Rev. No.

: 03
WORK ORDER TYPES Rev. Date: xx-xx-xxxx
Reference No.: W3-02-01

Work Order Type Codes


The Work Order Type Code indicates the nature of the asset management work. This code is applied to a
work order when it is approved. This code is essential for sorting the Ready Backlog during the planning
and scheduling processes and later for operational and KPI reporting of historical information.

WO Types WO Sub-Type Codes Description / Use Examples


CM-Replace Replacement of item by new Replacement of a worn-out bearing
or refurbished item of the
same type and make
CM-Repair Maintenance action is to Repack, weld, plug, reconnect, remake,
restore an item to its original etc.
state.
CM-Adjust Bringing any out-of- Align, set and reset, calibrate, balance,
tolerance condition into etc.
tolerance
CM-Refit Minor repair/servicing Polish, clean, grind, paint, coat, lube, oil
activity to return the item to change, etc.
an acceptable appearance,
Corrective
internal or external
Maintenance
CM-Troubleshoot The cause of the issue is Restart, resetting, no maintenance
(CM)
investigated, but no action, etc.
maintenance action is
performed, or the
maintenance action is
deferred. Able to regain
function by simple
maintenance actions, e.g.,
restarting or resetting
CM-Overhaul Major overhaul of a piece of Comprehensive inspection/overhaul
equipment with extensive disassembly and
replacement of items as specified or
required
PM-Inspection Periodic inspection/check: All types of general checks. Includes
scrutiny of an item carried minor servicing as part of the inspection
out with or without task.
dismantling, generally by the
Preventive
use of senses
Maintenance
PM-Service Tasks Periodic service tasks Cleaning, changing filters every month,
(PM)
(normally no dismantling of adjustments, and calibrations on a set
item) schedule.
PM-Test Periodic test of function Function test of gas detector, fire
performance alarms, a test of flow meter
PDM-Thermography Use of specific technologies Periodic checks using thermography
to monitor the condition of technologies to measure variables
Predictive
the equipment related to equipment condition
Maintenance
PDM-Ultrasonic Use of specific technologies Periodic checks using ultrasonic
(PDM)
to monitor the condition of technologies to measure variables
the equipment related to equipment condition

Page 1 of 2
Rev. No.: 03
WORK ORDER TYPES Rev. Date: xx-xx-xxxx
Reference No.: W3-02-01

WO Types WO Sub-Type Codes Description / Use Examples


PDM-Oil Analysis Use of specific technologies Periodic checks using oil analysis
to monitor the condition of technologies to measure variables
the equipment related to equipment condition
PDM-Vibration Use of specific technologies Periodic checks using vibration
to monitor the condition of technologies to measure variables
the equipment related to equipment condition
PRJ-Modify Replace, renew, improve, or Install a filter with a smaller mesh
Project change an item (or part of diameter, replace a lubrication oil pump
Maintenance the item) with an item/part with another type, reconfigure, etc. It
(PRJ) of a different type, make, could be CAPEX or OPEX.
material, or design.
Service SM Used to track minor service Hanging paper towel dispensers,
Maintenance tasks hanging whiteboard, mowing, moving
(SM) furniture, etc.
ST-Meeting Used to capture technicians Technicians attending departmental or
attending meetings. Set up plant-wide meetings.
as a standing work order.
ST-Training Used to track technicians Technicians are attending skills training
Standing (ST) attending training, seminars, sessions.
etc. Set up as a standing
work order.
ST-Wrench Used to capture Technicians watching a production line
miscellaneous wrench time. come up after wash down.
Asset Asset Reliability Review Used to capture reliability Root Cause Analysis (RCA), Failure Mode
Reliability (AR) review and analysis work and Effects Analysis (FMEA)

Page 2 of 2