Abstract of cost of Dam safety works of Tenughat Dam under Tenughat

Dam Division,Tenughat

APPENDIX IV-A
Cost Estimates of Rehabilitation Proposal
Sl.No. Work Description Amount in Rupees Remarks

A Structural Rehabilitation Works/Estimation Part

Estimate for rooting out and removal of vegetation of


1 Tenughat Dam Upstream slope as well as Downstream ₹ 1,48,13,011.0
slope as per DSRP 2021 Recommendation,

Estimate for Rearranging disturebd Rip Rap and


2 depressed patches as per DSRP Recommendation ₹ 1,82,81,273.0
Page 30 U/S Slope(b)(ii)

Estimate for Closing down the gap in U/S Parapet wall


and providing continous parapet wall and Removal of
3
different components as per DSRP 2021
₹ 1,66,469.0
Estimate has
Recommendation Page 30 (b)U/S Slope(iii) and (iv) been prepared
and sent to
Estimate for Cleaning and Repair of longitudinal
department vide
,transverse and toe drains as per DSRP 2021
4
Recommnedation of Page 30 ( C ) D/S Slope(iv) and
₹ 3,34,59,115.0 letter number CE
WRD HAZARIBAG
(v). 103/DATED
Estimate for Removal of coffer dam in U/S of Tenu 12/02/2024
Bokaro Link Canal approach Channel and cleaning of
5
approach channel of TBLC as per Recommnedation of
₹ 39,19,483.0
DSRP 2021 from Page 26.
Estimate for Filling the good quality compact earth
,Benching and Turfing in D/S slope of Tenughat Dam
6
as per DSRP Recommnedation from Page 30 ( C )D/S
₹ 1,34,25,956.0
Slope (ii) & (iii).
Estimate for Whitewashing of Parapet wall and
7 painting of Railing as per DSRP 2021Report Page ₹ 47,72,421.0
Page 52 1.3.7
Total Amount in Rupees for estimation prepared
as per Jharkahnd SOR July 2022 ₹ 8,88,37,728.0

Structural Measures for Ensuring Hydrological


B
Safety
a Spillway
(i)The U/S face in the non-¬overflow portion be
checked minutely and cracks/holes, if any observed,
1 mapping be done for such cracks by remote operated E.O.I
vehicle (ROV) to assess the extents of damages.
Cement/polymer grouting be taken up in the U/S face.

1
(ii)All the reports, findings and video recording after
ROV mapping should be submitted to Office of the
2 E.O.I
Executive Engineer Tenughat Dam Division
Tenughat.
(iii)However, if the mapping indicates presence of
more cracks / cavities, required remedial measures
with advance technology is recommended to prevent EOI has been
prepared and
such seepages. The application of CCGM/CCGC
3 E.O.I sent to
(Cementitious Geo-synthetic Concrete
department vide
Mattress/Carpet) as per Standards of EN 13253 &
letter number CE
13254 as used in Reservoir & Dams be adopted in the
WRD HAZARIBAG
u/s face of the spillway. 1016/DATED
(iv)The cavities occurred in the piers be filled up 08/12/2023
4 E.O.I
with CC M-30 to make the surface smooth.

(v)The damaged concrete surface of glacis below all


Tenughat Dam gates or wherever necessary be made
5 good with rich cement mortar and report about this E.O.I
should be submitted to Office of the Executive
Engineer Tenughat Dam Division Tenughat.

(vi)The damage below the bottom of the deck slab


6 E.O.I
be made good with rich mortar.
(vii)The vegetation noticed over the retaining wall
7 be uprooted and removed and the cracks be made E.O.I
good using rich cement mortar.

b Gallery: Inspection and Drainage gallery. E.O.I

Necessary remedial measures with application of


synthetic Cementous Concrete
Mattress/Geo‐synthetic Cementous Concrete Carpet
1 (GCCM/GCCC) as per Standards of EN 13253 & E.O.I
13254 used in Dams, as appropriate, be adapted in the
u/s face of the dam.

Necessary chemical and physical analysis of the


2 deposited /Injected Mud be tested in the soil testing E.O.I
laboratory for reference on remedial measure.
Chemical composition of mud and presence of
organic and inorganic substance test report which
clearly comprises the cause of deposition of mud and
3 E.O.I
preventive measures against this in future should be
submitted to Office of the Executive Engineer
Tenughat Dam Division Tenughat.
The calcinations occurred over the steps and floors
need to be removed. The U/S and D/S wall surface
4 E.O.I
need to be cleaned properly such that the walls will be EOI has been
free from calcinations. prepared and
sent to
2 department vide
letter number CE
EOI has been
prepared and
Prepare sent to
the detailed report the report should comprise cause of department vide
calcination and suggest the remedial measures to letter number CE
5 E.O.I
avoid future calcination. WRD HAZARIBAG
1016/DATED
08/12/2023
The vertical drainage in inspection gallery and
6 E.O.I
foundation drainage holes are reamed and cleaned.
Chainage, Reduced levels and other necessary
information such as component specifications are to
7 be painted over the wall in each block with block E.O.I
numbers at appropriate locations in English language
with illuminating paint colour.

