Daily Productivity Report 28-04-2024

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Sunday, 28 April 2024 Daily Productivity Report

Average Completed Planned Completion Date Completion date


Total Spot %
No Activity Unit
Quantity Productivity
weekly Quantity Finishing (Spot ( Average Status
Complete
Remarks
Productivity (Till Today) Date Productivity) productivity)

1 Excavation m3 4,002,874 5,090 8,932 3,702,462 14-Apr-2024 26-Jun-2024 31-May-2024 in progress 92.50%

2 Blasting m3 622,001 3,000 267,001 14-Mar-2024 24-Aug-2024 in progress 42.93%

3 Soil improvement m2 148,561 248 135 100,356 22-Apr-2024 8-Nov-2024 20-Apr-2025 in progress 67.55%

4 Shoring m2 20,565 136 68 19,333 14-Apr-2024 7-May-2024 16-May-2024 in progress 94.01%

5 Concrete (RC) m3 1,027,823 96 965 164,282 1-Oct-2025 13-Dec-2048 9-Oct-2026 in progress 15.98%

6 Rebar Ton 181,626 19 193 31,579 7-Sep-2025 11-Dec-2045 14-Jun-2026 in progress 17.39%

7 Surface Preparation (Walls) Sqm 159,802 67 1,010 28-Jul-2025 23-Dec-2037 in progress 0.63% Work Front 3,026 m2

8 Waterproofing (Walls) Sqm 159,802 0 32 420 28-Jul-2025 16-Dec-2037 in progress 0.26% Work Front 2,604 m2

9 Backfilling m3 4,200,000 0 705 23-Jan-2025 in progress 0.02%

10 Crashers m3 1,499,980 1,000 900 428,900 23-Jan-2025 4-Apr-2027 1-Aug-2027 in progress 28.59%

11 Disposal Material m3 2,844,269 14,883 2,539,310 14-Apr-2024 18-May-2024 in progress 89.28%