Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Q
Duration Complete Jan
Nov Dec
MFG00772 Cordova - Plant Expansion & 382
Modernization 276 35.01% 01-Dec-10 A 30-May-12 0

MFG00772.Auto Automated System 260 154 62.54% 01-Dec-10 A 08-Dec-11 121

MFG00772.Auto.DesEng Design Engineering 52 0 100% 01-Dec-10 A 14-Feb-11 A


MN1000 Define System Requirements 5 0 100% 01-Dec-10 A 09-Dec-10 A Define System Requirements
MN1010 System Design 40 0 100% 08-Dec-10 A 01-Feb-11 A
MN1120 Prepare Drawings for Temp Control Equipment 5 0 100% 24-Jan-11 A 28-Jan-11 A
MN1130 Prepare Drawings for System Controller 5 0 100% 24-Jan-11 A 28-Jan-11 A
MN1190 Review and Approve System Controller 10 0 100% 01-Feb-11 A 14-Feb-11 A
MN1180 Review and Approve Temp Control Equipment10 0 100% 02-Feb-11 A 14-Feb-11 A
MN1270 Approve System Design 5 0 100% 07-Feb-11 A 11-Feb-11 A
MFG00772.Auto.SysEng System Engineering 158 103 56.84% 14-Feb-11 A 26-Sep-11 172
MN1300 Site Preparation 2 0 100% 14-Feb-11 A 15-Feb-11 A
MN1360 Installation Begins 0 0 100% 16-Feb-11 A
MN1370 Install Electrical Power 27 0 100% 16-Feb-11 A 25-Mar-11 A
MN1760 Test & Debug Line A 24 24 0% 04-Aug-11 07-Sep-11 124
MN1770 Test & Debug Line B 24 24 0% 04-Aug-11 07-Sep-11 124
MN1840 Pilot Start Line A 1 1 0% 07-Sep-11 07-Sep-11 124
MN1850 Start-Up Line B 1 1 0% 07-Sep-11 07-Sep-11 124
MN1860 Path Refinement and Shakedown-Line A 10 10 0% 08-Sep-11 21-Sep-11 124
MN1870 Path Refinement and Shakedown-Line B 10 10 0% 08-Sep-11 21-Sep-11 124
MFG00772.Auto.SysEng.TempCtl Temperature Control 54 Equipment 20 100% 15-Feb-11 A 27-May-11 121
MN1310Prepare and Solicit Bids for Temp Control Equip
10 0 100% 15-Feb-11 A 28-Feb-11 A
MN1430Review Bids for Temp Control Equipment 3 0 100% 04-Mar-11 A 08-Mar-11 A
MN1450Award Contract for Temp Control Equipment 1 0 100% 09-Mar-11 A 09-Mar-11 A
MN1460Fabricate & Deliver Temp Control Equipment 16 0 100% 10-Mar-11 A 01-Apr-11 A
MN1520Install Temperature Control Equipment 20 20 100% 05-Apr-11 A 27-May-11 124
MFG00772.Auto.SysEng.RobotCtl Robot Controller 156 83 35.65% 16-Feb-11 A 26-Sep-11 121
MN1380Install Robot Base 18 0 100% 16-Feb-11 A 09-Mar-11 A
MN1390Run Sealant, Air, and Water Piping 11 0 100% 16-Feb-11 A 04-Mar-11 A
MN1560Set & Connect Robots 18 18 44.44% 31-May-11 23-Jun-11 124
MN1790Trim Robot Paths Line B 24 24 0% 04-Aug-11 07-Sep-11 124
MN1810Trim Robot Paths Line A 15 15 0% 17-Aug-11 07-Sep-11 124

Actual Level of Effort Remaining Work Page 1 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 1, 2011 Qtr 2, 2011
Jan Feb Mar Apr May Jun

14-Feb-11 A, MFG00772.Auto.DesEng Desig n Engineering

System Design
Prepare Drawings for Temp Control Equipment
Prepare Drawings for System Controller
Review and Approve System Controller
Review and Approve Temp Control Equipment
Approve System Design

Site Preparation
Installation Begins, 16-Feb-11 A
Install Electrical Power

27-May-11, MFG00772.Auto.SysEng.Tem
Prepare and Solicit Bids for Temp Control Equip
Review Bids for Temp Control Equipment
Award Contract for Temp Control Equipment
Fabricate & Deliver Temp Control Equipment
Install Temperature Control Equipment

