Packaged Equipment Inspection: Item Description of Check Subcontractor

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Packaged Equipment Inspection

Tag Description: Tag No.:


P. O. No.: Inspection Classification Area/Unit:
Subcontractor: Subcontractor Owner Turnover System:
Work Package: Company Other Sub – System:
Complete the following checks in accordance with project and vendor drawings, specifications and instructions:
Item Description of Check Subcontractor Client
01 Driver unit complete and correct.
02 Transmission unit complete and correct.
03 Driven unit complete and correct.
04 Skid pipework and supports complete and correct.
05 Piping, tubing and cable connections complete and correct.
06 All valves accessible, visible and operable.
07 Instrumentation complete, correct, accessible, visible and operable.
08 Unit rotates freely (manually).
09 Provision for expansion correct.
10 Couplings, belts and guards installed correctly.
11 Platforms and ladders complete and correct.
12 Internals installation correct.
13 Internal cleanliness correct.
14 Painting, trace heating, and insulation complete and correct.
15 Cooling water system complete and correct.
16 Vent and drain system complete, correct.
17 Exhaust system complete and correct.
18 Starting system complete and correct.
19 Package enclosure and ventilation system complete and correct.
20 Fuel and combustion air systems complete and correct.
21 Air drying system complete and correct.
22 Fire and safety systems complete and correct.
23 Chemical dosing systems complete and correct.
24 Check condition of flexible piping; ensure no kinks or twists & adequate support.
25 Air intake is installed and supported as per drawings.
26 Check preservation measures are intact and effective. Skid is clean of all
contamination, trade debris, etc.
27 Check direction of rotation is in accordance with specification & clearly marked.
28 All filters are correctly installed clean and to specification. *
29 Relief valves fitted and certified. *
30 Lubricants filled and to vendor’s specification. *
31 Lube oil system complete, correct, flushed and charged. *
32 Seal oil system complete, correct, flushed and charged. *
33 Nitrogen dampers/accumulators complete, correct, and pre-charged. *
34 Hydraulic circuits complete, correct flushed and charged. *
Company
Name:
Signature:
Date: