PR.09 Materials and Equipment Storage and Preservation0
PR.09 Materials and Equipment Storage and Preservation0
09
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
AMENDMENT RECORDS
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
1. PURPOSE
The purpose of this procedure is to establish the procedural steps necessary to control
handling, storing, preservation and transportation materials and equipment.
2. SCOPE
This procedure is applicable to all project materials and equipment of scope of work as
described;
A new booster pump station for the combined fire water/raw water system including a
chlorination room, an operator’s office for the occupancy of up to two (2) persons with
washroom and prayer room, a MCC room with control and switch panels. HVAC and
communications requirements and the requirements for a Store Room to be established after
discussion with SA Utilities.
The new raw water supply to the booster pump room including a tie-in to the source line with a
new manhole in accordance with WASA requirements.
Site development of Home Ownership lots as per Master plan.
Other lots as per Master plan: one (1) girls’ school, one (1) library, two (2) mosques, one (1)
commercial area, one (1) community support facility, parking lots and three (3) gardens.
Lots monuments construction.
Combined fire water/raw water network.
Wastewater network including tie-in to existing system.
Storm water drainage system (including a new evaporation pond located in Increment IV for
the southern portion of the site).
Primary and secondary electrical systems.
Telephone distribution system.
Tie-in to the Mubarraz-Salmaniyah Road.
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
4. REFERENCES
Schedule B
Schedule D
Schedule G
Schedule Q
SAEP-385 Preservation of Project Materials and Equipment
SAEP 381 Project Quality Issues Escalation Process
SAES-A-004 General Requirement for Pressure Testing
SAES-A-007 Hydrostatic Testing Fluids & Lay-up Procedures
SAES-A-113 Geotechnical Engineering Requirements
SAES-A-114 Excavation and Backfill
SAES-B-019 Portable, Mobile and special Fixed Firefighting equipment
SAES-D-100 Design Criteria of Atmospheric and Low Pressure Storage Tanks
SAES-H-001 Coating Selection & Application Requirements for Industrial Plants & Equipment
SAES-H-002 Internal and External Coatings for Steel Pipelines and Piping
SAES-H-002V Approved Saudi Aramco Datasheets for the Pipeline and Piping Coatings
SAES-H-101V Approved Saudi Aramco Datasheets – Painting & Coating
SAES-H-102 Safety Requirements for Coating Applications
SAES-J-003 Instrumentation and Control Building – Basic Design Criteria
SAES-J-100 Process Measurement
SAES-J-600 Pressure Relief Device
SAES-J-902 Electrical Systems for Instrument
SAES-K-001 Design and Installation of Heating, Ventilating and Air Conditioning Systems
SAES-K-100 Saudi Aramco Mechanical (HVAC) Code
SAES-K-101 Regulated Vendor List for HVAC Equipment
SAES-L-100 Applicable Codes and Standards for Pressure Piping System
SAES-L-101 Regulated Vendor List for Pipes and Fittings
SAES-L-102 Regulated Vendor List for Valves
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
5. RESPONSIBILITIES
5.1. Project Manager : Ensure compliance by all parties to this procedure, Quality Manual,
Inspection & Test plan and relevant Customers Specifications, Drawings and current Industry
Codes.
5.3. Construction Manager: Ensure compliance by all craftsmen to the content of this procedure,
Quality Manual, Inspection & Test Plan and Customers Specifications.
5.4. Superintendent/Supervisor: Ensure compliance by all drivers, riggers & other associated
craftsmen to the requirement of this procedure, relevant Specifications and QC Inspection
requirements.
5.5. Store Supervisor: Ensure Material are stored and handled in accordance to this procedure,
manufacturer's recommendations, project standards & specification.
5.6. Quality Control Inspector: Conducts inspections and periodic item preservation surveys in
accordance with this procedure project standards & specification.
6. PROCEDURE
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
In Laydown Area there will be as minimum below listed facilities for storage of items in
project site;
- Open areas
- Shaded Araes
- Closed buildings, containers, etc
- Temperature controlled closed buldings, containers, etc.
Addition to laydown area, depending on volume and frequency of items to be used, in project
site new storage facilities can be established.
Laydown area is mainly divided in three parts (Aramco, SEC, STC) as per items’ end users. And
each area will be divided in sub area for each discipline.
To identify and arrange the storage area, below listed criteias will be in consideration.
Dimension of storages will depend on quantity and usage frequency of them at site.
Store supervisor will be responsible to update and maintain storage areas on a layout and
make propor separation, identification of areas and sub-areas and items.
QA/QC department would be informed on time for the delivery date at project site to check
the transportation situation of Items before and on unloading from vehicle.
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
Pre-receiving
Warehouse staff handle the Items and store them as per approved MR and/or MSDS and/or
manufacturer manual of Item. Small Items have to be temporarily stored on designated
receiving ares in warehouse. To complete pre-receiving, warehouse staff compare the actual
Item quantity (By counting, weighting. etc.) with received vendor’s invoice/delivery note and
MCC’s PO. Warehouse staff prepare ‘Item Receipt Slip’ and in case of any deviation and
damage prepares Over Short and Damage Material Report.
Receiving Inspection
Item Receiving Inspector prepares related inspection package document (Inspection checklist,
drawings (if any), approved MR, test reports (MTC, TPI reports)) and start to internal inspect of
Item as per inspection checklist. In case of any deficiency, Item Receiving Inspector informs
Procurement department to coordinate vendor to take immediate action(s).
Item Receiving Inspector prepares Item Inspection Request (MIR) and submits it to Client for
External Inspection. Once client approve the inspection, Warehouse department stores Items
in designated location and sends a copy of ‘Item Receipt Slip’ to Procurement Department.
QC Inspector uses proper labels on items showing the result inspection as ‘Accepted’,
‘Rejected’ or ‘Hold’.
Starting Item receiving stage up to end of usage stage (installation, constructing etc.), the
required manufacturer tags, labels, etc must be kept on Items. If tag is not available,
Warehouse department must reproduce another lable for the identification. Each tag must
contain minimum requirement that described in related SAICs and must contain a traceability
number to reach the manufacturing history of Items.
Handling and preservation of items will be done based on Client requirements and
Manufacturer recommandations. If Client requirements will exceed the manufacturer
recommendations, manufacturer recommendations will be followed.
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
This weekly surveys will cover installed, erected items, backlog of incomplete, pastdue jobsite
equipment/piping preservation, hydrostatic pressure test, layup, and reinstatement activities
(Buildings, Tanks, pipes, etc), too. Any change on those installed, erected items Mastoura will
infor Client to take proper actions.
6.6. Quarantine area
Mastoura will identitfy the quarantine area for the rejected materials. Upon receiving or
rejected from site due to any reason. For any rejected material mastoura will mark rejected on
that material with red or black spray. During the departure of that material from quarantine
area to out of project or vendor facilty mastoura will inform through e-mail or call to SAPID
for witness and mastoura will also maintain the all record of rejected material in log for
tracibilty.
Procurement Manager coordinating with Top Management moves the quaranteen materials
Rev. No : 01
Item Storage and Preservation Procedure
Date : 11-Jul-21
away from Quarantine Area to ensure rejected materials shall not be used for project and
provide available space in that particular area to the temporarily storage of the possible future
material rejections.
Storage Supervisor updates damaged items with Damaged Items Tracking Log on time. This
log will be shared by Project Management when any item received to quarateen area and
release from there. Project Management informs Client for the each movement of damaged
items by email.
7. RECORDS