Install Robot Base


Run Sealant, Air, and Water Piping

Actual Level of Effort Remaining Work Page 2 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 3, 2011 Qtr 4, 2011
Jul Aug Sep Oct Nov Dec

26-Sep-11, MFG00772.Auto.SysEng System Engineering

Test & Debug Line A


Test & Debug Line B
Pilot Start Line A
Start-Up Line B
Path Refinement and Shakedown-Line A
Path Refinement and Shakedown-Line B
0772.Auto.SysEng.TempCtl Temperature Control Equip ment

Control Equipment
26-Sep-11, MFG00772.Auto.SysEng.RobotCtl Robot Controller

Set & Connect Robots


Trim Robot Paths Lin e B
Trim Robot Paths Lin e A

Actual Level of Effort Remaining Work Page 3 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Q
Duration Complete Jan
Nov Dec
MN1940Calibrate Robot Controller & Power Up 1 1 0% 26-Sep-11 26-Sep-11 124
MFG00772.Auto.SysEng.SysCtl System Controller 145 91 28.57% 15-Feb-11 A 08-Sep-11 131
MN1320Prepare and Solicit Bids for System Controller 5 0 100% 15-Feb-11 A 21-Feb-11 A
MN1400Review Bids for System Controller 4 0 100% 22-Feb-11 A 25-Feb-11 A
MN1420Award Contract for System Controller 1 0 100% 01-Mar-11 A 01-Mar-11 A
MN1440Fabricate and Deliver System Controller 60 39 80% 02-Mar-11 A 24-Jun-11 163
MN1590Install System & Misc. Components 30 30 0% 23-Jun-11 04-Aug-11 124
MN1780Install System Controller 16 16 0% 04-Aug-11 25-Aug-11 134
MN1800Install Bar Rails 20 20 0% 11-Aug-11 08-Sep-11 134
MFG00772.Auto.SoftEng Software Engineering 54 54 0% 22-Sep-11 08-Dec-11 121
MN1920 Install Processor/Software/Data Tapes 2 2 0% 22-Sep-11 23-Sep-11 124
MN1930 Production Start 0 0 0% 22-Sep-11 124
MN1950 Load System Software 20 20 0% 27-Sep-11 24-Oct-11 124
MN2030 Program 0 0 0% 25-Oct-11 25-Oct-11 124
MN2040 Test Software 18 18 0% 25-Oct-11 17-Nov-11 124
MN2050 Manual Operation Ready 0 0 0% 25-Oct-11 25-Oct-11 124
MN2110 Debug Software 1 1 0% 18-Nov-11 18-Nov-11 124
MN2120 Automatic Operation Ready 1 1 0% 21-Nov-11 21-Nov-11 124
MN2100 Startup Procedure Development 3 3 0% 22-Nov-11 25-Nov-11 124
MN2170 System Buyoff 0 0 0% 08-Dec-11 124
MFG00772.Auto.Train Training 9 9 0% 25-Nov-11 07-Dec-11 121
MFG00772.Auto.Train.Manual Manuals 9 9 0% 25-Nov-11 07-Dec-11 121
MN2140Training Manuals/System Operation 9 9 0% 25-Nov-11 07-Dec-11 124
MFG00772.Bldg Office Building Addition 246 140 32.57% 01-Dec-10 A 17-Nov-11 135

MFG00772.Bldg.DesEng Design and Engineering 29 0 100% 01-Dec-10 A 12-Jan-11 A


MN1020 Design Building Addition 15 0 100% 01-Dec-10 A 20-Dec-10 A Design Building Addition
MN1030 Review and Approve Designs 2 0 100% 22-Dec-10 A 23-Dec-10 A Review and Approve D
MN1070 Assemble Technic al Data for Heat Pump 3 0 100% 24-Dec-10 A 29-Dec-10 A Assemble Tech
MN1090 Review Technical Data on Heat Pumps 8 0 100% 04-Jan-11 A 12-Jan-11 A
MFG00772.Bldg.Found Foundation 64 0 97.04% 24-Dec-10 A 25-Mar-11 A
MN1040 Begin Building Construction 0 0 100% 24-Dec-10 A Begin Building Constru
MN1050 Site Preparation 18 0 100% 24-Dec-10 A 20-Jan-11 A

Actual Level of Effort Remaining Work Page 4 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 1, 2011 Qtr 2, 2011
Jan Feb Mar Apr May Jun

Prepare and Solicit Bids for System Controller


Review Bids for System Controller
Award Contract for System Controller

12-Jan-11 A, MFG00772.Bldg.DesEng Design and Engineering


gn Building Addition
Review and Approve Designs
Assemble Technic al Data for Heat Pump
Review Technical Data on Heat Pumps
25-Mar-11 A, MFG00772.Bldg.Found Foundation
Begin Building Construction, 24-Dec-10 A
Site Preparation

Actual Level of Effort Remaining Work Page 5 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 3, 2011 Qtr 4, 2011
Jul Aug Sep Oct Nov Dec
Calibrate Robot Controller & Power Up
08-Sep-11, MFG00772.Auto.SysEng.SysCtl System Controller

Fabricate and Deliver System Controller


Install System & Misc. Components
Install System Controller
Install Bar Rails

Install Processor/Software/Data Tapes


Production Start, 22-Sep-11
Load System Software
Program
Test Software
Manual Operation Ready
Debug Software
Automatic Operation Ready
Startup Procedure Deve

17-Nov-11, MFG00772.Bldg Office

Actual Level of Effort Remaining Work Page 6 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Q
Duration Complete Jan
Nov Dec
MN1200 Excavation 10 0 100% 21-Jan-11 A 02-Feb-11 A
MN1330 Install Underground Water Lines 5 0 100% 08-Feb-11 A 14-Feb-11 A
MN1340 Install Underground Electric Conduit 5 0 100% 08-Feb-11 A 14-Feb-11 A
MN1410 Form/Pour Concrete Footings 10 0 100% 15-Feb-11 A 28-Feb-11 A
MN1470 Concrete Foundation Walls 10 0 100% 03-Mar-11 A 16-Mar-11 A
MN1480 Form and Pour Slab 5 0 100% 17-Mar-11 A 23-Mar-11 A
MN1490 Backfill and Compact Walls 2 0 100% 24-Mar-11 A 25-Mar-11 A
MN1500 Foundation Phase Complete 0 0 100% 25-Mar-11 A
MFG00772.Bldg.Struct Structure 64 39 28.95% 28-Mar-11 A 27-Jun-11 236
MN1510 Erect Structural Frame 20 0 100% 28-Mar-11 A 21-Apr-11 A
MN1550 Floor Decking 14 15 78.57% 22-Apr-11 A 20-May-11 0
MN1540 Begin Structural Phase 0 0 100% 02-May-11 282
MN1580 Concrete First and Second Floor 15 15 0% 23-May-11 13-Jun-11 0
MN1630 Erect Stairwell and Elevator Wall s 10 10 0% 13-Jun-11 24-Jun-11 0
MN1640 Concrete Basement Slab 10 10 0% 13-Jun-11 24-Jun-11 0
MN1680 Structure Complete 0 0 0% 27-Jun-11 0
215
MFG00772.Bldg.MechSys Mechanical/Electrical Systems 138 24.5% 13-Jan-11 A 14-Nov-11 137
MN1650 Rough-In Phase Begins 0 0 0% 22-Jun-11 245
MN1990 Rough In Complete 0 0 0% 16-Sep-11 0
MFG00772.Bldg.MechSys.Elev Elevator 59 59 0% 27-Jun-11 19-Sep-11 38
MN1690Install Elevator Rails and Equipment 15 15 0% 27-Jun-11 18-Jul-11 44
MN2010Install Elevator Cab and Finishes 2 2 0% 16-Sep-11 19-Sep-11 38
MFG00772.Bldg.MechSys.HVAC HVAC 215 138 72.2% 13-Jan-11 A 14-Nov-11 0
MN1140 Prepare and Solicit Bids for Heat Pump 3 0 100% 13-Jan-11 A 17-Jan-11 A
MN1160 Review Bids for Heat Pump 2 0 100% 18-Jan-11 A 19-Jan-11 A
MN1210Award Contract for Heat Pump 1 0 100% 20-Jan-11 A 20-Jan-11 A
MN1230Fabricate and Deliver Heat Pump and Controls
90 43 80% 21-Jan-11 A 30-Jun-11 47
MN1660Install HVAC Ducts 10 10 0% 22-Jun-11 06-Jul-11 34
MN1890Insulate Ducts 2 2 0% 22-Aug-11 23-Aug-11 8
MN1910Set Heat Pump 5 5 0% 24-Aug-11 30-Aug-11 8
MN1980Startup and Test HVAC 1 1 0% 15-Sep-11 15-Sep-11 0
MN2090Install AC Grills and Registers 5 5 0% 19-Oct-11 25-Oct-11 2
MN2190Test and Balance HVAC Equipment 1 1 0% 14-Nov-11 14-Nov-11 0

