Professional Documents
Culture Documents
Construction Management
Construction Management
Model Exam
B) Transport sector
C) Water and Energy Works sector
D) Building and Energy Works sector
7) The main parties in CI are
A) Consultant B) client C) contractor D) owner E) all
8) One of the following is Negative impact of CI
A) Connecting society
B) Decreases protection against radiation in the environment
C) Social, economical and political development
D) Basis for the production and distribution of goods and services
9) A main building stakeholder engaged by owner to carry out and complete the works?
A) Consultant B) client C) contractor D) owner E) all
10) Which one of the following is third party stakeholder?
11) The one who transfers the wish of the owner into realizable form and makes the study, design
and possibly the supervision.
12) …….provides the working capital ,bid bond performance bond and payment bonds in the
construction.
13) -------is used to guarantee a contractor’s intentions in the case of complicated or large-scale
projects.
A) Performance bond B) Bid bond C) Payment bond
14) Payment bond is……..?
A) Required for bidding on a contract and guarantees that if awarded the contractor will
execute the job at the bid they have submitted.
B) Typically required for projects on a state level.
US College Department of Civil Engineering
C) Contractors must post a performance bond when they are awarded a projects to secure
they will perform according to the conditions of the projects.
D) A sum of money safeguard against defective or non-conforming work or materials
provided by the contractor.
15) Which one is correctly ordered for stages of civil engineering construction
1) Tendering Stage
2) Designing Stage
3) Briefing stage
4) Commissioning Stage
5) Construction Stage
16) Which one of the following is roles of consultant during tendering stage
a) Estimates cost and Examine user’s requirement.
b) Assess environmental and political impacts.
c) Examine different site conditions, drainage, water supply, sewerage and electricity.
d) Evaluate bid and select contractor
e) none
17) one of the following is NOT the function of contractors during construction stage
A) Prepare working drawing and schedules
B) Prepare materials, plant and manpower schedules
C) Prepare budget cash flow and fore
D) modify drawings in advance of work
18) one of the is the Project management process groups for any project
A) Initiating and Planning Process
B) Executing Process
C) Monitoring and Controlling Process
D) Closing Process
E) All
US College Department of Civil Engineering
19) The process of tracking, reviewing, and reporting the progress to the meet the performance
objectives defined in the project management plan is…..?
A) Planning Process
B) Executing Process
C) Monitoring and Controlling Process
D) None
20) ………has a definite beginning and a definite end to Construct a infrastructure or facility.?
A) Construction
B) Project
C) Construction management
D) All
21) One of the following is NOT the Project management knowledge areas
A) Project integration management
B) Project scope management
C) Project time management
D) Project quality management
E) none
22) The process of developing a document that formally authorizes the existence of a project and
provides the project manager with the authority to apply organizational resources to the
project activities is….
A) Project Execution
B) Project Management Plan
C) Project Scope Statement
D) Project charter
23) Construction Site Layout Planning is prepared and organized by
A) contractor B) consultant C) owner D) all
24) ………is applying the planned, systematic quality activities to ensure that the project
employs all processes needed to meet requirements.
A) Quality Control B) Quality Planning C) Quality Assurance D) all
25) Project Communications Management includes except
A) Communication planning B) Manage budget resource C) Manage stakeholders
US College Department of Civil Engineering
D) Performance reporting
26) A Project site planning is required for
A) Optimization of time, cost and transport
B) Minimization of damages , accidents and work safety
C) Maximization of work and efficiency operations
D) Minimization of transport times, resource consumptions and Material loss.
27) The processes involved in planning, estimating, budgeting, and controlling costs so that
the project can be completed within the approved budget.
28) Which one the following is NOT Characteristics of the construction site which influences
project site planning
A) Contract Planning
B) Procurement Management
C) Contract Management
D) All
A) Contract type
B) Contract Administration
C) Contract Closing
D) Contract Formulation
32) A process of ensuring the employer and the contractor fulfill all obligations they agreed
upon while signing the contract
A) Contract Planning
B) Contract Administration
C) Contract Management
D) Procurement Management
33) Which one of the following is role of Contracts manager procurement process and contracts
management?
34) A project delivery system is often promoted if the Project Owners believe that there is a
comparative advantage in quality, cost and time.
A) Design-Bid-Build.
B) Force account
C) Design-Build, DB
D) Design-Build-Operate
35) Which one of the following NOT true about Design-Bid-Build project delivery system?
D) Where the designer does not require detailed knowledge of the means and methods
of construction.
36) Which one of the following is advantage of Design-Build project delivery system?
A) Fewer competitors and increased risk may result in higher initial costs
B) Reduced opportunities for smaller, local construction firms
C) minimizing owner’s exposure to design errors and omissions
D) Elimination of traditional checks and balances
37) Assembling project team and assigning their responsibilities are done during which phase of
a project management?
A) Initiation
B) Planning
C) Execution
D) Closure
37) A horizontal bar chart that shows project tasks against a calendar is called
38) While assessing your project processes, you have identified some uncontrolled process
variations. Which of the following would be the appropriate chart you may use for this purpose?
A) Pareto diagram
B) PERT chart
C) Control chart
D) HR personnel chart
39) Due to the rapid expansion of your company, your boss decides to establish a project
management office (PMO) within the company and asks you to take the lead. According to the
PMBOK guide, to be the ideal PMO you can do which of the following?
40) Why does the creation of processes for developing teams, establishing priorities, and
distributing work and tasks require different sets of skills?
42) Which of the following statements about achieving a common understanding of the project
purpose is true?
45) Reasons why estimating time and cost are important include all of the following except:
A) To schedule work
B) To determine how long the project should take and cost
C) To develop cash flow needs D
D) All of the above are valid reasons
A) Labor
B) Materials
C) Equipment
D) A, B, and C are all considered direct costs
47) The process of forecasting or approximating the time and cost of completing project
deliverables is called
A) Budgeting
B) Predicting
C) Estimating
US College Department of Civil Engineering
D) Planning
48) During feasibility analysis it is necessary to examine several alternative solutions because
A) i and iii
B) i and iv
C) i and ii
D) ii and iv
A) Significant Cost
B) Insignificant costs
C) Direct Costs
US College Department of Civil Engineering
D) Indirect Costs
A) Shortening the project duration by reducing the time of one or more critical activities
B) Adding resources at critical points
C) Doing technical analysis of the finished work for review
D) Adding duration to each activity
55) This type of activities can be easily identified by reading the project’s drawings and
specifications
A) Production activities
B) Procurement activities
C) Management activities
D) All
56) The successor activity can begin only when the current activity complete is
A) Finish to start
B) Finish to finish
C) Start to start
US College Department of Civil Engineering
D) Start to finish
57) …. is the determination of the timing of the activities including the project to enable
managers to
A) Project Planning
B) Project Scheduling
C) Project Closing
D) 58)
58) ……..is a graphical representation of a project, depicting the flow as well as the
sequence of well-defined activities and events
A) Schedule
B) Network
C) Activity
D) All
59) The maximum amount of time an activity can be delayed from its early start without
delaying the entire project.
A) Interfering Float
B) Free float
C) Total float
D) Independent float
61) The Overall in-charge of an organisation at the site responsible for the execution of the
works, is
A) Executive Engineer
B) Engineer
C) Junior Engineer
D) Assistant Engineer
A) Material
B) Manpower and money
C) Machines and equipments
D) All
A) Performance Analysis
B) Quality Metrics
C) Process Improvement Plan
D) Quality Improvement Plan
64) Mr.’ X’ has joined as the Project Manager of a project. One of the project documents
available to Mr.’ X’s lists down all the risks in a hierarchical fashion. What is this document
called?
65) Same Consultancy is planning to buy ten desktops for ETB20000 each from a leading
computer store. Which type of contract will get signed in this case?
A) Purchase Order
B) Cost plus Fee
US College Department of Civil Engineering
C) Fixed cost
D) Time and Material.
66) Selamawit is a Project Manager. She is coordinating a bidder conference to allow vendors to
get clarification on the work that needs to be performed. Which phase of Project Management is
in progress?
A) Conduct Procurements
B) Plan Procurements
C) Control Procurements
D) Close Procurements
67) The first preferred way to resolve a dispute between the contracting parties is:
A) Arbitration
B) Litigation
C) Negotiation
D) Mediation
68) Following document define the legal rights and obligations of the parties and may be
described as the regulations under which the contract will be performed.
A) Specifications
B) General Conditions of Contract
C) Special provisions
D) Bill of Quantities
69) The minimum notice period for National Competitive bidding is:
A) 30 days
B) 45 days
C) 35 days
D) 15 days
70) The authority to make design changes in the field during construction can be exercised by
which of the following persons?
US College Department of Civil Engineering
71) When you receive the contractor's interim payment certificate (IPC) on a unit-price contract
project, the engineer or resident project representative should:
A) Just initial the form and forward it to the owner as no field review is necessary.
B) Reject it.
C) Check only the contractor's arithmetic on its payment request, while you "eyeball"
estimate the amount of work completed to see if it appears to compare favorably with the
contractor's claim.
D) Check the contractor’s entire field quantities accurately, along with all materials
delivered to the site, and the contractor's claims to percentages of the various parts of the
work completed.
72) Under a Differing Site Conditions clause, who is responsible for the timely removal,
relocation, or protection of any existing main utility facilities on a project site where such
utilities are not shown accurately on the Construction Drawings and could not be observed
during a pre-bid site visit?
A) design engineer/architect
B) contractor
C) Public Agency/owner of the project
D) Utility company who owns the utility line
73) A resident engineer may direct a change in the Work when such change is authorized in
writing by:
A) a code requirement
B) a subcontractor
C) a Supplier
D) the owner
US College Department of Civil Engineering
74) Determining what resources and quantities will be used for the project is part of:
A) Cost budgeting
B) Cost estimating
C) Resource planning
D) Cost control
76) Which one of the following outsourced financing project delivery system?
A) Design-Build-Finance-Operate
B) Build-Own-Operate
C) Build-Operate-Transfer
D) all
77) A private company is contracted to finance, design, construct, operate for a certain period
(usually 10 years) and transfer is
78) --------- is an Agreement between two or more parties to do or not to do something for a
certain consideration
A) Procurement
B) Contract
C) Tendering
D) Bidding
US College Department of Civil Engineering
A) legal part
B) technical part
C) commercial part
D) all
83) Which one of the following construction contracts is fixed price payment methods?
84) The contractor will receive the actual direct job cost plus a fixed percentage, and have little
incentive to reduce job cost.
A) Lump Sum
B) Unit price
C) Cost plus fixed percentage
D) Cost Plus Variable Percentage
A) General condition
B) Supplementary condition
C) Specifications
D) agreement
A) structural drawings
B) architectural drawings
C) mechanical drawings
D) electrical drawings
A) a project takes to pay back the loan taken to purchase the capital assets
B) equal to the useful life of the machines
C) a project takes to recover its initial cash outflow
D) over which the project will be getting operating cash inflows
88) Which of the following represents the estimated value of the work actually accomplished?
A) Start Activity
B) Critical Activity
C) Dummy Activity
D) End Activity
A) Equity Shares
B) Preference Shares
C) Debenture
D) All
A) Long-term Loans
B) Fixed Deposits
C) Bank Credit ,Customer Advances and Trade Credit
D) All
A) Preference shares
B) Equity shares
C) Deferred shares
D) Debenture
A) Excessive noise
B) Excessive overtime work for labor
C) Lack of awareness of safety regulations
D) Operating equipment without authority
E) all
US College Department of Civil Engineering
A) Scope
B) Resources
C) Team
D) Budget
95) Costs that are not directly related to the products or services of the project but are indirectly
related to performing the project.
A) Intangible Costs
B) Sunk Cost
C) Tangible Costs
D) Indirect Costs
96) The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
A) Slowly rise
B) Slowly drop
C) Drop sharply and then level out
D) Rise sharply and then level out
97) When classifying and ranking projects, which of the following refers to the extent to which
the project is viewed as helping the organization achieve its strategic objectives and long-term
goals?
A) Resource availability
B) Business placement
C) Strategic alignment
US College Department of Civil Engineering
D) Potential benefits
99) Which of the following is a main reason why project managers need to understand their
organization's mission and strategy?
100) The first step in creating the necessary information to manage a project is to