1 Scope definition /
2 Objective /
9 Preparation N/A
15 Testing/inspection plan /
Checked by : Reviewed by :
BUSDUCT INSTALLATION
Revision : 00
Consultant
Approved by Tan Jin Soon (Sepakat Setia
Perunding)
Construction
Reviewed by Ivan Lim Kien Aun
Manager
Sathyan A/L
Prepared by Project Manager
Anbalakan
Contents
1.0 SCOPE OF WORKS………………………………...…………………………….…………….….3
1.1 General Description………………………………………………………………………….…..3
1.2 Reference……………………………………………………….……………………………...…..3
1.3 Materials……………………………………………………………….……………………….…..3
1.4 Plant and Equipment………………………………………………………..……………….…..3
1.5 Manpower………………………………………………………………………….……………….4
1.6 Work Procedures………….………………………………………………………………….…..5
1.6.1 General………………………………………………………………………………………….…..5
1.6.2 Precaution of Works before Commence………………………………………………….…..5
1.6.3 Delivery of material and Inspection………...…………………………….…………………...5
1.6.4 Sequences of works……………….……………………………..………………………….…..5
1.6.5 Preparation Procedure Before Installation………………...…………………………….…..5
1.6.6 Installation Procedure of Busduct……………………………………..………………….…..6
1.6.7 Testing and Inspection Procedure…………………………………………………..………..8
2.0 SAFETY AND HEALTH REQUIREMENT……………………………………………….…...10
2.1 Job Safety & Health Analysis……………………………………………………………..…..10
2.2 Information to personnel………………………………………...………………………….…10
2.3 Emergency Arrangements…………………………………….…………………………….…10
2.4 Permit Requirements………………………………………..……………………………….…11
2.5 Housekeeping……………………………………………...………………………………….…11
3.0 ENVIRONMENTAL ISSUES…………………………………………………………………….12
3.1 Environmental Aspects, Impacts & Control Measures………………………….…….….12
3.2 Air Quality and Noise Level……………………………………..…………………………….12
3.3 Water Quality………………………………………………………………………….………….12
3.4 Waste Management………………………………………………………………………….….12
4.0 QUALITY ASSURANCE & QUALITY CONTROL……………………………………….…13
4.1 Contractual Requirement………………………………………………………………….…..13
4.2 Inspection and Testing………………………………………………………………….……...13
5.0 APPENDICES…………………………………………………………………………….…….…..14
5.1 Job Safety Analysis……………………………………………………………………….….…14
5.2 Emergency Response Flow Chart……………………………………………………….…...18
5.3 Environmental Aspect & Impact Register………………………………………………..…22
5.4 Inspection & Test Plan………………………………………………………………………….27
5.5 QAQC………………………………………………………………………….…………………..29
1.2 Reference
1) Item 1.1.9.5 – Method Statement, Tender Document Vol 2: Need Statement &
Specifications
1.3 Materials
1.3.1 Materials for busduct installation include the following:
Item Materials
1. Busducts
2. Bolts and nuts
3. M6 Bolts
4. Elbow Fitting, Flange End, Termination box
5. Drop Rods
6. Horizontal/Vertical Hangers
1.5 Manpower
Item Designation Responsibilities
1. Project Manager Responsible for overall commercial, contractual
and technical performances associated with
specific
projects. Responsible to the Project Manager.
2. Construction Manager Planning, coordinating, scheduling and monitoring
of site activities.
3. Project Engineer Responsible for overall operation including liaison
with service provider.
4. Site Supervisor Supervising site construction activities
5. SHE Officer To control and ensure the Safety, Health and
Environmental is adhere at site.
6. SHE Supervisor Supervising site construction activities, organize
toolbox meeting and prepare all relevant permit
before start work.
7. Environment Manager To monitor and control environmental issue onsite
to ensure compliance to the regulation.
8. Environment Officer Control and ensure all site activities comply with
environmental plans and requirement.
9. Machineries Operator To operate the machineries.
10. Surveyor/Chainman Setting out works.
11. Traffic controller To control ingress and egress of construction traffic
at site.
12. General Worker & Conduct general works at site.
Observers
13. Flagmen To provide high visible to public traffic to slow down
when a crossing the working area.
14. Flagman & Traffic Control To control traffic and avoid public enter to the
workplace
15. Traffic management officer Make sure activity at site adhere to Traffic
Management Plan
1.6.2.1 Pre-Task Talk shall be conducted with all site staffs and workers as required by
the Occupational Safety and Health Act (OSHA) regulations.