Actual Level of Effort Remaining Work Page 7 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 1, 2011 Qtr 2, 2011
Jan Feb Mar Apr May Jun
Excavation
Install Underground Water Lines
Install Underground Electric Conduit
Form/Pour Concrete Footings
Concrete Foundation Walls
Form and Pour Slab
Backfill and Compact Walls
Foundation Phase Complete,

Erect Structural Frame


Floor Decking
Begin Structural Phase, 02-May-11
Concrete First and

Prepare and Solicit Bids for Heat Pump


Review Bids for Heat Pump
Award Contract for Heat Pump

Actual Level of Effort Remaining Work Page 8 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 3, 2011 Qtr 4, 2011
Jul Aug Sep Oct Nov Dec

27-Jun-11, MFG00772.Bldg.Struct Structure

Concrete First and Second Floor


Erect Stairwell and Elevator Wall s
Concrete Basement Slab
Structure Complete,
14-Nov-11, MFG00772.Bldg.MechSys
Rough-In Phase Begins, 22-Jun-11
Rough In Complete,
19-Sep-11, MFG00772.Bldg.MechSys.Elev Elevator
Install Elevator Rails and Equipment
Install Elevator Cab and Finishes
14-Nov-11, MFG00772.Bldg.MechSys.

Fabricate and Deliver Heat Pump and Controls


Install HVAC Ducts
Insulate Ducts
Set Heat Pump
Startup and Test HVAC
Install AC Grills and Registers
Test and Balance HVAC Equipment

Actual Level of Effort Remaining Work Page 9 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Q
Duration Complete Jan
Nov Dec
74
MFG00772.Bldg.MechSys.Plumb Plumbing and Electrical 74 0% 01-Jun-11 14-Sep-11 0
MN1600Set Mechanical and Electrical Equipment 15 15 0% 01-Jun-11 21-Jun-11 34
MN1710Rough-In Plumbing/Piping 15 15 0% 28-Jun-11 19-Jul-11 34
MN1900Install Wiring and Cable 15 15 0% 22-Aug-11 12-Sep-11 0
MN1970Connect Equipment 3 3 0% 12-Sep-11 14-Sep-11 0
MFG00772.Bldg.ExtFinish Exterior Finishes 167 39 12.89% 24-Dec-10 A 22-Aug-11 197
MN1820 Close-In Phase Begins 0 0 0% 08-Aug-11 212
MN1880 Building Enclosed 0 0 0% 22-Aug-11 0
MFG00772.Bldg.ExtFinish.Brick Brick 158 30 22.87% 24-Dec-10 A 08-Aug-11 0
MN1080Assemble Brick Samples 5 0 100% 24-Dec-10 A 30-Dec-10 A Assemble Bric
MN1100 Review and Approve Brick Samples 10 0 100% 04-Jan-11 A 14-Jan-11 A
MN1150 Prepare and Solicit Bids for Brick Exterior 3 0 100% 17-Jan-11 A 19-Jan-11 A
MN1220Review Bids for Brick 3 0 100% 20-Jan-11 A 24-Jan-11 A
MN1240Award Contract for Brick 1 0 100% 25-Jan-11 A 25-Jan-11 A
MN1260Deliver Brick 60 0 100% 26-Jan-11 A 18-Apr-11 A
MN1700Brick Exterior Walls 30 30 0% 27-Jun-11 08-Aug-11 0
MFG00772.Bldg.ExtFinish.Roof Roof 10 10 0% 08-Aug-11 19-Aug-11 0
MN1830Insulation and Built-up Roofing 10 10 0% 08-Aug-11 19-Aug-11 0
14
MFG00772.Bldg.ExtFinish.DoorWin Doors and Windows 14 0% 05-Jul-11 22-Jul-11 20
MN1740Install Door and Window Frames 5 5 0% 05-Jul-11 11-Jul-11 20
MN1750Install Exterior Doors and Windows 10 10 0% 11-Jul-11 22-Jul-11 20
MFG00772.Bldg.IntFinish Interior Finishes 229 44 4.24% 24-Dec-10 A 17-Nov-11 135
MN2000 Drywall in Offices 15 15 0% 16-Sep-11 06-Oct-11 0
MN2060 Finishes Phase Begins 0 0 0% 07-Oct-11 168
MN2180 Touch-up and Clean-up 1 1 0% 11-Nov-11 11-Nov-11 0
MN2200 Finishes Milestone 0 0 0% 15-Nov-11 0
MN2210 Punch List 2 2 0% 15-Nov-11 16-Nov-11 0
MN2220 Building Addition Complete 0 0 0% 17-Nov-11 0
MFG00772.Bldg.IntFinish.Plumb Plumbing and Lighting14
Fixtures 14 0% 19-Oct-11 07-Nov-11 3
MN2080Install Lighting Fixtures 3 3 0% 19-Oct-11 21-Oct-11 4
MN2150Install Plumbing Fixtures 2 2 0% 04-Nov-11 07-Nov-11 3
MFG00772.Bldg.IntFinish.Floor Floor and Carpeting 220 5 67.97% 24-Dec-10 A 03-Nov-11 0
MN1060Assemble and Submit Flooring Samples 7 0 100% 24-Dec-10 A 03-Jan-11 A

