be suitable for use on 12V, AC 50 Hz., single phase supply or 230V, 50 Hz, single
phase AC, supply or as specified in the bill of quantities.
----------------------------------
47
Part IH - Chapter 9- Bell & Audible Wiring Systmes
-------------------------
The bell buzzer or bell indicator shall be mounted at an easily visible place on a suitable
mounting block or base and wired to bell pushes at different locations including the earth wire. 10.5
Re-setting of the buzzer should be provided at the location.
10.6
10.7
-----------------------------------------
48
; Systmes
CHAPTER 10
moulded Cables drawn into screwed solid drawn seamless or seam-welded steel conduit
lead sheathed steel wire armoured cable with PVC overall sheath
mineral insulated, metal sheathed cable
PVC insulated, wire armoured cable with PVC oversheath
moulded
ush plate 10.3 PVC Insulated Cables
PVC insulated cables for use in conduit system shall comply with BS 6004.
suitable
rth wire. 10.5 Mineral Insulated Cables
MICL Cables shall comply with BS 6207 and be provided with a PVC oversheath.
49
Part II- Chapter 10- Flame Proof Installation
10.9 Installation
10.9.1 Conduit
11.2
Conduit wiring shall comply with the requirements of Clause 405 of CP 1003.
11.2.
10.9.4 Apparatus
Apparatus shall be installed generally in accordance with manufacturer's instructions and in
positions exposed as little as possible to the substance giving rise to the risk.
11.2.3
11.2.4
11.2.5
50
allation
CHAPTERll
THE PROTECTION OF STRUCTURES AGAINST LIGHTNING
on and
11.1 General
The lightning protection installation shall comply with C.P.326. Radioactive type of lightning
All vertical conductors forming part of an air terminal network shall be of phosphor bronze of
not less than l O mm diameter.
:litionally
51
Part II- Chapter 1H - The Protection of Structures Against Lightning
All sharp bends and up turns shall be avoided. Any bend shall bave a radius as great as
possible. The number of joints shall be minimum and, if a joint is made it shall be brazed.
The roof and down conduction shall be clamped to the lower end of the finials by means of a
ridge saddle. Finials shall project to a height not less than 100 cm above the roof. The scope of
work shall be inclusive of supplying of a finial non metallic support, water tight seal and all
accessories, lead sheet, bitumen, compound cement, plaster etc. and installation of same
complete with all necessary connections and fixtures.
All finials, roof conductors, metallic projections such as chimneys, ducts, and vents above the
main roof surface shall be bonded together.
A combination of strip and rod conductors, reinforcing bars, structural steel stanchions, etc.
can be used as all or part of down conductor system provided proper electrical bonding is
assured from air terminal to earthing point.
52
Part II - Chapter/ I- The Protection of Structures Against Lightning
---
Lightning
eans of a
scope of
l and all
of same
ich shall
e blocks
plied and
ections.
1bove the
not more
:s screws.
necessary
lightning
ons, etc.
ording is
---- ---------------------------------------
53
52
CHAPTER 12
EARTHING
12.1 General
All conductors and extraneous metal parts of the installation covered by this specification shall
be connected back to the main earthing terminal.
All earthing installations, size of earth wires and bonding shall be in accordance with Chapter
54 of the IEE Wiring Regulations, 16th Edition or latest.
12.2 Earth Leakage Circuit Breakers (Residual Current Operated Circuit Breakers)
Unless otherwise specified all Earth Leakage Circuit Breakers (ELCBs) shall be residual
current devices. (Current operated ELCBs) and shall comply with BS 4293.
RCD's for computer systems should be of adequate operating current for this purpose. The
socket outlets feeding UPS systems which generate harmonics should have RCDs having a
sensitivity of 300 mA if the UPS system is not provided with necessary harmonic filter
designed in accordance with IEC 146, IEC 1000/4.
Minimum cross section of protective conductor in relation to the cross section area of
associated phase conductor should conform to Table 54G of the 16th Edition of IEE Wiring
Regulation.
54
CHAPTER 13
TESTING
55
CHAPTER 14
ELECTRICAL EQUIPMENT FOR INDUSTRIAL INSTALLATIONS
14.1 General
Specifications in the preceding chapters refer to general lighting and power distribution related
to buildings, whereas 'general specifications for electrical installations for industrial plants,
equipment and services such as air-conditioning and fire protection, pumps, are given in this
chapter.
14.2 Fixing
All fixings to the building structure shall be as follows.
Interior
finishes Chrome plated brass or steel
Timber plugs for screws in masonry work will not be accepted.
14.3 Painting
The Contractor shall paint all mounting brackets, supports, etc., whether of wood or metal and
where exposed to view or where corrosion/rotting is possible due to environmental conditions.
The paint system shall be appropriate to the material being painted and the colour shall match
the surrounding surface.
56
Part II - Chapter I4 - Electrical Equipment for Industrial Installations
14.4 Earthing
Earthing of equipment, structural steel, water piping etc., shall comply with the IEE
Regulations and any requirements of the local supply authority. All earth wires shall be green,
PVC insulated and shall be installed in accordance with the relevant clauses of this
specification.
14.5 Conduits
14. 5.1 Metal Conduits
The size of all conduits shall be one size larger than the minimum required by the IEE
Regulations for the number of cables to be drawn in, but in no case shall be smaller than 20
mm diameter. All conducting shall be run so as to enable cables to be drawn in after erection.
Sufficient accessible junction boxes shall be provided for this purpose. Inspection fittings are
not acceptable as draw in points.
All joints, junction box lids and conduits entrances shall be totally scaled so as to completely
prohibit the entry of insects or fine particles.
14.5.:
Specifications for the installation of metal conduits shall be as 111 Chapter 3 of the
Specification.
Rigid conduits shall be run directiy into fixed components such as switches, junction boxes,
etc .. Where the equipment being wired may need to be removed for maintenance, e.g. motors,
control components such as flow switches, thermostats and the like, the rigid conduit shall
terminate in a suitable junction box and the final connection shall be made via an approved
plastic covered flexible metal conduit with water tight screwed ends. Water tight screwed
14.5.4
reducers shall be used as required to match the flexible conduit to the equipment entry. The
final connection fitting shall be a barrel union so that conduits do not have to be rotated to
connect or disconnect plant.
Where rigid PVC conduit is used it shall in general conform to the installation requirements of
Clause, 14.5.1 together with the following additional requirements.
57
lations all-
Chapter I4 - Electrical Equipment for Industrial Installations
Rigid PVC conduit and fittings shall be of normal impact strength manufactured to Class A as
defined in BS 4607 Part I. Rigid PVC conduit shall be used throughout.
e IEE
green,
All joints shall be cemented with an approved cement and fittings shall be rigid PVC Screwed
f this
fittings shall NOT be used.
Rigid PVC conduit shall be securely fastened with approved saddles at a maximum spacing
of 450 mm and where necessary additional saddles may be provided to avoid sagging in the
conduit. Where any straight section of rigid PVC conduit not embedded in concrete exceeds
he IEE
3000 mm in length an approved expansion joint shall be provided for each 3000 mm or part
han 20
thereof along the entire length of the straight section.
ection.
ngs are
All sets and bends in rigid PVC conduit shall be made using approved internal springs of
correct size to prevent any collapse. Conduits in which any collapse of walls is evident will be
condemned.
pletely
----- 57
----------------------------------
58
Part II- Chapter I4 - Electrical Equipment for Industrial Installations
The ladder system shall be capable of supporting a load of 75 kgf/m along its length over a
span of6m with a vertical deflection (sagging) of less than 50 mm at mid span.
The ladder system shall be of an approved proprietary manufacture of welded or site fabricated
construction using either aluminium or steel components or both. All steel components shall be
14.9
hot dip galvanised. Electro galvanising will not be accepted.
14.9.
Unless shown otherwise on the drawings, ladder runs shall be parallel to walls, ceilings floors,
etc .. Supports shall be installed at centre-line distances not greater than that shown on the
drawings or, where not directed at distances not greater than those recommended by the
manufacturer for the loading concerned.
Ladder installation shall not interfere with other services in the same area.
Support brackets for cable trays shall be fabricated and finished as for the tray and provide at
intervals not exceeding 1200 mm. with 2 bolts to each bracket. Bracket shall be fixed to the
wall or other available and approved supports.
The trunking and all components shall be fabricated from minimum 1.2 mm machine cut and
folded panel steel. All steel work shall be hot dip galvanised after fabrication.
Unless detailed otherwise, all trunking shall be sized to accommodate all cables installed on
the same route with a space factor not more than 35% of the trunking cross section being
utilised for cable but shall not in any case be smaller than that shown on the drawings.
---------------------------------------------
59 --
ations
Part II- Chapter I4- Electrical Equipmentfor Industrial Installations
ver a
Support brackets for cable trunking shall be fabricated and finished as for the trunking and
shall be provided at intervals not exceeding 1200 mm except where other fixing arrangements
are detailed on the drawings.
icated
all be
14.9 Main and Sub Main Cabling
14.9.1 General
All cables shall be new and of the types specified on drawings and on distribution board
floors,
schedules. They shall be installed in accordance with the methods enumerated below.
on the
Terminating methods shall be as called for in the terminating and wiring clauses of this
by the
specification. Cable routes shown on the drawings or otherwise specified shall not be deviated
from without the express permission of the Engineer.
As an alternative for cable risers, bus bar trunking systems (bus risers) with suitable tap-off
units manufactured and tested according to IEC 439-1 or equivalent can be utilised as
feeders.
from a
proved
14.9.2 Cables Supports
etween
All cables except cables underground shall be fixed with saddles or clamps to the available
structure or support system detailed.
vide at
Upto two cables may be run together and neatly clipped to structures without the provision of
1 to the
cable trays.
Where three or more cables are to be run along the same route, cable trays or other approved
means of support shall be provided.
·ncealed
e.
14.9.3 Tray Ladder Run Cabling
Cables installed on tray and ladder shall be installed straight and true without kinking and so
cut and
arranged that there will be a minimum of crossing over. Not more than two layers of cable
shall be installed at any point. Cables shall be strapped to the tray/ladder with self locking
nylon cable ties at centre line distances not exceeding the following.
alled on
n being
Horizontal runs, cable on top of tray 1200 mm
-----
59 ---------------------------
60
Part II- Chapter I4 - Electrical Equipment for Industrial installations
Where cables leave the tray/ladder run additional approved supports shall be provided and
cables strapped to the support at centre as indicated above. Support methods where not
14
specifically detailed on the drawings shall subject to the approval of the Engineer.
Burial depths and spacings between cables shall not be less than those shown on the drawings.
All excavations for cable trenches, sanding, slabbing and backfilling shall be undertaken by the
contractor.
Cables shall be bedded in not less than 75 mm of washed sand, clear of all stone and other
foreign matter being of 'concreting' quality. Cable covers shall be of reinforced concrete, not
less than 150 mm wide and 40 mm thick and made specifically for the purpose of cable
covering. It is preferred that they be coloured red. Slabs used as cable covers shall project
beyond the cable outer diameter by not less than 40 mm.
14.9
No cable run shall be backfilled until it has been inspected and passed as satisfactory by the
Engineer.
PVC cable marker tape shall be laid continuously over the direct buried cables at a depth of
14.10
300 mm during the back-filling operations.
14.it
14.9.5 Ducted Cabling
Where shown on the drawings underground cables shall be installed in ducts laid by the
Contractor. Prior to commencing of cable pulling the duct shall be fully swabbed out and all
foreign matter removed. All rough edges shall be removed from duct entry and exit points.
61
ations
Part II- Chapter 14 - Electrical Equipment for Industrial Installations
A pull wire/rope of adequate section shall be used. All cables shall be pulled into the duct at
the same time. Once pulling commences it shall continue until completed in one shift. Cables
and duct may be lubricated with an approved lubricants such as talc.
Following completion of the pull the upper end of the duct shall be sealed with a butyl mastic
or other approved non-hardening sealing compound.
d and
re not
14.9.6 Cable Terminations
All cables for bolted connections shall be terminated with compression jointed cable lugs, with
a minimum of core insulation stripped back. All surfaces to be jointed shall be carefully
cleaned. For compression joints the correct sized die shall be used and all jointing and
other
termination procedures carried out shall be in accordance with manufacturer's
recommendations.
wings.
Multi-core wire armoured plastic insulated cables shall be terminated with weatherproof
compression glands. The wire armour shall be securely clamped within the gland and
by the
connected to the earthed switchboard gland plate or bonded to the earth bus bar.
Neutral screened conductors shall be terminated with weatherproof compression glands with
l other
the screen conductors terminated in a crimp lug on an earthed terminal. Bare conductors shall
te, not
be covered with a PVC insulating sleeve. All glands shall be covered with approved boots
f cable
after being made off.
project
epth of
14.10 Circuit Wiring
14.10.1 General
Circuit wiring shall comply with the relevant sections of this specification together with the
following additional requirements.
by the
: and all
All wires and cables shall be new and shall be brought to the site in their original packages.
ints.
All wiring in which kinks or abrasions occur will be condemned and shall be replaced by
----
61
62
'all-
Chapter I4- Electrical Equipment for Industrial Installations_
the Contractor at his own expense. All conductors shall be stranded and be of copper.
1
All wiring runs shall be installed straight, parallel with the buildings axis. All wiring shall be
fixed in a mechanically protected position and with a clearance of not less than 130 mm from
all other services, unless other suitable protection is provided.
Within the limits prescribed above the Contractor shall select in consultation with the Engineer
the most appropriate routes for wiring runs in the building. Unless specifically stated to the
contrary, the drawings should show switching and circuit connections only, not cable routes.
Where the cable route selected will result in a voltage drop in excess of that allowed by the
wiring regulations, the conductor cross-sections shall be increased to the appropriate size.
Conductors shal not, however, be smaller than those shown on the drawings.
14.
14.10.2Concealment
Unless shown or specified otherwise all wiring shall be concealed.
In unlined plaster finished areas without ceiling or wall cavities, PVC insulated cables shall be
provided in conduits cast into in situ concrete work and chased into site blockwork.
ln unlined plaster finished areas with only ceiling cavities wiring of each sub-circuit shall be in
either PVC insulated cables run in concealed conduits and trunking at all points or PVC
insulated and sheathed (TPS) cables surface run in concealed spaces and run in concealed
14.
conduits in the walls.
The Contractor shall be allowed to drill all holes and cut all chases as required and to make
good plaster work where concealed conduits are installed after plastering. Wherever possible,
conduits shall be installed prior to plastering and the Contractor shall co-operate with the
builder to meet this requirement.
TPS wiring surface run in concealed spaces shall be fixed with approved clips at intervals not
exceeding 220 mm to available structures or otherwise to suitable battens or shall be enclosed
in rigid PVC pipe or cable trunking fixed at 1000 mm. Intervals. Generally not more than 4
cables shall be clipped or enclosed bunched together. Any timber used shall be thoroughly
seasoned and chemically treated to resist fungi and insect attack.
63
tions
Part II- Chapter I4 - Electrical Equipment for Industrial Installations
An unfused spur shall be run from the junction box to the socket outlet.
gineer
In areas with plastered concrete ceiling the junction box shall be cast into the in-situ concrete.
:o the
In areas with removable tile false ceilings, the junction box shall be mounted in the ceiling
tes.
space.
y the
All junction boxes shall be accessible to enable the cable joints to be checked at any time after
size.
installation.
