HW - 1 - PEQ 303 - Dr. Adel Salem - Fall 2023

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Dr. Adel M.

Salem
Al-Azhar University
Faculty of Engineering, Qena Branch

Petroleum and Gas Assignment Fall 2023


Production Eng. No. 1 Oct. 21, 2023
PEQ 303

Part 1: Answer all the following:


1. Define each of the following:
a. Inflow performance relationship, IPR
b. Productivity Index, PI (=J)
c. Bubble point pressure

2. Draw the following:


a. a simple sketch of the Composite Production System, indicating
clearly the systems start and end points
b. IPR for three driving mechanism reservoirs.
c. PI for three different driving mechanism reservoirs.

3. What is the main reservoir driving mechanisms, describe in detail with


drawing?
4. Describe the main equipment of petroleum production system with
drawing

Part 2: Solve all the following:


1. A well that is producing from a reservoir having an average pressure of 3000
psig produced at a rate of 250 STB/day when bottom hole flowing pressure
was 1800 psig.
Calculate:
1. The productivity index, J.
2. The production rate if BHFP is decreased to 1500 psig.
3. The bottom hole flowing pressure (BHFP) necessary to obtain 450
STB/day.
4. AOF

Page 1 of 3 HW #1_ Dr. Adel M. Salem


Part 3:

1. Write down the missing labels from the following figures:

A. Write down the equipment listed in the following figure (1 to 4)

3 4

B. write down the parameter 1 and 2 for the given IPR

12

Page 2 of 3 HW #1_ Dr. Adel M. Salem


C. Write down the different reservoir driving mechanisms below

5
1

4
2

3
1

0
0 20 40 60 80 100

Cumulative oil produced, percent of original oil in place

All best wishes


Prof. Adel Salem

Page 3 of 3 HW #1_ Dr. Adel M. Salem