WORK SAMPLING IN THE MASK PRODUCTION PROCESS

Our group has do calculation observation of work samples ( Work Sampling ) in the
clothing production process from a shop “ blinglusten ”
which is done with use number random for know When time si worker operate activity work
Good That activity direct (which is done to machine or equipment production ), activities No
directly ( tool maintenance before used , activity planning ) and activities walk (travel / move
pacing ) with differentiate When time si worker productive and Non Productive To use get
the results of sampling, data uniformity , data adequacy , and calculations time raw , and we
do measurement time Where worker the done for 10 hours ie starting at 08.00 until 15.00.
Data capture highlight an operator in charge of the mask coloring process . The following
work samples done with unit 10 minutes long so that got data processing as following :
 Working hours / day : 7 Hours (08.00 – 15.00)
 Length Unit : 10 minutes
 Random number : ( 7 x 60 )/10 = 42 ( Random number no can more of 48)

So that processed in the table following :

No Activity
Number Productive Non
Random Calculation Time Productive
Take
1 2 (2x10)/60=0.333333333 8.00+0.333333333=8.333333 Material
Make
2 4 (4x10)/60=0.666666667 8.00+0.666666667=8.666667 pattern
Fill in fluid
dye to
3 6 (6x10)/60=1 8.00+1=9 bottle
Mask
4 8 (8x10)/60=1.333333333 8.00+1.333333333=9.333333 coloring
Fill in
return
fluid dye
5 10 (10x10)/60=1.666666667 8.00+1.666666667=9.666667 to bottle
Mask
6 13 (13x10)/60=2.166666667 8.00+2.166666667=10.16667 Coloring
Washing
7 15 (15x10)/60=2.5 8.00+2.5=10.5 masks
Mask
8 18 (18x10)/60=3 8.00+3=11 Sunbathing
9 20 (20x10)/60=3.333333333 8.00+3.333333333=11.33333 Wait dry
10 23 (23x10)/60=3.833333333 8.00+3.833333333=11.83333 Wait dry
11 24 (24x10)/60=4 8.00+4=12 Wait dry
Wait dry
12 25 (25x10)/60=4.166666667 8.00+4.166666667=12.16667
13 27 (27x10)/60=4.5 8.00+4.5=12.5 Wait dry
14 28 (28x10)/60=4.666666667 8.00+4.666666667=12.66667 Wait dry
Lifting
15 30 (30x10)/60=5 8.00+5=13 Mask
Mask
16 33 (33x10)/60=5.5 8.00+5.5=13.5 ironing
Mask
17 37 (37x10)/60=6.166666667 8.00+6.166666667=14.16667 ironing
Mask
Ordering
18 38 (38x10)/60=6.333333333 8.00+6.333333333=14.33333 for for sale
Mask
Ordering
19 41 (41x10)/60=6.833333333 8.00+6.833333333=14.83333 for for sale
Mask
Ordering
20 42 (42x10)/60=7 8.00+7=15 for for sale