14.10.4 Terminations
Terminations into motors and similar equipment and all terminations on wires larger than 2.5
mm shall be made using approved crimp lugs, unless terminals are specially designed to
accept bare conductors.
all be
Where equipment terminals are designed to accept bare conductors are of insufficient size to
accept the conductors used, the contractor shall either provide copper reducer sleeves and fit
II be in
these to the cables or replace the terminals with those of adequate size.
r PVC
cealed
14.10.5 Prohibited Installations
Cables shall not be embedded directly either fully or partially in concrete or plaster. Cables
shall not be bunched to such an extent that the necessary de-rated cable rating is less than the
make
actual circuit protection setting.
ssible,
·ith the
Cables shall not be fixed in position where they will be exposed to rain, dripping water,
condensation, tar-oil etc., or accumulations of water or oil at high temperature from hot water
vals not
pipes or other sources of heat unless the cables and accessories are adequately shielded or are
nclosed
specially designed to withstand the effect of exposure to water, oi I and heat etc.,
than 4
roughly
No through joints in cables shall be permitted other then in outlet fittings or equipment
terminal boxes, except that where express authority is granted in special circumstance, a
% an
my
maein
be
"eioint an
location.
accessible
in
amorovedtermina!boxfitted
64
{art- Chapter 14- Electrical Equipment for Industrial Installations
14.10.6 Identification
Phase identification shall be provided for all cable cores. If necessary to achieve this end,
coloured PVC sleeves shall be provided firmly attached to the cores.
All control and instrumentation circuit terminations shall be identified using engraved plastic
ferrules over every cable core end or by an approved alternative method. The identification of
each core shall be recorded on circuit diagrams.
Screw fixed engraved plastic labels shall be provided on all motor and equipment terminal
boxes, isolating and control switches etc., socket outlets and light switches identifying the
connection number of circuit reference of the outlet as appropriate.
The dimensions shown on the switchboard arrangement are typical only. However in the event
that the actual switchboard dimensions vary from those ·shown, it shall be the responsibility of
the Contractor to ensure that the board, as built will fit into the space allotted and is in every
way suitable for its intended propose.
The board shall be built by a vendor approved by the Engineer, who is regularly engaged in the
manufacture of similar switchboards.
Before manufacture is commenced thc Contractor shall provide reasonably detailed shop
I
drawings including layouts and wiring diagrams of the board for approval by the Engineer in
accordance with the provisions of the special conditions of Contract.
14.11.2 Construction
Dependent upon size, the switchboard may be constructed from modular components bolted
together or a custom built board of unitary construction.
65
Part II- Chapter I4- Electrical Equipment for Industrial Installations
lations
In either case it shall be of the metal clad, totally enclosed type. It shall be formed of either
folded and welded sheet steel modules bolted together or from sheet steel panels fixed to a
s end,
steel section frame work. The switch board carcass shall be provided with suitable stiffeners so
as form a completely rigid, flush fronted structure which will not deform during switching
operations.
plastic
tion of
The board shall be sufficiently rigid to be capable of being lifted by either crane or forklift
without damage.
rminal
All folds shall be machine made and all structural frames and exposed seams shall be
ng the
continuously welded and neatly ground off. All flat panels shall have a minimum of IO mm
turn-over on all edges and with welded or equivalent corners.
Each major unit of the switchboard such as main switch, fuse.switch, busbar chamber, motor
starter, etc., shall be mounted in a separate enclosure with metal or flame retardant insulating
power
barriers between each unit. All openings between separate enclosures or wiring connections
general
shall be protected with close fitting bushes. High fault boards (greater than 20 MV A
own in
prospective fault level) shall be provided with adequate explosion venting to prevent any
in the
possibility of operating staff being injured should a major fault develop.
Adequate ventilation with proof against vermin shall be provided. Louvred drip-proof
e event
openings fitted with screens having a maximum of 3 mm mesh shall be provided. All un-used
ility of
openings including the switchboard base shall be blanked off.
1 every
Substantial hinged panels shall be provided for front access to switchgear, fusegear, motor
starters, instruments and controls etc., with additional hinged panels for rear access for main
d in the
internal and out-going connection, where the board is of the rear access type. Door catches
shall be substantial.
d shop
Doors providing access to live electrical equipment shall be interlocked with the main isolator.
ineer in
All remaining doors shall be provided with locking type door handles using one common key
which will fit all locks provided on all panels delivered to this site.
The board shall be designed for the mounting arrangement and the access and cable entry
s bolted specified on the drawings. Adequate wireways shall be provided in a readily accessible
66
65
Part II- Chapter 14 - Electrical Equipment for Industrial Installations
location for cable rails and inter panel wiring. Substantial non magnetic, undrilled gland plates
shall be provided for the glanding off of incoming and outgoing cables. Gland plates shall be
bolted in position and shall be readily removable for drilling on site.
The contractor shall ensure that switchboards can be broken down into several sections of
such size as will pass through the finished building openings.
Thickness of the steel plate shall be not less than 2mm for floor standing panels and wall 1
mounting panels larger than 1 metre square. For smaller wall mounting panels lighter gauge
material can be used. Floor slanding panels shall be fitted with lifting eyes unless otherwise
specified. Where there will be no space limitations at site, panels shall be designed to meet the
following limitations.
14.11.3 Finish
All components shall be completely fabricated, drilled etc., before painting and painted before
final assembly. All metal work shall be thoroughly cleaned, de-burred, de-greased, all defects
filled and all surfaces and edges brought to a smooth finish.
The switchboard shall be painted inside and outside with a sprayed coat of self-etch zinc based
primer, followed by an undercoat and two coats of hard baked enamel finish, free of any
defect and of an approved colour within the manufacturer's standard range.
The board shall be supplied complete with I litre of paint of the finish colour for touch up
purposes.
14.11.4 Busbars
The switchboard shall be provided with high conductivity copper busbars adequately rated for
the through fault and load current specified in the specific specifications. Busbars shall
preferably be located in a separate busbar chamber but shall in any case be fully insulated with
67
lations Chap!e
{artll- E4- Electrical Equipment for Industrial Installations
plates phase coloured, solid insulation. Busbar joints which shall be bolted with high tensile bolts,
all be nuts and washers shall be provided with insulating barriers readily removable for joint
inspection and maintenance.
ons of Full length, with removable link neutral and earth busbars, shall be provided. All enclosures
and each section of the board frame shall be connected to the earth bar.
gauge The switchboard shall be supplied complete with all equipment necessary for safe and
erwISe functional operation. Equipment not specified in the equipment schedules or elsewhere on the
eet the drawings or in the detailed specification shall be subject to the approval.
All equipment shall comply with the following general requirements. Unless detailed or
approved otherwise, all equipment of a similar type shall be of the same manufacture. Front
I before safely closed manually in the event of a full fault with the closing lever on the breakers.
defects
Unless specified otherwise all breakers shall be withdrawable and shall be provided with a
'test' position whereby trip/close operations can be tested with the main contacts
disconnected. The mechanism shall be interlocked to prevent withdrawal or re-entry in the
• of any
Breakers shall be fitted with either series or shunt or shunt trips as specified, in either case
suitable relaying or other means shall be provided to give entirely independent inverse
Shunt tripped breakers shall be powered by motor wound springs. Spring stored energy
shall be such that at least two full close/ trip operations can be obtained from a fully wound
spring. Means shall be provided to hand charge the spring in the event of loss of motor
rated for
power.
ars shall
ted with
�------
67
--------------------------------------
68
Part II- Chapter 14 - Electrical Equipment for Industrial Installations
---------------------
Power for operation of the close/trip solenoid shall be provided by a capacitor stored
J
energy circuit powered from the incoming supply. This circuit shall be so arranged that it
can provide sufficient power for n trip operation within not more than I second after power
is applied and shall store sufficient charge to trip the breaker during a fault dropping the
supply voltage to zero for a period of 10 seconds.
MCBs shall be rated to withstand the through fault specified. Where required, the use of
backup fuses or fault limiters shail be provided by the switchboard vendor.
69
tions Part II- Chapter I4 - Electrical Equipment for Industrial Installations
tored per phase. For motor circuits a single CT on one phase shall be provided. Motor circuit
hat it ammeters shall be over scaled not less than 2x.
ower
g the Voltmeters shall be provided where specified and shall be complete with voltmeter switch
reading R-Y, Y-B, B-R, R-N, Y-N, B-N.
14.11.5.6 Fuses
All fuses shall be HRC cartridge type conforming to BS 88 category of duty 440V A2
minimum, complete with fuse carriers and bases etc., of approved manufacture. Motor
use of circuit main fuse and backup fuse for metering and instrumentation circuits and MCB's
shall be fixed directly onto and connected to main busbars.
Except where omission is necessary to comply with other requirements, separate fuses shall
be provided for control circuits and for circuits to power factor capacitors.
I cases All fuse links shall be rated to the appropriate application, with major and minor links rated
motor to ensure adequate discrimination .
hall be
14.11.5.7 Contactors
Contactors for motor and other circuits shall be of the block type, rated to comply with BS
775 for motor starting, category of duty AC 3 continuous operation, with triple pole main
contacts and additional auxiliary contacts as required for control and indication circuits.
rs shall Contactors shall be self-aligning and readily demountable for inspection. Except as detailed
or fuse or approved otherwise, operating coils shall be rated for 240 volts continuous operation.
f doors The whole assembly shall operate silently in the energised condition. Contactors for
monitored earth circuits shall incorporate a gravity operated fail safe mechanism on de-
energisation in the event of failure of release springs etc.
device.
relays) shall be of the plug in type and of machine tool operating quality. All relays used
shall be identical. Unless approved otherwise all operating coils shall be 230V AC. All
spring reserve lasting at least 18 hours and shall be suitable for one 'on' and one 'off
and equipment of suitable size and shape for any of the tariffs which may be offered by th is
authority for the installation. This shall be carried out as detailed and shall consist of an
enclosed cabinet with the switchboard, fitted with an insulating panel for the support of
meters, relays, time switches and terminal block, test links and potential fuses, all of which
shall be subject to the approval of the power supplying authority. A removable section of
busbar shall be provided to suit the mounting of metering current transformers (CTs).
The Contractor shall be allowed to supply CTs or to fit CTs supplied by the power
External connections to fuses and circuit breakers shall be made off directly into the fuse
circuit breaker terminals. Where such terminals are inaccessible suitable busbar
connection panels or heavy duty terminals shall be provided.
External connections to other circuits shall be made off into a rail mounted terminal block
71
ions
The line or live side of all protection equipment shall be at the top of the switchboard.
Wiring within panels shall be carried out in colour coded high grade insulated cables rated to
the manufacturer's recommendation. Wiring upto I 6mm will normally be colour coded as
:lass
follows.
used
. All
Phase connection Red, Yellow or Blue
Neutral Black
Earth Green or Green & Yellow
Low voltage Brown
ound
D.C. Grey
'off
For cable runs, plastic trunking will be used but cables shall. not occupy more than sixty per
cent of the volume to ensure adequate cooling.
hority When cables must be run in looms they shall be retained by cleats designed to prevent damage
y this to the cable insulation. A.II cleats should be screw fixed to the metalwork. Adhesive type clips
of an are not permitted.
ort of
which No single core cable will be used. Control circuit wiring shall be a minimum of 32/.20 mm
.ion of square.
Ts).
power All cables shall be identified at each end by means of colour coded ferrules with black lettering
which shall be cross-referenced in detail on schematic wiring diagrams.
Numbered ferrules shall be provided on all cable cores or core insulation with suitable self-
eakers, identification coding for all external control circuits, and also for all auxiliary instrument and
ps etc., internal control connect.ions longer than 100 mm or otherwise not readily traced visually. The
identification code shall apply the same.
he fuse core number to all points on the same connection which are electrically identical irrespective
busbar of the number of junctions connected together. Such core numbers shall be shown on final
circuit diagrams.
al block All terminal blocks shall be numbered to match the core numbers.
72
'al- Chapter 14 - Electrical Equipment for Industrial Installations
Terminals blocks for ELY wiring shail be segregated from LY blocks.
Except with the express approval of the Engineer, circuitry shall be such that each motor
starter is totally independent of every other starter, i.e. common control power circuits shall
not be used and there shall be no interlocking, wired directly from one starter to another
unless required for safety reasons. In general the basic control circuitry for any one type of
starter shall be identical and all interlockings or special control features shall be provided in
a separate relay panel with a single contact only being wired back to the motor starter for
operation on automatic control.
Each motor starter shall be provided with a control switch which can be operated in the
following positions:
Panel Enables starter mounted start/stop push button for test purposes.
Off Control power off
Local Enables start/stop push button or other manual control adjacent to 14.11
the driven device.
The fusing arrangement shall be such that main fuses can be withdrawn without removing
control power from the starter to allow full operational testing to be performed without causing
driven plant to operate.
73
ations Part II- Chapter I4- Electrical Equipment for Industrial Installations
Power factor correction capacitors which shall be of non PCB filled type shall be provided
individually for each motor. Power factor correction shall be to 0.95.
of the Where reduced voltage starters are required these shall be of the closed transition type.
Star Delta starter will not be acceptable.
motor Within panels, adequate labelling shall be provided, using white letraset "Helvetica
s shall medium 24 PT" capitals on the trunking lids coated with hard varnish for all fuses, relays,
.nother starters and control equipment. Such labelling shall correspond in detail with item
ype of numbers on the panel wiring diagrams.
ided in
ter for An internal layout drawings shall also be mounted on the inside of the access door giving
item numbers for additional identification of equipment.
in the Warning labels will be provided on each door or cover giving notice of any live medium
voltage circuits which will be exposed when the doors are open or when the cover plates
are removed.
All labels on the outside of the panels shall be fixed by means of 3mm chrome screws.
73 74
tions
Part II- Chapter I4 - Electrical Equipment for Industrial Installations
irely
single and multipole circuit breakers are fully interchangeable.
n the
A full height escutcheon plate shall be provided and so mounted that only the circuit
breaker operating toggles project. The panel shall be provided with full width neutral and
earth bars and adequate wire ways. It shall completely cover all terminations, busbars and
with
wiring. The panel shall be provided with a substantially hinged and latched door.
Upto two small relays or contactors for the control of external circuits may be located
behind the distribution panel escutcheon. Where the number exceeds this, or where called
for on the drawings, relays and contactors shall be located in a separate compartment
I ,
which shall be provided with a fixed cover held in position by plated acorn nuts.
1 Sze
Contactors and relays shall be mounted upon a rear gear tray.
14.12.4 Finish
Unless specified otherwise the boards shall have a painted finish with the final colour
being subject to the approval of the Engineer. The standard of the finish shall be in
vided
accordance with that specified in the switch board clauses of this specification.
All wiring and connections shall be to the same standard as that called for in the
Switchboard clauses of the specification.
ush or
all be
14.12.6 Equipment Identification
Each distribution board and individual equipment such as contactors, relays, etc. shall be
labelled as specified in clause 14.11.10.
·ulated
r fuse
:h that
76
Chap!e"
-'awl;'-
Electrical Equipment for Industrial Installations
14.12.7 Inspection
The Engineer reserves the right to inspect the distribution boards prior to their despatch from
the vendor's works.
The Contractor shall give adequate notice of completion to allow for this inspection to be
made.
Flush boxes mounted in block work walls shall be located in recesses saw cut into the block.
The flush boxes shall be fixed in place before final plaster finishes are applied.
Flush boxes mounted in masonry walls shall be securely fixed and conduited before bonding
concrete is poured. Flush boxes in framed up walls shall be fixed by screwing to studs,
noggings, etc. Where studs or noggings are not available in the locations required, the
coniactor shall install wooden noggings of minimum size 100 x 25 mm. Fixing methods
relying on nails driven through the boxes will not be accepted.
Surface boxes mounted on plaster finished masonry and block work shall be installed prior
to plastering so that in the final installation these boxes shall be semi- recessed in the plaster
work.
14.14 Commissioning
Upon satisfactory completion of all on site test measurements and inspections the Contractor
shall give notice in writing to the Engineer at least 14 days in advance of the intention to
commission the installations ready for foll service and arrange for the presence of all parties
concerned in consultation with the Engineer.
During final commissioning of the plant and installations suitably qualified stand by staff
shall be arranged from all trades in consultation with the Engineer so that all related services
are available during the commissioning.
Upon satisfactory commissioning the Engineer shall authorise the taking over and will issue
the appropriate certificate in accordance with the Conditions of the Contract.
