Professional Documents
Culture Documents
MOM of Eden 26.02.2024
MOM of Eden 26.02.2024
Points
Sl No Discussed Concerns Status Remarks
How many additional borewells will be provided to meet the AS per MOM -
requirement of phase 1 + 2 + 3 + 4 Close Century -
05.12.2023
Leakage and open taps to be addressed Close
1 Water Cleaning of sump and OHT AS per MOM -
Open Century -
05.12.2023
Commissioning of WTP as water being supplied is not potable
Close
AS per MOM -
Opening issues has not been fixed yet. Residents surveyed Close Century -
Compound and report sent 05.12.2023
4 wall
Kindly provide a permanent solution by replacing the broken
concrete wall Close
Nala /
Artificial
7
Water Body /
Rajkaluwe AS per MOM -
Open Century -
05.12.2023
17th & 18th cross legal issue(Series 490 to 521) on Area
Dimensions (Schedule B) - Deed rectification and Masterplan
updation
AS per MOM -
Close Century -
05.12.2023
8 Legal Issues
Near OHT empty land inside EDEN - brief about the barren
land + Clean + Gated Close
AS per MOM -
Entry of visitors / vendors / vehicles / maids - not being Close Century -
recorded in MyGate & Ledger
05.12.2023
Safety & Speed breaker to be provided / Speed marker Boards to be
10 MyGate AS per MOM -
installed Open Century -
05.12.2023
Safety &
10 MyGate
Notice Board Under Construction guidelines as defined in the sale deed - AS per MOM -
11 Guidelines Draft shared Century -
Close 05.12.2023 -
Link # 7
Shared
Plumber /
15 Electrician Need clarification Close
etc. with
Wintersun
Shared
Electricity &
16 Water with Need clarification Close Link # 5
Phase-2/3/4
construction
Multi Storey Owners need to identified and explained the single dwelling
17 Close
Construction concept in EDEN
19 CAM charges
CAM invoices to be rectified as per actual area - Refer Point AS per MOM -
19 CAM charges 8a Close Century -
05.12.2023
It is agreed in the previous meeting that the CAM charges will AS per MOM -
kept in abeyance until the open issues are not closed. Close Century -
05.12.2023
No approval taken to utilize the fund AS per MOM -
Open Century -
05.12.2023
Utilization report n/a AS per MOM -
20 Sinking Fund Open Century -
05.12.2023
Audit of Sinking Fund AS per MOM -
Open Century -
05.12.2023
REH MOM - Summary
Remarks- Century
CLOSED
Ongoing activity with high cost. We will take the next cleaning drive on receipt of
CAM from maximum residents
WTP is not a part of the project deliverables but we can share a couple of
proposals
STOPPED/CLOSED
CLOSED
CLOSED
CLOSED.
CLOSED, Had a walk with committee member and showed each n every
points mention in the list. If there are still any points left or new openings due
to waer and tear, we can fix it.
CLOSED
Ongoing activity with high cost. We will take the next servicing drive on receipt
of CAM from maximum residents
Century would provide single phase, but the cables are provisioned for 3 phase
connection.
Once the work completes, key will handled by FM team/adhoc committee. Last
mile work left.
95% of the job is done to refix the lights and their connections which were in
good state earlier.
CLOSED
WIP, will be finished on or before March 2024. It is a rework due to wear & tear.
Closed
Huge capital expenditure and necessary approvals needed. Can create more issues.
However existing set up will be monitored to avoid inconvience to residents
Due to statuatory restirctions the nala cannot be concealed with pipes as blockages
would lead to water being flushed back to the village.But nala is cleaned now, we
will cut the weeds any in the pathway. Any additional capital expenditure can only
we reviewed on receipt of CAM charges from maximum residents
we have reached out to customers were the physical area is less and shared the
revised CAM invoice. In most cases, the sale value was calcuated basis the actucal
size of the plot and therefore no concerns. Cases where area considered for CAM
billing had to be relooked is taken care and revised invoice is shared
As the case is not filed on century, we would need an update on current status
from the impacted party to proceed further and assist.
CLOSED
Staffing can be improved and quality of manpower too. We urge all residents to
pay the CAM charges. Already requested the agency to appoint new gaurds,Will
deploy the extra gaurds and they will take care every 6 cross.
CLOSED
Strict instruction given to Security Supervisor and Gaurds, and Mygate is being
use effectively. Without Mygate approval no delivery, cabs , gas delivery is not
allowed.
Initated
will install the speed limit board before March 10th 2024 and as well as security
will instruct the visitor to maintain the speed limit
Covered under construction guidelines
Closed.INITIATED
Initated
Weed cutting completed from 1st to 18th cross and it’s a regular pracrtice which is
going to happen further and Street maintenance is happening daily. 2nd time weed
cuting started from 1st cross
Closed Fencing of the parks will be reviewed once we have the CAM for most
cases
CLOSED/STOPPED
Closed
No such agreement. In fact it was agreed that Century will initiate work basis the
inputs received from the owners however the owners will continue to pay the
CAM
No CAM paid for since release deed and even after club house was handed over.
Century has spent over and above the Corpus amount.