Actual Level of Effort Remaining Work Page 10 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 1, 2011 Qtr 2, 2011
Jan Feb Mar Apr May Jun

Assemble Brick Samples


Review and Approve Brick Samples
Prepare and Solicit Bids for Brick Exterior
Review Bids for Brick
Award Contract for Brick
Deliver Brick

Assemble and Submit Flooring Samples

Actual Level of Effort Remaining Work Page 11 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 3, 2011 Qtr 4, 2011
Jul Aug Sep Oct Nov Dec
14-Sep-11, MFG00772.Bldg.MechSys.Plumb Plumbing and Electrical
Set Mechanical and Electrical Equipment
Rough-In Plumbing/Piping
Install Wiring and Cable
Connect Equipment
22-Aug-11, MFG00772.Bldg.ExtFinish Exterior Finishes
Close-In Phase Begins, 08-Aug-11
Building Enclosed,
08-Aug-11, MFG00772.Bldg.ExtFinish.Brick Brick

Brick Exterior Walls


19-Aug-11, MFG00772.Bldg.ExtFinish.Roof Roof
Insulation and Built-up Roofing
22-Jul-11, MFG00772.Bldg.ExtFinish.DoorWin Doors and Windows
Install Door and Window Frames
Install Exterior Doors and Windows
17-Nov-11, MFG00772.Bldg.IntFini
Drywall in Offices
Finishes Phase Begins, 07-Oct-11
Touch-up and Clean-up
Finishes Milestone,
Punch List
Building Addition Complete,
07-Nov-11, MFG00772.Bldg.IntFinish.Plumb Pl
Install Lighting Fixtures
Install Plumbing Fixtures
03-Nov-11, MFG00772.Bldg.IntFinish.Floor Floor and