1.6.2.2 Permit to work will be applied accordingly prior to any implementation of works.
1.6.2.3 Precautions should be taken to protect worker from possible hazards.
c) Use the hole on the side of the mounting plate as a guide to mark the
location of the holes to be drilled on the busduct.
d) Mount plate to busduct by holding the tapping bars in the busduct side
plate groove and tighten with the M6 bolts and washers.
e) Mount angle bracket to plate by selecting the correct slotted holes. Tighten
the bolts which positioned to engage spring assembly and floor flanged.
f) All busducts that penetrated the fire rated floor shall be sealed with
approved type of fire barrier.
Flow Chart
Start
Fail
Pass
End
2.3.5 The organization chart, list of emergency contact person and relevant authorities
with their contact numbers shall be showed in the Notice Board.
2.3.6 In the event of emergency, the site management staffs must evaluate the situation
and commence the necessary procedures as follow:
• Raise the alarm
• Stop works
• Remain composed.
• Make sure notifications of emergency or evacuation are in place for all
workers surrounding the vicinity.
• Make sure all workers are assembled at designated assembly point.
• Make sure first aid kits are prepared at assembly point.
• All workers are told not to leave the assembly point until clear sign is issued.
• Headcount shall be conducted
• First aiders shall attend to the injured workers
• Prepare assessment reports for the losses.
2.5 Housekeeping
Housekeeping is an essential part of SHE for the daily routine. Housekeeping
would include the following items:
• Maintain the access way to all working area.
• Proper material arrangement.
• Park the machineries in orderly manner.
• No littering around the site.
5.0 APPENDICES
5.1 Job Safety Analysis
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSIB
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING LE PERSON
STEPS Y OF MEASURES/ REQ
Proba Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
bility erity ROL
PxS PXS
(P) (S)
Sco Lev Sco Lev
re el re el
1. Mobilizing & Unstable/ soft Supervisor to check 2 3 6 M 3 Put steel plate at the soft OSHA ‘94 1 3 3 L Engineer /
materials to work ground, uneven surrounding and prepare ground access area FMA Supervisor /
area (apply access safe access (BOWEC) Traffic
throughout the 1986 Officer/
whole job Safety
sequence below) personnel
Slip, trip, fall into -Access way clear from 1 3 3 L 4 - OSHA ‘94 - - - - Engineer /
existing obstruction. FMA Supervisor /
drain/manhole -Cover openings with (BOWEC) Safety
sturdy materials. 1986 personnel
-Proper materials
arrangement and storage.
2. Use of hand Defective Check all equipment are in 2 2 4 L 3 - OSHA ‘94 - - - - Engineer /
Tools equipment good condition before use. FMA Supervisor /
Check all hoses / (BOWEC) Safety
connectors are in good 1986 personnel
condition. Remove
defective tools from site.
Page 1 of 4
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSIB
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING LE PERSON
STEPS Y OF MEASURES/ REQ
Proba Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
bility erity ROL
PxS PXS
(P) (S)
Sco Lev Sco Lev
re el re el
3. Busduct Falling from Secured working platform. 3 3 9 M 3 Inspect working platform OSHA ‘94 1 3 3 L Engineer /
Installation ladder/platform Provide body harness for / scaffold working FMA Supervisor /
during installation works more than 3 meter platform. Provide edges (BOWEC) Safety
high. Provide anchorage hard barricade or sturdy 1986 personnel
points or lifeline for working platform.
workers to hook their body
harness.
Unsafe access, Use of safety harness for 3 3 9 M 3 Use of industrial type OSHA ‘94 1 3 3 L Engineer /
unsecure working all work with fall of 3 ladder. Installation of FMA Supervisor /
platform & ladder meters or more. Inspection edge protection. (BOWEC) Safety
of access before use. Maintain 3point contact. 1986 personnel
Monitoring and Buddy system.
supervision
Page 2 of 4
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSIB
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING LE PERSON
STEPS Y OF MEASURES/ REQ
Proba Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
bility erity ROL
PxS PXS
(P) (S)
Sco Lev Sco Lev
re el re el
Busduct Electric shock Use industrial plugs / 2 3 6 M 3 Check all cables before OSHA ‘94 1 3 3 L Engineer /
Installation (cont.) cable. Electrical connection. Cable hangs FMA Supervisor /
equipment / wiring to be / not trailing on ground / (BOWEC) Safety
inspected / connected by in water 1986 personnel
electrician. Display
signages. Work briefing
prior to work start.
