RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.

COMPANY PROFILE
SAUDI ARABIA

WWW.RLCO.COM.SA
ORGANIZATION SRTUCTURE

INTEGRATED LIGHTING
COMPANY (ILC)

GENERAL MANAGER
GM

BUSINESS PRODUCTION ADMIN


SALES ACCOUNTING
DEVELOPMENT DEPARTMENT HR

CLIENTS SALES PRODUCTION


DEVELOPMENT ACTIVITIES LINE

IT
PRESCRIPTION ASSEMBLY
ACTIVITIES DEPARTMENT

PARTNERS FABRICATION
DEVELOPMENT DEPARTMENT

PAINT
TECHNICAL DEPARTMENT
SUPPORT

PURCHASES
ABOUT US
Since its establishment in 2008 , under the name (Al Noor Al Hadi
Energy Company Factory) until 2017, as this year witnesses our
development and the launch of our new identity and brand (Renewable
Lighting Factory – RLCO ) Our activity focused on the manufacture of
outdoor lighting - street lighting poles - power transmission poles -
decorative columns - cosmetic poles - spotlights - Islamic lanterns -
Bollard - Up Light - wall lighting and Smart light .

And we raised the level of industry and production lines by operating


production lines for smart poles, solar energy poles and LED lights,
and here we are today putting us a mission footprint in the field of
lighting industry in various parts of the Kingdom by maintaining a high
level of quality for our products and our service and achieving our
commitment to our customers, Quality is the permanent and
continuous slogan of our factory, and punctuality and credibility at
work are characteristics that cannot be changed .

Our factory is one of the leading factories in the field of outdoor


lighting, with an experience equivalent to 13 years of experience in the
field of mega projects in the local markets through a broad base of
customers throughout the Kingdom of Saudi Arabia, the Gulf countries
and Egypt .

The outdoor lighting activity supports a department specialized in


product design and development, which provides solutions to
customer requirements using the latest programs and systems,
starting from the stage of investments and design, to supplying
products to customers, in addition to after-sales services .

The Consultancy and Design Department also conducts field tests to


assess the efficiency and performance of products and the optimal use
of lanterns, lights, and poles in order to reach the highest levels of
quality and production .

The modern design and manufacturing capabilities of factory plant


allow for the production of a huge number of products that meet the
needs of all customers .

With this industrial structure and smart possible technology, the


factory guarantees that our products comply with local and
international specifications and standards and contribute to the
development of the national economy .

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
VISION:

TO GLOBAL MARKETS
WE PROMOTE THE LOCAL INDUSTRY
Our vision is to provide high quality standards and standards
in the manufacture of lighting poles

MISSION:
Our mission is to develop the lighting poles industry, and
to launch the smart poles industry in the Kingdom and
the Gulf countries

RLCO IN NUMBERS
The expected production capacity of RLCO in 2021

40.000.0 OCTAGONAL LIGHTING POLE


20.000.0 CONICAL LIGHTING POLE
20.000.0 LED LIGHTING FIXTURE
7000.0 DECORATIVE LIGHTING POLE
2000.0 SMART LIGHTING POLES
500.0 HIGH MAST LIGHTING POLE
500.0 SOLAR LIGHTING POLES

RLCO Timeline
Al-Nour Al-Hadi al Noor Al Hadi Adding a new
Corporation to Power Company production line,
import lighting Factory smart lighting poles

2015 2020
2008 2021
2010 2017
Our start
Al Noor Al Hadi Renewable Lighting Start production.
Establishment for Factory for Industry rlco-LED lighting
Lighting Poles fixture
rlco
WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
OUR PARTNERS
Lighting Design requires architecturally creative Lamp posts
and bollards, sophisticated tunnel solutions, smart roadway
systems, energy efficient LED luminaires, professional
stadium lighting, highly elegant garden lighting, innovative
down light development, etc. RLCO will be offering it all you.
Positively and sustainably RLCO Progressive Lighting is
growing and leading in the local and international market by
supplying, exclusively from leading partners from all over the
world:

USA UAE PRC EGYPT

GERMANY ITALY TURKEY CANADA

POLAND BULGARIA

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
OUR CLIENTS General Authority for Jubail and Yanbu
‫الهيئة العامه للجبيل وينبع‬

NEOM
General Authority of Civil Aviation
‫الهيئة العامة للطيران المدني‬
Ministry of Interior
‫وزارة الداخلية‬
Ministry of Defense
‫وزارة الدفاع‬
Royal Air Force
‫القوات الجوية الملكية‬
Saudi Armed Forces
‫القوات المسلحة السعودية‬
special forces
‫القوات الخاصة‬
Ministry of Finance
‫وزارة المالية‬
Ministry of Health
‫وزارة الصحة‬
Ministry of housing
‫وزارة االسكان‬
Ministry of education
‫وزارة التعليم‬
Ministry of Justice
‫وزارة العدل‬

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
OUR CLIENTS Ministry of Social Affairs
‫وزارة الشئون اإلجتماعية‬
Ministry of Environment, Water and Agriculture
‫وزارة البيئة و المياة و الزراعة‬
Ministry of Municipal and Rural Affairs
‫وزارة الشئون البلدية و القروية‬
AL-Qassim Municipality
‫أمانة القصيم‬
Municipality AL-Taif
‫امانة الطائف‬
Municipality AL-Ahsa
‫امانة األحساء‬
Hail Municipality
‫امانة حائل‬
AL-Jouf Municipality
‫امانة الجوف‬
Municipality AL-Baha
‫امانة الباحة‬
Medina Municipality
‫امانة المدينة المنورة‬
Riyadh Municipality
‫أمانة الرياض‬
Saudi Customs
‫الجمارك السعودية‬
Saudi Authority for Industrial Cities and Technology zones
‫الهيئة السعودية للمدن الصناعية‬

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
OUR CLIENTS The Public Institution for Social Security
‫الموسسة العامة للتأمينات اإلجتماعية‬
General Auditing Bureau
‫ديوان المراقبة العامة‬
The General Authority for Ports, Jizan Port
‫الهيئة العامة للموانئ ميناء جازان‬
Public Pension Agency
‫الموسسة العامة للتقاعد‬
King Abdullah bin Abdulaziz University for Science and Technology
‫جامعة الملك عبدهللا بن عبدالعزيز للعلوم و التكنلوجيا‬

King Saud University


‫جامعة الملك سعود‬
King Salman bin Abdulaziz University
‫جامعة الملك سلمان بن عبد العزيز‬
Shaqra University
‫جامعة شقراء‬
Majmaah University
‫جامعة المجمعة‬
Al Qassaim university
‫جامعة القصيم‬
Taibah University
‫جامعة طيبة‬
Hael University
‫جامعة حائل‬

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
OUR CLIENTS Jazan University
‫جامعة جازان‬
Taif University
‫جامعة الطائف‬
Northern Border University
‫جامعة الحدود الشمالية‬
Aljouf University
‫جامعة الجوف‬
AL-Baha University
‫جامعة الباحة‬
Tabouk University
‫جامعة تبوك‬
Najran University
‫جامعة نجران‬
Prince Satatam bin Abdulaziz University
‫جامعة األمير سطام بن عبدالعزيز‬

Municipality AL-Fawarah
‫بلدية الفوارة‬

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
NTRODUCTION // PRODUCTION LINES

OUR PRODUCTION LINES

CNC PRESS BRAKE NO.1 CNC PRESS BRAKE NO.2

TRAPEZIUM CUTTING L.P WELDING MACHINE CNC PLASMA CUTING

H.M WELDING MACHINE ELECTROSTATIC PAINT OVEN CNC ELECTROSTATIC PAINT OVEN
FOR LIGHTING FICTURES

DIA - CASTING INJECTION MACHINE GLADING MACHEIN

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
NTRODUCTION // PRODUCTION LINES

OUR PRODUCTION LINES

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
NTRODUCTION // PRODUCTION LINES

OUR PRODUCTION LINES

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
NTRODUCTION // OUR PROJECTS

overview at some of our projects

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
NTRODUCTION // OUR PROJECTS

overview at some of our projects

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
NTRODUCTION // OUR PROJECTS

overview at some of our projects

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
NTRODUCTION // OUR PROJECTS

solar lighting pole

WWW.RLCO.COM.SA
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
‫اﺳﻢ اﻟﻤﻨﺸﺄة‪ :‬ﺷﺮﻛﺔ ﻣﺼﻨﻊ اﻻﻧﺎرة اﻟﻤﺘﺠﺪدة ﻟﻠﺼﻨﺎﻋﺔ ﺗﺎرﻳﺦ اﻹﺻﺪار‪ 26-02-2021 :‬رﻗﻢ اﻟﺸﻬﺎدة‪2110128528 :‬‬

‫اﻟﺮﻗﻢ اﻟﻮﻃﻨﻲ‪7003652901 :‬‬ ‫اﻟﺴﺠﻞ اﻟﺘﺠﺎري‪1010464201 :‬‬

‫ﺗﺸﻬﺪ اﻟﻬﻴﺌﺔ اﻟﻌﺎﻣﺔ ﻟﻠﻤﻨﺸﺂت اﻟﺼﻐﻴﺮة واﻟﻤﺘﻮﺳﻄﺔ "ﻣﻨﺸﺂت" ﺑﺄن اﻟﻤﻨﺸﺄة اﻟﻤﺬﻛﻮرة أﻋﻼہ ﺗﻨﺪرج‬
‫وﻓﻘﺎ ﻟﻠﺘﻌﺮﻳﻒ اﻟﻤﻌﺘﻤﺪ ﻟﺪى "ﻣﻨﺸﺂت"‬
‫ﻣﻦ ﺿﻤﻦ اﻟﻤﻨﺸﺂت اﻟﺼﻐﻴﺮة واﻟﻤﺘﻮﺳﻄﺔ ً‬

‫ﻳﺘﻢ اﻟﺘﺤﻘﻖ ﻣﻦ اﻟﺸﻬﺎدة ﻣﻦ ﺧﻼل ﻣﻮﻗﻊ ﻣﻨﺸﺂت‬

‫‪https://profile.monshaat.gov.sa/validate‬‬

‫ﺗﻌﺪ ﻫﺬہ اﻟﺸﻬﺎدة ﻣﻦ اﻟﻮﺛﺎﺋﻖ اﻟﺤﻜﻮﻣﻴﺔ اﻟﺮﺳﻤﻴﺔ‪ ،‬وﻳﺤﻈﺮ ﻗﻄﻌﻴًﺎ ﺗﻘﻠﻴﺪﻫﺎ أو ادﺧﺎل أي ﺗﻌﺪﻳﻼت ﻋﻠﻴﻬﺎ‪ ،‬ﻛﻤﺎ ﺗﻌﺮض ﺻﺎﺣﺒﻬﺎ إﱃ اﻟﻤﻼﺣﻘﺔ اﻟﻨﻈﺎﻣﻴﺔ أﻣﺎم اﻟﺠﻬﺎت اﻟﻤﺨﺘﺼﺔ‪ ،‬وﺗﻌﺘﺒﺮ ﻻﻏﻴﺔ ﻓﻲ ﺣﺎل‬
‫وﺟﻮد أي ﻛﺸﻂ أو ﺗﻌﺪﻳﻞ‪ ،‬دون أدﻧﻰ ﻣﺴﺆوﻟﻴﺔ ﻋﲆ ﻣﻨﺸﺂت وﻣﺎ ﻳﺘﺮﺗﺐ ﻣﻦ أﺛﺮ ﻋﻠﻴﻬﺎ‪ .‬وﺗﻌﺘﺒﺮ ﻣﻨﺸﺂت ﻏﻴﺮ ﻣﺴﺆوﻟﺔ ﻋﻦ أي آﺛﺎر أﺧﺮى ﻣﺘﺮﺗﺒﺔ ﻋﲆ اﻟﺸﻬﺎدة أو أي ﻋﻤﻠﻴﺔ ﺗﻌﺪﻳﻞ أو ﺗﺰوﻳﺮ ﻋﲆ‬
‫اﻟﺒﻴﺎﻧﺎت اﻟﻮاردة ﻓﻴﻬﺎ‬
‫‪١٤٤٣/٠٦/١٧‬‬ ‫ﺍﻟﺘﺎﺭﻳﺦ‬
‫‪٢٠/٠١/٢٠٢٢‬‬ ‫ﺍﻟﻤﻮﺍﻓﻖ‬
‫ﺭﻣﺰ ﺍﻟﺸﻬﺎﺩﺓ ‪٤٣٥٧٣٩٩٤‬‬

‫ﺷﻬﺎﺩﺓ‬

‫ﻣﺼﻨﻊ ﺍﻻﻧﺎﺭﺓ ﺍﻟﻤﺘﺠﺪﺩﺓ ﻟﻠﺼﻨﺎﻋﺔ‬ ‫ﺇﺳﻢ ﺍﻟﻤﻨﺸﺄﺓ ‪:‬‬

‫ﺍﻟﺮﻳﺎﺽ‬
‫‪٠‬‬
‫‪٥٥٧٣٨٤٢٠٠‬‬ ‫ﺭﻗﻢ ﺍﻹﺷﺘﺮﺍﻙ ‪:‬‬
‫ﻣﺼﺪﺭﻩ ‪ :‬ﺍﻟﺮﻳﺎﺽ‬ ‫ﺭﻗﻢ ﺍﻟﺴﺠﻞ ﺍﻟﺘﺠﺎﺭﻱ‪١٠١٠٤٦٤٢٠١ :‬‬

‫ﻛﺘﺎﺑﺔ‬ ‫ﺭﻗﻤﺎ‬
‫ﺍﺣﺪ ﻋﺸﺮﻩ ﻣﺸﺘﺮﻛﺎ‬ ‫‪١١‬‬ ‫ﻋﺪﺩ ﺍﻟﻤﺸﺘﺮﻛﻴﻦ ﺍﻟﺴﻌﻮﺩﻳﻴﻦ‬
‫ﻋﺸﺮﻭﻥ ﻣﺸﺘﺮﻛﺎ‬ ‫‪٢٠‬‬ ‫ﻋﺪﺩ ﺍﻟﻤﺸﺘﺮﻛﻴﻦ ﻏﻴﺮ ﺍﻟﺴﻌﻮﺩﻳﻴﻦ‬
‫ﻭﺍﺣﺪ ﻭ ﺛﻼﺛﻮﻥ ﻣﺸﺘﺮﻛﺎ‬ ‫‪٣١‬‬ ‫ﺍﻟﻤﺠﻤﻮﻉ‬

‫ﺗﺸﻬﺪ ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﻠﺘﺄﻣﻴﻨﺎﺕ ﺍﻻﺟﺘﻤﺎﻋﻴﺔ ﺑﺄﻥ ﺍﻟﻤﻨﺸﺄﺓ ﺍﻟﻤﺬﻛﻮﺭﺓ ﺃﻋﻼﻩ ﻣﻨﺘﻈﻤﺔ ﻓﻲ ﺍﻟﻮﻗﺖ ﺍﻟﺤﺎﻟﻲ ﺑﺴﺪﺍﺩ ﻣﺪﻳﻮﻧﻴﺘﻬﺎ ﻋﻠﻰ ﺃﻗﺴﺎﻁ ﺷﻬﺮﻳﺔ‬
‫ﻭﻓﻖ ﺍﻟﺒﻴﺎﻧﺎﺕ ﺍﻟﻤﻘﺪﻣﺔ ﻣﻨﻬﺎ ﺣﺘﻰ ﺗﺎﺭﻳﺦ ﺇﺻﺪﺍﺭ ﺍﻟﺸﻬﺎﺩﺓ ﻭﺍﻟﺘﻲ ﺗﻢ ﻣﻨﺤﻬﺎ ﻟﺘﻘﺪﻳﻤﻬﺎ ﻷﻳﺔ ﺟﻬﺔ ﺗﻄﻠﺒﻬﺎ‪ ،‬ﻭﻫﻲ ﺻﺎﻟﺤﺔ ﻟﺠﻤﻴﻊ ﺍﻷﻏﺮﺍﺽ ﺍﻟﺘﻲ‬
‫ﻧﺺ ﻋﻠﻴﻬﺎ ﻧﻈﺎﻡ ﺍﻟﺘﺄﻣﻴﻨﺎﺕ ﺍﻻﺟﺘﻤﺎﻋﻴﺔ ﻓﻲ ﺍﻟﻤﺎﺩﺓ )‪ (١٩/٦‬ﻣﻨﻪ‪.‬‬
‫ﻫﺬﻩ ﺍﻟﺸﻬﺎﺩﺓ ﺳﺎﺭﻳﺔ ﺍﻟﻤﻔﻌﻮﻝ ﺣﺘﻰ ‪ ١٤٤٣/٠٧/١٧‬ﻫـ‪.‬‬

‫) ﺍﻟﺸﻬﺎﺩﺓ ﻣﻌﺘﻤﺪﺓ ﻣﻦ ﺻﺎﺣﺐ ﺍﻟﺼﻼﺣﻴﺔ ﻭﻻ ﺗﺤﺘﺎﺝ ﺇﻟﻰ ﺗﻮﻗﻴﻊ ﺃﻭ ﺧﺘﻢ (‬

‫ﺗﻌﺪ ﻫﺬﻩ ﺍﻟﺸﻬﺎﺩﺓ ﻣﻦ ﺍﻟﻮﺛﺎﺋﻖ ﺍﻻﻟﻜﺘﺮﻭﻧﻴﺔ ﺍﻟﺤﻜﻮﻣﻴﺔ ﺍﻟﺮﺳﻤﻴﺔ ‪ ،‬ﻭﻳﺤﻈﺮ ﻗﻄﻌﻴﺎ ﺗﻘﻠﻴﺪﻫﺎ ﺃﻭ ﺇﺩﺧﺎﻝ ﺃﻱ ﺗﻌﺪﻳﻼﺕ ﻋﻠﻴﻬﺎ ﺳﻮﺍﺀ ﺑﺎﻹﺿﺎﻓﺔ ﺃﻭ ﺍﻟﺤﺬﻑ‬
‫ﺃﻭ ﺍﻟﺘﻐﻴﻴﺮ ﻓﻲ ﺑﻴﺎﻧﺎﺗﻬﺎ ﺃﻭ ﻏﻴﺮ ﺫﻟﻚ ﻣﻦ ﺍﻧﻮﺍﻉ ﺍﻟﺘﻌﺪﻳﻞ ‪ ،‬ﻭﺗﻌﺪ ﺍﻟﺸﻬﺎﺩﺓ ﻻﻏﻴﺔ ﺇﺫﺍ ﺷﺎﺑﻬﺎ ﺷﻲﺀ ﻣﻦ ﺫﻟﻚ ‪ ،‬ﻛﻤﺎ ﺗﻌﺮﺽ ﺻﺎﺣﺒﻬﺎ ﻟﻠﻤﻼﺣﻘﺔ ﺍﻟﻨﻈﺎﻣﻴﺔ‬
‫ﺃﻣﺎﻡ ﺍﻟﺠﻬﺎﺕ ﺍﻟﻤﺨﺘﺼﺔ ﺑﺎﻹﺿﺎﻓﺔ ﺇﻟﻰ ﻣﺎﻳﻔﺮﺿﻪ ﻧﻈﺎﻡ ﺍﻟﺘﺄﻣﻴﻨﺎﺕ ﺍﻻﺟﺘﻤﺎﻋﻴﺔ ﻣﻦ ﻋﻘﻮﺑﺎﺕ ‪ ،‬ﻭﻻﻳﺠﻮﺯ ﺗﺪﺍﻭﻝ ﺍﻟﺸﻬﺎﺩﺓ ﺇﻻ ﻓﻲ ﺍﻷﻏﺮﺍﺽ ﺍﻟﺘﻲ‬
‫ﺃﺻﺪﺭﺕ ﻷﺟﻠﻬﺎ ﻭﻓﻘﺎ ﻷﺣﻜﺎﻡ ﻧﻈﺎﻡ ﺍﻟﺘﺄﻣﻴﻨﺎﺕ ﺍﻻﺟﺘﻤﺎﻋﻴﺔ ‪ ،‬ﻭﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﻠﺘﺄﻣﻴﻨﺎﺕ ﺍﻻﺟﺘﻤﺎﻋﻴﺔ ﻏﻴﺮ ﻣﺴﺆﻭﻟﻪ ﻋﻦ ﺃﻱ ﺁﺛﺎﺭ ﺃﺧﺮﻯ ﻣﺘﺮﺗﺒﺔ‬
‫ﻗﺒﻞ ﺍﻟﻐﻴﺮ ﻋﻦ ﺍﻟﺸﻬﺎﺩﺓ ﻭﻏﻴﺮ ﻣﺴﺆﻭﻟﺔ ﻋﻦ ﺃﻱ ﻋﻤﻠﻴﺔ ﺗﺰﻭﻳﺮ ﺃﻭ ﺗﻌﺪﻳﻞ ﺗﺘﻢ ﻋﻠﻰ ﺍﻟﺒﻴﺎﻧﺎﺕ ﺍﻟﻮﺍﺭﺩﺓ ﻓﻴﻬﺎ ‪.‬‬
2/13/22, 3:23 PM Aconex

Bechtel Document Management Final (WF-023834) 10-661160-1100001342-MAG-ELE-MAT-0000… 2:56 PM


BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-044878

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-044878 BEC-WTRAN-044878

Final (WF-023834) 10-661160-1100001342-MAG-ELE-MAT-000004_WO 04-Material Submittal


for Foundation and Battery Chamber from RLCO -RD 16

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (2) NEOM ETSD Document Control - NEOM - Engineering & Technical Services Dept (+1 more...)

