Combined Area Acceptance

Tag Description: Tag No.:

P. O. No.: Inspection Classification Area/Unit:

Subcontractor: Subcontractor Owner Turnover System:

Work Package: Company Other Sub – System:

Item Description of Check Subcontractor Client

01 All floor gratings installed as per design drawings.


02 All handrails are complete and correctly installed as per
design drawings.
03 All ladders, complete with safety hoops and safety bars are
correctly installed as per drawings.
04 All doors and windows are installed correctly as per design
drawings and specifications.
05 All internal wall and floor finishes are correct to design
specification and free from damage.
06 All furniture and fittings including sanitary fixtures are installed
as per design drawings and free from damage.
07 All painting / passive fire protection is correct to design
drawings and free from damage.
08 All kitchen equipment is installed as per design drawings and
specifications and free from damage.

09 Area is clean and free of all debris.

Notes: