METHOD STATEMENT FOR PAINTING

Project: Construction of Cargo Warehouse,


Hyderabad.

Client: GMR Airport Development Limited


Method Statement for Painting
Rev. 1
PROJECT Cargo Warehouse
CLIENT GMR Airport Development Limited
CONTRACTOR Consolidated Construction Consortium Limited Page 2 of 6

PAINTING

1. KNOWLEDGE OF ACTIVITY

1.1 STORAGE OF PAINT

All containers of paint, thinners and allied materials shall be stored preferably in a separate room.

The room shall be well ventilated and free from excessive heat, sparking and direct rays of the sun.

The lids of containers shall not be opened except when using the paint. The paint shall be used

before the expiry of its shelf life marked on the containers.

1.2 CHECKS PRIOR TO START OF WORK

1. The approved and duly certified shade and type of paint shall be made available at site in
sufficient quantity.

2. Ensure that the wall and ceiling surfaces are completely dry prior to the application of paint.

3. Ensure that all furniture and the flooring is protected before starting the painting works.

4. Proper scaffolding arrangement with safety measures to be taken.

5. All loose particles, dirt and dust must be thoroughly scrubbed from the surface using sandpaper.

6. All painting accessories like brush, roller, mixing tray etc to be thoroughly cleaned and washed
outside the working premises before starting the works.

7. Before starting the putty ensure the surface leveling on ceiling.

[Type text] Page 2


Method Statement for Painting
Rev. 1
PROJECT Cargo Warehouse
CLIENT GMR Airport Development Limited
CONTRACTOR Consolidated Construction Consortium Limited Page 3 of 6

8. Application of 2 putty coats, ensure the first coat is thoroughly dried before applying the final
coat.

9. Putty to be applied uniformly to cover all undulations.


11. Proper sanding of surfaces to render a smooth surface prior to the application of primer and
paints. Ensure that the dust on the surface is thoroughly wiped off after sanding the puttied surface.

10. After the putty primer application with brush dilution ratio not to exceed 1:1 with water as thinner
solvent.

1.3 GUIDELINES TO OBSERVE WHILE PAINTING

1. First coat paint to be applied with brush and finished with roller preferably with single mix and
dilution ratios not to exceed the below said criteria. i.e., 2 parts of paint to 1 part of water.

2. Ensure a drying period of 4 to 6 hours before application of the final coat of paint.

3. All external walls and semi-exposed areas such as balconies and utility walls, to be given a
textured finish.

2. TOOLS TO BE USED BY TRADESMEN

Required tools must be available at site to ensure correct work. Basic tools of the painting
gang are:
1. Paint brushes
2. Rollers
3. Trowels
4. Line dory
5. Tube levels
6. Plumb bobs
7. Aluminum straight edge
8. Leveling threads

[Type text] Page 3


Method Statement for Painting
Rev. 1
PROJECT Cargo Warehouse
CLIENT GMR Airport Development Limited
CONTRACTOR Consolidated Construction Consortium Limited Page 4 of 6

3. METHODS FOLLOWING IN PAINTING

3.1 Internal Painting

1. In internal painting the first step is rendering the all ceiling areas to get even leveled surface.

2. Clean the all mortar droppings and any other foreign materials.

3. Mixing the putty with water as per specifications and start the first coating of putty uniformly and

level the all undulations in walls and ceilings.

4. Leave it to one day dry and next day will start the second coating of putty to appear smooth

finishing.

5. Leave the surfaces two days to dry and start the proper sand papering on surfaces.

6. After the sand papering the primer coat applying will start on surfaces.

7. Finally the three coats of painting shall be start.

3.2 External Painting

1. Clean the all mortar droppings and any other foreign materials in the external wall.

2. Apply the first coat of exterior textured paint evenly on the wall surfaces.

3. The second coat to be start after the first coat dry.

4. Completion of second coat textured paint one coat of primer to be start.

5. After primer applying water proof paint of approved color and shade is to be applying.

6. Where ever textured paint is not require there follow the internal painting procedures as above.

[Type text] Page 4


Method Statement for Painting
Rev. 1
PROJECT Cargo Warehouse
CLIENT GMR Airport Development Limited
CONTRACTOR Consolidated Construction Consortium Limited Page 5 of 6

4. SAFETY:

Safety supervisor / steward should ensure that Hazard Identification & Risk Analysis (HIRA) is
followed for this particular process.

5. INSPECTION:

All the step by step activities should be carrying out as per approved methodology and GFC
Drawing to the satisfaction of customer/Inspection Authority.

6. DOCUMENTATION:

• Inspection Check List for Painting.


• Field Quality Plan.

....END OF DOCUMENT….

[Type text] Page 5


Method Statement for Painting
Rev. 1
PROJECT Cargo Warehouse
CLIENT GMR Airport Development Limited
CONTRACTOR Consolidated Construction Consortium Limited Page 6 of 6

[Type text] Page 6