Finding the cause of Seepage in Galleries and on d/s


8 face of the dam and provide feasible solution of this. E.O.I

Removal of mud deposits, Presence of calcium and


other deposits from the drains inside the inspection
9 E.O.I
gallery.

In inspection gallery there are leaching from the


seepage water and deposition of lime near the seepage
10 E.O.I
of exit spots, Finding the cause of this and provide
feasible solution of this.

c Masonry/Concrete dams & Spillways

Cracking in concrete (potential causes are alkali –


aggregate reaction, thermal stresses because of heat of
hydration or temperature variations, foundation
problems). Prepare the detailed report on this and
1 E.O.I
submitted to Office of the Executive Engineer
Tenughat Dam Division Tenughat.

Repair to upstream face of masonry dams in case the


pointing is damaged, leading to increased seepage. To
2 ensure that the dam is behaving as designed based on E.O.I
instrumentation programs. EOI has been
prepared and
Periodic maintenance should be performed of all sent to
concrete surfaces to repair deteriorated areas. Repair department vide
deteriorated concrete at the earliest; it is most easily letter number CE
repaired in its initial stages. Deterioration can WRD HAZARIBAG
3 accelerate and, if left unattended, can result in serious E.O.I 1016/DATED
08/12/2023
problems or dam failure. For this prepare the report
which comprises types and causes of concrete
deterioration and use of most suitable type of
concrete.
3
Repair the Damages on spillway glacis, spillway piers,
training/divide walls, energy dissipaters, downstream
areas (probable causes are cavitation, abrasion,
4 unsymmetrical flows, unfavourable downstream E.O.I
conditions). Prepare the detailed report on this and
submitted to Office of the Executive Engineer
Tenughat Dam Division Tenughat.

d General cleaning
As already suggested, for proper operation of
spillways, sluiceways, approach channels, inlet and
outlet structures, stilling basin/ energy dissipation
arrangements, discharge conduit, dam slopes, trash
E.O.I
racks, debris control devices etc., regular and thorough
cleaning and removal of debris is necessary. Cleaning
is especially important after large floods, which tend
to send more debris into the reservoir.
EOI has been
prepared and
sent to
department vide
e Drains and Seepage letter number CE
WRD HAZARIBAG
(i)Remove debris in and around the Tenughat Dam 1016/DATED
to prevent clogging. 08/12/2023
(ii)Remove debris and repair the small drainage
channels leading to the Tenughat Dam so that water is E.O.I
properly directed and contained within the channels.
(iii)Clean algae and dirt from the Tenughat Dam
staff gauges to allow easy reading.

f Embankment Protection E.O.I


(i)Maintain fences to provide site security and to
exclude livestock from the embankments. Repair E.O.I
damaged embankment surfaces.

C Water Quality Aspects


(i) Chemical and physical analysis of reservoir
water all water tests should be done confirming IS
Code IS 3025-11 (1983): Methods of sampling and
Test of water and waste water) and IS 10500:2012 ) E.O.I
and detailed test result report should be submitted to
Office of the Executive Engineer Tenughat Dam
Division Tenughat.

D Non-structural Measures

4
Survey of Tenughat dam u/s land for acquisition and
1 E.O.I
rehabilitation problem
Periodic chemical analysis of Tenughat Dam
2 Reservoir water from different location (Quotation E.O.I
item). EOI has been
prepared and
Calibrated V notches be provided at the end of the sent to
3 drain in both sides of the river to measure seepage E.O.I department vide
discharge through the Earth dam, letter number CE
WRD HAZARIBAG
E Basic Facilities Improvement 1016/DATED
1 Maintenance of cleanliness aroud dam area, E.O.I 08/12/2023
Maintenance of Electrical items and electrification of
2 E.O.I
Tenughat Dam top road and Dam Gallery.

F Instrumentation, SCADA, Surveillance system, etc.


Recommendation regarding Instrumentation, SCADA,
1 E.O.I
Surveillance system, etc.
CCTV installation around Tenughat Dam to ensure
2 E.O.I
safety.

G Others (investigation, Design Studies, Consultancy)


1 Consultancy charges of Emergency action plan E.O.I
2 Consultancy charges of Dam Break Analysis E.O.I
3 Consultancy charges of Geotechnical Investigation E.O.I
4 Consultancy charges of Geophysical Investigation E.O.I
Consultancy charges of Stability analysis and other
5 E.O.I
studies

J.E A.E Executive Engineer


Tenughat Dam Division,Tenughat