Sent Sunday, 13 February 2022 2:56:35 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

10-661160-1100001342-MAG- WO 04-Material Submittal for Foundation and Battery A - Work May


02 03/02/2022
ELE-CRS-000009 Chamber from RLCO -RD 16_CRS Proceed

10-661160-1100001342-MAG- WO 04-Material Submittal for Foundation and Battery A - Work May


02 03/02/2022
ELE-MAT-000004 Chamber from RLCO -RD 16 Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "10-661160-1100001342-MAG-ELE-MAT-000004_WO 04-Material Submittal for Foundation and Battery Chamber
from RLCO -RD 16" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

10-661160-1100001342-MAG-
EPM DCC B Document Management A - Work May Proceed
ELE-CRS-000009

10-661160-1100001342-MAG-
EPM DCC B Document Management A - Work May Proceed
ELE-MAT-000004

https://ksa1.aconex.com/Logon 1/1
2/13/22, 3:32 PM Aconex

Bechtel Document Management Final (WF-023836) 10-661120-1100001342-MAG-CIV-MAT-0000… 2:42 PM


BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-044870

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-044870 BEC-WTRAN-044870

Final (WF-023836) 10-661120-1100001342-MAG-CIV-MAT-000026_WO 03-Material Submittal


for Foundation and Battery Chamber from RLCO -RD12

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (2) NEOM ETSD Document Control - NEOM - Engineering & Technical Services Dept (+1 more...)

Sent Sunday, 13 February 2022 2:42:26 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

10-661120-1100001342-MAG- WO 03-Material Submittal for Foundation and Battery A - Work May


02 03/02/2022
CIV-CRS-000044 Chamber from RLCO -RD12_CRS Proceed

10-661120-1100001342-MAG- WO 03-Material Submittal for Foundation and Battery A - Work May


02 03/02/2022
CIV-MAT-000026 Chamber from RLCO -RD12 Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "10-661120-1100001342-MAG-CIV-MAT-000026_WO 03-Material Submittal for Foundation and Battery Chamber
from RLCO -RD12" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

10-661120-1100001342-MAG-
EPM DCC B Document Management A - Work May Proceed
CIV-CRS-000044

10-661120-1100001342-MAG-
EPM DCC B Document Management A - Work May Proceed
CIV-MAT-000026

https://ksa1.aconex.com/Logon 1/1
1/15/22, 11:54 AM Aconex

Ayman Negm Final (WF-010620) 14-4800000322/000-IN-Project Mana… 11:41 AM


AECOM WORKFLOW TRANSMITTAL ACM-WTRAN-023756

14 Outer Regions
Riyadh, KSA
Riyadh
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal ACM-WTRAN-023756 ACM-WTRAN-023756

Final (WF-010620) 14-4800000322/000-IN-Project Management - IFR-PQD

From Mr Ayman Negm - AECOM

To (2) Mr Ayman Negm - AECOM (+1 more...)

Cc (7) Mr Soner Keskinel - AECOM (+6 more...)

Sent Saturday, 15 January 2022 11:41:36 AM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

14-662000-4800000322-MOB- 4800000322/000 - Pre-Qualification Data A - Work


01 06/01/2022
ELE-CRS-000077 of RLCO for Lighting Poles May Proceed

14-662000-4800000322-MOB- 4800000322/000 - Pre-Qualification Data A - Work


01 06/01/2022
ELE-PQD-000019 of RLCO for Lighting Poles May Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "14-4800000322/000-IN-Project Management - IFR-PQD" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

14-662000-4800000322-
NEOM/AECOM_Review A Negm A - Work May Proceed No Objection
MOB-ELE-PQD-000019

14-662000-4800000322- NEOM/AECOM_Review A Negm A - Work May Proceed No Objection

https://ksa1.aconex.com/Logon 1/2
1/15/22, 11:54 AM Aconex

MOB-ELE-CRS-000077

https://ksa1.aconex.com/Logon 2/2
5R\DO&RPPLVVLRQIRU-XEDLODQG<DQEX
'LUHFWRUDWH*HQHUDORIWKH5R\DO&RPPLVVLRQLQ-XEDLO
&RQVWUXFWLRQ'HSDUWPHQW

5&75$160,77$/
5( $EGL$EGLZDKDE
3/($6($&.12:/('*(5(&(,37$1'5(7851,00(',$7(/< '$7( 2FW
ŽĐƵŵĞŶƚdLJƉĞ͗ ŽĚĞ͗ &RQWUDFW1R &
9 DĞƚŚŽĚ^ƚĂƚĞŵĞŶƚ D^ŝ dĞĐŚŶŝĐĂů 5&7UDQVPLWWDO1R 7

9 WůĂŶ W> dĞĐŚŶŝĐĂů

9 ^ŚŽƉƌĂǁŝŶŐ ^ dĞĐŚŶŝĐĂů

9 /&ͬ&ŝŶĂůYƵĂŶƚŝƚLJ /&Y EŽŶͲdĞĐŚŶŝĐĂů

9 Ed^ͲKƚŚĞƌ d^E EŽŶͲdĞĐŚŶŝĐĂů


$77(17,216833/,(56$//),1$/'5$:,1*668%0,77('727+(52<$/&200,66,210867%(,1*22'48$/,7<0</$5
'RFXPHQW1R 5HY 'HVFULSWLRQ7LWOH $FWLRQ& $FWLRQ 5HIHUHQFH
1R RGH &RGH 7UDQV1R 'DWH5HFHLYHG
76
  0HWKRG6WDWHPHQWIRU$QWL&DUERQDWLRQ&RDWLQJIRU([SRVHG  &06L  
&RQFUHWHDW6WUXFWXUDO 
  7UDIILF0DQDJHPHQW3ODQIRU$UHD 5RDG +''3LSHIRU  3/$  
:RUNLQJZLWK&RQWLQJHQF\3ODQ
  6KRS'UDZLQJIRU7UDIILF6LJQDO,QWHUVHFWLRQV  6'  
  6KRS'UDZLQJIRU7UDIILFVLJQDOLQWHUVHFWLRQV$UHD  6'  
  6KRS'UDZLQJIRU+LJK0DVW)RXQGDWLRQRI$UHD  6'  
  6KRS'UDZLQJIRU6DQLWDU\:DVWH:DWHU6\VWHP)53  6'  
0DQKROH´
  6KRS'UDZLQJRI6WRUP'UDLQDJHLQ$5 7\SLFDO2QHLQOHW  6'  
ZLWK2QH2XWOHWZLWK6LQJOH*UDWLQJ
176
  )LQDO4XDQWLW\3D\,WHP1RD$VSKDOW&RQFUHWH  ,)4  
%DVH&RXUVHPPWKN
  )LQDO4XDQWLW\3D\,WHP1RD$JJUHJDWH5RDG  ,)4  
%DVH&RXUVHPPWKN
  )LQDO4XDQWLW\3D\,WHP1RF5HLQIRUFHG&RQFUHWH  ,)4  
IRU6XE6WUXFWXUH&ODVV&6WUXFWXUH%
  )LQDO4XDQWLW\3D\,WHP1RE5HLQIRUFHG&RQFUHWH  ,)4  
IRU6XE6WUXFWXUH&ODVV&6WUXFWXUH
  7HFKQLFDO6XEPLWWDORI$UHD6WUHHW/LJKWLQJ3ROHVE\5/&2  761  
7RWDO,WHPV 

72 )520 Digitally signed by Abdullah


DN: cn=Abdullah, o, ou,

'DWH
Abdullah email=KHALDIABD@RCJubail.gov
.sa, c=<n
Date: 2021.10.18 16:05:44 +03'00' 'DWH 2FW
0XVWDID$ONKDWHHE 6,*1$785(
3URMHFW0DQDJHU &216758&7,213'0&'(3$570(17
0RIDUUHK0DU]RXJ$O+DUEL 3DUWQHUV&R/WG 5&%/(9(/5DV$O.KDLU2IILFH

.,1'/<6,*1$1'5(78517+(25,*,1$/)250727+(52<$/&200,66,21 3URFHVVHG%\ $%'8//$+


3DJHRI
52<$/&200,66,21)25-8%$,/$1'<$1%8
52<$/&200,66,21,1-8%$,/
&216758&7,21'(3$570(17
1217(&+1,&$/68%0,77$/5(9,(:&RQWUDFWRU&RS\

&RQWUDFW1R &
&6  :RUN0D\3URFHHG &6  5HYLVHDQG5HVXEPLW:RUN
&2175$&72568%0,77$/12  'RF1R  0D\1RW3URFHHG

5&75$160,77$/1R &6
x  5HYLVHDQG5HVXEPLW &6  5HYLHZ1RW5HTXLUHG
:RUN0D\3URFHHG
7,7/( 7HFKQLFDO6XEPLWWDORI$UHD6WUHHW/LJKWLQJ3ROHVE\ VXEMHFWWRLQFRUSRUDWLRQRI :RUN
5/&2 FKDQJHVDQGFRPPHQWV
&6 0D\3URFHHG
&6 0D\1RW3URFHHG
Note: Permission to proceed does not constitute acceptance or approval of
design details, calculation analyses, test methods or materials developed or
selected by the supplier does not relieve the contractor from his contractual
obligations.