Actual Level of Effort Remaining Work Page 12 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Q
Duration Complete Jan
Nov Dec
MN1110 Review and Approve Flooring 10 0 100% 05-Jan-11 A 18-Jan-11 A
MN1170 Prepare and Solicit Bids for Flooring 5 0 100% 19-Jan-11 A 25-Jan-11 A
MN1250Review Bids for Flooring 3 0 100% 26-Jan-11 A 28-Jan-11 A
MN1280Award Contract for Flooring 1 0 100% 01-Feb-11 A 01-Feb-11 A
MN1290Fabricate and Deliver Flooring 60 0 100% 02-Feb-11 A 25-Apr-11 A
MN2130Install Floor and Carpeting 5 5 0% 28-Oct-11 03-Nov-11 0
MFG00772.Bldg.IntFinish.Carp Carpentry 25 25 0% 07-Oct-11 10-Nov-11 0
MN2070Install Ceiling Grid 15 15 0% 07-Oct-11 27-Oct-11 0
MN2160Finish Carpentry and Millwork 5 5 0% 04-Nov-11 10-Nov-11 0
MFG00772.Bldg.IntFinish.Paint Paint 15 15 0% 27-Sep-11 17-Oct-11 18
MN2020Paint Building Interior 15 15 0% 27-Sep-11 17-Oct-11 18
MFG00772.Conv Conveyor System 331 276 6.99% 14-Feb-11 A 30-May-12 0
80
MFG00772.Conv.SysDesEng System Design and Engineering 25 48.61% 14-Feb-11 A 06-Jun-11 68
MN1350 System Design 40 0 100% 14-Feb-11 A 05-Apr-11 A
MN1530 Review and Approve Design 15 0 100% 12-Apr-11 A 28-Apr-11 A
MN1570 Prepare Drawings for Conveyors 20 20 15% 02-May-11 27-May-11 70
MN1610 Review and Approve Drawings for Conveyors 5 5 0% 31-May-11 06-Jun-11 70
MFG00772.Conv.FieldOps Field Operations 252 252 0% 06-Jun-11 30-May-12 0
MFG00772.Conv.FieldOps.Install Installation 251 251 0% 06-Jun-11 30-May-12 0
MN1620Prepare and Solicit Bids for Conveyors 10 10 0% 06-Jun-11 17-Jun-11 70
MN1670Review Bids for Conveyors 2 2 0% 20-Jun-11 21-Jun-11 70
MN1720Award Contract 1 1 0% 22-Jun-11 22-Jun-11 70
MN1730Fabricate and Deliver Conveyors 50 50 0% 23-Jun-11 01-Sep-11 70
MN2230Start Conveyor Installation 0 0 0% 17-Nov-11 0
MN2240Site Preparation 15 15 0% 17-Nov-11 08-Dec-11 0
MN2250Install Conveyor 211 14 14 0% 08-Dec-11 28-Dec-11 0
MN2260Install Conveyor 212 50 50 0% 28-Dec-11 07-Mar-12 0
MN2270Field Piping 50 50 0% 22-Feb-12 01-May-12 0
MN2280Field Wiring 50 50 0% 22-Feb-12 01-May-12 0
MN2290Install Conveyor 213 10 10 0% 07-Mar-12 20-Mar-12 0
MN2300Install Conveyor 214 30 30 0% 21-Mar-12 01-May-12 0
MN2310Field Painting 20 20 0% 21-Mar-12 17-Apr-12 10

Actual Level of Effort Remaining Work Page 13 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 1, 2011 Qtr 2, 2011
Jan Feb Mar Apr May Jun
Review and Approve Flooring
Prepare and Solicit Bids for Flooring
Review Bids for Flooring
Award Contract for Flooring
Fabricate and Deliver Flooring

06-Jun-11, MFG00772.Conv
System Design
Review and Approve Design
Prepare Drawings for Conveyors
Review and Approve Drawin

Prepare and S

Actual Level of Effort Remaining Work Page 14 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 3, 2011 Qtr 4, 2011
Jul Aug Sep Oct Nov Dec

Install Floor and Carpeting


10-Nov-11, MFG00772.Bldg.IntFinish.Carp
Install Ceiling Grid
Finish Carpentry and Millwork
17-Oct-11, MFG00772.Bldg.IntFinish.Paint Paint
Paint Building Interior

n-11, MFG00772.Conv.SysDesEng System Design and Engineering

or Conveyors
w and Approve Drawings for Conveyors

Prepare and Solicit Bids for Conveyors


Review Bids for Conveyors
Award Contract
Fabricate and Deliver Conveyors
Start Conveyor Installation, 17-Nov

Actual Level of Effort Remaining Work Page 15 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Q
Duration Complete Jan
Nov Dec
MN2330Conveyor System Complete 0 0 0% 30-May-12 0
MFG00772.Conv.FieldOps.OnsiteTest Onsite Testing 20 20 0% 02-May-12 30-May-12 0
MN2320Start-Up & Debug System 20 20 0% 02-May-12 30-May-12 0
MFG00772.Conv.Train Training 90 90 0% 01-Sep-11 10-Jan-12 103
MFG00772.Conv.Train.OpsManual Operation Manuals 90 90 0% 01-Sep-11 10-Jan-12 103
MN1960Operation Manuals 90 90 0% 01-Sep-11 10-Jan-12 104

Actual Level of Effort Remaining Work Page 16 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 1, 2011 Qtr 2, 2011
Jan Feb Mar Apr May Jun

Actual Level of Effort Remaining Work Page 17 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Cordova - Plant Expansion Modernization Classic Schedule Layout 22-Apr-24 19:08
Qtr 3, 2011 Qtr 4, 2011
Jul Aug Sep Oct Nov Dec

Actual Level of Effort Remaining Work Page 18 of 18 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation