Daily Progress Boiler Valve U3 Outage 2023
Daily Progress Boiler Valve U3 Outage 2023
Daily Progress Boiler Valve U3 Outage 2023
0 1.1 0.56 1.39 4.72 3.33 2.22 2.78 3.89 5.28 6.11 6.67 6.11 5 5.56 4.94 5.78 6.44 6 4.5 3.61 2.5 1.72 1.11 0.89 0.83 0.83 1.11 1.11 1.39 1.33 0.83 0.28 0.06 0.00
0 1.1 1.66 3.05 7.77 11.1 13.3 16.1 20 25.3 31.4 38.1 44.2 49.2 54.7 59.7 65.4 71.9 77.9 82.4 86 88.49 90.21 91.32 92.21 93.04 93.9 95 96.1 97.5 98.8 100 99.9 99.98 100 PLAN
Legend :
PTW Received 5% PLAN overall work progress up today : 100.00%
Work plan for tomorrow:
Overhaul 6 ~ 15% Assist Instrument team to calibration Flash Pipe Level control valve 03LCQ02AA700 (1st floor)
Cleaning 16 ~ 25%
Repair 26 ~ 45%
Lapping 46 ~ 65%
Contact Check 66 ~ 75%
Reassembly 76 ~ 95%
Painting 96 ~ 99%
Completed 100%
Obstacles:
ACTUAL
PLAN
18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22