$EGL$EGLZDKDE Abdiwahab I. Abdi


Digitally signed by Abdiwahab I. Abdi
DN: cn=Abdiwahab I. Abdi, o=., ou=., email=abdia@rcjubail.gov.sa,
c=<n
Date: 2021.10.17 16:11:44 +03'00'
17.10.2021
Resident Engineer 6,*1$785( DATE

1RWH
Comments must be written on the Comments sheet and attached. Comments which can only be possible on the contractor's
submittal must be indexed on this form

Document status applies to technical content only. Use of foreign materials, equipment and services is subject to royal
commission's approval. Once this technical submittal is given code 1 or 2 status, contractor shall submit vendor approval(with
technical submittal package) for royal commission's review. Procurement prior to this approval is done at the contractor's own risk.

# To complete and clearly compare on comparison sheet the RC specification requirements to the manufacturer's performance data.Any deviation shall be identified and a justification will be given.

7XHVGD\2FWREHU
12/11/21, 11:56 AM Aconex

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-031455 BEC-WTRAN-031455

Final (WF-017159) 10-662155-1100001334-AAC-ELE-MAT-000002 WO.007 –


Material Submittal of Solar Lightening Material Renewable Lightening Factory for
Industry LLC ‘RLCO’-RD-15 E ( C ) (41-45 KM)

From Bechtel Document Management - Bechtel KSA

To (2) Mr 1100001334 DCC - Al Ayuni Investment & Contracting

Bechtel Document Management - Bechtel KSA

Cc (2) NEOM ETSD Document Control - NEOM - Engineering & Technical Services Dept

NEOM Spine DC - NEOM - Projects

Sent Saturday, 11 December 2021

MESSAGE

Workflow Review History

The attached documents have completed the "10-662155-1100001334-AAC-ELE-MAT-000002 WO.007 – Material Submittal of Solar
Lightening Material Renewable Lightening Factory for Industry LLC ‘RLCO’-RD-15 E ( C ) (41-45 KM)" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

10-662155-1100001334- B - Incorporate
EPM DCC B Document Management
AAC-ELE-CRS-000002 Comments - Proceed

10-662155-1100001334- B - Incorporate
EPM DCC B Document Management
AAC-ELE-MAT-000002 Comments - Proceed

https://ksa1.aconex.com/Logon 1/1
12/29/21, 10:21 AM Aconex

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-032422 BEC-WTRAN-032422

Final (WF-017769) AlAyuni DCC to EPM DCC-1100001334_WO 05- Road


15W_R02

From Bechtel Document Management - Bechtel KSA

To (2) Mr 1100001334 DCC - Al Ayuni Investment & Contracting

Bechtel Document Management - Bechtel KSA

Cc (2) NEOM ETSD Document Control - NEOM - Engineering & Technical Services Dept

NEOM Spine DC - NEOM - Projects

Sent Wednesday, 15 December 2021

MESSAGE

Workflow Review History

The attached documents have completed the "AlAyuni DCC to EPM DCC-1100001334_WO 05- Road 15W_R02" workflow with the following
results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

10-662151-1100001334- B - Incorporate Comments


EPM DCC B Document Management
AAC-ELE-CRS-000001 - Proceed

10-662151-1100001334- B - Incorporate Comments


EPM DCC B Document Management
AAC-ELE-MAT-000001 - Proceed

https://ksa1.aconex.com/Logon 1/1
12/29/21, 10:17 AM Aconex
Mr 110000133
10 Spine DCC
Cross Project Search
Infrast. Al Ayuni Investmen
Contracting
Tasks Models Documents Mail Field Packages

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-031458 BEC-WTRAN-031458

Final (WF-018174) AlAyuni DCC to EPM DCC-1100001334_WO 05- Road


15W_R02

From Bechtel Document Management - Bechtel KSA

To (2) Mr 1100001334 DCC - Al Ayuni Investment & Contracting (+1 more...)

Cc (2) NEOM ETSD Document Control - NEOM - Engineering & Technical Services Dept (+1 more...)

Sent Saturday, 11 December 2021

MESSAGE

Workflow Review History

The attached documents have completed the "AlAyuni DCC to EPM DCC-1100001334_WO 05- Road 15W_R02" workflow with the following
results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

10-662151-1100001334- B - Incorporate Comments


EPM DCC B Document Management
AAC-ELE-CRS-000002 - Proceed

10-662151-1100001334- B - Incorporate Comments


EPM DCC B Document Management
AAC-ELE-MAT-000002 - Proceed

https://ksa1.aconex.com/Logon 1/1
ü
No objection for the proposed 12 m height pole for time lapse camera, subject to the following
1. Submission and approval of pole structural design and design of pole foundation
2. No maintenance access provision shown in the proposal, Contractor to provide proposal for accessing
the camera location for maintenance / repairs.
3. Contractor to ensure above comments are addressed before commencement of pole installation
4. Final location of the time lapse camera to be agreed before installation
Siddique Israr Resident Engineer 21/12/2021
Firefox https://ksa1.aconex.com/rsrc/20211215.0853/en_AU_DOC/mail/view/in...

11 Regional Infrastructure
Regional Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal ACM-WTRAN-008597 ACM-WTRAN-008597

Final (WF-006026) 11-0000100322/007-IN-Construction - IFR

From Mr Mouneimne Ahmad - AECOM

To (3) Mr Mouneimne Ahmad - AECOM (+2 more...)

Cc (5) Khaled Ismail - AECOM (+4 more...)

Sent Tuesday, 21 December 2021 11:55:11 AM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

100322/07 - Single and Double Arm


B - Incorporate
11-000000-0000100322- Solar Power Lighting Pole Technical
01 11/12/2021 Comments -
SPC-ELE-CRS-000003 Submittal including all Accessories.
Proceed
(RLCO)

100322/07 - Single and Double Arm


B - Incorporate
11-000000-0000100322- Solar Power Lighting Pole Technical
01 11/12/2021 Comments -
SPC-ELE-MAT-000004 Submittal including all Accessories.
Proceed
(RLCO)

MESSAGE

Workflow Review History


The attached documents have completed the "11-0000100322/007-IN-Construction - IFR" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

1 of 2 12/23/2021, 11:19 AM
Firefox https://ksa1.aconex.com/rsrc/20211215.0853/en_AU_DOC/mail/view/in...

Refer to CRS file no


11-000000-0000100322-
11-000000-0000100322- B - Incorporate
NEOM/AECOM_Review M Ahmad SPC-ELE-
SPC-ELE-MAT-000004 Comments - Proceed
CRS-000003_01 for
review comments.

Refer to CRS file no


11-000000-0000100322-
11-000000-0000100322- B - Incorporate
NEOM/AECOM_Review M Ahmad SPC-ELE-
SPC-ELE-CRS-000003 Comments - Proceed
CRS-000003_01 for
review comments.

2 of 2 12/23/2021, 11:19 AM
Bechtel Document Management Final (WF-018677) 10-662171-0000100324-FTC-CIV-MA… 1:48 PM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-033303

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-033303 BEC-WTRAN-033303

Final (WF-018677) 10-662171-0000100324-FTC-CIV-MAT-000020_100324-031 –


Material Submittal for LED Lighting Fixture, Solar Panel, Battery and Charge
Controller By: RLCO.

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc NEOM Spine DC - NEOM - Projects

Sent Sunday, 19 December 2021 1:48:31 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

B-
10-662171- 100324-031 – Material Submittal for LED Lighting
Incorporate
0000100324-FTC- 01 12/12/2021 Fixture, Solar Panel, Battery and Charge
Comments -
CIV-CRS-000088 Controller By: RLCO._ CRS
Proceed

B-
10-662171- 100324-031 – Material Submittal for LED Lighting
Incorporate
0000100324-FTC- 01 12/12/2021 Fixture, Solar Panel, Battery and Charge
Comments -
CIV-MAT-000020 Controller By: RLCO.
Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "10-662171-0000100324-FTC-CIV-MAT-000020_100324-031 – Material Submittal for LED
Lighting Fixture, Solar Panel, Battery and Charge Controller By: RLCO." workflow with the following results :
This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

10-662171-0000100324- B - Incorporate Comments


EPM DCC B Document Management
FTC-CIV-MAT-000020 - Proceed

10-662171-0000100324- B - Incorporate Comments


EPM DCC B Document Management
FTC-CIV-CRS-000088 - Proceed
10/23/21, 8:48 PM Aconex

Mohammed Farazuddin Final (WF-000135) 20211020-MAH-MATERIAL TECHNIC… 1:50 PM


SAK ENGINEERING CONSULTANCIES WORKFLOW TRANSMITTAL SAK-WTRAN-000282

SEVEN Madinah SAK ENGINEERING CONSULTANCIES


Riyadh front Seven HO 2388 JEDDAH 21451
Riyadh SAUDI ARABIA
Saudi Arabia JEDDAH
SAUDI ARABIA 00966 Saudi Arabia
Ph. +966 12 6695832

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal SAK-WTRAN-000282 SAK-WTRAN-000282

Final (WF-000135) 20211020-MAH-MATERIAL TECHNICAL SUBMITTAL FOR 25-


METER HIGH MAST POLE & 6 METER LIGHTING POLE FROM RLCO
SUPPLIERS-4MADN03-MADN-07-MAH-EL-MAT-00001_01

From Mr Mohammed Farazuddin - SAK ENGINEERING CONSULTANCIES

To (5) Mr Mark Valenzuela - MOFARREH ALHARBI AND PARTNERS

Mr Muhammed Najim - MOFARREH ALHARBI AND PARTNERS

Mr Mohammed Mujeeb - SAK ENGINEERING CONSULTANCIES

Mr Mohammed Farazuddin - SAK ENGINEERING CONSULTANCIES

Raed Almanie - SEVEN

Cc (4) Mr Ashraf Yunus - SAK ENGINEERING CONSULTANCIES

Mr Mohammed Al Jabri - SAK ENGINEERING CONSULTANCIES

Mr Sarfaraz Mateen - SAK ENGINEERING CONSULTANCIES

Mashael Al Otaibi - SEVEN

Sent Saturday, 23 October 2021 1:50:19 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Planned
Revision
File Document No Revision Title Status Submission
Date
Date

Material Technical Submittal for B - Approved


4MADN03-MADN-07-
01 20/10/2021 High must pole solar pole from with
MAH-EL-MAT-00001
RLCO Comments

https://ksa1.aconex.com/Logon?mainTarget=%2FViewCorrespondence%3FCorrespondence_ID%3D1351009856%26CORRESPONDENCE_MAILBO… 1/3
10/23/21, 8:48 PM Aconex

ATTRIBUTES

Attribute 1 CI - Civil Works (Infrastructure)

