OHSE SERVICE DELIVERY - ISO 9001 - TRACKER

Name of the project:________________________ Project Manager:

Location : ________________________________ OHSE In charge :


Vendor-2 Vendor-3
Project details: Date of Tracker Issued:

Actual Date of Scheduled Date of Actual Date of Scheduled Date of Actual Date of
S. No. OHSE IMPLEMENTATION TRACKER FOR THE PROJECT Target duration
Completion of points Completion of points Completion of points Completion of points Completion of points

Submittals
1 Vendor's OHSE Plan Within 1week vendor on board (submission & approval )
2 Emergency Preparedness Plan Within 1week of work commencement
3 Waste management plan Within 1week vendor on board (submission & approval )
4 Site Logistics Plan From day one of work commencement (submission & approval )
5 Sign off responsibility matrix, penalty classes, gate & waste management Kickoff meeting
6 Safety organization Chart Within 1week after work commencement
7 Hospital Tie Up Letter for emergency treatment Within 1week vendor on board (submission & approval )
8 Form work engineer's test certificate for Scaffold/Mobile scaffold Within 1week vendor on board (submission & approval )
9 Drinking water Test certificate Within 1week after work commencement
10 Profiles of Safety personnel's Within 1week of work commencement
11 Authorization letter for Electrician & profile Within 1week vendor on board (submission & approval )
12 Authorization letter for Scaffolder & profile Within 1week after work commencement (Scaffold work)
13 Authorization letter for Qualified & experienced Male Nurse or First-aider Within 1week vendor on board (submission & approval )
14 ID Card approval from CLIENT In the kick off meeting
15 PPE approval from CLIENT In the kick off meeting
16 Job specific training-calendar Within 1week after work commencement
17 Tool Box Talk & Pep Talk- From day one of work commencement
18 Emergency evacuation Mock drill-Matrix Regular monthly once
19 ELCB ELCB/RCCB Testing-Matrix Within 1week after work commencement
20 Tools & tackles and Ladders inspection-Matrix Within 1week after work commencement
21 Snake & Pest Control -Matrix(For base build projects) Kick off meeting/ From day one of work commencement
22 Safety committee formation & meeting-Matrix Kick off meeting/ Within 1week of work commencement
23 Illumination study around the site From day one of work commencement
24 Noise study at site and maintain records Within 1week after work commencement & on the day of the work activity
25 PPE test certificates From day one of work commencement
26 Fire Extinguisher test certificates From day one of work commencement
27 Competency certificate for crane operators From day one of work commencement
28 Welder qualified certificate From day one of work commencement
29 Labor license From day one of work commencement
30 Third party liability policy From day one of work commencement
31 Labor compensation policy From day one of work commencement
32 CAR policy From day one of work commencement
33 Labor migration certificate From day one of work commencement
34 Medical fitness certificate for tower crane operator From day one of work commencement
35 Color vision test report for Tower crane operators From day one of work commencement
Valid driving licenses , vehicle fitness, insurance for the vehicles & equipments
36 ( wheel mounted cranes, earth moving machines like JCBs etc.) Kick off meeting/ regular monitoring

37 Calibration certificates for welding machines Kick off meeting/ From day one of work commencement
38 Third party certificates for air compressors From day one of work commencement
39 Material safety data sheets(MSDS) of all materials From day one of work commencement
40 Delegation of OHSE responsibilities Kick off meeting
41 Non conformity reports Kick off meeting/From day one of work commencement
42 Daily observation & compliance file Within 1week after work commencement
43 Site notes & mail correspondence etc. Within 1week after work commencement
44 Method statements & job safety analysis Kick off meeting/ From day one of work commencement
45 All work permits Kick off meeting/From day one of work commencement
46 Relevant checklist Kick off meeting/From day one of work commencement
47 List of project documents maintained at site Kick off meeting/From day one of work commencement
48 Incident, Accident investigation reports Regular as & when required
49 HIRA & AIA Kick off meeting/From day one of work commencement
Mandatory OHSE Items
50 Safety Posters Kick off meeting/From day one of work commencement
51 Safety Sign Boards Within 1week after work commencement
52 Safety policy display at site Within 1week after work commencement
53 Project Information Board Within 1week after work commencement
54 Emergency Contact Number display Kick off meeting/From day one of work commencement
55 OHSE statistic board Within 1week after work commencement
56 Safety Bulletin board Kick off meeting/From day one of work commencement
57 PPE display Board Within 1week after work commencement
58 Emergency vehicle/ ambulance on the day one of work commencement ti all project teams
59 Mandatory First Aid medicines and accessories Kick off meeting/From day one of work commencement
60 Fire extinguishers & Fire Buckets Kick off meeting/ within 1 week of work commencement
61 Outdoor industrial Metal PDB with lock & key Kick off meeting/From day one of work commencement
62 Emergency siren(For base build projects) Kick off meeting/ within 1 week of work commencement
63 Mega Phone Kick off meeting/ From day one of work commencement
64 Nail collecting Magnet(For base build projects) Kick off meeting/ From day one of work commencement
65 Scaffolding Tags Kick off meeting/ From day one of work commencement
66 LOTO Tags Kick off meeting/ From day one of work commencement
67 Trash Bins Kick off meeting/ From day one of work commencement
68 Barricades/ caution tapes/routing signage's From day one of work commencement
Site Implementation
69 HIRA & AIA brief to the project team From day one of work commencement
70 Training by CBRE OHSE on Responsibility matrix, penalties, reporting structure Within 1week of work commencement
71 Drinking water arrangement for workers Within 1week after work commencement
72 Workers Toilet & sanitation Within 1week after work commencement
73 First Aid center Before two days of work commencement
74 Safety Induction Room From day one of work commencement
75 Emergency Assembly point From day one of work commencement
76 Emergency vehicle/ ambulance Driver Number display at security room From day one of work commencement
77 Vehicle barrier at entry(For base build projects) From day one of work commencement
78 Safety gate & park Kick off meeting/ within 1 week of work commencement
79 Scrap Yard From day one of work commencement
80 DA Gas Cylinder Yard From day one of work commencement
81 Oxygen Gas Cylinder Yard From day one of work commencement
82 Welding yard From day one of work commencement
83 Fuel storage yard(For base build projects) From day one of work commencement
84 Cement storage Yard From day one of work commencement
85 Chemical storage Yard From day one of work commencement
86 Other flammable storage Yard From day one of work commencement
Format No. K024-OHS-SD-Tr-026/ Rev02/Dec 2019