Jsa Roof
Jsa Roof
PROJECT : CADANGAN PEMBANGUNAN SKIM PERUMAHAN DI ATAS LOT PRECINT 5, BANDAR AMANJAYA, DAERAH KUALA MUDA,
WESTFIELD, SG. PETANI.
JSA No : KMCSB001
ROOF Rev B
HSE-JHA-001
4.0 Moving machinery 1. Vehicle not stop at safe area 1. Ensure proper area to stop the vehicle
into work area 2. Turn on hazard light before went off from the vehicle
2. Flying object from surrounding 1. Always aware on the surrounding condition
2. Wear proper PPE (safety helmet, dust mask, Site staff/
safety shoes) Supervisor,
Workers, Lorry
3. Traffic interaction, potential 1. Proper barricade work area Drivers
collision and crash injuries 2. Wear proper PPE (safety helmet, dust mask,
safety vest, safety shoes) for flagman
No Job description Potential Hazard / Risk Control / Recovery Measures Action By
1. Ensure ground grading should be conducted prior
5.0 Loading/ offloading1. Uneven ground
to
material to unloading material work
2. Backhoe driver should confirm ground is even and
designated area
tipper is
using backhoe stable before unloading material
3. Backhoe shall consider to offload at safe ground Site Supervisor/
Staff, workers,
Lorry driver
2. Unloading or working near edge 1. Only loading/ offloading material on even and
stable
ground
2. Assist signalman/ banksman to assists lorry
driver when offloading/ unloading work
6.0 Placing of roof 1. Wire rope, chain sling swing movement 1. Operator to be competent
trusses on roof 2. Weekly safety briefing before work start
beam structure
using crane &
install roof
trusses
Site Supervisor/
1. Wear proper PPE (safety helmet, long sleeves Staff, workers,
2. Falling from height
jacket, face mask, hand gloves, safety shoes, lorry driver
Safety harness)
2. Weekly safety briefing before work start
3. Exposed to extreme heat weather 1. Sufficient drinking water
2. Frequent and enough rest when hot weather
No Job description Potential Hazard / Risk Control / Recovery Measures Action By
7.0 Install roof 1. Falling from height 1. Wear proper PPE (safety helmet, long sleeves
braces jacket, face mask, hand gloves, safety shoes,
Safety harness)
2. Weekly safety briefing before work start Site Supervisor/
Staff, workers,
2. Exposed to extreme heat weather 1. Sufficient drinking water
machinery
2. Frequent and enough rest when hot weather operator
3. Pinch point 1. Ensure workers using proper PPE (hand gloves)
2. Using proper technique when install braces
8.0 Install roof 1. Falling from height 1. Wear proper PPE (safety helmet, long sleeves
tiles jacket, face mask, hand gloves, safety shoes, Site Supervisor/
Safety harness)
2. Weekly safety briefing before work start Staff, workers
2. Exposed to extreme heat weather 1. Sufficient drinking water
2. Frequent and enough rest when hot weather
9.0 Fix timber with 1. Falling from height 1. Wear proper PPE (safety helmet, long sleeves
mild steel bolts, jacket, face mask, hand gloves, safety shoes,
nail & gusset plate Safety harness)
2. Weekly safety briefing before work start Site Supervisor/
2. Exposed to extreme heat weather 1. Sufficient drinking water Staff, workers,
2. Frequent and enough rest when hot weather machinery
operator
3. Pinch point 1. Ensure workers using proper PPE (hand gloves)
2. Using proper technique when fix timber
Job description Potential Hazard / Risk Control / Recovery Measures Action By
### Housekeeping 1. Ergonomic (Repetative work) 1. Ensure using proper technique for manual handling
2. Not carrying overload loads
Site Supervisor/
2. Bad material arrangement and 1. Designated dump/dispose area Staff, workers
housekeeping