MESSAGE

Workflow Review History

The attached documents have completed the "20211020-MAH-MATERIAL TECHNICAL SUBMITTAL FOR 25-METER HIGH MAST POLE & 6
METER LIGHTING POLE FROM RLCO SUPPLIERS-4MADN03-MADN-07-MAH-EL-MAT-00001_01" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

4MADN03-MADN-07-
Step 1 - MAH Upload M Najim A - Approved
MAH-EL-MAT-00001

We have reviewed the


Material technical
submittal for 25-Meter-
Light mast pole & 6 Meter
lighting pole from RLCO
Supplier, please find below
our comments with Code
B: Approved with
comments 1. RLCO make
sure poles metal formed
as one piece without any
connection, joint, welding
and Hot galvanized deep.
Step 2 - SAK Review M Farazuddin Approved with Comments 2. High mast poles must
be provided with earth
point. 3. High mast poles
model shall be mentioned.
4. Type test from
independent laboratory for
proposed material shall be
provided (min 5 years old)
5. Contractor Must be
adhere to technical specs,
BOQ and approved
drawing as per SBC. 6.
Warranty Certificate is
missing

Step 3 SEVEN Review R Almanie Approved with Comments Approve RLCO as supplier
ONLY. To get the final
approval, MAH have to
submit the Design

https://ksa1.aconex.com/Logon?mainTarget=%2FViewCorrespondence%3FCorrespondence_ID%3D1351009856%26CORRESPONDENCE_MAILBO… 2/3
10/23/21, 8:48 PM Aconex

calculation transmittal,
LUX calculation and brand/
type of the lights that will
be used In addition to that
the ref. No (4TBUK04-
TBUK-07-MAH-CI-DED-
00019), that been
mentioned in the RLCO
PQ is not existing.

Please follow SEVEN and


Step 4 SAK Feedback M Farazuddin Approved with Comments
SAK Comments

Step 5 - Resubmit if Please follow SEVEN and


M Farazuddin Approved with Comments
Required and Closeout SAK Comments

https://ksa1.aconex.com/Logon?mainTarget=%2FViewCorrespondence%3FCorrespondence_ID%3D1351009856%26CORRESPONDENCE_MAILBO… 3/3
12/11/21, 11:56 AM Aconex

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-031455 BEC-WTRAN-031455

Final (WF-017159) 10-662155-1100001334-AAC-ELE-MAT-000002 WO.007 –


Material Submittal of Solar Lightening Material Renewable Lightening Factory for
Industry LLC ‘RLCO’-RD-15 E ( C ) (41-45 KM)

From Bechtel Document Management - Bechtel KSA

To (2) Mr 1100001334 DCC - Al Ayuni Investment & Contracting

Bechtel Document Management - Bechtel KSA

Cc (2) NEOM ETSD Document Control - NEOM - Engineering & Technical Services Dept

NEOM Spine DC - NEOM - Projects

Sent Saturday, 11 December 2021

MESSAGE

Workflow Review History

The attached documents have completed the "10-662155-1100001334-AAC-ELE-MAT-000002 WO.007 – Material Submittal of Solar
Lightening Material Renewable Lightening Factory for Industry LLC ‘RLCO’-RD-15 E ( C ) (41-45 KM)" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

10-662155-1100001334- B - Incorporate
EPM DCC B Document Management
AAC-ELE-CRS-000002 Comments - Proceed

10-662155-1100001334- B - Incorporate
EPM DCC B Document Management
AAC-ELE-MAT-000002 Comments - Proceed

https://ksa1.aconex.com/Logon 1/1
14 Outer Regions
Riyadh, KSA
Riyadh
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal ACM-WTRAN-018906 ACM-WTRAN-018906

Final (WF-008554) 14-4800000229/000-IN-Construction - IFR_

From Mr Piotr Rozpedowski - AECOM

To (3) Neom Pmc Region 14 - AECOM (+2 more...)

Cc (5) Khaled Ismail - AECOM (+4 more...)

Sent Monday, 6 December 2021 5:34:19 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

A-
14-187100- 4800000229/000-Hot deep galvanized - Octagonal Lighting
Work
4800000229-MAH- 01 29/11/2021 Pole - 12.85m high -Dia. (310/110mm) - Thk 4mm with
May
ELE-CRS-000008 Base Plate 500x500x25 and Solar Bracket
Proceed

A-
14-187100- 4800000229/000-Hot deep galvanized - Octagonal Lighting
Work
4800000229-MAH- 03 29/11/2021 Pole - 12.85m high -Dia. (310/110mm) - Thk 4mm with
May
ELE-MAT-000002 Base Plate 500x500x25 and Solar Bracket
Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "14-4800000229/000-IN-Construction - IFR_" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

14-187100-4800000229-
NEOM/AECOM_Review P Rozpedowski A - Work May Proceed
MAH-ELE-CRS-000008
14-187100-4800000229- NEOM/AECOM_Review P Rozpedowski A - Work May Proceed
MAH-ELE-MAT-000002
10/23/21, 8:48 PM Aconex

Mohammed Farazuddin Final (WF-000135) 20211020-MAH-MATERIAL TECHNIC… 1:50 PM


SAK ENGINEERING CONSULTANCIES WORKFLOW TRANSMITTAL SAK-WTRAN-000282

SEVEN Madinah SAK ENGINEERING CONSULTANCIES


Riyadh front Seven HO 2388 JEDDAH 21451
Riyadh SAUDI ARABIA
Saudi Arabia JEDDAH
SAUDI ARABIA 00966 Saudi Arabia
Ph. +966 12 6695832

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal SAK-WTRAN-000282 SAK-WTRAN-000282

Final (WF-000135) 20211020-MAH-MATERIAL TECHNICAL SUBMITTAL FOR 25-


METER HIGH MAST POLE & 6 METER LIGHTING POLE FROM RLCO
SUPPLIERS-4MADN03-MADN-07-MAH-EL-MAT-00001_01

From Mr Mohammed Farazuddin - SAK ENGINEERING CONSULTANCIES

To (5) Mr Mark Valenzuela - MOFARREH ALHARBI AND PARTNERS

Mr Muhammed Najim - MOFARREH ALHARBI AND PARTNERS

Mr Mohammed Mujeeb - SAK ENGINEERING CONSULTANCIES

Mr Mohammed Farazuddin - SAK ENGINEERING CONSULTANCIES

Raed Almanie - SEVEN

Cc (4) Mr Ashraf Yunus - SAK ENGINEERING CONSULTANCIES

Mr Mohammed Al Jabri - SAK ENGINEERING CONSULTANCIES

Mr Sarfaraz Mateen - SAK ENGINEERING CONSULTANCIES

Mashael Al Otaibi - SEVEN

Sent Saturday, 23 October 2021 1:50:19 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Planned
Revision
File Document No Revision Title Status Submission
Date
Date

Material Technical Submittal for B - Approved


4MADN03-MADN-07-
01 20/10/2021 High must pole solar pole from with
MAH-EL-MAT-00001
RLCO Comments

https://ksa1.aconex.com/Logon?mainTarget=%2FViewCorrespondence%3FCorrespondence_ID%3D1351009856%26CORRESPONDENCE_MAILBO… 1/3
10/23/21, 8:48 PM Aconex

ATTRIBUTES

Attribute 1 CI - Civil Works (Infrastructure)

MESSAGE

Workflow Review History

The attached documents have completed the "20211020-MAH-MATERIAL TECHNICAL SUBMITTAL FOR 25-METER HIGH MAST POLE & 6
METER LIGHTING POLE FROM RLCO SUPPLIERS-4MADN03-MADN-07-MAH-EL-MAT-00001_01" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

4MADN03-MADN-07-
Step 1 - MAH Upload M Najim A - Approved
MAH-EL-MAT-00001

We have reviewed the


Material technical
submittal for 25-Meter-
Light mast pole & 6 Meter
lighting pole from RLCO
Supplier, please find below
our comments with Code
B: Approved with
comments 1. RLCO make
sure poles metal formed
as one piece without any
connection, joint, welding
and Hot galvanized deep.
Step 2 - SAK Review M Farazuddin Approved with Comments 2. High mast poles must
be provided with earth
point. 3. High mast poles
model shall be mentioned.
4. Type test from
independent laboratory for
proposed material shall be
provided (min 5 years old)
5. Contractor Must be
adhere to technical specs,
BOQ and approved
drawing as per SBC. 6.
Warranty Certificate is
missing

Step 3 SEVEN Review R Almanie Approved with Comments Approve RLCO as supplier
ONLY. To get the final
approval, MAH have to
submit the Design

https://ksa1.aconex.com/Logon?mainTarget=%2FViewCorrespondence%3FCorrespondence_ID%3D1351009856%26CORRESPONDENCE_MAILBO… 2/3
10/23/21, 8:48 PM Aconex

calculation transmittal,
LUX calculation and brand/
type of the lights that will
be used In addition to that
the ref. No (4TBUK04-
TBUK-07-MAH-CI-DED-
00019), that been
mentioned in the RLCO
PQ is not existing.

Please follow SEVEN and


Step 4 SAK Feedback M Farazuddin Approved with Comments
SAK Comments

Step 5 - Resubmit if Please follow SEVEN and


M Farazuddin Approved with Comments
Required and Closeout SAK Comments

https://ksa1.aconex.com/Logon?mainTarget=%2FViewCorrespondence%3FCorrespondence_ID%3D1351009856%26CORRESPONDENCE_MAILBO… 3/3
9/25/21, 10:58 PM https://ksa1.aconex.com/rsrc/20210805.1103/en_AU_DOC/mail/view/index.html#/1342179436/1350405414

Mohammed Farazuddin Final (WF-000049) RLCO Prequalification Documents 15/08/2021


SAK ENGINEERING CONSULTANCIES WORKFLOW TRANSMITTAL SAK-WTRAN-000075

SEVEN Tabuk SAK ENGINEERING CONSULTANCIES


Riyadh front Seven HO 2388 JEDDAH 21451
Riyadh SAUDI ARABIA
Saudi Arabia JEDDAH
SAUDI ARABIA 00966 Saudi Arabia
Ph. +966 12 6695832

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal SAK-WTRAN-000075 SAK-WTRAN-000075

Final (WF-000049) RLCO Prequalification Documents

From Mr Mohammed Farazuddin - SAK ENGINEERING CONSULTANCIES

To (4) Mr Gernel Jones Dumpa - MOFARREH ALHARBI AND PARTNERS (+3 more...)

Cc (3) Mr Hefzy Ezelarab - MOFARREH ALHARBI AND PARTNERS (+2 more...)

Sent Sunday, 15 August 2021 4:19:55 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Planned
Revision
File Document No Revision Title Status Submission
Date
Date

RLCO
4TBUK04-TBUK-07-MAH- B - Approved
01 07/08/2021 Prequalification
EL-PRQ-00004 with Comments
Documents

ATTRIBUTES

Attribute 1 CI - Civil Works (Infrastructure)

MESSAGE

Workflow Review History

The attached documents have completed the "RLCO Prequalification Documents" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

4TBUK04-TBUK-07-
Step 1 - MAH Upload G Dumpa A - Approved
MAH-EL-PRQ-00004

https://ksa1.aconex.com/rsrc/20210805.1103/en_AU_DOC/mail/view/index.html#/1342179436/1350405414 1/3
9/25/21, 10:58 PM https://ksa1.aconex.com/rsrc/20210805.1103/en_AU_DOC/mail/view/index.html#/1342179436/1350405414

Step 2 - SAK Review M Farazuddin B - Approved with We have reviewed the


Comments RLCO Prequalification
Documents, please find
below our comments with
Code B: Approved with
Comments 1) Saudization
Achievement Certificate-
Missing 2) General
Organization for Social
Insurance- 28-10-1442-
Expired 3) Industrial
Register Certificate-
Missing. 4) Industrial
activity license- Missing 5)
SASO certification-
Missing 6) Safety
Procedures-Missing 7)
Quality procedure, quality
control plan - Missing 8)
RLCO must comply the
project specification and
Contract (External Lighting
Items D1 & D2) 9) Provide
the statement of work. 10)
Provide copy of the
agreement. 11) Provide
duration of the third party.
12) Contractor Must be
submit separate technical
specification for material
according to the project
specification & Contract
{CONTRACT
REFERENCE NO. 22.21
(A)} to get approval of the
materials & final shape of
design according to
Contract Drawings &
SPECS. 13) This approval
does not give the
contractor any authority to
change the type of
materials or design, must
be follow the SPECS of
Contract NO. 22.21 (A)
14) Not allow by any
Technical Query to change
shape of design or type of
material 15) Test results
for random samples is
missing. 16) Precautions
for storage and optimal

https://ksa1.aconex.com/rsrc/20210805.1103/en_AU_DOC/mail/view/index.html#/1342179436/1350405414 2/3
9/25/21, 10:58 PM https://ksa1.aconex.com/rsrc/20210805.1103/en_AU_DOC/mail/view/index.html#/1342179436/1350405414

use is missing. 17)


Warranty Certificates is
missing. 18) Authority
papers must be valid
before start supply of
material and before
payment for main
contractor

The contractor/supplier
should submit the below
missing document:- 1-
Safety Procedure 2-
quality Procedure in
addition to that this PQD is
applicable for supplier /
B - Approved with brand only, not valid to
Step 3 SEVEN Review M Almajed
Comments purchase/ order the
materials, contractor
should submit a separate
technical material
according to the project
specification & Contract to
get the approval of the
materials

B - Approved with Please follow SAK and


Step 4 SAK Feedback M Farazuddin
Comments SEVEN comments

Step 5 - Resubmit if B - Approved with Please follow SAK and


M Farazuddin
Required and Closeout Comments SEVEN comments

https://ksa1.aconex.com/rsrc/20210805.1103/en_AU_DOC/mail/view/index.html#/1342179436/1350405414 3/3
Bechtel Document Management Final (WF-010959) 4800000283 - Prequalification Docum… 8:03 AM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-017474

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-017474 BEC-WTRAN-017474

Final (WF-010959) 4800000283 - Prequalification Documents RLCO (Solar Lighting


Pole) ‐ Design & Build of Spine Site Offices

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (4) Mr David Quigley - Bechtel KSA (+3 more...)

Sent Wednesday, 22 September 2021 8:03:54 AM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

4800000283 - Prequalification Documents RLCO Work


10-721500-4800000283-
01 19/09/2021 (Solar Lighting Pole) ‐ Design & Build of Spine Site May
MAH-ELE-CRS-000002
Offices_CRS proceed

4800000283 - Prequalification Documents RLCO Work


10-721500-4800000283-
01 19/09/2021 (Solar Lighting Pole) ‐ Design & Build of Spine Site May
MAH-ELE-PQD-000002
Offices proceed

MESSAGE

Workflow Review History

The attached documents have completed the "4800000283 - Prequalification Documents RLCO (Solar Lighting Pole) ‐ Design & Build of Spine
Site Offices" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments


10-721500-4800000283- EPM DCC B Document Management Work May Proceed
MAH-ELE-CRS-000002

10-721500-4800000283-
EPM DCC B Document Management Work May Proceed
MAH-ELE-PQD-000002
9/14/21, 8:07 AM Aconex

Bechtel Document Management Final (WF-008310) WO 26- Pre-Qualification for Renew… YESTERDAY
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-016413

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-016413 BEC-WTRAN-016413

Final (WF-008310) WO 26- Pre-Qualification for Renewable Lighting Factory


(RLCO) Supplier of Solar Street Lighting System-RD-17 West 2(4-10km)&RD-11A

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (4) Mr David Quigley - Bechtel KSA (+3 more...)

Sent Monday, 13 September 2021 4:45:54 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(2 selected)

Revision
File Document No Revision Title Status
Date

10-662171- WO 26- Pre-Qualification for Renewable Lighting Factory Work


0000100201-MAH- 01 14/08/2021 (RLCO) Supplier of Solar Street Lighting System-RD-17 May
ELE-CRS-000002 West 2(4-10km)&RD-11A_CRS proceed

10-662171- WO 26- Pre-Qualification for Renewable Lighting Factory Work


0000100201-MAH- 01 14/08/2021 (RLCO) Supplier of Solar Street Lighting System-RD-17 May
ELE-PQD-000002 West 2(4-10km)&RD-11A proceed

MESSAGE

Workflow Review History

The attached documents have completed the "WO 26- Pre-Qualification for Renewable Lighting Factory (RLCO) Supplier of Solar Street
Lighting System-RD-17 West 2(4-10km)&RD-11A" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

https://ksa1.aconex.com/Logon 1/2
9/14/21, 8:07 AM Aconex

10-662171-0000100201- EPM DCC B Document Management Work May Proceed


MAH-ELE-CRS-000002

10-662171-0000100201-
EPM DCC B Document Management Work May Proceed
MAH-ELE-PQD-000002

https://ksa1.aconex.com/Logon 2/2
JJ'i,.1'
4J.r-y
,:.lrri.! iJ.:t! al} /i!fi r+{t.! :1 lt-!r
arJarr i+.tr (rrra! ,Jj,
H.+t &JE

irlnrj JLJfn i-u,lr irtr


iJri., irr- J 4i,ri iJll
-nl t t l/o/Y. -: i.:_,:E s' f, l1/.Y/. t/r.rr1 ..../yyrf y _: er,.iJt t'J
L.rsJr i5^, 41"31 6JLiyt ctsri ijl+_r Lu._s _.irJ.ilt r-t
-r 1{ tl/V/I . -; dr
i.r,l1 '!.'ir Jl BJljYt C.* -. rJ/lF Ji r1-' iJl -.:.
t.l.l 11

Oil+ll !,-ll O" l€l-J lJ.re .!"Ji . i,+Jt r-!


,.iLJ *iilr .i ,
rriiill aiJ +ri e.:ii r
|,riill !.)Ll
:L.icl r sLt-\ E 6LJL- E r arE
.9,Pl E ,t+-,r+s
- E -', ill
l-_]. .. -, r
rrur.lA L--J r-!e lJt4jlr-_; -: iilcE i:l*^i,!!! L L: r-l +L!JJJ< -inr_)o
,/Y eiJl
r
iJl.l iillt Li€JJ aiJJ ast

..a.i ilcL--$
-"!Jr ..Jti)l 6u.-lrll ...,6 LJiUI +].lt o-.,lr.ii
Ci* 4_dl .)J-L $-Ji
Ji- o eEJl
+tjJ -..!-i.tr ;JLyt (ltisul
..r.i ei- .!dl ...,* OiL-n aJ- s!.+l !-te .! 'Jr
.r. tlnrt
^
i Sa#F# r.'ir ! ejjYl ,.i-.
1Bc q *i6 -*
r E-.trJ9LEn'd+J -.Jtl)r .l-
L,ti-lils.:L!Jr +.rJ ir. ..Jr.i.j
JL
JJ,Jc

^ tLirJl
.-tdl
+rr al\

J& !t
tri.. JL o tEJl .rJF rl \.1_j+: r}l! t4ir !-Ji

,W
azzi rn at.Snareet
_.J+ji ;'ui "I,,i*l J.ii*lr .J-
irr,irll
,.+FrF hI I *r 6U.ti-j.l t"lj t^ljilt rj:L ilridl Ot+ cJ3liJt \ - r, drtiJl 6LL-,).
JJidl r:llelii-l
thhJlr:ilq[itrI /e.Jilr /ei-ill ol.il.Il.-/.r yr

40311146=80ri.' LUJ
^ Lnt:
c ii*!l ilr-
*:
. .3
't
:,t* -,'il1:. a..:..W. 2 z- i. .. .........
!a!*.,7* U.-a
U-p. !.
......,....!...... -{-a. t :.-...).t. 1 :. r..t,. 6...........

.d1;,*tf?.*{4:hfJY.*aJi:a;iii
I [ni/: i ; .rt. .V..
j;;i;ieL l
.*4a_.e........
.. {F-"dL*+r. ZJ, !-.L.ai*!.!=.!..A ty.! I
clr4t..qr-.......

jlt
/
t /dr
J+():'rr...

rL.Jal uJ|J , ij$. Jl J


I J c
d$a- / i-l,EJl
'o-.ru Co
J oib

.,i..t+ it -.rlt+. -r"" /


- :t"ic.Yl ilL
6$cYl t crLt:)..r \'i-J c A

E ,s^-fs^ D a+n 6r!cl OJ'j 6LL-)-, '.i-J o


'
i J:, q.'. rl i 4{i--l.lf a-Sfor..ff'
; {g,-i.tig; J'tltl U9j '-'dldr})
2{; 3s i-.iLsa!l; r ar
'a-:lt i-Jt€.1
dru:n.
&,-lrll iJtrJl llrlt
tlrioralsll rtil.,oi iJ-ilb
HOIY MAXXAII MUltll<IPALITY
- lll. ,L. &s!i ;.rt-i?l i-iU,-, Ll-a;li
"j4

g.}l-,r-)ll ia+
JrBrt
Li.r/l +i Ji J,.oU ?tf 'r;=-* ;;Ull3,i.,ialt i..LJl :.11:11

i;tiIl crta*,1 :;,!,,or.|ai:c : !l",.tt gl . rt/.Y/. !/r.rr1. "'lYYttY r r -l"li 6-i I

1
r\!ttlo./Y'
r'1 I .-l!) A.A.tt,!Yt
r11t!/AIYY .1 ..olltl/V,/Y'

o|eiell iobtl rrl$iCl i#)l


Pl1r i51i I 6iLll
.'.t'r1y^1iJj:.r t.tY1aYr 6- .r rdwalY f -.r,r i'A&r'- ir!J-:s' 1tlt' fI
at

, , , a6l4J-!Ja!t i---r3 e<-+ fY-''Jl


. rl.r.r,';al& ::t &ll
c,lAJEe-, pS,u,r;* -6t[tYlA/lt 5:]3 (fY"Y1A\n) FJ l{loi"J l3-'4 6jJIl
: !Jh!l s!3Jt is&I cJ:!,iJ19 r:tlc'3

.!
T
t lJ..
J t- -lJ
c J-L..
..-,*.,tf f ... .rg.*!l.y.rlaar :jrrlc y,<.- ;3 + r-;
Y J-ta :. I crl

iJ" LP 0
LBrl gssQ: ,1 13J+.?.i {.L e.lbji3
,IrJ,
u
!
1
L; t, E-l!
ijr3 .rlJLa JE . Ji ;3e:ri.oll -tG* 'le *. ** *:i JrJi
)-r-e

<':l e'93
. .-r.
fJ +i"Ub1,:>
sllall fa.lEe
.r-*.lE ;r^ O*.s<'-I L^t -Ai ;g lL r)lr'i 'J-Jll.lt p1.ra i'c.;-" # i!:Jbtl
2-- j
. .,Je i4otLa:tl ;it-r,iJt J*aitl fi3'-
d.U! f U;I,I .lr,Jt-
e4lE*f*.
,,, g$4f? f,If
ijr!1r-r .. ::.ii,:"si
--,. -"1',r
-
.s--1 ff
, . ''r.;i :r r *-
$liA. : '1.,
",, r _r.r. Vt. :i-s
.i':'iI

,rl* i-+r gl

tlrn : .r.{rr }rr ^.Yr


: lJnll r.3r, *+ttL
O *o& .;6sae+oo*o (,, +36612s739555 € +96612573655 g inio@holfnaklah.gov.se
nL!i.:jit <.
e/
.l t
, ,:,I ^... q, lir -l:{!trt
A-.g1i.l9r *.rJaX rrqfJi.Jt 6r;9
astaar,r^lt6{ drLl i-itr.6Jl3 r a-i:tl i-qS,
,(}lv tur(t x tr.t.l't( ,rt
,.t. rL:*L:
;rtj:l, iJ'Jal, i......-,l,rl iJ+rl
.

LL-jr! i--jl..a, iki;i irl{

! r.^,i"t: jtr-:,t! +l
-r- --:-, !r lr sL: r .r&.: ,_\)z' IJ,r4 e4! ,- r,

;jGrt -!rs-i ::t-5 .!i5 : !t-Jr 1-l . 11/. rr " rlr..!.ra".. -rYY!tr r. ,:ll .i.

.r,.i,J! i*. tL, i"alt !ti.


".\:1: li,'rt :

g;r.;i.U &rrll r;rl3lidl &-r;Il relf iSj I SlLIl

. , . <it A;rj ai.ll ;-.--13 p<ryfc. lXJl


.:l#.l.___.ri :Si-alll
: LiLl3r :rJr .r,;9t jl ,r*Jr;.; irra:.9 , .y-aiaJJq+ -F=..r,Lr;irlr -j!:;ul ,aJ,ldl
:-.AJI
!-. I .r,;:,.-ll
1. | +r:{L;lJr:i::'E
*---5. J..Jt .',. -l+.j t-tk.1bf
.r-+*Jl 2 *7y

.;r r'! :i;jr :i.rJ-l ir;...ry'!


;. c . L{.t...+.=:J: .i -j-.:! ;r-tr .'-rA=>.; +;j
t.-
. :i1 -,- a-,...L- i' lj; t!
t-_':."-..-
r'.-r (*
jLi" r. --bl-:.=1#it +:i
-r1-1-. :' :+::yolt
.r*-

.1te 1..' ;;rl


.l:+ i,--r; i-...r tll:.il c.rlrl E .i.r!J ;L-!.J!. &t..l rU.*a.:l f,:.d: * f'.5+ L'
i-.- : tatr&tl
. *.r;ts 4'+Jl; l-orl..a:.c"1
,.. {Xail ,5lt
5;bfi;rx I
rJ.*i&a
,*J* gtir* Jl J-+r Ur F--aa

t.i"l I ri-rr;'.r' t'lr : l,L;!.l Jrl


r) 3,{s $ *9f6!3eaooaea { *eer*srs*ec6 S.grorzsr$crc
j.r.,r::',D\r!ty' / r r 3r.;* 1{ -! \J1:J\+*
9/6/2021 Aconex

Bechtel Document Management Final (WF-009159) WO 22- Material Approval for Solar St… 10:17 PM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-015488

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-015488 BEC-WTRAN-015488

Final (WF-009159) WO 22- Material Approval for Solar Street lighting System by
RLCO-RD-15E B(25-41KM)

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (4) Mr David Quigley - Bechtel KSA (+3 more...)

Sent Monday, 6 September 2021 10:17:24 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

Work
10-662154-0000100201- WO 22- Material Approval for Solar Street lighting
02 24/08/2021 May
MAH-ELE-CRS-000011 System by RLCO-RD-15E B(25-41KM)_CRS
proceed

Work
10-662154-0000100201- WO 22- Material Approval for Solar Street lighting
02 24/08/2021 May
MAH-ELE-MAT-000004 System by RLCO-RD-15E B(25-41KM)
proceed

MESSAGE

Workflow Review History

The attached documents have completed the "WO 22- Material Approval for Solar Street lighting System by RLCO-RD-15E B(25-41KM)"
workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

https://ksa1.aconex.com/Logon 1/2
9/6/2021 Aconex

10-662154-0000100201- EPM DCC B Document Management Work May Proceed


MAH-ELE-CRS-000011

10-662154-0000100201-
EPM DCC B Document Management Work May Proceed
MAH-ELE-MAT-000004

https://ksa1.aconex.com/Logon 2/2
8/4/2021 Aconex

Bechtel Document Management Final (WF-006846) WO 22- Material Approval for Solar … YESTERDAY
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-011542

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-011542 BEC-WTRAN-011542

Final (WF-006846) WO 22- Material Approval for Solar Street lighting System by
RLCO-RD-15E B(25-41KM)

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (4) Mr David Quigley - Bechtel KSA (+3 more...)

Sent Tuesday, 3 August 2021 10:08:46 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

WO 22- Material Approval for Solar Street Incorporate


10-662154-0000100201-
01 25/07/2021 lighting System by RLCO-RD-15E B(25- Comments -
MAH-ELE-CRS-000011
41KM)_CRS Proceed

WO 22- Material Approval for Solar Street Incorporate


10-662154-0000100201-
01 25/07/2021 lighting System by RLCO-RD-15E B(25- Comments -
MAH-ELE-MAT-000004
41KM) Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "WO 22- Material Approval for Solar Street lighting System by RLCO-RD-15E B(25-41KM)"
workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

https://ksa1.aconex.com/Logon 1/2
8/4/2021 Aconex

10-662154-0000100201- EPM DCC B Document Management Incorporate Comments -


MAH-ELE-CRS-000011 Proceed

10-662154-0000100201- Incorporate Comments -


EPM DCC B Document Management
MAH-ELE-MAT-000004 Proceed

https://ksa1.aconex.com/Logon 2/2
Makkah Public Transport Program - MPTP
Bus Network Civil Infrastructure Works Phase - 1

PQD for Renewable Lighting Factory for Industry


Document Title: L.L.C – RLCO (Supply and Installation of Bus Flag
Doc No.: BP1CIWC-AIC-CIV00-PQD-000088-A

Document Number: BP1CIWC-SKAA-CIV00-CRS-000735 Rev. A

Approval Code: B - No Objection with Comments

Date: Wednesday, July 28, 2021


Makkah Public Transport Program (MPTP)
PQD for Renewable Lighting Factory for Industry L.L.C – RLCO (Supply and Installation of Bus Flag

Document Title: PQD for Renewable Lighting Factory for Industry L.L.C – RLCO (Supply and Installation of Bus Flag

Document No. : BP1CIWC-AIC-CIV00-PQD-000088 Date : 06.07.2021 Version : A

Page Review
Item Report/Document Ref. Review Comments Rev. Response from Contractor Status
No. er

1 General - 33 Acceptance is subject to compliance with the A OPEN


contract documents and satisfactory performance
during the contract period.

2 General - 33 Factory specialization Prequalification is showing the A OPEN


activity for steel pole lighting and Prequalification is
not related to manufacturing of aluminum flags.
Therefore the approval given is conditional and is
related to the mockup quality satisfaction from client
and supervision.
Otherwise, vendor approval is considered canceled
and submittal to be withdrawn.

3 General 33 All material (with data sheets) to be submitted A OPEN


separarelty with no istallation to be done until final
approval of fabrication shopdrawings.

Disclaimer: This document Review corrections or comments made relative to submittals during this review is not exclusive and does not relieve the contractor from his responsibilities and particularly compliance with the requirements of his Contract,
drawings and specifications.
BP1CIWC-SKAA-CIV00-CRS-000735-A Legends for Status: OPEN CLOSED Page 1 of 1
8/8/2021 Aconex

Bechtel Document Management Final (WF-006844) WO 22- Material Approval for solar St… 10:04 AM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-011981

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-011981 BEC-WTRAN-011981

Final (WF-006844) WO 22- Material Approval for solar Street lighting column by
RLCO-RD-15E B(25-41KM)

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (4) Mr David Quigley - Bechtel KSA (+3 more...)

Sent Sunday, 8 August 2021 10:04:02 AM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

Work
10-662154-0000100201- WO 22- Material Approval for solar Street lighting
02 25/07/2021 May
MAH-ELE-CRS-000005 column by RLCO-RD-15E B(25-41KM)_CRS
proceed

Work
10-662154-0000100201- WO 22- Material Approval for solar Street lighting
02 25/07/2021 May
MAH-ELE-MAT-000001 column by RLCO-RD-15E B(25-41KM)
proceed

MESSAGE

Workflow Review History

The attached documents have completed the "WO 22- Material Approval for solar Street lighting column by RLCO-RD-15E B(25-41KM)"
workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

https://ksa1.aconex.com/Logon 1/2
8/8/2021 Aconex

10-662154-0000100201- EPM DCC B Document Management Work May Proceed


MAH-ELE-CRS-000005

10-662154-0000100201-
EPM DCC B Document Management Work May Proceed
MAH-ELE-MAT-000001

https://ksa1.aconex.com/Logon 2/2
Chris J Myers Final (WF-001535) 14-4800000229/000-IN-Project Manag… 5:34 PM
AECOM WORKFLOW TRANSMITTAL ACM-WTRAN-002130

14 Outer Regions
Riyadh, KSA
Riyadh
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal ACM-WTRAN-002130 ACM-WTRAN-002130

Final (WF-001535) 14-4800000229/000-IN-Project Management - IFR

From Mr Chris J Myers - AECOM

To (3) Neom Pmc Region 14 - AECOM (+2 more...)

Cc (4) Khaled Ismail - AECOM (+3 more...)

Sent Monday, 21 June 2021 5:34:00 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Revision
File Document No Revision Title Status
Date

14-187100-4800000229-MAH- 4800000229-RLCO-Prequalification Work May


02 14/06/2021
ELE-PQD-000003 Documents (SOLAR POLE SUPPLIER) proceed

MESSAGE

Workflow Review History

The attached documents have completed the "14-4800000229/000-IN-Project Management - IFR" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

14-187100-4800000229- NEOM/AECOM_Review C Myers Work May Proceed This PQD is applicable for
MAH-ELE-PQD-000003 supplier/Brand only but not
applicable to
purchase/order the
materials, Contractor to
submit separate technical
material submittal for
technical review and
approval in order to get
approval of the materials.
8/4/2021 Aconex

Bechtel Document Management Final (WF-006846) WO 22- Material Approval for Solar … YESTERDAY
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-011542

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-011542 BEC-WTRAN-011542

Final (WF-006846) WO 22- Material Approval for Solar Street lighting System by
RLCO-RD-15E B(25-41KM)

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (4) Mr David Quigley - Bechtel KSA (+3 more...)

Sent Tuesday, 3 August 2021 10:08:46 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

WO 22- Material Approval for Solar Street Incorporate


10-662154-0000100201-
01 25/07/2021 lighting System by RLCO-RD-15E B(25- Comments -
MAH-ELE-CRS-000011
41KM)_CRS Proceed

WO 22- Material Approval for Solar Street Incorporate


10-662154-0000100201-
01 25/07/2021 lighting System by RLCO-RD-15E B(25- Comments -
MAH-ELE-MAT-000004
41KM) Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "WO 22- Material Approval for Solar Street lighting System by RLCO-RD-15E B(25-41KM)"
workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

https://ksa1.aconex.com/Logon 1/2
8/4/2021 Aconex

10-662154-0000100201- EPM DCC B Document Management Incorporate Comments -


MAH-ELE-CRS-000011 Proceed

10-662154-0000100201- Incorporate Comments -


EPM DCC B Document Management
MAH-ELE-MAT-000004 Proceed

https://ksa1.aconex.com/Logon 2/2
7/28/2021 Aconex

Bechtel Document Management Final (WF-004726) WO 22- Pre-qualification for Solar Ligh… 5:47 PM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-010915

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-010915 BEC-WTRAN-010915

Final (WF-004726) WO 22- Pre-qualification for Solar Lighting System (RLCO)-RD-


15E B(25-41KM)

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (5) Kieran Cliffe - Bechtel KSA (+4 more...)

Sent Wednesday, 28 July 2021 5:47:36 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

Work
10-662154-0000100201- WO 22- Pre-qualification for Solar Lighting
01 16/06/2021 May
MAH-ELE-CRS-000008 System (RLCO)-RD-15E B(25-41KM)_CRS
proceed

Work
10-662154-0000100201- WO 22- Pre-qualification for Solar Lighting
01 16/06/2021 May
MAH-ELE-PQD-000004 System (RLCO)-RD-15E B(25-41KM)
proceed

MESSAGE

Workflow Review History

The attached documents have completed the "WO 22- Pre-qualification for Solar Lighting System (RLCO)-RD-15E B(25-41KM)" workflow with
the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

https://ksa1.aconex.com/Logon 1/2
7/28/2021 Aconex

10-662154-0000100201- EPM DCC B Document Management Work May Proceed


MAH-ELE-CRS-000008

10-662154-0000100201-
EPM DCC B Document Management Work May Proceed
MAH-ELE-PQD-000004

https://ksa1.aconex.com/Logon 2/2
6/5/2021 Aconex

Bechtel Document Management Final (WF-003386) WO 022 - Prequalification for Solar Po… 1:04 PM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-006222

10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal BEC-WTRAN-006222 BEC-WTRAN-006222

Final (WF-003386) WO 022 - Prequalification for Solar Pole Supplier (RLCO


FACTORY) RD 15E B

From Bechtel Document Management - Bechtel KSA

To (2) Bechtel Document Management - Bechtel KSA (+1 more...)

Cc (5) Kieran Cliffe - Bechtel KSA (+4 more...)

Sent Saturday, 5 June 2021 1:04:06 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (2)

(0 selected)

Revision
File Document No Revision Title Status
Date

Work
10-660000-0000100201- WO 022- Prequalification for Solar Pole
01 22/05/2021 May
MAH-ELE-CRS-000002 Supplier (RLCO FACTORY) RD 15E B_CRS
proceed

Work
10-660000-0000100201- WO 022 - Prequalification for Solar Pole
01 22/05/2021 May
MAH-ELE-PQD-000002 Supplier (RLCO FACTORY) RD 15E B
proceed

MESSAGE

Workflow Review History

The attached documents have completed the "WO 022 - Prequalification for Solar Pole Supplier (RLCO FACTORY) RD 15E B" workflow with
the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

https://ksa1.aconex.com/Logon 1/2
6/5/2021 Aconex

10-660000-0000100201- EPM DCC B Document Management Work May Proceed Full Material submittal
MAH-ELE-PQD-000002 required for the product

10-660000-0000100201- Full Material submittal


EPM DCC B Document Management Work May Proceed
MAH-ELE-CRS-000002 required for the product

https://ksa1.aconex.com/Logon 2/2
Chris J Myers Final (WF-001609) 14-4800000229/000-IN-Project Mana… 23/06/2021
AECOM WORKFLOW TRANSMITTAL ACM-WTRAN-002229

14 Outer Regions
Riyadh, KSA
Riyadh
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal ACM-WTRAN-002229 ACM-WTRAN-002229

Final (WF-001609) 14-4800000229/000-IN-Project Management - IFR-PQD

From Mr Chris J Myers - AECOM

To (3) Neom Pmc Region 14 - AECOM (+2 more...)

Cc (4) Khaled Ismail - AECOM (+3 more...)

Sent Wednesday, 23 June 2021 11:00:16 AM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Revision
File Document No Revision Title Status
Date

4800000229/000-RLCO PREQUALICATION Incorporate


14-187100-4800000229-
01 15/06/2021 DOCUMENTS (SOLAR LIGHTING Comments -
MAH-ELE-PQD-000006
SYSTEM) Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "14-4800000229/000-IN-Project Management - IFR-PQD" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

14-187100-4800000229- NEOM/AECOM_Review C Myers Incorporate Comments - The contractor should


MAH-ELE-PQD-000006 Proceed provide and include the
below mentioned
document/certificates in the
submittal. 1. Attached
GOSI and ISO certificates
are expired. Valid certificate
should be provided. 2. All
products should be SASO
approved and SASO
certificate should be
provided. 3. Saudization
certificate should be
provided. 4. For imported
parts/equipment country of
origin and “sole
agent/supplier/distributor”
certificate should be
provided. 5. The
manufacturer shall be as
per NEOM approved
vendor list. 6. This PQD is
applicable for
supplier/Brand only, not
valid to purchase/order the
materials, Contractor to
submit separate technical
material submittal for
technical review and
approval to get approval of
the materials.
Mouneimne Ahmad Final (WF-000219) 00-0000100747/000-IN-Construction - IFR 3:50 PM
AECOM WORKFLOW TRANSMITTAL ACM-WTRAN-000415

00 NEOM Wide
NEOM Wide
NEOM
Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal ACM-WTRAN-000415 ACM-WTRAN-000415

Final (WF-000219) 00-0000100747/000-IN-Construction - IFR

From Mr Mouneimne Ahmad - AECOM

To (2) Neom Pmc Region 01 - AECOM (+1 more...)

Cc (4) George Rosales - AECOM (+3 more...)

Sent Wednesday, 27 January 2021 3:50:56 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Revision
File Document No Revision Title Status
Date

00-150000-0000100747-NAP- 0000100747/000 – Lighting Pole-(Renewable Lighting Incorporate


01 24/01/2021
CIV-MAT-000036 Factory for Industry)-(RLCO) Comments - Proceed

MESSAGE

Workflow Review History

The attached documents have completed the "00-0000100747/000-IN-Construction - IFR" workflow with the following results :

This transmittal was automatically generated.

Review
Doc No Step Participant Comments
Outcome

*The submitted 6.0 m lighting pole manufactured by "RLCO" is accepted as noted: *Concrete
00-150000-
Incorporate compressive strength = 35 MPa *A suitable waterproofing system shall be provided. * All metal parts
0000100747- NEOM
M Ahmad Comments & accessories shall be galvanized. *Earthing/grounding system shall be provided. * For precast
NAP-CIV- Review
- Proceed footing: provide underneath polyethylene vapor barrier sheet. *For cast-in place footing: provide
MAT-000036
underneath blinding & polyethylene vapor barrier sheet.

/
RENEWABLE LIGHTING FACTORY FOR INDUSTRY L.L.C
WWW.RLCO.COM.SA
INFO@RLCO.COM.SA
FACTORY ADDRESS :
ALKHARJ ROAD ,EXIT 11( FAWZAN INDUSTRIAL
CITY )
RIYADH ,KSA .
HEAD OFFICE ADDRESS :
AZ-ZUBAIR IBN AL AWAM , AR-RAWABI
RIYADH KSA ,
+966-564223572