Page 3 of 4
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
1 Elimination
2 Substitution
3 Engineering controls, reorganization of work, or both:
4 Administrative Control
5 PPE
Page 4 of 4
Rev. No:01 / Date: 18 JAN 2023
RWTP
RASAU WATER TREATMENT PLANT
Fire Emergency
Identifier alert
Major Minor
Emergency
terminates
Debriefing by Conduct
Emergency investigation Finish
commander
Risk: 1. Recommend to conduct work at night or during off peak hours to minimize traffic
- Public complaint disruption.
- Heavy traffic congestion 2. Maintain most number of lanes wherever possible.
3. Reduce number of lanes (only when unavoidable and when all other alternatives
Road closure, lane diversion and
Traffic congestion N 3 2 6 YES Opportunities: have been exhausted) to be design to facillitate contra flow options.
reduction
- NA 4. Provide sufficient warning signs and flagmen at all work areas to facillitate better
traffic flow.
5. Maintain traffic management devices and temporary/ warning signs to ensure
maximum effectiveness in terms of traffic management.
Risk:
1. Inspection by weekly and maintenance of machinery to be conducted regularly to
Legal action by authorities
ensure machines are in good working condition with no leakage.
Oil spillage/ leakage Land contamination A 2 2 4 YES
2. Manually excavate the contaminated area and put into a suitable container and
Opportunities:
must be stored at scheduled waste storage for proper disposal.
- NA
Risk:
- Legal action by authorities
Generation of scheduled waste Immediately clear any spillage on the ground. Scheduled waste will be stored at
Land contamination N 2 2 4 YES
(including disposal of waste) scheduled waste storage area and disposed by licensed contractor.
Opportunities:
- NA
1.Mobilisation / Risk:
Demobilization (loading/ Public complaint
unloading of machinery)
Opportunities:
1. The machinery will be maintained in good working order to ensure that exhaust
- Regular maintenance of
Generation of black smoke Air pollution N 2 2 4 YES emission is controlled.
machinery
2. Allow only machinery that is in good condition to enter the site.
- Increase life span of machinery
Risk: 1. Speed limits (15km/ hr) and traffic volume restriction within the site area will be
- Public complaint implemented to reduce the dust dispersion.
2. Dampen all access. Water bowser need to standby for watering all the time.
Generation of dust Air pollution N 2 2 4 YES
3. Vehicles transporting earth to be installed with tailgate and covered with tarpaulin.
Opportunities: 4. To wash the construction vehicles wheels at a wash trough facility before leaving
- NA from construction site.
Risk:
Inspection by weekly and maintenance of machinery to be conducted regularly.
- Public complaint
Installation of hoarding or temporary noise barrier. All noise generating equipment
Generation of noise/ vibration noise/ vibration nuisance N 3 2 6 YES
and machinery will be shut down when not in use and work will be conducted within
Opportunities:
approved working hour.
- NA
Risk:
- Public complaint 1. Wash trough to be provided at the site exit with water jet and operator.
Dirtying of public road Public nuissance/ public complaint N 3 2 6 YES 2. Temporary drainage will be constructed to channel surface runoff to silt trap.
Opportunities: 3. Water bowser need to be standy for watering purposes.
- NA
Appendix 5.3
Risk:
- Legal action by authorities
2. Setting out (Use of Used spray paint container will be stored at scheduled waste storage area and
Land contamination N 2 2 4 YES Opportunities:
marking spray paint) disposed by licensed contractor.
- NA
Generation of scheduled waste
(including disposal of waste) (Use
of marking spray paint) Risk:
- Legal action by authorities
Immediately clear any spillage from surface water, stream, pond by using spill kit
Water pollution N 2 2 4 YES Opportunities: manually and put into a suitable container and must be stored at scheduled waste
- NA storage prior to disposal.
Risk:
- Legal action by authorities All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste
Land contamination N 2 2 4 YES Construction Waste Management Plan. Open burning is strictly prohibited. Waste
(including disposal of waste)
Opportunities: will be disposed at the approved disposal site.
- NA
Risk:
- Legal action by authorities
Public nuisance/ complaint N 2 2 4 YES Provide maintenance on time for fuel burning equipment, vehicle & machineries.
Opportunities:
- Nil.
3. Busduct installation Noise generation Risk:
- Nil
Limit working hour. Working hours are in accordance with permissible times as per
Noise pollution N 2 2 4 YES Opportunities:
authority instructions.
-Nil
Risk:
- Public complaint
Generation of dust Air pollution N 2 2 4 YES Dampen the work area to reduce dust dispersion.
Opportunities:
- NA
Appendix 5.3
Risk:
- Public complaint
- Legal action by authorities All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste
Land contamination N 2 2 4 YES Construction Waste Management Plan. Open burning is strictly prohibited. Waste
(including disposal of waste)
Opportunities: will be disposed at the approved disposal site.
