Item Description of Check Subcontractor Client 01 All shipping stops, bracing and packaging removed. 02 Nameplate details correct and in accordance with the data sheet. Nameplate securely attached, readable not obscured. 03 Unit installed according to vendor instructions, with location and orientation correct, holding down arrangement complete and secure. 04 Supplier / vendor equipment release note available. 05 Unit free from external damaged and all paint work in good condition. 06 Where preservation materials are installed, equipment is suitably marked “PRESERVATION INSIDE”. 07 Piping, tubing and cable connections complete and correct. 08 All valves accessible, visible and operable. 09 Instrumentation complete, correct, accessible, visible and operable. 10 Relief valves fitted, tagged and certified with valid calibration date. 11 Lubricants filled and to vendor’s specification. 12 Unit rotates freely (manually). 13 Provision for expansion correct. 14 Couplings, belts and guards installed correctly.