INCEPTION REPORT
VOLUME 1 – INTRODUCTORY INFORMATION
REVISION 2
APRIL 2017
BACKGROUND
The roads agency of Moçambique, Administração Nacional De Estradas (ANE), awarded the Simple
Output and Performance Based Roads Contract (OPRC) For Design, Rehabilitation/Improvement, Routine
Maintenance Works of Chissano to Chibuto and N/C Crz. N220 to N1 to Zhongmei Engineering Group.
The provision of design phase reporting is included in this project.
The objective of this Inception Report is to present the work plan, environmental strategies, social
strategies and quality assurance methodologies that are to be implemented, according to the
specifications of the Contract Document.
WORK PLAN
The milestones for the detailed design phase are as set out in the contract specifications (Ref. Section
VI – Specifications: Part A3 – Service Level, Paragraph 3.1.1) and are summarised as part of the work
plan as follows:
Detailed design and construction drawings of new bridge for approval 6 months
i
The Monitoring Consultant (and/or ANE) shall receive the detailed designs for the various
subsections for approval for construction.
The work plan for the construction period indicates the various rehabilitation, improvement and
maintenance works for the various road sections, according to the Contract Document and also
makes provision for the various monthly reporting.
The various strategies that are to be implemented for all stages of the project have been highlighted
in this report. The performance indicators that need to be monitored, according to the specifications
of the Contract Document are monitored as per the quality control forms for various testing and
service level requirements as indicated in Annexure D.
The implementation of these strategies will be required to measure the ongoing and ultimate
successful performance of the contracting entity.
ii
TABLE OF CONTENTS
INTRODUCTION .................................................................................................. 1
1.1. APPOINTMENT AND TERMS OF REFERENCE ........................................................... 1
iii
LIST OF FIGURES
LIST OF TABLES
iv
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
INTRODUCTION
1.2. BACKGROUND
Administração Nacional De Estradas (ANE) identified roads within their network in need
of rehabilitation, improvement and routine maintenance work. The roads that form
part of this contract are indicated in blue on the locality plan below.
Page 1
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
The Inception Report has been subdivided into four volumes for ease of reference, as
follows:
Volume 1: Introductory Information
Volume 2: Environmental and Social Strategies
Volume 3: Safety Strategies
Volume 4: Quality Assurance Manual
This volume (Volume 1) considers the general project background and addresses the
details of the work plan for the duration of the project.
Volume 2: Environmental and Social Strategies discusses the environmental impact, social
impact and the management framework studies that were performed for the project.
It also provides the best practices for the environmental management plan of the
project.
Volume 3: Safety Strategies provides the various safety plans for the project. This
includes the Health and Safety Plan, the Emergency Procedures and Contingency Plan
and the Traffic Management Plan. It also provides a baseline risk assessment in terms
of health and safety for this project.
Volume 4: Quality Assurance Manual provides the processes and systems that have been
put in place for this project in order to ensure that all aspects of construction work and
Page 2
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
testing is tracked and monitored, according to the relevant service levels and
specifications.
Page 3
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
WORK PLAN
2.1. OVERVIEW
The duration of the Contract is composed of two periods as follows (as defined in the
specifications of the Contract (Ref. Section VI – Specifications: Part A2 – Description of
Services, Paragraph 2.1.1):
“Works Period: That (first) period of the Contract in which the Contractor is obliged
to complete and maintain all the Rehabilitation and Improvement Works. This period
starts at the Start Date of the Contract and ends at the completion date of the Works
Period. The duration of this period is 18 (eighteen) months.
Defects Liability Period: That (second) period of the Contract in which the Contractor
is obliged to maintain all the roads and hydraulic structures included in the Contract.
This period starts at the end of the Works Period and ends at the end of the Contract.
The duration of this period is 12 (twelve) months.
The Start Date of the Contract was 06 February 2017. The works period therefore ends,
according to the current work plan, on 06 August 2018 and the defects liability period
therefore ends on 06 August 2019.