---
llations
- Part II- Chapter I4 - Electrical Equipment for Industrial Installations
specification and shall be submitted to the Engineer in three sets prior to the issue of the
certificate of completion.
n to be
surface
• block.
onding
studs,
ed, the
ethods
·d prior
plaster
tractor
tion to
parties
y staff
;ervices
ill issue
---- 78
77
PART III
AIR- CONDITIONING AND VENTILATION
CONTENTS
Page
Chapter 1 Introduction to the Specifications for Air-Conditioning
and Ventilation Systems
J. l Specifications and Standards . 84
2.3 Welding . 88
2.4 Pipe Hangers and Supports .. 89
2.5 Expansion of Pipework 90
2.6 Valves and Cocks 91
2.6.1 Drain Cocks 91
2.6.2 Air Cocks 91
2.6.3 Terminal Units . 91
2.6.4 Ball Float Valves . 92
2.6.5 Automatic Air Valves .. 92
2.6.6 Safety Valves . 92
2.7 Pipe Sleeve and Floor Plates . 92
2.8 Strainers 93
2.9 Plugs for Open Pipes and Ducts .. 93
2.10 Flushing and Cleaning 93
2.11 Protection of Pipework 94
2.12 Painting 94
79
2.13 Testing of Pipework 94
2.14 Valve and Equipment Labels 95
.
101
101
101
102
,
·1
l1
;:
3.11 Diffusers, Registers, Grills and Troffers .. 105
3 .11.1 Diffusers 105
3. I l.2 Registers 105
4.
3.11.3 Grills .. 106 41
3 .11.4 Troffers
:
. 106
3.12 Louvres .. 106
3 .13 Sound Attenuators .. 106 41
4.
3 .14 Flexible Connections . 107
4.
3.15 Connections to Builders Work .. 107
4.
3.16 Fans . 108
4.
3.16.1 Roof Extract Fans .. 108
4.
3.16.2 Window/WallMountedExtractFans .. 1 08
3 .16.3
3 .17
3. l 7. l
Duct Mounted Extract Fans
Other Systems of Ventilators
Hoods
..
..
.
108
109
109
"
4.
4.
4.1
3 .17 .2 Roof Exhausters and Ventilators .. 109
80
3.17.3 RotoryTurbineVentilators,WindActuated 109
-go
81
Chapter 5 - Controls and Instrumentation
6
5.1 General 127
6
5.2 Sensors 127
6
5.2.1 Temperature Sensors (Thermostats) 127
6
5.2.2 Humidity Sensing Elements 127
6
5.2.3 Pressure Sensors (Pressure Gauges) ..... .. .. .. .. .. .. .. .. .. .. .. 127
5.2.4 Water Flow Meters 128
5 .3 Controls 128
7.
5.3.1 Control Valves 128
7.
5.3.2 Chilled Water Control 128
7.
5.3.3 AHU/FCU Start up and Controls: Recirculation Plant 128
7.
5.3.4 Indicating Panels 129
7.
5.4 Auxiliary Controls 129
5.4.1 Electrical Controls 129
5.4.2 Pneumatic Controls 130
5.5 Pressurised Expansion Tank 130
5.6 Water 'Treatment .......8......88......88.888..8.8088....38..3.8.888.................8............. 13]
Chapter 6- Insulation
6.1 General 132
6.2 Thermal Insulation for Air Conditioning Ductwork . 132
6.2.1 General . 132
6.2.2 Air Conditioned Spaces . 134
6.2.3 Non Air Conditioned Spaces .. 134
6.2.4 Plant Roon1s . 134
6.2.5 External Duckwork . 134
6.2.6 Fittings 135
6.2.7 Supports 135
6.3 Thermal Insulation for Air Conditioning Pipework .. 135
6.3.1 General . 135
6.3.2 Chilled Water Pipework 136
6.3.3 Air Conditioned Spaces 136
6.3.4 Runouts . 137
6.3.5 Non- Air Conditioned Spaces . 137
6.3.6 Plant Roorns . 137
6.3.7 External to Building above Ground .. 137
-
82
6.3.8 External to Building below Ground 138
--82 83
CHAPTER 1
INTRODUCTION TO SPECIFICATIONS FOR AIR
CONDITIONING AND VENTILATION SYSTEMS
!n adopting the recommendations of this part of the specifications attention shall always be
placed on the need to optimize the energy consumption and the need to reduce hazards and
minimize effects detrimental to the environment.
All designs and construction works shall follow the latest standards of specification and
regulations. In every respect this specification should be considered as a 'General
Specification' and any conflicts of interpretation of any particular area of the specification
shall be referred to the Engineer for final decision.
84
Part- II- Chapter I- Introduction to Specification for Air-Conditioning & Ventilation Systems
85
2ms
CHAPTER 2
or PIPE WORK
ent,
Flanges or unions, the latter of the spherical bronze seat type shall be fitted to facilitate
installation and maintenance at not more than 20m intervals and at all connections to
equipment.
Screwed joints shall be made with the approved PTFE tape up to 40mm size and hemp/jointing
compound for 50mm size and above and each screwed joint shall be in accordance with the
appropriate British Standard.
All flanges shall be in accordance with BS 4504 and joints shall be made with full faced
Any copper alloy used 111 fittings, brazing rods, etc., shall be capable of withstanding
dezincification.
Runs of piping shall be supported so that a clear space of not less than 50 mm is left between
the pipes or lagging and the nearest wall ceiling or other surface.
Al! reductions in pipe sizes shall be made using standard reducing fittings. Changes in
direction shall be made with standard bends.
All pipes, fittings, etc., are to be cleaned of any foreign matter, open ends plugged during
erection and the complete system flushed out or blown through before putting into service.
86
85
Part III - Chapter 2-Pipe Work
All other chilled water supply and return pipes to air handling units shall be in black heavy
weight steel conforming to BS 1387, with screwed joints and malleable iron fittings to BS 143
and 1256 or in unplasticised PVC conforming to SLS 147, Type 1000. Where suitable, and 2.1.
approved by the Engineer, small diameter connections may be in light gauge copper
conforming to BS 2817, Table X with capillary type fittings.
All copper tubing shall be of refrigeration quality (sealed ends). Joints shall be avoided but
where required and approved by the Engineer shall be interconnected (or expanded) or by
means of copper solder fittings and silver solderes using Bakers soldering flux or Silfos l 5
Alloys solder. Bends shall have an inner radius of not less than five times the diameter of the
tube to avoid crimping. If copper solder fittings are used, the bend radius should be according
to the standard radius. Tubing shall be installed neatly and shall be supported in the following
manner:
In vertical runs, clamps shall consist of hard wooden clamping blocks cut in half and provided
with holes for the tubing. Alternatively proprietary piping fixtures may be used subject to the
approval of the Engineer. The maximum distance between clamps shall be 1.00 m and the
distance from a bend in the tubing to a clamp shall be not more than 300mm.
2.3
All tubing shall be leak tested before the commissioning of the unit.
The compressor suction line shall be insulated by means of appropriate insulating sleeves to be
approved by the Engineer. In cases where this sleeve is exposed to mechanical damage in
outdoor locations an adequate aluminium sheathing protection shall be installed.
87
Part III- Chapter 2- Pipe Work
---
e Work
Where metal clamps are used, the tubing shall be insulated from these or protected, short
wrappings of plastic tape shall be used to prevent chaffing and galvanic action.
black
2.1.4 Condenser Water Piping
ittings
shall Condenser water piping may be unplasticised PVC pipes conforming to SLS 147; Type I 000
or to BS 3505, Class E with solvent cement joints and injection moulded rigid PVC fittings
5 with conforming to SLS 147; or BS 4348 or black heavy weight steel to standards specification in
2.1.2 above. All condenser water pipes within plant rooms and pipes in other areas (if diameter
exceeds 100 mm) shall be of black heavy weight steel or galvanized from to BS 1387 heavy
heavy gauge.
S143
, and 2.1.5 Condenser Drains
opper Condenser drains shall be in unplasticised PVC conforming to SLS 147 or BS 3505, wth
solvent cement joints and injection moulded rigid PVC fittings conforming to BS 4348.
d but Wherever possible, piping shall be graded to permit natural venting and draining to a minimum
s 15
f the Manual air vents shall be fitted at high points and at all potential air pockets on all chilled
wing
20 mm diameter drain valves suitable for hose coupling shall be fitted to all low points in the
piping system.
ided
the Grading of all drain and vent lines shall be in the direction of flow and not less than I in 200.
I the All vents and drain valves shall be mounted outside the insulation.
2.3 Welding
Welding of mild steel pipework shall be carried out by either the oxy-acetylene method 111
accordance with BS 1821 or the metal arc method in accordance with BS 1856.
be
e 1 Brazing of copper pipelines shall be carried out by the self-bronze process.
87 88
Part III - Chapter 2- Pipe Work
All workmen carrying out welding on the site shall be in possession of a valid welding
certificate.
The Engineer reserves the right to carry out the tests as detailed in the appropriate British
Standard on one percent of the welds in the installation. All weld joints unless otherwise
specified shall be subject to at least a dye penetrant check after welding.
All clips, brackets, supports, etc., in contact with the pipe wall shall be of the same material as
the pipe, otherwise an approved non-metallic packing material is to be inserted between the
Straight pipework shall be supported at centres not less than those given in Table B 16.3 of the
[HYE Guide 1970 or to manufacturer's recommendations.
Pipework shall be supported as indicated on the drawings or, if not specifically detailed, in
accordance with the following:
Horizontal main shall be supported on rollers and chairs or by standard mild steel hangers and
clips from lengths of channel iron or "Unistrut" type channel either built-in or bolted to the
structure.
Branch mains shall be supported as above or by means of standard munsen ring clips, built-in 2.5
screwed to the adjacent structure.
Vertical mains shall be supported from anchor points fixed rigidly to one intermediate floor
slab with guide supports at the remaining floor slabs.
89
Part IHI - Chapter 2- Pipe Work
Work
Small diameter run-outs shall be supported by standard school-board pattern clips, built-in or
ding
screwed to the adjacent structure Qr, by means of standard double saddle clips.
All ferrous brackets or parts thereof shall be painted two coats of red lead primer before fixing.
itish
wise
Chilled water pipework operating at a temperature below ambient dew point shall have
supports arranged to fit around the outside of the pipe insulation. A vapour sealing, a 1.5mm
thick galvanised sheet steel half sleeves, two diameters in length or machine cut timber support
blocks shall be fitted over the insulation to spread the load at every support point. Heavy
that
density expanded polystyrene or cork shall be fitted round the pipe as insulation under the
the
sleeves.
Supports on horizontal and vertical piping shall be spaced as follows, unless otherwise
specified.
l as
the
Pipe Pipe Support Centres Minimum Support Rod
(mm)
the
Steel PVC
15 2.0 1.25 10
20 2.4 I.SO 10
line
32 2.7 2.00 10
40 3.0 2.00 10
50 3.4 2.20 10
' 111 65 3.7 2.40 15
80 3.7 2.40 15
t-in
2.5 Expansion of Pipe work
All pipework shall be erected, and on completion be left in such a manner that expansion and
contraction is taken up without excessive stress on the pipe to the building structure. Where
0or
this cannot be achieved with the normal run of pipework, special expansion loops or expansion
90
89
Part I - Chapter 2- Pipe Work
------------ --·----
Expansion loops shall be made up from pipe of the same quality as the main, either with
welded elbows or fabricated from a single length of pipe with pulled or fire-set bends.
Expansion joints shall be of the stainless steel bellows type adequately supported, in
accordance with the manufacturer's instructions and with guides on the mains adjacent to the
joints.
"Cold draw" shall be applied, suitable to the pipe work and service, by pulling up through long
bolts on the expansion loop/joint flanges. The long bolts shalt afterwards be replaced by
normal or expansion unit bolts.
The provision for expansion is to be checked before and after any enclosure of the pipework.
Cocks 25mm and under, shall comply in all respects with BS 2879, Type A, bronze draining
taps, screw down pattern, lock-shield design with loose key.
2.6.2 Aircocks
All air bottles on low pressure systems shall have 6 mm, aircocks fitted with loose key, as
detailed on the drawings.
91
Work
- Part HI - Chapter 2 - Pipe Work
with The connection to the unit shall be of the metal to metal union pattern and the opposite end
appropriate to the pipework.
, In The flow valve shall be of the wheel type and the return valve of the lockshield type.
the
Where visible, valve bodies shall have a polished finish.
mng ends.
as provided with PVC sleeves having an internal diameter at least 50mm larger than the outside
of the pipe (or pipe with insulation, in case of insulated services), suitably packed and finished
not less than 2mm proud or the finished surface. The annular space between the pipes and
sleeves shall be adequately caulked with asbestos rope to reduce noise transmission.
67, In wet areas, sleeves through floors are to be extended 30mm above the finished floor.
tic
as A chromium plated rolled steel hinged cover plate shall be provided and fixed to all exposed
pipes at each end of each sleeve and to every exposed pipe rising through floors.
92
91
Part IHI - Chapter 2 - Pipe Work
----------
Where pipes pass through trench covers, specially approved flanged sleeves shall be provided
to form watertight seals.
2.8 Strainers
Strainers shall be supplied and installed in the pipework as indicated on the drawings or, if not 2
specifically indicated, to provide at least one strainer for each water circuit.
isolating valves shall be provided on each side of the strainer or the strainers to be fixed
relative to equipment isolating valves so that the strainer can be opened and cleaned without
draining down the circuit. 2.
Strainers, 65mm and over, shall be of the 'Y' pattern with cast iron body, 1.5mm stainless
steel screen and flanges conforming to PN 16.
Strainers, 50mm to 32mm, shall be of the 'Y' pattern with gunmetal body, Imm brass screen
and screwed BSPT ends.
Strainers, 25mm and under shall be of the 'Y' pattern with pressed brass body, 1 mm brass
screen and screwed BSPT ends.
Strainers in external pipework, 65mm diameter and larger shall be of the bucket type with 2.
flanges conforming to PN 16.
The piping system shall be thoroughly flushed out with water. Strainers of not less than 0.7
mm ( number 40 ) mesh shall be installed during this period. The strainers shall be cleaned and
inspected after flushing has been completed.
----------------·--··----·-·- ---
93
Part III- Chapter 2 - Pipe Work
.rk �-------------------------------
ed After draining of flushing water, each system shall be filled with softened fresh water from the
lowest point, de-aerated and checked for full water flow, in each system. All subsequent
fillings and toppings shall be softened water.
ed applied.
ut
2.12 Painting
Items of equipment shall be provided with the manufacturer's standard finish which, on
2ss completion of installation, shall be in good condition or brought up to original standard.
Ferrous pipework, brackets, etc., shall be painted two coats of red lead primer. Alternatively,
en where steelwork is completely enclosed a proprietary anti-rust coating may be used.
Pipework, brackets, etc., in public spaces shall be painted two coats of red lead primer, and a
ass decorative finish coat as specified elsewhere or otherwise in accordance with the colour code,
conforming to BS 1710.
ted
All tests are to be recorded and signed by the contractor's senior representative on site and, so
far as possible, witnessed by the Engineer. All pipework except open ended vents and drain
pipes, shall be tested at 700 kN/m2 or at twice the working pressure whichever is greater, for a
period of three hours. During the tests welds shall be hammered. All pipework shall be flushed
ed
out after testing. It is the Contractor's responsibility to see that tests are correctly carried out
ure
and that any remedial measures necessary are effected and re-tests carried out so that on
the
completion of the works each and every section has been satisfactorily tested and a complete
set of certificates forwarded to the Engineer.
0.7
Following completion of satisfactory section tests a complete system test shall be carried out,
and
witnessed and approved by the Engineer.
94
93
Part III- Chapter 2- Pipe Work
All equipment shall be clearly labelled. The labels shall be of multi layer, white and black
plastic similar to that previously specified, front engraved, securely fixed to the equipment by
means of stainless steel screws or blind rivets. All equipment labels shall be engraved with a
number, name of the equipment and service as previously specified but with the legend on the
face only.