- To reuse/recycle the waste for
other purposes
N* = Normal
Prepared by Reviewed By Approved By
A* = Abnormal
E* = Emergency
Name Siti Norlissa Bt Ishak Siti Khairiah Mohd Hashim Ivan Lim Kien Aun L* = Likelihood (refer to Appendix B)
S* = Severity (refer to Appendix B)
# Risk Rating calculation shown in Appendix B
Signature
Risk Rating
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000052-00 Page 1
ITP FOR BUSDUCT INSTALLATION FOR ELECTRICAL SERVICES
Document No. RWTP-GB-M&E-ITP-000052-00
Revision No. 00 Rev. Date 29/12/2023
Signature
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000052-00 Page 2
RWTP
RASAU WATER TREATMENT PLANT
5.5 QAQC
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 1 of 9
Rasau WTP Form detail report
1.9 Material
2. Description of works
Check layout and position according to approved construction/shop drawing.
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. Description of works
Check material brand & type of insulation are according to approved Equipment and Material List.
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 2 of 9
Rasau WTP Form detail report
4. Description of works
Check busduct size & rating according to approved construction shop drawing.
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. Description of works
Check number of busbar (phases) according to approved construction drawing.
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. Description of works
Check that busduct no visible damage & busbar spacing is good condition & secured properly.
6.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 3 of 9
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. Description of works
Check busduct labeling / markings are according to approved construction drawing.
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. Description of works
Check that all busbar are terminated to the correct busbar (phase) according to approved construction
drawing.
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 4 of 9
Rasau WTP Form detail report
9. Description of works
Check all busduct joint section align sealed properly with joint cover.
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
11.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 5 of 9
Rasau WTP Form detail report
11.3 CA Representative
Pass Fail N/A
12.1 Contractor
Pass Fail N/A
12.3 CA Representative
Pass Fail N/A
13.1 Contractor
Pass Fail N/A
13.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 6 of 9
Rasau WTP Form detail report
14.1 Contractor
Pass Fail N/A
14.3 CA Representative
Pass Fail N/A
15.1 Contractor
Pass Fail N/A
15.3 CA Representative
Pass Fail N/A
16.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 7 of 9
Rasau WTP Form detail report
16.3 CA Representative
Pass Fail N/A
17.1 Contractor
Pass Fail N/A
17.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 8 of 9
Rasau WTP Form detail report
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:40 AM UTC+08:00 Page 9 of 9
Rasau WTP Form detail report
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 1 of 7
Rasau WTP Form detail report
1.9 Material
2. DESCRIPTION OF WORKS
D.O Copy attachment
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. DESCRIPTION OF WORKS
Test certificate copy attachment
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 2 of 7
Rasau WTP Form detail report
4. DESCRIPTION OF WORKS
Test certificate issued to the correct material delivered (refer to material tagging identification)
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. DESCRIPTION OF WORKS
Brand / Type of material as per approved submission
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. DESCRIPTION OF WORKS
Size, length & dimension as per D.O
6.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 3 of 7
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. DESCRIPTION OF WORKS
Color of material (if applicable)
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. DESCRIPTION OF WORKS
Material unloading & delivery plan (any major equipment that require)
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 4 of 7
Rasau WTP Form detail report
9. DESCRIPTION OF WORKS
Condition of material before & after unloading
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
11.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 5 of 7
Rasau WTP Form detail report
11.3 CA Representative
Pass Fail N/A
12.1 Contractor
Pass Fail N/A
12.3 CA Representative
Pass Fail N/A
If any
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 6 of 7
Rasau WTP Form detail report
Remarks: If " Final Inspection" record Fail Status, Please refer to NCR.
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 7 of 7
PM&C : Page No. : 1 of 1
Doc Ref. :
No.
Project :
TRADE CONTRACTOR/ SUPPLIER: Trade
:
Package
Location/ Zone/ Sub-Zone/ Level/ Block /Unit/ Area : Drawing Ref. No. :
TEST INSTRUMENT :
MANUFACTURER :
Voltage Rating :
500 Volt
STATUS OF INSPECTION
We have carried out all necessary inspections and verify that the above items/ activities conform to the contract specifications/ document
Checked By: Checked By: Checked By:
Location/ Zone/ Sub-Zone/ Level/ Block /Unit/ Area : Drawing Ref. No. :
TEST INSTRUMENT :
MANUFACTURER :
Voltage Rating :
500 Volt
STATUS OF INSPECTION
We have carried out all necessary inspections and verify that the above items/ activities conform to the contract specifications/ document
Checked By: Checked By: Checked By: