BOQ Amount ₹ 130,500,000.

00
Work Done Amount till date
Project Completion % 0.00%

Orginal shedule
Sl. No Activity
Starting date End date
SKODA EXPANSION PROJECT
PROJECT TENTATIVE DATES 2/7/2024 10/7/2024
A) Main Plant
1 Mobilisation 2/7/2024 2/17/2024
2 Site cleaning 2/18/2024 2/23/2024

3 MS Barrication work around work premises 2/20/2024 3/21/2024

4 Removing/breaking existing structures 3/1/2024 4/15/2024

5 Breaking of Hard strata upto required level 3/21/2024 5/30/2024

6 RCC work upto plinth 4/10/2024 6/19/2024


7 Filling in plinth 4/30/2024 7/2/2024
8 Supply and Erection of PEB 5/10/2024 8/8/2024
9 FM-2 Flooring Work 6/9/2024 8/18/2024
10 Deck Slab 7/9/2024 8/8/2024
11 BBM & Plaster work above plinth 6/19/2024 8/28/2024
Jointry works (Doors,Windows, RS,
12 7/9/2024 9/7/2024
Partitions )
13 Utilities 5/10/2024 9/7/2024
14 Internal & Ext. painting 7/19/2024 9/17/2024
15 Underground services & Road work 6/9/2024 10/7/2024
16 Toilet Block Work ( Int & Ext Plumbing ) 7/9/2024 9/7/2024