A valve chart indicating the duty and position of all valves shall be fitted into a glazed frame
and fixed in an agreed position.
Identical copies shall be handed over to the Engineer as a part of the record drawings.
·---···------------------------
95
CHAPTER -3
ti- INSTALLATION OF VENTILATION SYSTEMS
of
ne
3.1 Sheet Metal Duet Work
ey
3.1.1 General
ll1
Ductwork shall be supplied and installed generally as shown on the drawings to provide a
all
complete working installation and in accordance with the details stated hereafter.
Dimensions of ductwork shall be as given on the drawings, except where site measurement
ck
necessitates variation, in which case the specified cross-sectional areas to be adhered to and the
by
change in section made with tapered transfer pieces. Sizes given on the drawings are internal
1a
sizes and where internal insulation and/or acoustic lining is provided the duct is to be increased
the
in size to give the specified free internal dimensions.
Ductwork shall be cleaned out as erection takes place and all openings blanked off until he
me
whole system is in operation.
All raw edges of ductwork shall be painted with one coat of aluminium paint before leaving
All ductwork passing through plant room floors and walls shall be provided with a sleeve and
the space between the duct and the sleeve shall be packed with suitable sound insulation
material to reduce the noise transmitted to other parts of the building from the plant room.
Where there is a possibility of the transmission of vibration the duct work shall be isolated
from the building structure.
Where ducts pass through the structure, holes shall be provided with 50mm x 50mm timber
frames around the perimeter by the Contractor. Angle flanges to be secured around the
perimeter of the ducts shall be supplied and fixed to the timber frames.
The material used shall be selected with service in mind, and special consideration shall be
given when equipment has to handle corrosive gases, dust and similar contaminants.
Galvanised steel, shall be used for all metal duct work, unless otherwise specified. All
96
95
Part II- Chapter 3 - Installation of Ventilation Systems
structural supports and parts shall be of structural steel conforming to BS 449 or ASTM A 36.
In other cases, where material in ducts are different to supports etc., materials used shall be
well insulated so as to avoid direct metal to metal contact.
The Duct design shall be such that it will supply the specified volume of air to each area within
the facility, at a specified pressure and velocity. Low pressure ducts shall have static pressures
upto 500 Pa and a velocity of l 3 mis. High pressure ducts shall have pressures of 0.75 to 25
kPa static pressure and velocities above 10 m/s.
The duct design shall ensure that the noise levels are low and tolerable.
The sections of the duct may be rectangular or circular conforming to the preliminary drawings
and the recommended section shall be used for the fabrication of ductwork.
The duct assembly shall be air tight as to allow leakage of not more than 1.0 percent of the
total flow rate. Any leak in the system shall not create any audible noise.
Pressure relief controls shall be provided to overcome problems due to excessive pressure
loads, and fire dampers provided shall have a minimum of 1.5 hour, standard fire protection
rating.
Joints, except for those made on site, shall be of the lock form type.
97
ms Part HI - Chapter 3 - Instatlation of Ventilation Systems
6. Site erection joints up to 600mm size shall be drive cleats or slip joints, the latter lapped in
be direction of flow secured with self tapping screws sealed with mastic and/or taped with plastic
Site erection joints over 600mm size shall be as above but further reinforced with the relevant
size of angle stiffener. Alternatively, large ducts may be jointed by means of angle iron flanges
ed
and suitable gaskets and /or mastic.
mnd
Ing
Apart from painting requirements specified elsewhere, all stiffeners and angles, if not
galvanised after manufacture, shall be painted with red oxide undercoat and aluminium paint
finish before fixing to duct. All screws, fastenings etc. are to be sheradised.
hin
res
Back draft dampers shall be of the same material as the duct work, and multiblade type. Blades
. 25
shall have felt strips riveted or crimped in place and shall be joined using suitable connection
bars. Each blade shall be attached to the pivot rod, and the pivot rod shall extend into an oil
Acoustical duct lining shall be flexible or rigid mineral fibre. The lining shall not be less than
1gs
25mm thick. When acoustic lining is used duct size shall be adjusted to compensate for the
thickness of lining .
the
In lieu of acoustical lining, factory fabricated sound attenuators may be provided. Factory
fabricated attenuators shall be constructed of galvanised steel sheets. The outer casing of which
shall be not less than 0.9 mm and the pressure drop through the attenuator is not more than 15
sure
percent of total external static pressure of the air hand! ing system. When sound attenuators are
tion
to be site fabricated, construction details and behaviour shall be similar to the factory
fabricated units.
Low pressure ductwork will not normally be pressure tested but if inspection and/or air flow
and
tests suggests air loss, a pressure/smoke test will be called for by the Engineer.
the
. air
Wherever mitred bends are indicated on the drawings, radius bends shall be installed in
accordance with HVCA Specification DW 141, unless space limitations require square bends,
in which case air turn vanes shall be provided.
98
97
Part III- Chapter 3 - Installation of Ventilation Systems
------
Details given in Table 1 shall be used in the construction of low pressure type rectangular
ductwork unless otherwise specified.
Table 1
Galvanized Maximum Type of Transverse Bracing
joints.
99
S
Sound traps shall be provided on the discharge and suction duct of each high pressure fan
operating at pressure above 1 kPa. Maximum permissible pressure drop across a sound trap
shall not exceed 150 Pa. The traps shall be air tight when operating under an internal pressure
of2 kPa.
Sound trap shall be site or factory fabricated. In case of site fabricated sound trap, it shall be
contained in an oversized section of duct constructed of galvanized iron not thicker than 1.3
mm or of 1.6 mm thick aluminium, having a suitably sealed joint. Each trap shall be
constructed of No. 2 mesh galvanised wire cloth or 1.6mm galvanised expanded metal, and
shall have a nett inside dimension not less than the connecting discharge duct. The layers of25
mm or thicker acoustic blanket shall be installed between the duct and the wire cloth to provide
the required sound reduction.
100
Part II- Chapter 3 - Installation of Ventilation Systems
The ducting shall be subject to the relevant fire resistance requirements of the enclosing space
and shall be insulated. •
3
Ducts shall be fabricated with material suitable to handle the type of contaminants in the air
and shall withstand the design air flows and pressures.
Horizontal runs shall be fixed by means of mild steel brackets connected onto a mild steel band
encircling the duct or fixed to the stiffening angles for larger duct sizes. The brackets shall be
suspended from the structure by flexible hangers or supported on cantilevers.
Low level ductwork shall in general, be supported as above or otherwise on special mild steel
frames.
3
One anchor type support shall be provided for each main run of ductwork, or each 20m, either
by fixing rigidly to the structure or by cross braced hanger supports.
Vertical runs shall be fixed rigidly to and completely encircling the duct and be arranged so
that the whole weight of duct is transferred to the support.
191
ns
Part III- Chapter 3- Installation of Ventilation Systems
In insulated ducts where the dew point of the enclosing space is below the duct air temperature,
th
brackets shall be of standard size and the insulation carried over the bracket. Where the dew
n-
point is above duct air temperature, the brackets are to be oversized and fitted with rigid
lly
insulation between the duct wall and the bracket.
3.5 Dampers
ce
3.5.1 Control Dampers
Adjustable dampers shall be installed generally as indicated on the drawings, but at all main
branches in the ductwork, the fresh air inlet, the recirculation main duct, and also where
air
necessary for correct balancing of the system.
Dampers shall be of the manually adjustable type with indicating quadrant and lockable lever
and are to be of rigid construction, free from noise or rattle under operating conditions.
WI
Dampers with side dimensions less than 300mm shall be of the single blade type of thickness
not less than 1.6mm with I 0mm diameter pivot rods and rigid bearings.
for
Dampers with side dimensions over 300mm shall be of the multi-leaf type of thickness not less
at
than 1.6 mm and no blade shall be more than 250mm wide. They shall be provided with
10mm diameter pivot rods, aerofoil section set in rigid bearings and linked externally to a
single quadrant and lever.
and
I be After final commissioning, the position of the dampers should be indicated with durable paint.
Unless access is feasible through adjacent equipment, hand access panels shall be provided to
teel enable full inspection of the blades.
l so Fire dampers shall be located within the thickness of a fire barrier. Where this is not possible,
the section or ductwork between the damper and fire barrier shall have a fire resistance equal
to that of the damper itself, and not less than 6mm thick mild steel plates.
101 102
Part IHI - Chapter 3 - Installation of Ventilation Systems
-�------------··-----·----
Each fire damper assembly shall be held in the open position by a fusible link, generally set to
release at a temperature of 7(''C and all blades must be weighted to ensure immediate closure
on release of the link.
Access doors shall be provided at all fire dampers to enable full inspection of the blade and
fusible 'ink.
Access doors shall not be less than 450mm x 450mm clear, unless this effects the duct
dimensions.
Fire dampers shall be of the type having the shutter outside the normal airstream.
() Access for personnel for maintenance and replacement of plant items, where
appropriate.
(ii) Access for routine maintenance, lubrication and adjustment of items not requiring full
access.
(iv) Access for inspection of items concealed in ductwork such as dampers, fusible links,
thermostats, etc..
Access doors shall be not less than 450mm x 450mm clear, unless this affects the duct
dimensions. They shall be hinged and fitted with felt seals, secured to prevent stripping and
provided with cam lock fasteners. Holes cut in the duct walls for the access doors shall be
provided with stiffening frames.
Where hinged doors cannot be included due to space limitations, bolted-on type with quick
3.9
Access holes shall be 200mm x 200mm clear, unless this affects the duct dimension. They
shall be of the bolted-on type and be fitted with felt seals.
103
ns Part III - Chapter 3 - Installation of Ventilation Systems
to Access doors on insulated ducts are to be insulated and a retaining frame is to be provided for
re the duct insulation where it abuts the door opening.
Test holes shall be made up of a brass nipple and cap welded to the duct or casing adjacent to
each temperature sensing device. On low pressure system and on fan suction sides of all
casings an instrument test hole with cap may be used in lieu of a welded brass nipple.
Sheet metal thicknesses and reinforcements shall be selected so that under normal operating
1ks, pressures the casing wall shall not deflect excessively. The strength of panels under normal
operating pressures shall be so as to limit the deflection to 1/240th of the unsupported panels
span.
luct
and Access doors shall be provided in each section of the casing and shall be of air tight
I be construction. Each door shall have a neoprene or similar type gasket. When doors are provided,
the hinge mechanism and fastening mechanism shall be constructed of corrosion free material
such as brass. The fastening shall have provisions for opening from inside or outside. Doors
rick shail swing so that the fan suction or the pressure holds the doors in closed position.
3.9 Eliminators
hey Each cooling coil in the field fabricated casings and duct work having an air velocity of over
2m/s. through the net face area shall be equipped with moisture eliminators, unless the coil
-------------------------------------
103 104
Part IHI- Chapter 3 - Installation of Ventilation Systems
manufacturer guarantees that no moisture will be carried beyond the drip pans under actual
operating conditions.
Eliminators shall be constructed so that they are removable through the nearest access door in
the casing or duct work.
including headers, return bends, distributors and uninsulated pipe and fittings. Where
individual eliminator blades are made in sections, auxiliary drip through shall be provided at
the bottom of each section with drains and drip pans. Material used in drip pans shall resist
corrosion for long times and shall be removable easily for replacement.
Ceiling diffusers shall be circular, square, rectangular perforated face, perforated plate or linear
type. Diffuser shall be sized in accordance with the recommendations of the manufacturer, and
shall be equipped with baffles or other devices required to provide proper air distribution 3
pattern. Factory fabricated turning vanes furnished by the manufacturers shall be provided at
each diffuser, branch duct or take off except where flexible duct is used. Volume dampers and
separate pattern adjustments shall be fixed so that it could be removed through the diffuser
neck for access into the duct. Diffusers used for the exhaust or return shall be similar to
diffusers used for supply, except that, elements used for air pattern control is only eliminated.
3.11.2 Registers
Registers shall be provided with factory fabricated volume dampers, furnished by the register
manufacturer. Volume dampers shall be group operated, opposed blade and adjustable type.
Exhaust and return registers shall be similar to supply registers except that they shall have a
-------------------·-------------------
105
----------- ----------------------------
single set of non directional face bars or vanes having the same appearance as the supply
register. Registers shall be factory primed ready for finish, painting.
n 3.11.3 Grills
Grills shall be manufactured and finished as registers except that the volume dampers shall be
omitted.
ts 3.11.4 Troffers
e The air handling portion of the combination light and air handling troffer shall be provided
at with a method of balancing the air in the supply troffer, which shall be accessible for
st adjustment without requiring the removal of troffer components or ceiling panels after
installation. Supply air shall be delivered in uniform adjustable pattern along the entire length
and/or width of the troffer. The return air handling section shall vent room air and attenuate
room noise passing into the ceiling plenum. Return and supply air handling sections shall be
ll interchangeable except that distribution plenums are not required for return sections
3.12 Louvres
Louvres which are connected directly by the duct work to air handling equipment shall be
·d, made of galvanised steel or aluminium unless otherwise specified. All louver shall have 50
·re percent free area and shall be constructed to withstand a wind pressure of 1.5 kPa. They shall
be designed and manufactured with accurately fitted blades with folded edges to exclude
nd
on 3.13 Sound Attenuators
at Sound attenuators shall be supplied and installed as indicated and scheduled on the drawings
nd and also as necessary to achieve the sound levels in accordance with design criteria specified
to
I. It shall be the Contractor's responsibility to ensure that the sound attenuators provided are
capable of reducing the sound power level of the fans and system, as installed, to the design
room conditions as noted.
ster
pe. The sound attenuator casing shall be manufactured from pre-galvanised steel to the appropriate
106
105
Part II- Chapter 3- Installation of Ventilation Systems
---------------------------
The acoustic lining material of the sound attenuators shall be of inorganic incombustible
fibreglass having a minimum density of 32kg/m3 protected from air stream erosion by a
reinforced glass fibre mesh and be contained within a 0.91mm thick pre-galvanised metal
splitter on each side of which shall be an exposed face of material.
The splitters shall be arranged within the casing to provide a number of airways, the width of
each being determined by the required acoustic performance. A half width splitter shall be
fixed on the attenuator side walls for minimising flanking problems. Splitters shall be secured
to the casing by pop rivets or self-tapping screws.
Where zinc galvanising is destroyed during the manufacturing process, all such places shall be
The sound attenuators shall be installed with suitable transformation pieces to adjacent
ductwork.
Sound attenuators handling saturated air shall be manufactured generally as above but in lieu
of the reinforced glass fibre mesh, the acoustic infill shall be inserted behind scrim and be of
0.55 mm thick perforated sheet steel having 50 percent free area and hot dipped galvanised
after perforation.
In all cases the duct end shall finish with a mating flange and where this is fixed to a timber
frame the flange should be wide enough to overlap the joint between timber and masonry by at
least 15mm.
107
Part II - Chapter 3- Installation of Ventilation Systems
2 3.16 Fans
a 3.16.1 Roof Extract Fans
.l
Roof extract fan units shall be of the axial/mixed flow type, as indicated and scheduled on the
drawings.
f
The weather skirt, cowl and impeller shall be constructed in glass fibre reinforced resin, with
e
polypropylene shutters and aluminium fittings. The motors shall have ball bearings and be of
d
the totally enclosed type.
Each fan shall be provided with a suitable flush or surface mounted starter/switch unit with red
indicating light.
nt
supports.
Flexible connections, not less than 75mm, shall be fitted on both inlet and outlet.
by
red,
Extract fan with twin fan system shall be equipped with auto-changeover facility to ensure
be
continuous operation, in the event of failure of the duty fan and the facility to indicate the
an
faulty condition on the control box accordingly.
Extract fans connected to extract hoods in kitchens shall be bifurcated (motor located outside
1ber
the air stream) type. Impellers shall be of non-ferrous construction and suitable for air laiclen
y at
with grease from cooking area.
107 1 08
Part H- Chapter 3- Installation of Ventilation Systems
3.1
All roof mounted ventilators shall be designed and installed in a manner that will withstand the
maximum wind velocities expected under cyclone conditions and such velocities must be
equivalent to those used in the building design.
Screen protection provided against birds, insects etc., shall not restrict the air movement and
they shall be fitted in such a way that cleaning or replacement of same could be done without
any difficulty.
Dampers/covers shall be provided if the ventilators are open to the atmosphere. Such systems
shall have means for operating manually or by sensors and automatic controls to detect rain
etc .. Dampers/covers should be designed to withstand heavy tropical rains and should be
provided with water tight seals.
----------------------------
109
ns Part IHI - Chapter 3 - Installation of Ventilation Systems
as
3.18.1 Dry Type Filters
be
Filters shall be constructed in such a way that they contain frames or cells to carry filter media
111
which could be easily detachable for removal or replacement of filter media.
Filter media may be wool, felts, specially woven fabrics, glass wool synthetic fibres or
cellulose. These materials must be rot proof, vermin proof, fire proof, and odourless. Adhesive
"De or viscous materials should not be used as coatings on the cleaning surfaces. The filter as a
ns whole should be a leak proof construction and should carry indicators to show when the filter
as
is clogged.
Two complete sets of spare filtering pads shall be supplied along with the filter, and complete
ial
technical information including filter efficiencies, air flow rates and resistance offered by the
1rs,
filtering media should be provided.
manufacture or treated with a similar corrosive resistant material. Spray nozzles shall be of non
corrodible material such as gun-metal. Construction shall permit easy disassembly for cleaning
2ms
and replacement purposes.
rain
be
The collecting tank shall be fitted with a primary water filter/and a 'ball valve' of not less than
9mm bore with a visible over-flow with a connection from the permanent water supply.
Access doors should be provided for routine maintenance of the washer. They should be fitted
1 be with water tight seals and non corrodible hinges.
Where dust loading is light, 1'cellular air washers" consisting of multiple cells fitted with glass
109 110
Part llJ - Chapter 3 - Installation of Ventilation Systems
filaments can be used. Low pressure water could be used in these systems and all cells shall be
kept wetted at all times.
In viscous filters where the surfaces are kept continuously or periodically moved a properly
designed drive mechanism should be incorporated. Means must be provided to remove excess
oil from the filters prior to coming into contact with the main air stream.
3
3.
3.19 Test Points and Instruments
Test points shall be provided and installed, generally as given below and as further indicated
on the drawings, to allow in-operation temperature and/or pressure readings to be taken. (The
test points are supplementary to instruments specifically detailed in equipment clauses).
Pressure test points for pipework shall comprise of a I 0mm f x F brass gauge cock and brass
plug.
Temperature test points for pipework shall comprise of a 100mm long x 15mm BSPT brass
pocket.
Pressure and temperature test points in pipework systems shall be provided at all mam
branches and on flow and return of all cooling coils.
Temperature test points shall be provided on all three connections to mixing valves.
Pressure gauges for pipework shall be of the Bourdon type with 100mm dial, black case,
chrome bezel and IOmm BSPT connection. The scale shall be marked in N/mn.
Thermometers for pipework shall be of the bi-metal type with a 100mm dial, black case,
chrome bezel, 100mm long stem and I5mm BSPT connection. Scale range shall be 0 to 120"C.
Pressure and temperature test points for ductwork shall be 25mm diameter holes provided with
an effective seal.
1!H
ms
Part- IHI- Chapter 3 - Installation of Ventilation Systems
be
Pressure and temperature test points in ductwork systems shall be provided before and after all
air handling units, cooling coils and at the fresh air and recirculation inlets.
Pressure gauges for ductwork shall be of the diaphragm actuated type with I 00mm dial, black
ls case and bezel and 3mm BSPT connections. The scale shall be marked in N/m2.
oil
Thermometers for ductwork shall be of the bi-metal type with a 100mm dial, black case,
chrome bezel, 300mm long stem. The scale range shall be 0 to 50'€.
rly
Supply instruments and leave in such of the above test points as agreed with the Engineers.
2$s
Segmented 90 degree bends shall be of five section elbows. Segmented 45 degree bends shall
be of three section elbows. Bends shall have a ratio of centre line radius to diameter of at least
ass
1.4 to I. All tees shall have conical or tapered branches. Where no details have been given,
duct designs shall be in accordance with Ductwork Specifications published by Heating and
Ventilation Contractors' Association or in accordance with the Hand Book of American
ain
Society of Heating, Refrigerating and Air conditioning Engineers.
Flange joints shall have angles welded on to the duct work to make the mating surfaces.
Mating surfaces shall be ground smooth and be punched for 8mm bolts at not more than 150
mm centres.
use,
1sC,
Where necessary in the duct work or in the casings, access doors shall be provided to permit
inspection, operation and maintenance of all fans, dampers, controls or other apparatus
concealed behind the metal work. Access door shall be 450 mm x 450mm clear or larger to suit
vith the size of the equipment fitted adjacent to the same, and where the above size is not permitted,
50mm narrower than the duct width.
1!I 11 2
Part - III- Chapter 3 - Installation of Ventilation Systems
Volume dampers shall be of the quadrant type of heavy construction, pivoted with approved
operating and locking devices, mounted on the out side of the duct in an accessible place. Fully
open and fully closed positions of the device shall be clearly marked. Dampers in ducts over
450 mm deep shall be of the multi-blade parallel type. Multi-blade dampers shall be provided
in large ducts.
3.20.4 Hangers
Hangers shall be provided generally in accordance with Clause 3.4. The work shall be securely
anchored to the structure. Suspension from the ceiling work is not permitted. Hangars shall be
located suitably and shall be adjustable in the vertical plane. Cadmium or galvanized fasteners
shall be used in exposed, areas.
113
Part III - Chapter 3 - Installation of Ventilation Systems
'ms
DC - Drive Cleat
led
3.20.7 Lighting
Kitchen hood shall be illuminated with heat, dust and moisture proof GCE valiant lamp
ce,
:CSS
lied
rely
I be
ners
114
1i3
CHAPTER 4
AIR CONDITIONING PLANT
4.1 General
This chapter covers all equipment that shall be used to provide chilled water or direct air
cooling. The performance characteristics of the system shall meet the requirements of the areas
to be air conditioned. All calculations and design data used in the selection of equipment shall
All equipment shall be in the form of packaged units manufactured in a reputed establishment.
The Contractor shall ensure that each individual piece of equipment in the plant has been tested
and certified before delivery and that all items in the plant are covered under the guarantees
required.
Mechanical and electrical plant shall be selected or suitably silenced to achieve the specified
If these noise levels cannot be achieved by the plant then attenuators shall be installed to
achieve the recognized levels. Where no noise levels have been specified the Contractor shall
be guided by the NC, decibel levels recommended in the ASHRAE Guide and Data Book,
Residences (suburbia) 20 25 30
Residence (urban) 25 30 35
115
Part IHI- Chapter 4 - Ar Conditioning Plant
Hospital rooms 25 JO 35
Hospital operating rooms, wards 30 30 40
Hospital public spaces 35 40 45
Music auditoriums 20 22 25
Radio and TV broadcasting 20 22 25
Theatres 25 27 30
Assembly halls 30 32 35
Church Sanctuaries 20 25 30
School libraries 30 35 40
Laboratories 35 40 45 4.
Recreation halls 35 40 50
t
Department stores (upper floors) 2 40 45
Clothing Stores 35 40 45
Department stores (main floors) 40 45 50
Supermarkets, Retail stores 40 45 50
Sports coliseums 30 35 40
Bowling alleys 35 40 45
116
Int Part III- Chapter 4 - Air Conditioning Plant
Swimming pools 40 50 55
Factories-supt. offices 40 45 50
Light manufacturing 45 60 70
Heavy manufacturing 55 65 75
4.2 Refrigerant
Selection of the refrigerant shall remain the responsibility of the manufacturer of the plant.
Wherever, possible, refrigeration machines shall be selected which work on ozone friendly
refrigerant. Refrigerants used should preferably be a type 'generally' used and available for
replenishment. In case of commonly used compression type refrigerant the selection shall
'ASHRAE' hand book published by the 'American Society of Heating, Refrigerating and Air
Conditioning Engineers'. All relevant information of the refrigerant used in the system together
with any special requirement against leaks and safety measures to be adopted shall be clearly
indicated in the Instruction Manuals.
expansion device, evaporator and the automatic control panel. The unit shall be fixed on a base
frame ready to be mounted on a suitably designed foundation. The number of chiller units
required to handle the air conditioning load shall be decided by the supplier taking into
consideration of the air conditioning requirements. When several chiller units are used, a
4.4 Compressor
Reciprocating/rotary serviceable hermetic compressor shall be equipped with automatically
reversible oil pump, operating oil charge, suction and discharge shut-off valves and insert type
crankcase heater. Motors shall be cooled by the suction gas passing around the windings and
shall be provided with over temperature protection, a contactor and a calibrated manual re-
start, ambient-insensitive overload protectors and all other required protectors for the proper
and safe operation of the compressor. The overload protector shall open all three phases in the
event of overload in any one of the three phases.
117
Part IHI - Chapter 4 - Air Conditioning Plant
-----------------�-
The controls shall include under/over voltage protection, so that, in the event of the occurrence
of a power supply fluctuation that could be harmful to the motors, the equipment is shut down,
with automatic reset occurring following a preset delay after power restoration. The complete
unit shall be a robust and compact construction and shall be mounted on spring type vibration
isolators.
Selection of a suitable type from the two types of compressors shall depend on the condenser
pressure. In high pressure systems reciprocating type shall be incorporated. Each chiller unit
shall have a minimum of two compressors each with their own independent refrigerant circuit
and electrical connections to ensure an element of stand by should one compressor fail. 4
Each compressor shall be of two speed type and the unit shall also be complete with acoustic
shroud which shall be made demountable to make maintenance access as easy as possible. All
exposed nuts and bolts shall be made of stainless steel and exposed surfaces shall be painted
with anti rust paint to prevent possible deterioration under salty and humid atmosphere
conditions.
4.6 Condensers
Condensers shall be either air cooled type or water cooled type and shall be designed to match
the entire plant.
integrally fined copper tubes having removable heads or shell and coil type, double pipe type
118
Part III- Chapter 4-Air Conditioning Plant
nt
er
As far as possible water cooled condensers shall be coupled to water re-circulating systems.
it
tit
4.7 Evaporator or Cooler
Evaporators shall be 'dry expansion cooler type' having the shell and tube arrangement or the
1C
'direct expansion coil type'. Shell and tube type evaporator shall have adequate baffle spacers
and the tube arrangement shall be accessible for maintenance and repair purposes.
re Direct expansion coil type shall have manifolds fitted on either end depending on the direction
of flow of refrigerant. Tubes shall be seamless copper suitably expanded into the tube sheets.
Refrigerant side of the evaporator shall be manufactured in accordance with the ASME code
for unfired pressure vessels. Insulation shall be polyvinyl chloride or similar approved
material. Coolers shall have capacities as indicated on equipment list when fouling factor is
ll
er 0.0005
al
of
4.8 Cooling Towers
Cooling tower shall be of induced or forced draught type. Towers shall be provided with fans
to provide a positive or constant air flow and should be designed for normal out air condition
In the design of the cooling tower adequate provisions should be made to ensure that no
recirculation of vapours take place and the draught losses do not exceed 0.2 percent of the
circulating rate. Tower casing shall be made out of modular fibreglass polyester or similar
ed
material and the tower construction should be adequately protected to prevent corrosion. Noise
le
level of the tower should be kept to a minimum. Whilst the installation shall be capable of
cooling the condenser water to specified levels the tower shall have provisions for easy
installation in any convenient location in the building including the roof slab.
ith
18 119
Part III - Chapter 4 - Air Conditioning Plant
--- .---------- -
The unit shall be packaged factory assembled units, piped, wired and charged with refrigerant
and comprise screw/reciprocating compressors and hermetically sealed motors, shell and tube
evaporators, aluminium finned cooper condenser coils with vertical discharge low speed
propeller type fans and complete control packaged to include starters, loading/unloading and
cycling controls for compressors, all of which should be subject to the Engineer's approval.
The units shall have anti-vibration spring type isolators with 75mm static deflection under load
conditions as a minimum. The aluminium fins shall be treated suitably to prevent deterioration
Selection of chiller and compressor unit shall be according to the following cr.iteria.
Chiller should work on 'ozone friendly refrigerant' which are easily available
in the market.
The pumps shall be of the centrifugal, direct driven, long coupled type with cast iron casing,
gunmetal impeller, stainless steel shaft, mechanical seal and flexible coupling drive to a totally
enclosed industrially silent horizontal splash proof three phase motor. The pump and motor
shall be mounted on a common cast iron bed plate. Wiring shall be tropicalized insulation class
F. Closed discharge head of pumps shall not exceed working head by more than 25 percent and
pump motors shall be sized to operate continuously throughout the performance range of pump
without exceeding the nameplate rating of motor. Pumps performance shall be not less than 5
percent below point of maximum efficiency.
120
Part Ill - Chapter 4-Air Conditioning Plant
High points of the pump casing shall be provided with air vent cocks. These cocks shall be
extended outside of any insulation specified. Low points of the casings shall be fitted with
drains. Each removable casing part weighing over 125 kg shall be provided with a lifting eye
or lug.
Each pump shall be fitted with isolating valves on the suction and delivery connections, and
where pumps are in duplicate, a non-return valve on either connection. Where necessary a
drain connection shall be run from the base plate to the nearest gully.
Pressure gauge cocks shall be fitted to the pump casing on the suction and delivery
connections.
The pressure gauge tapping shall be piped-up with a three way cock to enable the differential
pressure to be taken by one pressure gauge which shall be a I 00mm diameter flanged type
rigidly fixed to adjacent structure and with a red pointer set at normal delivery pressure.
Each pump shall be works tested and characteristic curves of pressure and flow provided,
related to the pressure gauge tapping on the pump casing. These charts shall be available at the
time of commissioning and testing and copies are to form part of the instructions manual.
The pumps shall be fixed on insulated concrete bases, the insulating material characteristics
being related to the pump weight and speed.
20 121
Part IHI- Chapter 4 - Air Conditioning Plant
The plant shall be provided with a suitable control system either pneumatic or electrical, to
control the temperature of chilled water, to modulate heat energy input to the machine etc., and
controls for safety of plant, should the temperature in the evaporator becomes dangerously low
over heating the pump during the operation of plant.
A bitumen coated drip tray with drain outlet and connection to a uPVC drain pipe shall be
provided under the element, with the discharge so arranged to be run to the nearest convenient
drain or as shown on the drawings.
The fans shall be double inlet, centrifugal type fully balanced with a totally enclosed, factory
lubricated, sealed sleeve bearing, three speed motors, all assembled as an easily withdrawable
unit for inspection and cleaning. Anti-vibration mountings shall be incorporated in the unit to
ensure that no vibration from the fan/motor combination is transmitted to the structure.
Each unit shall be provided with air cocks, union lock shield valves, on the returns and union
wheel valves on the flow as specified.
Each unit shall be fitted with a washable filter of flame retardant material, with an efficiency of
55% when tested using No 2 test dust to comply with the test requirement specified in BS
2831. Filter shall be easily removable through the access panel.
All internal wiring shall be integral with the unit and connected to the adjacent single phase
supply through a terminal block.
Each unit shall be provided with a four position switch giving high, normal, low and off
positions. Thermostatic control shall be provided in the form of control packages consisting of
three port control valves and associated wiring. Fan coil units in common areas are to be
interconnected to a common thermostat as indicated on the drawings.
Units mounted in plant rooms or in false ceilings shall have a remote mounted combined four
position switch and thermostat mounted in room as shown in the drawings.
122
t Part I II- Chapter 4-Air Conditioning Plant
I-
The units shall be capable of providing the required air flow against the total air resistance of
d the system as installed and be capable of the required cooling duties, with chilled water, as
scheduled and shall be selected to achieve the required sound levels without additional duct
attenuators.
t The casings shall be double skinned and constructed of heavy gauge galvanised sheet steel
reinforced with mild steel angle or channel members. Access panels and hand holes shall be
provided underneath the units to give easy access to all parts of the unit.
·y
le The cooling coils shall be of non-ferrous construction and provided with a condensate drain
:o pan, the discharge arranged to be run to the nearest convenient drain or as shown on the
drawings. Maximum velocity of air flow through coil shall be 2.Sm/s. All sections outside the
internal air flow shall be insulated and vapour sealed.
n
The fans shall be of the belt driven centrifugal type with fully balanced impellers. The motors
shall be mounted inside the unit on adjustable mountings and be supplied complete with vee
rope drive and adjustable pulleys. Fan motors shall be capable of two speed and have an
operating margin of not less than 25% above the theoretical BHP. The duty of the fans shall be
related to the resistance of the system as actually installed.
5e
Filters shall be of the types as scheduled and specified hereafter.
A mixing box with multi-leaf dampers on both inlets shall be fitted to the air handling units
fr where scheduled.
of
)€
The fan units shall be fixed on flexible mountings suited to the characteristics of the unit, so
that no perceptible vibration is transmitted to the surrounding structure. Flexible sleeves shall
be provided on the inlet and outlet air conditioning connections to the Units to prevent
ur vibration been transmitted to the ductwork. These sleeves shall be approximately 150 mm
wide, of air proof non-organic flexible fabric or sheet and shall be held in place with heavy
22 123
Part III- Chapter 4 - Air Conditioning Plant
metal bands or flanges. Supports shall be arranged to prevent any static loading being carried
Anti-vibration mountings shall be installed to the air handling units (AHU) as per the
following requirements:
High efficiency filters shall be provided within each air handling unit.
The filters shall be of the extended surface type with glass/synthetic fibre media, protected on
both sides with scrim positively located in steel holding frame with supporting wire mesh bag.
All metal parts shall be rust proofed and located in a steel installation frame providing for easy
withdrawal and shall be completely sealed with mastic or foam strip.
Each unit shall consist of clements which in total give the required air flow at an initial
resistance of not more than 50 N/m2 at a filtration efficiency of 99.2% for when tested using
No 2 dust in compliance with tests detailed in BS 2831.
The air cooled condensing units shall have self-contained compressors mounted in an anti
corrosive rust resistant, galvanized steel plate and double backed acryl resin finished casing.
Each condensing unit shall be suitably mounted on an angle iron structure with an air guide
louvre in the service area.
The fan coil units shall be of the direct expansion type with the cooling capacity scheduled
when operating with its associated condensing unit. The unit shall comprise of a cooling coil
of non-ferrous construction, double inlet centrifugal fan with totally enclosed motor and
condensate drain pan. The casing shall be of heavy gauge steel, insulated and vapour sealed
throughout. Fan coil units shall be either cassette type or wall mounted type as detailed and
scheduled on the drawings.
124
Part III - Chapter 4-Air Conditioning Plant
Refrigerant connection between remote condenser and fan coil unit shall be made together
d
with all necessary valves, controls, wall mounted thermostat/fan switches, control wiring, etc.,
to make a complete installation. All refrigerant pipes shall be insulated with 19mm thick
e closed cell, flexible foamed pipe sleeves. Condensate drains shall be insulated with 6 mm
thick foam t.ape.
Unless otherwise specified the remote control thermostat/fan switch shall be mounted on the
wall at the same height as the light switches.
Condensate drain pipes shall be in PVC, to conforming to SLS 147 type 1000 or BS 3505
Class E with solvent cement joints and shall be laid to falls discharge into nearest drain point
complete with trap.
Refrigerant pipes on roof shall be properly supported and. protected with solar resistant
n aluminium tapes.
£. Refrigerant pipes down walls shall be installed in uPVC flush mounted duct. The control unit
sy for split units shall be wall mounted and shall have a rear entry cable entry suitable for wiring
in a concealed conduit installation.
The air handling unit shall be capable of providing the required air flow against the total air
resistance of the system as installed and be capable of the required cooling duties with
nti refrigerant.
ide The casing shall be constructed of heavy gauge galvanised sheet steel reinforced with mild
steel angle or channel members and with the cooling section adequately insulated. Access
panels and hand holes shall be provided as required to give easy access to ali parts of the unit.
led
The unit shall be suitably weather proofed for rooftop installation.
·oil
1nd
The cooling coil shall be of non-ferrous construction and provided with condensate drain pan,
led
with the discharge to be nm to the nearest convenient drain. Maximum velocity of air flow
nd
through the coil shall be 2.5 m/s. AII sections outside the internal air flow shall be insulated
and vapour sealed.
124
125
Part II - Chapter 4 - Air Conditioning Plant
The fan shall be of the belt driven centrifugal type with fully balanced impellers. The motor
shall be mounted inside the unit on adjustable mountings and be supplied complete with vee
rope drive and adjustable pulleys. Fan motors shall have an operating margin of not less than
25% above the theoretical BHP. The duty of the fan shali be related to the resistance of system 5
as actually installed.
The primary filters shall be of the washable type and consist of demembraned polyurethane,
foam bounded around non-rusting internal reinforcement and contained in a frame made of 1.2
mm thick, rust-proofed mild steel finished in white stove enamel or of all plastic construction.
The individual elements shall be easily withdrawable and mounted in a rigid rust free frame.
Each unit shall consist of elements which in total give the required air flow at an initial
resistance of not more than 30N/m at a filtration efficiency of not less than 70% when tested
using No.2 dust in compliance with tests detailed in BS 2831.
5.
5..
Medium efficiency filters shall also be installed within the unit as shown on the drawing. The
filters shall be of semi-cleanable/throw away type having a glass {ibre filter medium with
4.t6 Guards
Moving parts of all machines installed and supplied shall be protected by rust proofed
permanent guards, including all parts fixed at high level to which there is no permanent means
of access.
5.
126
t
CHAPTER 5
r
e CONTROLS AND INSTRUMENTATION
n
n 5.1 General
A complete control system shall be supplied and installed in the building as approved to meet
the control requirements and functions of the system as detailed on the drawings, schematics
and as specified. It shall include instruments for monitoring, adjustment and calibration of
2 various sections of the system described below. The Contractor shall submit detailed wiring
l.
diagrams for the electrical control system together with a detailed valve schedule giving
reference numbers, duty and pressure drops all of which shall be approved by the Engineer
5.2 Sensors
5.2.1 Temperature Sensors (Thermostats)
e
Thermostats provided shall suit the application and shall be of a commonly used types such as
h
(i) bi-metal
(ii) rod and tube
(iii) sealed bellows
(iv) remote bulb
d
(v) resistance ( electrical)
S
Room thermostats shall be of a concealed adjustment type with concealed indicators. Unless
otherwise specified thermostats shall be installed at a height of 1 .6m from the ground. Colour
of thermostat cover shall suit the room and its hardware.
g
A gauge cock shall be provided in the sensing lines between the piping system and the pressure
gauge and pulsation dampers shall be provided for gauges used with reciprocating
compressors.
5.3 Controls
5.3.1 Control Valves
Electrically activated control valves shall regulate the pressure in the circuit it controls. Valves
shall be at the closed position when power supply is removed. The valve body, moving
components, seats etc., shall be of material suitable for the service requirements.
A temperature sensor located in the common return of the recirculating plants from the
controlled space shall work in conjunction with the chilled water cooling coils and the three
port modulating control valves to maintain the required temperature in the space, however
temperature adjustment shall be at the unit for the AHU's.
Each air handling unit shall be complete with locally mounted on/off switch and a controller.
Each fan coil unit shall be complete with locally mounted combined thermostat/ three speed
controller and on/off switch.
2s
Part III - Chapter 5-Controls & Instrumentation
The panel board shall be constructed weather proof using steel and/or timber. The panel shall
be installed with adequate space all round for easy access during repairs and maintenance.
e
The following provisions shall apply to all electrical cupboard type control panels containing
motor starter equipment, etc.
e
The selection of all electrical equipment shall be based on the recommendation laid down by
the British Standards Institute, unless otherwise agreed by the Engineer. The control panels
shall be designed and manufactured in accordance with principles laid down by the 'Institute
of Electrical Engineers' Regulations for Equipment within buildings.
r.
The Automatic Controls Specialist shall take full responsibility for the integration of the
·d
automatic control system equipment to ensure correct operation and interlocking between
devices and equipment.
129
Part HI - Chapter 5 - Controls & Instrumentation
The Automatic Controls Specialist shall provide a Senior Specialist Engineer to witness and
supervise where necessary the complete commissions of all motor starter and temperature
control equipment supplied with the system. This work shall be carried out on site during the
progress of the Contract and the cost shall be included for within the tender figure. The
purpose of the control panels is to centralise the control of various motor starter equipment for
fans, pumps etc., automatic temperature control equipment and to centralise the distribution to
j
various environmental package units.
Each of the water chillers shall have its own separate starter panel. These shall be in
accordance with the Cupboard type specification. Each of the panels shall have an individual
These panels shall form an integral part of the packaged refrigeration machine supplied by the
compressor, connecting air line and electrical gear required for the system. Other than
electrical switch gear required for the system as outlined elsewhere the controls shall include-
The tank shall be connected into the circulation system by means of an air purger consisting of
a one piece cast iron chamber with internal contoured waterways to separate entrained air from
the system water and to discharge the air through a separate float operated automatic air vent
130
7
Part Ill - Chapter 5- Controls & Instrumentation
The size of the unit shall be checked before ordering against the system as installed. The
installing, filling and commissioning procedure shall be in accordance with the manufacturer's
recommendations.
)
131
CHAPTER 6
INSULATION
6.1 General
The entire system including components that carry heated or chilled fluid shall be insulated
from the atmosphere. Vapour barriers in addition to insulations shall be used in areas that are
liable to cause condensation. In selecting a suitable insulating material other than the ones
specified, following characteristics shall be checked and agreed with the Engineer:
(i) fire properties
(ii) property to withstand rotting fungal growth and vermin attacks
(iii) possible health hazards.
All insulation material and adhesives used shall comply with the requirements stipulated by
the relevant authorities.
All adhesives, vapour barriers and coatings shall have the following indices (tests as defined in
BS 874 and BS 2972):
Ignitability Zero
Heat Evolved Zero
Smoke developed- Not greater than three
The insulation material for cooled surfaces shall be 50mm thick glass fibre slabs or pre-formed
sections with a thermal conductivity K' value not greater than 0.04 W/m"C.
Adhesives and sealers of approved manufacture shall be supplied. Slabs on ductwork 900
mm x 900 mm and over shall, in addition to an adhesive, be further held in position by means
132
Part II- Chapter 6 - Insulation
Any combustible facing shall be not more than 0.8 mm thick and comply with the relevant
regulations for flame spread.
As an alternative, foamed plastic slabs or preformed pipe sections may be used, only in
situations acceptable to the relevant fire authority or provided in local regulations. Such
materials shall have a K' value not greater than 0.04 Wm''C and be non-flammable or self
extinguishing.
Vapour barriers shall be continued over the thermal insulation including branch connections,
flanges, hangers and similar equipment and where of necessity the insulation is terminated the
end shall be fully sealed.
Access doors in ductwork shall be fitted with purpose made, rigid fibre, removable covers
with quick release bands or fasteners.
All insulation applied to any ductwork or plant shall be neatly cut around all dampers, test
holes, thermometers, etc., to provide accessibility.
6
Alternative proposals for insulation, adhesives and finishes will be considered, but the standard
produced shall not be less than that given in the detailed specification.
Details of the alternative proposal must be submitted to the Engineer and approved by him
before commencing work on site.
All insulation, finishes and adhesives employed must be acceptable to the local tire authority.
133
Part III - Chapter 6- Insulation
The Contractor shall submit samples of all types of insulation to the Engineer for approval.
The insulation shall then be finished and protected with 0.55 mm 'hammered' aluminium
sheeting, all joints being overlapped and secured with pop rivets. Bends shall be neatly fanned
with segments and tees gartered and bands shall be fitted at all termination points.
6.2.6 Fittings
Fittings requiring insulation shall be covered with an insulation of thickness of equal to that
of the adjacent duct and cut to shape. It shall then be fixed to the metal and to adjacent
insulation with the appropriate adhesive and with any open joints filled in with a mixture of
mastic and granulated insulation; thereafter the whole smoothed down by building up sharp
corners with mastic, covered with reinforced expanding foam, a further coating of sealer and
painted in accordance with the requirements for the adjacent ductwork.
6.2.7 Supports
Hangers and brackets supporting insulated services in non-air-conditioned spaces shall be
fixed external to the thermal insulation and vapour barrier with a 1.6 mm thick galvanised
sheet half sleeve with a length of not less than one twentieth of the circumference of the duct.
Rigid insulating material is to be inserted between the sleeve and the duct of thickness equal to
that of the normal insulation.
The insulating material for cooled surfaces shall be rigid glass fibre slabs or preformed
sections with a thermal conductivity (K) value not greater than 0.04 W/m'C,
Any combustible facing shall not be more than 0.8mm thick and comply with the relevant
regulations for flame spread.
If put forward as an alternative, foamed plastic slabs or preformed pipe sections may only be
used where acceptable by the Fire Authority or Local Regulations and shall have a 'K' value
not greater than 0.04 W/m"C and be non-flammable or self extinguishing.
The following are terms for the standards of finishes for different areas:
(i) Air conditioned space surface or pipework fixed in areas where the
differential temperature, water to
surrounding air dew point is greater than
'c.
Part III - Chapter 6- Insulation
Vapour barriers shall be continuous over the thermal insulation including connections, flanges,
valves, pumps, hangers and like equipment and where of necessity the insulation is terminated
the end shall be fully sealed. Vents shall not be insulated within the building.
All insulated pipework shall be coloured in accordance with the colour code specified in BS
1710.
All insulation applied to any pipework or plant shall be neatly cut around gaugers, thermostats,
etc., to provide accessibility.
Alternative proposals for insulation and finishes will be considered, but the standard produced
shall not be less than that given in the detailed specification.
Details of the alternatives must be submitted to the Engineer and approved by him before
commencing work on site.
All insulation, finishes and adhesive employed must be acceptable to the local fire authority.
The Constructor shall submit samples of all types of insulation to the Er:gineer for approval.
6.3.4 Runouts
Runouts to individual room units, if not greater than 20 mm diameter, may be insulated with
19 mm thick, closed cell, flexible foamed pipe sleeves with a thermal conductivity (K) value
not greater than 0.04 W/m'C. Condensate drains shall be insulated with 6 mm thick closed cell,
flexible foam tape.
foil/paper laminate, securely fixed with an approved adhesive directly to the pipe surface. All
joints between sections shall be covered with 75 mm wide plastic contact adhesive tape fixed
to a tack coat of adhesive on the aluminium surface. All raw edges shall be filled with
reinforced expanded foam. The insulation shall be covered with a coat of sealer, and whilst
tacky with a covering of heavy quality canvas; the whole being then covered with a finishing
coat of sealer, and finishing material.
The insulation shall then be finished and protected with 0.55 mm 'hammered' aluminium
sheeting, all joints overlapped and secured with pop rivets. Bends shall be neatly formed with
segments, tees gartered and bands shall be fitted at all termination points.
137
Part III- Chapter 6 - Insulation
The insulation shall then be finished and protected with 0.55 mm 'hammered' aluminium
sheeting, all joints overlapped and secured with pop rivets. Bends shall be neatly formed with
segments, tees gartered and bands shall be fitted at all termination points.
Pipework and fittings below ground shall be of the pre-insulated 'pipe within a pipe' system.
The inner pipe shall be steel with an outer casing of polyethylene securely bonded to the inner
pipe with rigid polyurethane foam. Joints shall be carried out using specially developed plastic
coated steel fittings and purpose made bends and tees. Expansion of the underground mains
shall be checked by the specialist manufacturers and purpose made foam pads shall be Installed
in accordance with their recommendations.
6.3.10 Supports
Hangers and brackets supporting insulated services in non-air conditioned spaces shall be fixed
external to the thermal insulation and vapour barrier with a 1.6 mm thick galvanised sheet half
sleeve of not less than twice the bore of the pipe. Rigid insulating material or timber rings shall
be inserted between the sleeve and the pipe. On services in air conditioned spaces the bracket
or support shall be fixed to the pipe and the thermal insulation and vapour barrier carried over
and any gap filled in with mastic.
t Valves, pumps and strainers shall be neatly boxed in, using sectional styrene insulation with
internal cavities filled, and external surface finished as specified for the piping. Boxes shall be
trimmed around the top of the valves leaving the gland exposed for inspection and re-packing.
7 138
Part II- Chapter 6 - Insulation
-
.., Detachable boxes shall be provided for pumps.
139
CHAPTER 7
COMMISSIONING OF PLANT AND SUBMISSION OF DOCUMENTS
Initial start-up and commissioning of the chiller unit shall be done by or in the presence of the
approved supplier. Final commissioning report shall be approved and signed by the supplier.
Finally the Contractor shall demonstrate to the Engineer that the operation and the installation
is in accordance with the specification.
All testing and commissioning records shall be bound into the operation and maintenance
manuals when the system has been successfully completed and witnessed by the Engineer.
At the completion of each section of the work a record drawing should be prepared by the
Contractor for submission to the Engineer.
The record drawings shall show the position of every item of plant, all pipework runs, valves,
drain cocks and all items requiring access for maintenance or cleaning and any other item of
equipment forming part of the Mechanical Services Installation. Where relevant all sizes,
capacities or ratings of equipment shall be given. All items buried or otherwise concealed shall
be precisely located on the 'as installed' drawings by means of dimensions taken on site from
some readily identifiable point (ie. main walls of building or finished floor levels). Where
140
Part II- Chapter 7 - Commissioning of Plant & Submission of Documents
necessary, the Contractor shall also produce sections, elevations and part plans.
When all record drawings have been submitted to the Engineer and have subsequently been
approved, the Contractor shall supply copies of these drawings in the following forms:
() Brief description of the system and the list of all parties involved in the project;
architects, consultants, contractors etc.
(iii) Manufacturer's catalogues for all items of equipment forming the mechanical services
installation
(iv) Manufacturer's operating and maintenance instructions for any item of plant chillers,
pumps, air handling units, tanks etc.
(v) Manufacturer's drawings and spare parts schedule for the major items of equipment.
(vi) List of local suppliers and manufacturers of all items of equipment forming the
mechanical services installation with their addresses, telephone/telex/fax numbers,
contact personnel etc.
141
Part III - Chapter 7 - Commissioning of Plant & Submission of Documents
The Contractor having obtained the Engineer's approval for the Operating and Maintenance
Manual shall supply three copies in PVC covered binders, PRIOR TO COMPLETION
CERTIFICATES BEING ISSUED.
Two keys shall be provided for each size of lock-shield regulating valve air cock, automatic air
valve or other valve requiring special tools to operate, together with duplicate keys for any
clockwork mechanism or locks or instruments, safety valves, etc., supplied under the Contract.
Two grease guns of the lever type with oiling heads to suit grease nipples on equipment
should also be supplied.
142
PART- IV
LIFTS
CONTENTS
Pages
Chapter 1-General Requirements
1.1. Introduction 146
143
2.9 Car and Landing Door Operator 159
2. IO Car Door and Gate Contacts 160
2.11 Landing Door and Gate Interlocks I 60
2.12 Indicators 160
144
2.24 Fireman's Switch .. .. 168
2.25 Control Switch in Lift Pit .. .. .. 169
2.26 Car Load Weighing Device - Automatic By-Pass 169
2.28 Arrival Gong 169
145
CHAPTER 1
GENERAL REQUIREMENTS
1.1 Introduction
The lift and equipment proposed shall be of a reputed manufacture and shall be represented
locally by a well established firm comprising qualified engineers and technical staff and
capable of offering an efficient after sales service and who will also maintains adequate
quantities of spares for the complete range of products. The lift manufacturer and local
agent/supplier shall be in a capacity to design and supply equipment to comply with the
requirements of the Contract.
The supply shall blend aesthetically with the architecture of the building and the environment
in which the lift works.
(i) The relevant parts of latest British standard, British Standard codes of practice or
Japanese Industrial Standards/Codes of Practice.
146
Part IHW- Chapter I- General Requirements
------------------------
(ii) British Standard Code of practice CP 407 (latest issue)
1.4 Drawings
Specification for drawings shall be generally as in Part I, of these specifications. Following
specific requirements shall be referred together with the relevant clauses in Part I of these
specifications.
Whilst it shall remain the responsibility of the Contractor to identify and provide full and
detailed installation drawings the following is a guide to the categories which will be required:-
(i) General arrangement drawings showing detailed layout of lift wells and steel work in
equipment room with dead loads on beams.
(v) Winding or driving gear complete with controls and control panels. In case of
hydraulic lifts, circuits with piping, pumps, valves, jacks etc.
147
Part IV - Chapter I - General Requirements
(ix) Section through lift wells and motor rooms showing positions of built 111 fixing
devices.
(x) General arrangement drawings of all plant and equipment, switch and distribution
boards etc., showing the positions of the equipment and associated ancillaries,
trunking, racking and cable connections etc.
Details of holes required for all devices including landing buttons positions indicators and hall
lanterns shall be provided.
Electrical power requirement in the machine room and the loads in the machine room and the
lift pit shall clearly indicated.
The Contractor shall be responsible for any discrepancies, errors or omissions in the drawing
and other particulars, whether approved by the Engineer or not, provided that such
Such diagrams shall be fully comprehensive and shall co-ordinate the manufacturers' data in
respect of individual items of equipment so as to present, as a whole, the complete information
for any interconnected group or groups of such items. They shall include -
(i) Co-ordinated wiring/connection details between equipment and cables showing
terminal block coding, cable core size and identification.
(ii) Schematic layouts presented in ladder ' or a similar format such that it is possible to
comprehend the operation of a particular system the inter-connection between the
148
Part IW- Chapter I - General Requirements
various systems and to identify the components and wiring/connections shown on co-
ordinated wiring connection diagrams.
(i) Inserts and fixtures that go into the building structure for fixing of rails guides,
architraves, steps etc.,
(ii) Safe clearances between lift car, counter-weight and the building structure,
(v) Nearest point at which the mains supply must be made available, during erection as
temporary supply,
(vi) Nearest point at which mains supply must be made available for the permanent
installation,
1.6 Ventilation
Motor room or machine room, lift shaft, the lift car etc. shall be provided with adequate
ventilation. Ventilation provided must be capable of handling heat generation in :he
machinery. Top of each lift shaft shall be provided with at least 930 cm2 space area for
ventilation purpose. This shall be checked by the Lift Contractor prior to installation and if
found inadequate, same shall be brought to the notice of building designers for consideration.
149
Part IV - Chapter I - General Requirements
1. 7. Electrical Installations
Reference shall be made to the Part II, of these specifications for the specifications not covered
under the following clauses.
All electrical motors and their switch and control gear shall be designed for a 3 phase AC
power supply of 400V at 50Hz. All electrical appliances within the lift car shall be designed
for a single phase AC supply of 230 Vat 50Hz.
All cables other than travelling cables shall be armoured or enclosed in steel conduit, duct or
trunking or be of mineral insulated metal sheathed type.
Each lift circuit shall be provided with a means to isolate the motors, controllers and automatic
circuit breaker.
The metal frame work of the lift, equipment, machinery, switch gear and electric conduits
shall be properly earthed. In case of the car frame earthing shall be achieved via a conductor in
the travelling cable.
Power supply to all machinery shall be 400 Y_. 3 phase 50 Hz. and in case of the lift car the
power supply shall be 230 V, single phase, 50 Hz.
Car interior shall be provided with adequate artificial lighting to suit the design of the lift
which will be as detailed in the particular specification. The lighting shall be provided by
concealed fluorescent lamps.
The machine room shall be provided with adequate lighting and provision shall be allowed for
f socket outlets for hand lamps in the machine room, on top of lift car, lift well and basement pit.
150
Part W -Chapter I -General Requirements
---------
1.7.3 PVC Insulated Cables
PVC insulated cables shail be 450/750 V grade, manufactured in accordance with BS 6004.
1.8 Motors
Type of motor to be used shall be chosen depending on the supply characteristics, car speed
and quality of service. Motors provided shall run at speeds less than or equal to 1000 rev/min
unless otherwise specified and depending on the speed of the lift car and shall operate with the
necessary levels of silence at all loads.
Starting torque of motor shall be at least twice the full load torque. The shaft of the rotor shall
extend beyond the motor housing and have the facility to connect a hand wheel for emergency
hand winding.
Motors shall be rated to comply with the temperature rise limitations in services as stated in
clause 3.1- Testing.
Motors and motor generator sets shall have ventilated protected enclosures or totally enclosed
and shall be provided with thermistor type thermal overload protection.
151
Part IV- Chapter - I General Requirements
(i) Section of lift well and motor room with location of car and counter weight etc. and all
critical dimensions.
(ii) Maximum number of passengers that can be accommodated and maximum load
(viii) Type and size of lift rope in case of electric lift or grade of hydraulic oil in case of
hydraulic lifts.
152
CHAPTER 2
ELECTRIC PASSENGER AND GOODS LIFTS
Straightness of the guides shall be within 0.05 mm and the defection of guides shall not exceed
3 mm under normal operation.
Guide Rails shall be provided with a system for lubricating automatically such as by providing
self lubricating type shoes or by wick lubrication. Where wick lubrication is used a drip pan
should be provided below the guides in the pit to catch surplus oil.
Guide shoes should have liners of nylon or other suitable material to absorb shocks and to
provide good riding comfort.
2.3 Ropes
2.3.1 Suspension Ropes
The suspension ropes shall be from a specialised rope manufacturer, specially manufactured
.
for elevators each capable of sustaining the weight of the car with safety.
The manufacturer's test certificate for the ropes shall be provided.
Not less than two ropes independent of one another shall be used for suspensiori. No car or
counter weight rope shall be spliced other than for the purpose of attachment to counter-
153
Part IW- Chapter 2 - Electric Passenger & Goods Lifts
weight, car or anchorage. Each rope shall have its own independent attachment.
Care shall be taken during installation to ensure that, the ropes are taut and there are no kinks
due to mishandling.
passing round a pulley in the pit. The ropes shall be tensioned by gravity and a safety switch
shall be provided.
2.4 Buffers
The lift car and the counter weights shall be fitted with suitable buffers conforming to BS 5655
to compress and absorb shocks of a fully loaded car or counter weight. Buffers shall be located
suitably so as to maintain the car and counter weight in equilibrium on hitting the buffers.
Spring buffers should be used for speed upto I mis. For speeds above I mis, oil buffers of
spring return type should be used.
In the event the pit depth being inadequate for contract speed, suitable speed reducing controls
shall be incorporated to reduce terminal speed.
Overhead clearance of lift shall be checked for suitability of safe operation of the lift at its
contract speed.
154
Part IW - Chapter 2- Electric Passenger & Goods Lifts
Adjustable guide slippers shall be fixed on the top and bottom of the frame.
The steel suspension ropes shall be attached to the car frame with provision for taking up any
inequalities between the ropes. The rope should be connected to thimble rod by babit metal
mouiding and springs should be fixed between thimble rod and car frame to avoid transmission
of vibrations to the car.
(ii) The roof of the car shall be sufficiently reinforced to withstand the distributed weight
of two men.
(iii) Mechanical means of ventilation shall be provided in the design of the car enclosure
consistent with the designated occupancy of the lift.
(iv) Each car shall be fitted with emergency hatch way on the roof for emergency
purposes. It shall have a minimum size of 450 x 500 mm and open outwards.
(v) All emergency exits should be fitted with electric interlocks, which will prevent the lift
from being operated if an exit is left open.
(vi) Inspection controls shall be fitted to call passenger carrying lifts in accordance with
relevant British Standards. A 13A, 3 pin switched socket outlet and a permanent light
of the protected bulkhead or well glass type with controlling switch shall also be
provided on top of the car.
(vii) Toe guard should be provided for full entrance opening width.
(viii) Lighting shall be provided by means of fluorescent lamps concealed above a dropped
ceiling. The lighting circuit shall be taken from the lift machine room.
155
Part IV- Chapter 2- Electric Passenger & Goods Lifts
(ix) An emergency lighting system shall be provided which will give not less than three
hours lighting time using a rechargeable battery in case of mains failure.
(x) A data plate should be fixed on the cross head showing the load on ropes, contract load
and speed.
(xi) An alarm bell and telephone shall be installed to enable a call for assistance when lift
failure occurs between floors.
(xii) Car operating micro touch buttons or other car controls as specified shall be provided.
In case of micro touch buttons they should not have mechanical displacement of more
Lift car shall be constructed of steel and lined internally with plastics and or other
Suitable hand rails shall be fitted in passenger lifts and the car platform shall be lined
with a suitable material that can resist abrasion etc .. When goods lifts are installed it is
necessary to consider in detail the type of loads to be carried and the loading and
unloading arrangement. Such lifts shal I be able to withstand loads of pallet trucks and
other appliances during loading and unloading operations.
Materials used in the construction of the lift car, and its allied machinery shall comply
with British Standards or similar international standard with regard to fire-resistance,
smoke control and flame spread and other fire safety requirements specified therein.
All material shall withstand intense heat during a fire within acceptable limits.
Doors shall be properly designed to eliminate draughts, noise, risks of injury and shall
provide a good and acceptable appearance. Passenger lifts shall not be equipped with
collapsible gates.
156
Part IV - Chapter 2 - Electric Passenger & Goods Lufts
Type of door in lift car shall be decided from the following options depending on the
opening required in the car for the purpose of the lift in use.
() Two panel centre opening type doors. Panels open in two directions. (for passenger
lifts)
(ii) Two panel with one sliding panel moving behind a stationary panel (for hospital
(iii) Three panel with two sliding panels moving behind a stationary panel.
(iv) Four panel sliding, two speed centre opening type doors.
(vi) Vertical bi-parting doors, with two panels sliding vertically upwards and down wards.
Every landing door shall be rated for one and a half fire hour resistance.
Doors shall be power operated using AC motors in the car door and shall be coupled to the
Doors on passenger lifts shall be generally in accordance with the following specifications.
The entrances shall be protected by horizontal sliding metal doors with the finish and opening
arrangements as detailed in the schedule of requirements. Panel rigidity shall be obtained by
suitable steel reinforcement.
The doors shall be hung on sheave hangers running on a polished steel track and guided at the
bottom by non-metal shoes sliding in a smooth threshold groove. Door hanger sheave shall
have non-metallic contact with the track for smooth and noiseless door operation.
Suitable means shali be used to transmit motion from one door panel to the other.
The car landing doors and their tracks shall withstand a thrust not less than 350 N (35 kg.9)
applied normally at any point.
157
Part IV - Chapter 2 -Electric Passenger & Goods Lifts
Each car door and gate shall be provided with an electrical contact arranged to prevent the
operation of the lift unless the door is closed and the interlocking circuit established.
(ii) Sills
The sills shall be of a finish that will meet the requirement given in Annexure C and
shall have an approved non-slip wearing surface. They shall be in one piece, of
sufficient length to suit the two supporting struts and grooved for the door guides.
(iii) Doors
Doors shall be of the type specified in the schedules. The door panels shall be formed
to match the unit frames. The bottom of the doors shall be provided with guides to run
in the sill slots with minimum clearance. Door hanger roller shall have non metallic
contact with the header track for smooth door operation.
(v) Erections
All work shall be set in perfect alignment with lift car opening and landing. All
structural parts shall be painted.
