Sr. No.

Activity Hours Consumed


1 Floor Marking 2.5
2 Hole Making for grouting 2.5
2 Grouting of anchor bolt 2.5
3 Assembly of columns 4
4 Erection of partially assembled block 3
5 installation of balance frames 4
6 Installation of GI plates for Bin resting 3
7 Vertical Aligning 3
8 Vertical Aligning Continued 2
9 Levelling 5
10 Hex Rod Installation 2
Tightening of Balance hardware, Dimensions verification and
11 handover

Note: from Day 2, a team was involved in tightening of Hardware till entire activity, 2 manpower

Sum of Column E 164


2 gang of 2 each for hardware, Day 2 & Day 3 64
1 gang of 2 each on day 3 to install leftout component 16
244
Manpower Manhour Day Team Start Finish
2 5 Day 1 Team 1 11:00:00 AM 01:30:00 PM
2 5 Day 1 Team 1 01:30:00 PM 04:00:00 PM
2 5 Day 1 Team 1 01:30:00 PM 04:00:00 PM
8 32 Day 1 Team 2 11:00:00 AM 03:00:00 PM
12 36 Day 1 Team 1 + Team 2 03:00:00 PM 06:00:00 PM
10 40 Day 2 Team 1 + Team 2 10:00:00 AM 02:00:00 PM
2 6 Day 2 Team 1 02:00:00 PM 05:00:00 PM
4 12 Day 2 Team 2 02:00:00 PM 05:00:00 PM
4 8 Day 3 Team 1 09:00:00 AM 11:00:00 AM
3 15 Day 3 Team 2 09:00:00 AM 02:00:00 PM
Day4 02:00:00 PM 04:00:00 PM

Day 4

ctivity, 2 manpower
2 Manpower were involved in miscelaneous activity like
material movement, cutting of threaded rod etc, throughout
day

2 gang of 2 each was working on tightening of hardwares,

on Day 4 Nilkamal team had left around 4 PM