ENGINEERING MANAGEMENT
CASE STUDY ASSIGNMENT
PROGRAM: .
SECTION: .
Marks
TITLE Marks Obtained
3. Transportation Model
ENGINEERING MANAGEMENT Case Study / Assignment
OSCM 2
ENGINEERING MANAGEMENT Case Study / Assignment
Inventory plan for Zhou Bicycle Company. The forecasted demand is summarized in the following table.
The manager of that company has been facing problem at the time of placing order every time. Some time it
is incurring too much cost and the order quantity is not right. As a result, over stock or under stock are natural
phenomena for that company. To solve this problem Company Manager appointed a demand planner – Sun
Moon who has recently graduated from “BD University”.
To calculate the right (Economic Order Qty) order quantity Sun Moon collected the following data:
Purchasing Cost/Bicycle: $ 102
Ordering Cost/Order : $ 65
Holding Cost was considered as 20% of per unit purchasing cost.
Questions:
1. What should be the Economic Order Quantity?
2. How many orders should be placed to meet annual demand?
3. What will be the total cost at EOQ?
OSCM 3
ENGINEERING MANAGEMENT Case Study / Assignment
OSCM 4
ENGINEERING MANAGEMENT Case Study / Assignment
D1 200
350 13
S1 14 5
15 17
16 D2 200
19
300 17
S2
16
D3 300
14
19
350 S3
D4 300
13
OSCM 5