RWTP GB MNE MST 000050 Switches, Sso and Isolators
RWTP GB MNE MST 000050 Switches, Sso and Isolators
RWTP GB MNE MST 000050 Switches, Sso and Isolators
1 Scope definition /
2 Objective /
9 Preparation N/A
15 Testing/inspection plan /
Checked by : Reviewed by :
Revision : 00
Consultant
Approved by Tan Jin Soon (Sepakat Setia
Perunding)
Construction
Reviewed by Ivan Lim Kien Aun
Manager
Sathyan A/L
Prepared by Project Manager
Anbalakan
Contents
1.0 SCOPE OF WORKS………………………………...…………………………….…………….….3
1.1 General Description………………………………………………………………………….…..3
1.2 Reference……………………………………………………….……………………………...…..3
1.3 Materials……………………………………………………………….……………………….…..3
1.4 Plant and Equipment………………………………………………………..……………….…..3
1.5 Manpower………………………………………………………………………….……………….4
1.6 Work Procedures………….………………………………………………………………….…..5
1.6.1 General………………………………………………………………………………………….…..5
1.6.2 Precaution of Works before Commence………………………………………………….…..5
1.6.3 Delivery of Materials and Inspection…………………….……………….…………………...5
1.6.4 Sequences of work ………………………………………..………………………….………….5
1.6.5 Preparation Procedure Before Installation ………………….…….…………………….…..5
1.6.6 Installation Procedure for Switches, SSO and Isolators…………………...………….…..6
1.6.7 Testing Procedure…………………………………………………………………....……...…...8
2.0 SAFETY AND HEALTH REQUIREMENT……………………………………………….…...10
2.1 Job Safety & Health Analysis……………………………………………………………..…..10
2.2 Information to personnel………………………………………...………………………….…10
2.3 Emergency Arrangements…………………………………….…………………………….…10
2.4 Permit Requirements………………………………………..……………………………….…11
2.5 Housekeeping……………………………………………...………………………………….…11
3.0 ENVIRONMENTAL ISSUES…………………………………………………………………….12
3.1 Environmental Aspects, Impacts & Control Measures………………………….…….….12
3.2 Air Quality and Noise Level……………………………………..…………………………….12
3.3 Water Quality………………………………………………………………………….………….12
3.4 Waste Management………………………………………………………………………….….12
4.0 QUALITY ASSURANCE & QUALITY CONTROL……………………………………….…13
4.1 Contractual Requirement………………………………………………………………….…..13
4.2 Inspection and Testing………………………………………………………………….……...13
5.0 APPENDICES…………………………………………………………………………….…….…..14
5.1 Job Safety Analysis……………………………………………………………………….….…15
5.2 Emergency Response Flow Chart……………………………………………………….…...21
5.3 Environmental Aspect & Impact Register………………………………………………..…22
5.4 Inspection & Test Plan………………………………………………………………………….25
5.5 QAQC………………………………………………………………………….…………………..28
1.2 Reference
1) Item 1.1.9.5 – Method Statement, Tender Document Vol 2: Need Statement &
Specifications
1.3 Materials
1.3.1 Materials for Switches, SSO and Isolators Installation include the following:
Item Materials
1. Switches
2. Switch Socket Outlet (SSO)
3. Isolators
4. Wall Plugs
1.5 Manpower
Item Designation Responsibilities
1. Project Manager Responsible for overall commercial, contractual
and technical performances associated with
specific
projects. Responsible to the Project Manager.
2. Construction Manager Planning, coordinating, scheduling and monitoring
of site activities.
3. Project Engineer Responsible for overall operation including liaison
with service provider.
4. Site Supervisor Supervising site construction activities
5. SHE Officer To control and ensure the Safety, Health and
Environmental is adhere at site.
6. SHE Supervisor Supervising site construction activities, organize
toolbox meeting and prepare all relevant permit
before start work.
7. Environment Manager To monitor and control environmental issue onsite
to ensure compliance to the regulation.
8. Environment Officer Control and ensure all site activities comply with
environmental plans and requirement.
9. Machineries Operator To operate the machineries.
10. Surveyor/Chainman Setting out works.
11. Traffic controller To control ingress and egress of construction traffic
at site.
12. General Worker & Conduct general works at site.
Observers
13. Flagmen To provide high visible to public traffic to slow down
when a crossing the working area.
