INSPECTION AND TEST PLAN (RECEIVING & IN-PROGRESS)

PROJECT: CATEGORY : M & E WORK

No. Description Of Inspection / Test Point Of Inspection / Test Responsibility Acceptance Criteria / Verifying Action By / Inspection & Test %
Frequency Document Contractor BV Client
a) Type
1.0 Receiving inspection of Plumbing Upon delivery to site. Surveyor / b) Classification Delivery order I, N, J, A 100% J, F 5% C
materials and equipment. M&E c) Quantity
Engineer d) Physical condition

2.0 Inspection of Plumbing works Before, during and upon completion of Surveyor / Refer to checklist Inspection checklist - I, N, J, A 100% J, F 10% C
Plumbing works M&E Plumbing works
Engineer
a) Type
3.0 Receiving inspection of Electrical Upon delivery to site. Surveyor / b) Classification Delivery order I, N, J, A J, F 5% C
materials and equipments. M&E c) Quantity
Engineer d) Physical condition

4.0 Inspection of Electrical works Before, during and upon completion of Surveyor / Refer to checklist Inspection checklist - I, N, J, A J, F 20% C
Electrical works M&E Electrical works
Engineer
a) Type
5.0 Receiving inspection of Air Upon delivery to site. Surveyor / b) Classification Delivery order I, N, J, A J, F 5% C
Conditioning materials and M&E c) Quantity
equipments. Engineer d) Physical condition

6.0 Inspection of Air Conditioning works Before, during and upon completion of Surveyor / Refer to checklist Inspection checklist - I, N, J, A J, F 20% C
Air Conditioning works M&E Air Conditioning works
Engineer

7.0 Receiving inspection of Lift materials Point of origin / Upon delivery to site. Surveyor / a) Type Delivery order I, N, J, A J, F 5% C
and equipments. M&E b) Quantity
Engineer

8.0 Inspection of Lift works. Before, during and upon completion of Surveyor / Refer to Safe Operating Safe Operating Procedures I, N, J, A J, F 20% C
Lift works. M&E Procedures
Engineer
INSPECTION AND TEST PLAN (RECEIVING & IN-PROGRESS)
PROJECT: CATEGORY : M & E WORK

No. Description Of Inspection / Test Point Of Inspection / Test Responsibility Acceptance Criteria / Verifying Action By / Inspection & Test %
Frequency Document Contractor BV Client

a) Type
9.0 Receiving inspection of Fire Protection Upon delivery to site. Surveyor / b) Classification Delivery order I, N, J, A J, F 5% C
materials and equipment. M&E c) Quantity
Engineer d) Physical condition

10.0 Inspection of Fire Protection works Before, during and upon completion of Surveyor / Refer to checklist Inspection checklist - I, N, J, A J, F 30% C
Fire Protection works M&E Fire Protection works
Engineer

I - Implement J - Joint Inspection N - Notify A - Obtain Approval F - File C - Copy