This is required for review and approval by the Project Manager up to 3 months from
commencement of the Contract. This section is selected as N220: Chissano to Chibuto,
km11+700 to km19+500 and N/C Crz. N220, km0+000 to km2+200. According to the
work plan, this detailed design is scheduled for submission on 06 May 2017.
This is required for review and approval by the Project Manager up to 4 months from
commencement of the Contract. This section is selected as N220: Chissano to Chibuto,
km0+000 to km5+000. According to the work plan, this detailed design is scheduled
for submission on 06 June 2017.
Page 4
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
This is required for review and approval by the Project Manager up to 6 months from
commencement of the Contract. The reconstruction of this 80 m length existing bridge
is along N220 at km20+500. According to the work plan, this detailed design is
scheduled for submission on 06 August 2017.
This is required for review and approval by the Project Manager up to 6 months from
commencement of the Contract. This section is selected as N220: Chissano to Chibuto,
km5+000 to km11+700 and km19+500 to km32+800. According to the work plan, this
detailed design is scheduled for submission on 06 August 2017.
This is required for review and approval by the Project Manager up to 8 months from
commencement of the Contract. This section has been classified as N220: Chissano to
Chibuto, km32+800 to km39+200; N/C Crz. N220 – km2+200 to km18+000. According
to the work plan, this detailed design is scheduled for submission on 06 October 2017.
A detailed design report is required for submission to the Project Manager for review
and approval 5 months after the start of the Contract, according to Section VI –
Specifications: Part A3 – Service Level, Paragraph 3.6.5. According to the work plan, this
detailed design report is scheduled for submission on 06 July 2017.
A final design report is required for submission to the Project Manager for review and
approval 8 months after the start of the Contract, according to Section VI – Specifications:
Part A3 – Service Level, Paragraph 3.6.5. According to the work plan, this detailed design
is scheduled for submission on 06 October 2017.
Page 5
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
The Project Manager is required to respond within 14 days of receipt of the document
with written approval or disapproval of the document. Failing to respond within this
timeframe, the said document shall be deemed to have been approved by the Project
Manager (Ref. Section VII – General Conditions: Clause 8.4.2).
The work plan for the construction period indicates the various rehabilitation,
improvement and maintenance works for the various road sections, according to the
Contract Document.
Monthly reporting
These reports will be in line with the relevant specifications and in line with the service
level requirements of the Contract.
This report will address all aspects of the rehabilitation/improvement works, including
financial summaries, recommendations for future periodic maintenance and other
requirements, according to Section VI – Specifications: Part A3 – Service Level, Paragraph
3.6.5. A set of as-built drawings in digital format on CDs containing all this information
is to be submitted to the Monitoring Consultant and Employer, within 8 weeks of the
completion of the rehabilitation/improvement stage.
The Contractor is also to prepare and submit as-built drawings to the Project Manager
all work undertaken. These shall be supplied for approval within ten days of the
submission to the Project Manager for the commencement of Defects Liability Period
for a designated section defined as being completed sections, including pavement
marking (Ref. Section VI – Specifications: Part B – General Specifications, Item 20).
Page 6
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
2.6. CONCLUSIONS
The work plan described above has been based on the requirements of the Contract
Document and has been illustrated in a Gantt chart as attached in Annexure A of this
document.
Page 7
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
The work plan, environmental strategies, social strategies, safety strategies and quality
assurance methodologies that are to be implemented for all stages of the project have
been highlighted in this report. The performance indicators that need to be monitored,
according to the specifications of the Contract Document are monitored as per the
quality control forms for various testing and service level requirements.
The implementation of these strategies will be required to measure the ongoing and
ultimate successful performance of the contracting entity.
Page 8
Inception Report Rev2 – Volume 1
ADMINISTRAÇÃO NACIONAL DE ESTRADAS
SIMPLE OUTPUT AND PERFORMANCE BASED ROAD CONTRACT (OPRC)
FOR DESIGN, REHABILITATION/IMPROVEMENT, ROUTINE MAINTENANCE WORKS
OF CHISSANO TO CHIBUTO AND N/C Crz.N220 TO N1
A
Inception Report Rev2 – Volume 1