Professional Documents
Culture Documents
Revised DNIT Water T
Revised DNIT Water T
Revised BOQ of DNIT for Water Proofing, Expansion Joint Treatment, Welding, Civil
works and painting in PCA, I.S BINDRA, International Cricket Stadium, Mohali
RequiredAp Ratein
Sl.No. Description Unit prox.Qty Rs. Amount
WATER PROOFING
TREATMENTINPAVILION TERRACE
SLAB,TWIROOM ROOF SLAB AND
VOC(N.P):
Thoroughly Cleaning surface
ofthesubstrate using suitable
equipmenttomake it free from all
contaminationforoptimum
performance of thefurthersystem.
ii) Applying the dust
2 controllingchemicalafter cleaning the
surface.
iii) Repairing of minor cracks
bymaking“V” grooves with
requiredsealant.
iv) Applying single coat of
bondingagent/waterproof primer along
with 3 coatsofElastic layer chemical
along withfibreglass coated mesh of 45
gsmthickness.
(v) Final layer consists of 2 layer
ofHardcoating UV resistant
13.90+1 Water Proofing on the
a) chemicalwithrequiredcolour. sqmtr 2075 605.44 1256288.00
3.91 PavilionTerraceSlab
Make: Asian, Berger,(559.09+119
Dr.
13.90+1 =678.09)
Water Proofing in the
Fixit,Fosroc,Vikani TWI
orequivalent
b) sqmtr 1300 605.44 787072.00
3.91 RoomroofSlab
13.90+1
c) InKitchen sqmtr 40 605.44 24217.60
3.91
SouthPavilion62’levelRoofSlabandGut
ter/Drain:
The scope of work
alsoincludedremoving the old bitumen
tar feltandmaking slope with concrete
13.90+1 Sqmt
d) withcementmotar, after surface 355 605.44 214931.20
3.91 r
preparationandclearing, washing and
scraping allloosematerial/particle in all
respect as perthespecification and
Channelizing ofwaterinto the existing
main waterpipesdirection of the
engineerincharge. Note: 1:2:4 concrete
to be paid separately.
3RD FLOOR
STAIRCASELEAKAGEREPAIR
BOTH SIDES:
M.S Sheet 2mm thick welding in
3 M.R Kg 300 120 36,000
frontofPavilion lifts both sides to
protectwaterleakage from existing MS
sheets totheconcrete wall/Girder at roof
ofsouthpavilion in AC loungestaircase.
MS sheet 2mm 51’ X 2’ = 19sqmtr
Banquet Hall Ceiling
RepairNearStair case 1C to
Basement:Providing and Fixing ceiling
consistingof12.5mm thick Gypsum
4a) 13.65 Board of anysize Sqm 22.30 1179.4 26301.96
G.I. Cradling hanged from the 6
ceilingbymeans of G.I. hanger complete
alongwithdismantling of existing hangers
etc asperdrawings, specifications and
Basement Banquet
tothe
hallwaterManagement:
entire satisfaction of engineer-in-charge.
Construction of One Sump size4’X4’X2’
b) M.R and reduction of PCC Floor 8’’ to1’ JoB 1 50000 50,000
approx. 200 sqft area
withpropersloping 6’’ to 12’’ to the
sumpin Basement banquethall
Providing and laying vitrified floor
tilesof different sizes in light
colourshades made using Double
Chargetechnology (thickness to be
c) 14.113 sqmtr 60 935.71 56142.60
specified bythe manufacturer)
with waterabsorption’s less than
0.08% and conforming to IS:
15622 of approved make in
allcolours and shades, laid on
20mm thickcement mortar 1:4 (1
cement: 4 finesand),complete. (
Design ishomogenous throughout
the tile body )size 600x600mm
Make: Johnson, Kataria, Nitco, Somany
Ssupports fortheHoarding’stomake
strengthening with
additionalsupportsStructural steel work
in compoundgirdersor Stanchions built
up from two ormore
R.S. joists or channel section or
plates&angles etc. including cutting and
fixingalllattice bars, stiffeners,
gussetplates,bolts, nuts, rivets, welding
rod,etc.complete with flange plates,
5a) 18.7 Qtl 15.52 6610.71 102598.22
heads,soleplates, angle connections,
etc.withhoisting and erecting in
positionincluding joints of two hoardings
approx.ISMC 75x40x 4.8mm 122 nos X 2’
andBack supports angle 50x 6mm 20 nos
X3’ Approx. Total 1200 Kg for 49 Nosof
hoardings to connect each andBack
supports. The rates quoted for thesupply
and fixing of MS Channel, Angles,Plates
as per the
Cement siterequirements
concrete 1:2:4
10.13 12522.33
b) mixingbymechanical means using Cum 03 4174.11
a(ii)
concretemixer volumetrictype
Painting and Polishingwork
6 Make: Asian, Berger,
Dulux,Nerolac,Vikani orequivalent
Scraping White wash, Paint andcolour
a) 8.31 Sqm 4700.00 6.25 29375.00
wash
Preparation of plastered surfacesfor
distempering including surface,applying
filling with approved qualityfiller
b) 16.6 Sqm 4700.00 54.46 255962.00
consisting of plaster of paris andchalk
mitti including finishing the surfaceto
the required finishcomplete
Finishing walls with acrylicsmooth
exterior paint of required shade withtwo
or more coats applied @1.67
c) 16.59 Sqm 2000.00 81.25 162500.00
litre/10Sqm over and including basecoat
of water proofing Cement Paintapplied
@ 2.20 Kg/10Sqm
7 MoatWork
Dismantling stonemasonry/Rubble
masonry including stacking ofserviceable Cum 149 613.39 91395.11
a) 8.1
materials and disposal ofunserviceable
materials
d) 24.6 (b) Excavation of extra earth by hydraulic Cum 480.00 141.07 67713.60
means including carrying cutting and
disposal of the same within lead up to 100
mtr.
Specification:
1. The Water Proofing Chemical to be used Asian, Berser, Dr. Fixit, Fosroc, Vikani orequivalent.
2. The cement to be used ACC, Birla,Ultratec
3. Paint material ASIAN, BERGER andNEROLAC
4. Steel material to be used Tata,Jindal
5. The contractor shall execute all the work including any civil works required as per thesite
and no extra cost will be given. Before quote the rate the contractor will be visit thesite.
6. GSTasapplicablewillbepaidextraaftersubmissionofGSTRreturns(GSTR-1&GSTR-3B)
depictingtheproofofdeposit.TheAssociationwillpayGSTamount,aftercheckingtheGSTin GSTR-
2B of PCA. The GST number of PCA is03AAATP3502C1ZD
7. The agency will quote Percentage (+/-) in figures as well in word as per the above quotedamount i.e., on
Rs. 71,98,090/-.