14. Flagman & Traffic Control To control traffic and avoid public enter to the
workplace
15. Traffic management officer Make sure activity at site adhere to Traffic
Management Plan
1.6.5.2 To plan out the best layout of the buildings and prepare a room layout shop
drawing if applicable.
1.6.5.3 To submit and obtain consultant approval/comments and endorsement for shop
drawings of mounting height for switches/sso/isolators as well as other technical
data required.
1.6.5.4 To submit and obtain consultant approval/comments of method of installation of
switches/sso/isolators.
1.6.5.5 Prepare delivery schedule and inform suppliers. Coordinate with main-contractor
to check if site is ready for delivery and installation of the switches/sso/isolators.
1.6.5.6 Coordinate with site workers responsible for the installation of the
switches/sso/isolators.
1.6.5.7 If delivery is required before location for installation of the switches/sso/isolators
is ready, coordinate with main-contractor for a safe storage area and protection
from weather and damage should be made ready.
Flow Chart
Start
Visual Inspection
Testing procedures
Fail
RFI will be submitted for inspection during the
course of installation
Pass
End
2.5 Housekeeping
Housekeeping is an essential part of SHE for the daily routine. Housekeeping
would include the following items:
• Maintain the access way to all working area.
• Proper material arrangement.
• Park the machineries in orderly manner.
the oil spillage all over the place. Subsequent waste shall be collected and transfer
to area as assigned.
5.0 APPENDICES
5.1 Job Safety Analysis
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSIB
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING LE PERSON
STEPS Y OF MEASURES/ REQ
Pro Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
babi erity ROL
PxS PXS
lity
(S)
(P) Sco Lev Sco Lev
re el re el
1. Mobilizing & Unstable/ soft ground, -Supervisor to check 2 3 6 M 3 Put steel plate at the soft OSHA ‘94 1 3 3 L Engineer /
materials to uneven access surrounding and prepare ground access area. FMA Supervisor /
work area safe access. (BOWEC) Traffic
(apply -Prepare sturdy working 1986 Officer/
throughout the platform for the workers’ Safety
whole job access. personnel
sequence
below) Slip, trip, fall into -Access way clear from 1 3 3 L 4 - OSHA ‘94 - - - - Engineer /
existing drain/manhole obstruction. FMA Supervisor /
-Cover openings with (BOWEC) Safety
sturdy materials. 1986 personnel
-
2. Use of hand Defective equipment -Check all equipment are 2 2 4 L 3 - OSHA ‘94 - - - - Engineer /
Tools in good condition before FMA Supervisor /
use. (BOWEC) Safety
-Defective equipment to 1986 personnel
be removed from site.
-Check all hoses /
connectors are in good
condition.
Page 1 of 3
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSIB
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING LE PERSON
STEPS Y OF MEASURES/ REQ
Pro Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
babi erity ROL
PxS PXS
lity
(S)
(P) Sco Lev Sco Lev
re el re el
3. Switches/SSO/I Electric shock Use industrial plugs / 2 3 6 M 3 Check all cables before OSHA ‘94 1 3 3 L Engineer /
solators cable. Electrical connection. Cable hangs FMA Supervisor /
Installation equipment / wiring to be / not trailing on ground / (BOWEC) Safety
inspected / connected by in water 1986 personnel
electrician. Display
signages. Work briefing
prior to work start.
Defective hand tools -Inspection all tools before 2 2 4 L 4 - OSHA ‘94 - - - - Engineer /
or electrical tools use. FMA Supervisor /
-Remove any defective (BOWEC) Safety
tools from working area. 1986 personnel
-Proper electrical
connection. Use industrial
socket.
Unsafe access -Ensure access scaffold 2 3 6 M 3 -Ensure that the OSHA ‘94 1 3 3 L Engineer/Sc
scaffolding/working with inspection tag before foundation of the FMA affolder/Supe
platform use. scaffold access is on the (BOWEC) rvisor/ Safety
-Ensure the scaffolding is firm ground. 1986 personnel
erected as per design.
Page 2 of 3
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
1 Elimination
2 Substitution
3 Engineering controls, reorganization of work, or both:
4 Administrative Control
5 PPE
Page 3 of 3
Rev. No:01 / Date: 18 JAN 2023
RWTP
RASAU WATER TREATMENT PLANT
Fire Emergency
Identifier alert
Major Minor
Emergency
terminates
Debriefing by Conduct
Emergency investigation Finish
commander
Type of Work: SWTCHES, SWITCH SOCKET OUTLET(SSO) AND ISOLATORS INSTALLATION Date: 29/3/2024
Risk: 1. Recommend to conduct work at night or during off peak hours to minimize traffic
- Public complaint disruption.
