CA NO. CE (AF) G/JAM/OLD/04 OF 2022-2023 SERIAL PAGE NO.

248

PARTICULAR SPECIFICATIONS (CONTD….)

YARD STICK
YARD STICK PERCENTAGES
(FOR PAYMENT OF RARS, UNDER CONDITION 64 OF (IAFW-2249))
SCH ‘A’ PART-I, ITEM NO-01: BRIEFING ROOM

Sr Percentage
Stage of Works Recommended
no.
1 Stage - 1 : Upto Plinth Level
Surface dressing, excavation and earthwork, PCC, RCC M-30 in 24.00%
foundation and in columns including steel reinforcement and form
work, PCC block masonry, returning filling in foundation, back filling
under floors including ATT etc. complete upto plinth level.

2 Stage - 2 : Plinth Level to GF Lintel/ Tie Level


RCC M-30 in columns including steel reinforcement and form work, 12.50%
PCC block masonry, RCC M-30 in GF Lintel and Chajjah including
steel reinforcement and form work etc. complete from plinth level to
GF Lintel/ Tie Level.
3 Stage - 3 : GF Lintel/ Tie Level to GF Slab Level
RCC M-30 in columns including steel reinforcement and form work, 32.00%
PCC block masonry, RCC M-30 in GF Slab Beams and GF Slab,
RCC Fascia/ Parapet including steel reinforcement and form work etc.
complete from GF Lintel/ Tie Level to GF Slab Level.
4 Stage - 4 : Plaster Work
Plaster to internal surfaces of walls, ceiling and external surfaces of 5.00%
walls, etc. complete.

5 Stage - 5 : Joinery
Door frames, door shutters, windows and ventilators, PVC door frame 5.50%
and shutter etc. including iron mongery, GRC moulding, False ceiling
etc. complete.
6 Stage - 6 : Surface Finishes
Painting work for newly plastered internal, external and ceiling 2.00%
surfaces complete.
7 Stage - 7 : Flooring
PCC flooring, sub base to floors, vitrified tiles, , ceramic tiles, Granite, 7.00%
kota stone work, including skirting/ dado to floor etc. complete.
8 Stage - 8 : Plinth Protection to building
PCC 1:3:6 type C1 plinth protection to building, hard core etc. 0.50%
complete.

9 Stage - 9 : Roof Treatment


Roof treatment complete. 3.00%

10 Stage - 10 : Sanitary Fixtures


Sanitary items, fixtures etc. complete. 3.00%

11 Stage - 11 : Misc Items


Site Clearance, and left out Items Etc. 5.50%
Total: 100.00%
CA NO. CE (AF) G/JAM/OLD/04 OF 2022-2023 SERIAL PAGE NO. 249

PARTICULAR SPECIFICATIONS (CONTD….)

YARD STICK
YARD STICK PERCENTAGES
(FOR PAYMENT OF RARS, UNDER CONDITION 64 OF (IAFW-2249))
SCH ‘A’ PART-I, ITEM NO-02: AIR CREW REST ROOM

Sr Percentage
Stage of Works Recommended
no.
1 Stage - 1 : Upto Plinth Level
Surface dressing, excavation and earthwork, PCC, RCC M-30 in 22.00%
foundation and in columns including steel reinforcement and form
work, PCC block masonry, returning filling in foundation, back filling
under floors including ATT etc. complete upto plinth level.
2 Stage - 2 : Plinth Level to GF Lintel/ Tie Level
RCC M-30 in columns including steel reinforcement and form work, 12.00%
PCC block masonry, RCC M-30 in GF Lintel and Chajjah including
steel reinforcement and form work etc. complete from plinth level to
GF Lintel/ Tie Level.
3 Stage - 3 : GF Lintel/ Tie Level to GF Slab Level
RCC M-30 in columns including steel reinforcement and form work, 32.00%
PCC block masonry, RCC M-30 in GF Slab Beams and GF Slab,
RCC Fascia/ Parapet including steel reinforcement and form work etc.
complete from GF Lintel/ Tie Level to GF Slab Level.
4 Stage - 4 : Plaster Work
Plaster to internal surfaces of walls, ceiling and external surfaces of 5.50%
walls, etc. complete.
5 Stage - 5 : Joinery
Door frames, door shutters, windows and ventilators, PVC door frame 8.50%
and shutter etc. including iron mongery, GRC moulding, False ceiling
etc. complete.
6 Stage - 6 : Surface Finishes
Painting work for newly plastered internal, external and ceiling 3.00%
surfaces complete.
7 Stage - 7 : Flooring
PCC flooring, sub base to floors, vitrified tiles, , ceramic tiles, Granite, 6.00%
kota stone work, including skirting/ dado to floor etc. complete.

8 Stage - 8 : Plinth Protection to building


PCC 1:3:6 type C1 plinth protection to building, hard core etc. 0.50%
complete.

9 Stage - 9 : Roof Treatment


Roof treatment complete. 2.50%
10 Stage - 10 : Sanitary Fixtures
Sanitary items, fixtures etc. complete. 3.00%
11 Stage - 11 : Misc Items
Site Clearance, and left out Items Etc. 5.00%
Total: 100.00%

AAD (Contracts)
(Signature of Contractor) For Accepting Officer