158
Part IW- Chapter 2 - Electric Passenger & Goods Lifts
An AC variable voltage variable frequency type door operator shall be provided to open and
close the car and landing doors when the car is at a landing. The car door and landing door at
any landing shall be opened and closed simultaneously. They shall be power opened and
closed. Door movements shall be cushioned or chocked at both limits of travel.
The doors shall be automatically opened when the car is level at the respective landing and
shall again close after a pre determined time interval has lapsed. A 'door open' button shall be
provided in the car and the momentary pressure of which shall reverse the motion, reopen the
doors and reset the time interval.
The car door shall be provided with a protective device extending the full height and projecting
beyond the front edge of the door. This device shall be so arranged that should it touch a
person or any obstruction in its path while the door is closing, it shall automatically cause both
the car door and the landing door to return to the open position. The doors shall remain open
until the expiration of a time interval and then close automatically. The pressing of a car
button, once the doors are fully open shall cause the doors to close immediately.
Mechanical safety edges shall be retractable. If centre opening doors are used, both doors
should have safety shoes.
The devise is to be arranged so as to ensure the doors exerting the absolute minimum force on
a person obstructing the closing operation.
The doors that are power operated but not automatically closed, generally in cargo lifts, shall
be closed by continuous pressure buttons, the release of which shall stop and cause doors to re-
open.
Leading edges of doors shall be fitted with a suitable cushion to reduce impact and the kinetic
energy and force of closing shall be as described above.
159
Part IW - Chapter 2- Electric Passenger & Goods Lifts
operation of the lift unless the door is closed and the interlocking circuit established.
prevent the operation of the lift unless the doors are closed and positively locked. The interlock
shall also prevent the opening of any door until the car has reached the respective landing zone
with the operating circuit open.
Emergency opening of the doors and gates from the landings shall be possible by means of a
key operation irrespective of the position of the car. The Contractor shall provide two keys to
the Engineer after successful commissioning of the installation.
In case of service lifts the mechanical locking unit may be separate from the electrical
interlock.
2.12 Indicators
All indicators shall be fitted with neon lamps instead of ordinary bulbs to enhance the life and
sharpness of the indicator.
(ii) be clear of any apparatus mounted above the roof of lift car,
(iii) be held by suitable fasteners which can be opened only from outside the lift car, i.e
without a key.
(iv) be provided with a switch which will prevent operation of the lift when the panel is
open and which will restore operation of the lift only when the fastening have been
manually restored.
160
Part IV - Chapter 2 - Electric Passenger & Goods Lifts
2.13.3 Interphone
An interphone shall be fixed in the cabin, which allows the passengers to communicate with
the building supervisor outside the elevator cabin in the event of a breakdown or emergency.
Three phase AC from the power supply is converted by the diode into DC and smoothed by the
capacitors. This smoothed DC is then converted into three phase AC by the transistor inverter
and supplied to the induction motor. The transistor inverter changes the voltage and frequency
of the three phase AC output to govern the torque and rotary speed of the induction motor.
Torque ripple in the motor is minimized by having the inverter use plus width modulation
(PWM) to give motor current that approximates to sine wave. This system is also referred to as
AC Variable Voltage Variable Frequency Control.
The tenderer may propose any other equivalent or superior system and substantiate with
documents.
161
Part IV-Chapter 2 - Electric Passenger & Goods Lifts
The break lifting device shall be so arranged that it is impossible for the brake to be left in the
lifted position.
The direction of winding corresponding to the raising and lowering of the lift car shall be
clearly indicated.
A prominent notice shall be displayed stating that hand winding shall be undertaken only by
authorised persons and the notice shall detail the step by step procedure to be taken to move
the lift in an emergency.
If special tools are required they shall be supplied and located in a suitable wall mounted
fixture.
2.14.6 Vibration
All lift gear including traction motor and controllers shall be as silent in operation as possible
and in addition are to be effectively insulated from the structure so that no noise or vibration is
162
'l-Chapter 2- Electric Passenger & Goods Lifts
2.15.2 Controllers
The controllers in sheet steel cubicles, shall contain the necessary contactors, microprocessors
as appropriate, overload protective gear to the motor, reverse phase and single phase preventers
together with all necessary relays and switches for the starting, slowing, levelling and stopping
of the lift. It should be properly ventilated and doors should be screwed to the control panel.
The controllers should be designed to cut off the current automatically, apply the brake and
bring the car to a standstill in the event of a supply failure.
The current supply for solenoids, magnetic brake and other magnetic devices is to be d.c.
obtained from a suitable full wave rectifier. Suitable circuit breaker or fuse protection shall be
provided on each outgoing circuit.
The controller circuits shall be designed to prevent the lift being operated by the main motor
until all car and landing doors are closed, except with the levelling zone of the floor at which
the lift is stopping.
163
Part IV - Chapter 2 - Electric Passenger & Goods Lifts
Provision shall be made for easy release and resetting of the safety gear after it has been
operated.
For elevator speeds of I m/s and above gradual safety should be used and for speeds 0.75 m/s
and below instantaneous safety can be used.
Ropes for operating safety gear shall be independently supported on its own pulley system,
and shall not be less than 8 mm in diameter.
l
)64
Part IV - Chapter 2 - Electric Passenger & Goods Lifts
connected electrically with the microprocessor governing floor selection and direction of travel
to supply the operation described below.
The system shall be so designed that when the car is standing at the main floor, registration of
one or more 'car' or 'hall' calls will start the car 'Up' as soon as the door interlock circuit is
established. The car will answer the car calls and 'Up' hall calls as the floors are reached
irrespective of the order in which the call was registered, provided the button for a given floor
was pressed sufficiently in advance of the arrival of the car at the floor to permit a stop to be
made. The time control by microprocessor will hold the car at each floor for a sufficient time
for the doors to be opened and closed before it will again start in response to other calls.
'Down' hall calls will have no effect during the upward movement of the car but will remain
registered to be answered on the down ward trip except that the car will stop in answer to the
highest 'Down' cal!, if it is above the highest car or 'UP' hall call. When the car has answered
for the highest car call or the highest 'Down' hall call, the car will automatically reverse and
proceed down answering car or 'Down' hall calls in a similar manner. 'Up' hall calls will have
no effect during the downward movement of the car but will remain registered to be answered
on the next up trip. Hall calls for the direction in which the car is moving, placed too late to be
answered on that trip, will remain registered to be answered on the next trip in that direction.
The car will park at the last call floor with the doors closed.
Power operated doors will open automatically and will close after a definite time. Pressure of
the hall button at the floor where the car is standing will reopen the doors. A door open button
will be provided in the car operating panel to reopen the doors from the car. The momentary
pressure of a door close button will permit the doors to close immediately. A protective device
will be mounted on the leading edge of the car door which will extend beyond the door a
sufficient amount and be sufficiently flexible so that when it meets an obstruction in the
closing motion, it will operate a contact and cause the doors to reopen.
165
Part IV - Chapter 2 - Electric Passenger & Goods Lifts
This artificial intelligence group control supervisory system should be programable, in order
that shatter waiting time is achieved by means of a data base and should also take into
consideration physiological waiting time.
The following main features should be built into this group control system:
Control of Service
The system will exclude an elevator from the assignment of hall calls when the car cannot
respond to the calls registered. Another car in the group will operate as a backup for the
excluded car to ensure continuity of service to all hall calls.
Off-Hour Spotting
During off-time hours, after the elevator cars have been waiting with doors closed for a
predetermined amount of time, the system disperses each car to a designated location, thus
allowing more efficient service to future hall calls.
The system so designed should provide for micro processors to be located in the elevator
machine room on each car and on each floor with each module being linked via serial
transmission line to form a data network.
The system should incorporate a backup system to safeguard against group control computer
malfunction, group controller malfunction and car control malfunction. In addition the
operation of the group control system should provide to reduce the physical waiting time and
provide optimum service when under group control mode. Jt should calculate penalty values
for such things as bypassing, reversal and response to distantly positioned elevators and
assigns a call to each elevator that will minimize the penalty value thereby reducing congestion
and improve elevator service. The use of optical fibre cables to improve date transmission
should be provided for.
166
Part IW- Chapter 2- Electric Passenger & Goods Lifts
The operating equipment will consist of a series of micro touch buttons in each car numbered
to correspond to the various landings, a single riser of 'UP' and 'down' buttons at the
intermediate landings and single button at the terminal landings, all connected electrically with
the microprocessor governing floor selection and direction of travel to supply the operation
described below.
One of the cars will be normally parked with doors closed at the main floor and the other will
be a 'free' car which parks with doors closed at its last call floor.
Each car will answer its car calls of all floors respectively.
The micro processor calculates penalty values for such things as by-passing, reversal, and
response by distantly positioned elevators and assigns the call to the elevator that will
minimize the total penalty value.
Response to hall calls will be on the basis of same direction priority response, nearest cage
response, long waiting time prevention, car bunching prevention etc..
(i) The lift shall be controlled from micro-touch buttons in the car, numbered to
correspond to the landing served, and by single micro - touch buttons on the landing.
(ii) The operating device shall give the person in the car uninterrupted use of the lift until
the car has reached the desired landing, and the car has been opened and again closed.
167
Part IV- Chapter 2- Electric Passenger & Goods Lifts
Momentary pressure of a landing button shall bring the car to that landing.
(iii) After the car stops at a landing in response to a landing call, a time delay shall render
the car inoperative from the landing buttons for a pre-determined interval.
2.21 Reserved Operation under Emergency use (Applicable for Hospital Bed
Elevators)
A special micro - touch button with in-use sign which will appear on energising the button
should be provided. This should enable, on emergency condition, the elevator service to other
floors to be suspended and elevator to be despatched direct for transport of patients and
surgical equipment etc ..
2.22 Door Close Delay Function (Applicable for Hospital Bed Elevator Unless
Otherwise Specified)
A door closing delay button should be provided in the car operating panel to keep the doors
open until such time activities such as loading and unloading of hospital beds, surgical
equipment etc.
168
Part IV- Chapter 2- Electric Passenger & Goods Lifts
position. The car operating panel should have the facility to indicate that the elevator is in
fireman's mode when the fireman's switch is activated.
In the event of the car being loaded to its full capacity, then it will not stop to answer any hall
calls and will stop only at the registered car call. This will continue until such time the loading
is reduced from its full capacity. This operation shall be in both directions of travel.
2.29 Painting
All iron and wood-work, except where finished bright or plated shall be thoroughly cleaned of
all scale and rust and painted two coats of oil paint at maker's works. On completion of the
work on site the paint work shall be touched up to make good any damage sustained during
installation. All bright and plated parts are to be greased or otherwise protected against
corrosion or discolouring during erection.
Cellulose and other special finishes shall be protected so that they are handed over in perfect
condition.
169
CHAPTER3
TESTING, COMMISSIONING AND SUBMISSIONS
(ii) The brake sustains the car with contract load plus 25%.
(iii) Satisfactory operation of the safety gear and over-speed governor under over speed
conditions.
(iv) The various safety devices, locks and other safety provisions operate as intended.
(v) The operation of the lift and doors in response to the car switches and push buttons is
as intended.
(vi) The levelling is correctly adjusted for each floor and remains so after extended use.
(vii) The car shall be loaded to the full specified load and the lift run from top to bottom
continuously, for the full travel of the lift, allowing the normal time interval at each
terminal, during which the doors are to be opened and closed. The test shall be
continued for I hour during which the motor, motor generator and gear box shall be
assumed to have attained their maximum operating temperatures.
All instruments required for the tests shall be provided by the Contractor.
170
Part IV - Chapter 3 - Testing, Commissioning and Submissions
At the completion of each section of the work a record drawing shall be prepared by the
Contractor for submission to the Engineer.
The record drawing shall show the position of every items of plant and all items requiring
access for operation and maintenance or cleaning, any other item of equipment forming part of
the complete installation with particular attention to control circuiting underground or
concealed services and safety gear. Where relevant all sizes, capacities or ratings of equipment
shall be given. All items underground or otherwise concealed shall be precisely located on the
'as installed' drawings by means of dimensions taken on site from some readily identifiable
point (i.e. main walls of building or finished floor levels). Where necessary, Contractor shall
also produce sections, elevations and part plans.
When al! record drawings have been submitted to the Engineer and have subsequently been
approved, the Contractor shall supply copies of these drawings in the following forms.
(iii) Three sets of reduced prints on A4 size card (Suitable for inclusion in operating and
maintenance manual binder).
(i) Manufacturer's catalogues for all items of equipment forming the installation.
(iii) Manufacturer's drawings and spare parts schedules for the major items of equipment
17l
Part IV - Chapter 3 - Testing, Commissioning and Submissions
(v) List of local suppliers and stokists of all items of equipment forming the services
installation.
The contractor having obtained the Engineer's approval for the operating and maintenance
manual shall supply three copies in PVC covered binders, PRIOR TO COMPLETION
CERTIFICATE BEING ISSUED.
All necessary spares, tools and other material required for such work shall be included.
An efficient local brakedown call-out organisation whereby the services of an Engineer can be
obtained immediately at any hour of the day or night, will be deemed to fulfil the above
requirements.
172
ANNEXURES
Annexure A
173
Annexure A
ALRCONDITIONING ANDVENTILATION
174
Annexure A
Regulating Valve
Orifice Valve
Motorized Valve
e s1.
Strainer
Drain Cock
Union
Flexible Connection
( Pressure Gauge
( Thermometer
0 Thermostat
@ Pump
E Flo Switch
@3 Pressure Switch
ARD
Non Return Damper (Air pressure operate)
Sound Attenuator.
74 175
Annexure ]
FIRE PROTECTION
Fire Extinguishers
foam Type
Fire Extinguishers
Dry Powder Type
Fire Extinguishers
Carbon Dioxide Type
Fire Extinguishers
Vaporising Liquid Type (BCF)
Fire Extinguishers
Water Type
Fire Blanket(s)
Hose Reels
Exit Boxes
Directional
"Fire Exit"
Signs
Exit Directional
Signs
176
Annexure A
Notices on Doors
0 Exit Boxes
�
Manual Fire Alarm Sounders
Internal Telephone
Fire Alarm System
6 177
E
Annexure A
* means of escape
0 Window Exits
SD Security Doors
178
Annexure A
HrL Handrail(s)
Guadrail(s)
G+L Balustrade(s) or
Wall(s)
WP Weather Protection
Ramps
F Occasional Occupancy
78
179
a j
Annexure B
2
No Description Symbol
2
Routing of Conductors 2
27.5.5 Meter L 2
-----------------------·----
180
Annexure B
Switch outlets
Socket outlets
Fixed apparatus
27.6.2 Fan
27.6.4 Motor 0
27.6.6 Thermostat 0
27.6.11 Bell
2.4.11 Buzzer
2.4.12 Siren
2.4.13 Horn
181
Annexure B
27.3.11 Pushbutton 0
27.3.12 Luninous pushbutton ®
27.6.8 Restricted access pushbutton for fire alarm (El
27.7.6 Aerial Y
27.7.7 Earth
Clocks
Thermostat
Extract fan
Ceiling fan
Isolator switch
Distribution Board
82 183
Annexure B
G2-
-
Fire Alarm Bell
@- T.V. Outlet
@- Speaker
184
A TYPICAL FORMAT FOR
Annexure C
l
SCHEDULE OF REQUIREMENTS
Quantity
2 Purpose of Elevater
8 Operation
9 Hoistway Size
10 Overhead Height
11 Depth of Pit
12 Position of Machine room
13 Height of Machine Room
ELEVATOR
14 Design
15 Car Internal Dimension
16 Car Celling Lighting and
Ventilation System
17 Car Walls & Doors
18 Entrance Columns
19 Car Sill
20 Car Flooring
21 Landing Entrances
22 Hoistway Door at all Floors
23 Landing Sill at all Entrances
ENTRANCE INDICATORS
24 All Floors
25 Signals in the Cabin
185
Annexures C
Attendant Services
Automatic by pass
27 Safety Requirements:
28 Buffers
29 Guide rails
30 Counter Weights
31 Power Supply at Machine
Room.
186