- Heavy traffic congestion 2. Maintain most number of lanes wherever possible.
3. Reduce number of lanes (only when unavoidable and when all other alternatives
Road closure, lane diversion and
Traffic congestion N 3 2 6 YES Opportunities: have been exhausted) to be design to facillitate contra flow options.
reduction
- NA 4. Provide sufficient warning signs and flagmen at all work areas to facillitate better
traffic flow.
5. Maintain traffic management devices and temporary/ warning signs to ensure
maximum effectiveness in terms of traffic management.
Risk:
1. Inspection by weekly and maintenance of machinery to be conducted regularly to
Legal action by authorities
ensure machines are in good working condition with no leakage.
Oil spillage/ leakage Land contamination A 2 2 4 YES
2. Manually excavate the contaminated area and put into a suitable container and
Opportunities:
must be stored at scheduled waste storage for proper disposal.
- NA
Risk:
- Legal action by authorities
Generation of scheduled waste Immediately clear any spillage on the ground. Scheduled waste will be stored at
Land contamination N 2 2 4 YES
(including disposal of waste) scheduled waste storage area and disposed by licensed contractor.
Opportunities:
- NA
1.Mobilisation / Risk:
Demobilization (loading/ Public complaint
unloading of machinery)
Opportunities:
1. The machinery will be maintained in good working order to ensure that exhaust
- Regular maintenance of
Generation of black smoke Air pollution N 2 2 4 YES emission is controlled.
machinery
2. Allow only machinery that is in good condition to enter the site.
- Increase life span of machinery
Risk: 1. Speed limits (15km/ hr) and traffic volume restriction within the site area will be
- Public complaint implemented to reduce the dust dispersion.
2. Dampen all access. Water bowser need to standby for watering all the time.
Generation of dust Air pollution N 2 2 4 YES
3. Vehicles transporting earth to be installed with tailgate and covered with tarpaulin.
Opportunities: 4. To wash the construction vehicles wheels at a wash trough facility before leaving
- NA from construction site.
Risk:
Inspection by weekly and maintenance of machinery to be conducted regularly.
- Public complaint
Installation of hoarding or temporary noise barrier. All noise generating equipment
Generation of noise/ vibration noise/ vibration nuisance N 3 2 6 YES
and machinery will be shut down when not in use and work will be conducted within
Opportunities:
approved working hour.
- NA
Risk:
- Public complaint 1. Wash trough to be provided at the site exit with water jet and operator.
Dirtying of public road Public nuissance/ public complaint N 3 2 6 YES 2. Temporary drainage will be constructed to channel surface runoff to silt trap.
Opportunities: 3. Water bowser need to be standy for watering purposes.
- NA
Appendix 5.3
Type of Work: SWTCHES, SWITCH SOCKET OUTLET(SSO) AND ISOLATORS INSTALLATION Date: 29/3/2024
Risk:
- Public complaint
Generation of dust Air pollution N 2 2 4 YES Dampen the work area to reduce dust dispersion.
Opportunities:
- NA
Risk:
- Legal action by authorities
1. A petroleum based machines or equipment be placed on the secondary
Land contamination N 2 2 4 YES Opportunities: containment/ tray.
- NA 2. Any spillage to be collected and treated as scheduled waste.
Risk:
- Public complaint
- Legal action by authorities All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste
Land contamination N 2 2 4 YES Construction Waste Management Plan. Open burning is strictly prohibited. Waste
(including disposal of waste)
Opportunities: will be disposed at the approved disposal site.
- To reuse/recycle the waste for
other purposes
N* = Normal
Prepared by Reviewed By Approved By
A* = Abnormal
E* = Emergency
Name Siti Norlissa Bt Ishak Siti Khairiah Mohd Hashim Ivan Lim Kien Aun L* = Likelihood (refer to Appendix B)
S* = Severity (refer to Appendix B)
# Risk Rating calculation shown in Appendix B
Signature
Risk Rating
RASAU WATER TREATMENT PLANT SWITCHES, SSO AND ISOLATORS INSTALLATION FOR ELECTRICAL
Project: ITP for: Rev: 00
(RWTP) SERVICES
Discipline: M&E Ref. No: RWTP-GB-MNE-ITP-000050-00
Discipline code: REFER TO PROCEDURE Date: 20/3/2024 No of Pages: 2 1 of 2
Inspection Point
No. Activity Description Controlling Document Acceptance Criteria Frequency Record
CR SC CA
Technical Prior to
Submission of Method Method Statement and Approved Method of
1.1 Specification/Construction commencement of H R R
Statement Inspection Test Plan (ITP) Statement; Approved ITP
Drawing work
Technical Prior to
Submission of Material for Comment Review Sheet
1.2 Technical Specification Specification/Construction commencement of H R S
approval for Material Submission
Drawing work
Material Submission Approved Material
Technical Prior to
Material Receiving Inspection Approval Submission / Request for
1.3 Specification/Construction commencement of H W S
Catalogue Inspection (RFI) / Delivery
Drawing work
Order (D.O.)
Prior to
Method Statement: RWTP-
1.4 Installation Inspection As-built Survey data / Record commencement of Survey Record H W S
GB-MNE-MST-000050
work
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000050-00 Page 1
ITP FOR SWITHCES, SSO AND ISOLATORS INSTALLATION FOR ELECTRICAL SERVICES
Document No. RWTP-GB-M&E-ITP-000050-00
Revision No. 00 Rev. Date 29/12/2023
Signature
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000050-00 Page 2
RWTP
RASAU WATER TREATMENT PLANT
5.5 QAQC
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:23 PM UTC+08:00 Page 1 of 7
Rasau WTP Form detail report
1.9 Material
2. Description of Works
Check layout and position according to approved construction/shop drawing.
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. Description of Works
Check brand, type and rating are according to Approved Equipment and Material List.
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:23 PM UTC+08:00 Page 2 of 7
Rasau WTP Form detail report
4. Description of Works
Check mounting height according to approved construction/shop drawing or specification.
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. Description of Works
Check correct polarity of connection.
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. Description of Works
Check and ensure earth continuity conductor is properly connected between the light switch / switch socket
outlet and the surface mounted or concealed knockout box using cable lug.
6.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:23 PM UTC+08:00 Page 3 of 7
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. Description of Works
Check all connections are properly tightened.
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. Description of Works
Check all normal light switch / switch socket outlets are not exposed to rain or water splashing,
weatherproof type to be installed for such case.
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:23 PM UTC+08:00 Page 4 of 7
Rasau WTP Form detail report
9. Description of Works
Check all Data & Network socket outlet are terminated properly to Data & Network cable.
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
11.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:23 PM UTC+08:00 Page 5 of 7
Rasau WTP Form detail report
11.3 CA Representative
Pass Fail N/A
12.1 Contractor
Pass Fail N/A
12.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:23 PM UTC+08:00 Page 6 of 7
Rasau WTP Form detail report
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:23 PM UTC+08:00 Page 7 of 7
Rasau WTP Form detail report
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 1 of 7
Rasau WTP Form detail report
1.9 Material
2. DESCRIPTION OF WORKS
D.O Copy attachment
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. DESCRIPTION OF WORKS
Test certificate copy attachment
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 2 of 7
Rasau WTP Form detail report
4. DESCRIPTION OF WORKS
Test certificate issued to the correct material delivered (refer to material tagging identification)
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. DESCRIPTION OF WORKS
Brand / Type of material as per approved submission
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. DESCRIPTION OF WORKS
Size, length & dimension as per D.O
6.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 3 of 7
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. DESCRIPTION OF WORKS
Color of material (if applicable)
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. DESCRIPTION OF WORKS
Material unloading & delivery plan (any major equipment that require)
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 4 of 7
Rasau WTP Form detail report
9. DESCRIPTION OF WORKS
Condition of material before & after unloading
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
11.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 5 of 7
Rasau WTP Form detail report
11.3 CA Representative
Pass Fail N/A
12.1 Contractor
Pass Fail N/A
12.3 CA Representative
Pass Fail N/A
If any
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 6 of 7
Rasau WTP Form detail report
Remarks: If " Final Inspection" record Fail Status, Please refer to NCR.
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 7 of 7
LIGHT SWITCH, SWITCH SOCKET OUTLET, DATA & NETWORK OUTLET
FUNCTIONING TEST REPORT
TEST INSTRUMENT :
MANUFACTURER :