Abstract of cost for Renovation of Tenu Bokaro Link Canal Under Tenughat Dam Division
Tenughat
S.No. Item of work Quantity Unit Rate Amount
Clearing and Grubbing road land (clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300mm removal of stumps of trees cut earlier and disposal of unserviceable material and stacking of serviceable material and stacking to be 1 used of auctioned up to a lead of 1000 meter 1.896 Hectare 88499.00 167820.65 including removal and disposal of top organic soil not exceeding 150mm in thickness)S.N.2.3 (i)A Common SOR Page 195 Part A in area of light jungle
Clearing and Grubbing road land (clearing and
grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300mm removal of stumps of trees cut earlier and disposal of unserviceable material and stacking of serviceable material and stacking to be 2 0.813 Hectare 108259.80 87982.74 used of auctioned up to a lead of 1000 meter including removal and disposal of top organic soil not exceeding 150mm in thickness)S.N.2.3 (i)B Common SOR Page 195 in area of thorny jungle
Earth work in bed clearance or desilting of canal
carrying F.S. discharge of 2 cumecs (1000 cusecs) or more in dead course of rivers etc. in ordinary 3 soil and removing the excavated earth in proper 5411.25 M3 120.61 652650.86 profile in spoils etc. with initial lead of 1.5 m as per specifications and direction of E/I.(7.1.20/ P-135 )/ WRD Part B SOR July 2022 Extra for earth work in marshy, slushy and daldal soil (vide classification of soil item-F) all complete 4 as per specification and direction of E/I.(7.1.11 P- 5411.25 M3 28.64 154978.20 133 )/ WRD SOR July 2022
Labour charge for taking out disturb boulder from
boulder pitching or rip-rap or rock toe etc .and 5 cleaning the surface and stacking the same within a 2668.72 M3 398.00 1062150.37 lead of 100M as per specification and direction of E/I. (7.7.41 P-153 )/WRD SOR July 2022 Supply of Boulder size 300mm (add 14.95%) M 6 018 page 80 common part A july 2022) 444.79 M3 517.26 230070.31
Labour charge for pitching on apron slope of bank
with stone boulder duly packed (uncrated) 7 complete job (material within 150M and all lifts as 3113.51 M3 968.17 3014403.20 per specification and direction of E/I.(7.7.18 P- 151)/ WRD SOR july 2022
Chapter 1A Abstract of cost of Renovation of Tenu Bokaro Link Canal Page 1
Supply of Fine sand at quarry (M-002/page 8 778.38 M3 451.75 351631.59 33/WRD 2022)(10 CP and 4.95% OHC)
Labor for laying fine filter sand or coarse dry
graded filter either of Jhama khoa or stone matel or stone chips under brick pithcing or boulder pitching 9 778.38 M3 398.00 309793.86 in slope and approach including light ramming etc. all compelete as per specification and direction of E/I.(7.7.13/WRD 2022/page 151)
Providing compacted 150 mm thick sand filter of
required FM as per design on side slopes and in bed of canal with coarse sand including cost of 10 water ramming laveling and dressing etc all 8081.28 M2 208.60 1685755.01 complete ase per specification and direction of E/I.(7.2.1/A/ P-140)/WRD SOR july 2022
with nominal mix of (1:2:4) with well graded stone chips (20mm abd down) and coarse sand of approved quality of requisite F.M. (2.5 to 3.0) in side and bottom curved portion of the canal in 12 1054.59 M3 8289.57 8742097.63 panel with construction joined including cost of form work and its removal curing, royalty and all other taxes, complete job as per specification and direction of E/I. (7.2.19.1 page 142 )/wrd SOR July 2022 Providing rough dressed random rubble stone masonary in cement mortar (1:4) in super structure with approved quality of course sand of requisite F.M.(2.5 to 3.0) washed and screened with raking out joints to 12 mm depth, curing scaffolding and 13 312.66 M3 2906.96 908888.09 its removal wherever required including royalty and all etc. complete job as per specification and direction of E/I. (Common SOR /page 204/5.2.31 july 2022)
Extra for each subsequent earth work of 1.5 m after
initial lift of 1.00 m all complete as per specification and direction of E/I.(6.1.18 P-120 )/ 5411.25 14 M3 79.62 430843.73 WRD SOR july 2022 (6.00 nos. lift = 6.00x13.27)
Earth work in filling in canal banks canal discharge
upto 28 cumecs as well as special repairs of canal 15 banks in ordinary soil with initial lead of 15 m and 4228.26 M3 127.93 540921.81 lift is 1.50 meter as per E/I.(7.1.25 Page-135 WRD SOR july 2022)
Chapter 1A Abstract of cost of Renovation of Tenu Bokaro Link Canal Page 2
Fine dressing of the canal banks or embankment and turfing with 75 MM thick grass sods ,obtained 16 withing lead of 150 m including the cost of 15.06 % M2 1502.86 22626.70 watering and grass surface as per E/I.(7.1.42.1 WRD SOR)/page 137/sor july 2022
Dismantling M15 of structure (dismantling of
existing structures like culverts,bridge,retaining walls and other structures comprising of cement 17 20.62 M3 652.80 13459.43 concrete …..do….. common sor part A/ page 196 /july 2022/2.4(i)(I) b disposal lead = 1000 m 18 Carriage of Cement 394.77 MT 530.50 209423.66 Carriage of Sand 19 1559.83 M3 212.65 331698.75 Carriage of Chips 20 949.13 M3 547.45 519601.77 Carriage of Boulder 21 757.45 M3 547.45 414663.75
Total =(A) Total 20133275.85
(B)=18% GST ON (A)= 18 % GST 3623989.65
Sub total = ( C ) = (A) +(B) = Sub total 23757265.50
Labor Cess 1% of ( C ) = (D) Add 1% L.C. 237572.66
Contigency 1% of ( C ) = ( E ) Add 1% CNC 237572.66
Grand Total =(F) = ( C ) +(D)+ ( E ) Grand total 24232410.81
Say= Rs. 2,42,32,411=00
Assistant Executive Engineer
Junior Engineer Engineer TenughatDam Division
Chapter 1A Abstract of cost of Renovation of Tenu Bokaro Link Canal Page 3