PROPOSED PRIVATE RESIDENTIAL DEVELOPMENT AT SHORELINE ESTATE, IKOYI, LAGOS

ID Task Name March 2024 Duration Start Finish Predecessors April 2024 May 2024
31 5 10 15 20 25 30 5 10 15 20 25
1 PROPOSED RESIDENTIAL DEVELOPMENT 40 days Wed 4/3/24 Sat 5/18/24
2 ALTERATION WORKS 6 days Mon 4/15/24 Sat 4/20/24
3 Toilet 6 days Mon 4/15/24 Sat 4/20/24
4 Toilets Niche 6 days Mon 4/15/24 Sat 4/20/24
5 Making good of existing duct 1 day Wed 4/17/24 Wed 4/17/24 4SS+2 days
6 FINISHINGS 40 days Wed 4/3/24 Sat 5/18/24
7 Dry Finishings (Internal) 40 days Wed 4/3/24 Sat 5/18/24
8 Covering of Master bedroom opening 2 days Wed 4/17/24 Thu 4/18/24 5SS
9 Girls room ceiling alteration 3 days Thu 4/18/24 Sat 4/20/24 8SS+1 day
10 Testing of Electrical fittings and HVAC 5 days Mon 4/15/24 Fri 4/19/24 4SS
systems
11 First coat painting (Internal) 14 days Mon 4/22/24 Tue 5/7/24 10,9
12 Installation of hand railings 5 days Mon 4/22/24 Fri 4/26/24 11SS
13 Complete Installation of wardrobes 8 days Mon 4/15/24 Tue 4/23/24 4SS
and kitchen
14 Final coat painting (Internal) 10 days Wed 5/8/24 Sat 5/18/24 11
15 External Painting 25 days Wed 4/3/24 Wed 5/1/24 4SS-10 days
16 Swimming pool works 15 days Thu 4/18/24 Sat 5/4/24
17 Screeding of concrete base 2 days Thu 4/18/24 Fri 4/19/24 8SS+1 day
18 Tiling of pool and Balancing tank 7 days Sat 4/20/24 Sat 4/27/24 17
19 Installation of fittings 4 days Wed 5/1/24 Sat 5/4/24 18FS+2 days
20 External works/Fence 25 days Mon 4/15/24 Mon 5/13/24 8SS-2 days
21 Cleaning on completion 5 days Tue 5/14/24 Sat 5/18/24 14FS-5 days
22 Demobiliazation 8 days Fri 5/10/24 Sat 5/18/24 21SS-3 days

Task Project Summary Manual Task Start-only Deadline

Project: Completion POW 1504 Split Inactive Task Duration-only Finish-only Progress
Date: Tue 4/16/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

WALSHER DB LTD Page 1