Doors and Hatches (Offshore Facilites) Inspection

Checklist
Tag Description: Tag No.:

P. O. No.: Inspection Classification Area/Unit:

Subcontractor: Subcontractor Owner Turnover System:

Work Package: Company Other Sub – System:

Item Description of Check Subcontractor Client


01 Door / hatch identification in accordance with plot plan/
architectural GA(s).
02 All shipping stops, bracing and packaging removed.
03 Door / hatch installed according to specification in correct
location and orientation.
04 Nameplate securely attached, readable not obscured and
nameplate data conforms to the information given on data sheet.
05 Unit and all associated equipment clean and undamaged.
06 All shipped loose/knocked down items reinstalled in accordance
with specified requirements.
07 Door / hatch operates correctly.
08 Pressure relief port operates.
09 Panic bar functions.
10 Door / hatch seals in accordance with specifications and fire
rating requirements.
11 Door closer correctly adjusted.
12 Pneumatic / hydraulic systems connected / installed.
13 Door stopper installed and functioning.
14 Paint system applied according to specification and in
accordance with supplier requirements.
15 All specified adhesion tests completed and accepted.